approved minutes of the june 1 2016 rcc meeting
TRANSCRIPT
September 24, 2016
Members, Reliability Coordinating Committee
and
Members, Task Force on Coordination of Operation
Members, Task Force on Coordination of Planning
Members, Task Force on Infrastructure Security and Technology
Members, Task Force on System Protection
Members, Task Force on System Studies
Re: Minutes of the June 1, 2016 RCC Meeting
Sir / Madam:
Attached are the minutes of the June 1, 2016 meeting of the NPCC Reliability Coordinating
Committee; as approved at the September 7, 2016 RCC meeting.
Sincerely,
Phil Fedora Philip A. Fedora
Assistant Vice President-Reliability Services
cc: NPCC Staff
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 2
Mr. Schiavone called the meeting of the Reliability Coordinating Committee (RCC), held at
the New York Times Square Residence Inn by the Marriott to order at 10:00 am.
Attendance
Officers of the Reliability Coordinating Committee
Michael Schiavone, Chair National Grid USA
Brian Evans-Mongeon, Co-Vice Chair Utility Services, Inc.
Randy Crissman, Co-Vice Chair New York Power Authority
Sector 1 - Transmission Owners
Central Hudson Gas & Electric Corp. Frank Pace
Central Maine Power Company David Conroy
Consolidated Edison Company Michael Forte
of New York, Inc.
Hydro-One, Inc. Tom Irvine
Long Island Power Authority Anie Philip – Alternate (via phone)
National Grid USA Michael Schiavone
New Brunswick Power Corporation Randy McDonald (via phone)
New York Power Authority (proxy to Randy Crissman)
New York State Electric & Gas Corp. Ray Kinney (via phone)
Nova Scotia Power Paul Casey
David Stanford (Alternate)
Rochester Gas & Electric Corporation (proxy to David Conroy)
Vermont Electric Power Company, Inc. Hantz Presume
Sector 2 – Reliability Coordinators
New Brunswick Power Corporation (proxy to Randy MacDonald – via phone)
Ontario Independent Electricity System Len Kula
Operator
ISO-New England, Inc. Mike Henderson
New York Independent System Operator (proxy to Zach Smith)
Sector 3 – Transmission Dependent Utilities, Distribution Companies and Load Serving
Entities
Consolidated Edison Company (proxy to Michael Forte)
of New York, Inc.
Eversource Energy Barry Bruun (via phone)
Long Island Power Authority (proxy to Anie Philip – via phone)
New York Power Authority (proxy to Randy Crissman)
Sector 4 Generation Owners
Consolidated Edison Company (proxy to Mike Forte)
of New York, Inc.
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 3
Dominion Resources Services, Inc. Connie Lowe (via phone)
Dynegy, Inc. James Watson (via phone)
Eversource Energy (proxy to Barry Bruun)
Long Island Power Authority (proxy to Anie Philip – via phone)
New York Power Authority Randy Crissman
NextEra Energy Resources (via written proxy)
Ontario Power Generation, Inc. David Ramkalawan (via phone)
Sector 5 – Marketers, Brokers, and Aggregators
Consolidated Edison Company (proxy to Michael Forte)
of New York, Inc.
Long Island Power Authority (proxy to Anie Philip)
New York Power Authority (proxy to Randy Crissman)
Talen Energy Marketing, LLC Elizabeth Davis - Alternate (via phone)
Utility Services, Inc. Brian Evans-Mongeon
Sector 6 – State and Provincial Regulatory and/or Governmental Authorities
Long Island Power Authority (proxy to Anie Philip – via phone)
New York Power Authority (proxy to Randy Crissman)
New York State Department Ed Schrom
of Public Service
Sector 7 – Sub-Regional Reliability Councils, Customers, other Regional Entities and
Interested Entities
New York State Reliability Council, LLC Roger Clayton (via phone)
NPCC Staff
Sal Buffamante Assistant Vice President Audits and Risk
Assessment
Gerry Dunbar Manager of Reliability Criteria
Requirements
Phil Fedora Assistant Vice President, Reliability Services
Jessica Hala Manager, Finance and Accounting
Damase Hebert Compliance Attorney
Brian Hogue Information Systems & Security
Management
Andreas Klaube Engineer, Operations
Stan Kopman Assistant Vice President Compliance
Enforcement and Mitigation
Quoc Le Manager, System Planning and
Protection
Michael Lombardi Manager, System Studies
Neeraj Lal Senior Reliability Engineer
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 4
Scott Nied Manager, Operations and Planning Compliance
Audits
Andrey Oks Director of Operations Coordination
Lee Pedowicz Manager, Reliability Performance and Criteria
Assessment
Paul Roman Director, Operations Planning
Frantz Roc Manager, Information Technologies
Ralph Rufrano Manager, Events Analysis
Rafael Sahiholamal Senior Reliability Engineer
Guy Zito Assistant Vice President of Standards
Guests
Sean Bodkin (via phone) Dominion Resources Services, Inc.
Francois Brassard Hydro-Quebec TransEnergie
Simon Couture-Gagnon (via phone) Chair, SS-38 Load Modeling Working Group
Kevin DePugh Vice Chair, Task Force on System Studies
Farzad Farahmand Ontario Independent Electricity System
Operator
Mark Graham New York Power Authority
John Helme Chair, Task Force on Infrastructure Security
and Technology
Liana Hopkins New York Power Authority
Mohammed Hossain New York Power Authority
Hung Huynh Nova Scotia Power, Inc.
Humayun Kabir New York State Department of Public Service
Dean Latulipe (via phone) Chair, SS-38 Working Group
George Wegh Chair, Task Force on System Protection
Quorum Statement
Mr. Fedora indicated that a quorum had been achieved, by member attendance, proxy or
alternate designation. He also noted having received the following written proxy:
Sector 4 – Generator Owners Alan Schriver - NextEra Energy Resources
Antitrust Guidelines for NPCC Meetings
Mr. Fedora reviewed the NPCC Antitrust Guidelines in the Agenda package, and suggested
contacting NPCC Inc.’s Secretary, Ruta Skucas at (202) 530-6428 for further information.
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 5
President & CEO Report Mr. Fedora explained that Mr. Schwerdt was attending the FERC Reliability Technical
Conference; he explained that the following topics would be discussed: 2016 NERC State of Reliability Report; and
Identified Emerging Issues
o International Perspectives
o Resource Mix.
Details regarding the FERC Reliability Technical Conference Panel Sessions have been
provided in the RCC agenda package.
He then introduced Ms. Hala, who provided an overview of the 2017 Draft NPCC Business
Plan &Budget provided in the Agenda package.
She explained that for 2017, NPCC’s total budget and assessments are down by -0.3%. The
Criteria Services division budget decreased by -11.3% primarily related to the termination of
the defined benefit plan. In addition: NPCC is currently fully staffed and there are no additional FTE’s budgeted for 2016;
There has been no change in the Working Capital and Operating Reserve Policy since last
year; and,
The defined benefit pension plan was successfully terminated and fully paid out during 2015.
She showed the breakdown of the percentage of total resources by program area for the
Regional Entity division. Standards and Situation Awareness each represented 10% last year;
in 2017 Standards is down to 7% and Situation Awareness increased to 13% as a result of
reprioritization and reallocation of resources. Standards and IT each have one less FTE, and
Compliance and Situation Awareness are each up one FTE. The IT position moved to
Situational Awareness and Infrastructure Security (SAIS); the Standards position was moved
to Compliance. There were no changes in Criteria Services FTEs.
She noted that the assessment and reprioritization of staffing and resources is ongoing and
will continue through 2017; based on the responsibilities detailed in the business plan,
staffing and funding are assessed to be adequate, barring any unforeseen circumstances or
initiatives.
While the full impact of any special reliability studies to address potential resource adequacy
impacts related to the EPA’s Clean Power Plan are currently unknown, for 2017 NPCC is
budgeting one sub-regional U.S. only reliability study (estimated at $50,000) allocated to
U.S. only Balancing Authorities.
As in previous years, the Compliance Monitoring and Enforcement and Organization
Registration and Certification (CORC) Program costs were allocated to reflect the specific
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 6
compliance responsibilities within each of the Canadian provinces within NPCC. Within
Quebec these costs are funded directly by the regulator.
NPCC is fully aligned with ERO Enterprise Strategic Plan and Goals; she highlighted the
following primary 2017 focus areas of focus for the ERO: Reliability Standards are at a relative steady-state; emphasis for 2017 will be on enhanced
periodic reviews of existing standards and assessment of cost-effectiveness;
SAIS: continued focus on cyber and physical security issues;
CORC: Risk-focus initiated in 2015; efficiencies obtained by reducing the use of contract
auditors and enhancing ERO Enterprise-wide consistency; and,
Reliability Assessment and Performance Analysis is addressing both existing and emerging
risks with increased analytical sophistication.
The Working Capital and Operating Reserves Policy remains unchanged since last year: Operating Reserves requirement is a range between 8.33% and 25% (90 days) to provide
more stability in annual funding assessment.
the Working Capital requirement target level of 8.33% (30 days) of the annual budget.
projected RE Total Reserve balance at year end 2017: $3,069,085 (20.26% of total budget)
In response from a question from Mr. Henderson, Mr. Fedora explained that the referenced
sub-regional U.S. only reliability study was a place-keeper for the identification of possible
reliability impacts from the proposed EPA CPP State Implementation Plans and/or other
related State initiatives. These could include (but not limited to) assessment of the NERC
identified Essential Reliability Services of voltage, ramping and frequency performance, for
example.
Chair Report Meeting Agenda
Mr. Schiavone referred the RCC to the Agenda provided in the Agenda package.
The RCC then approved the Agenda.
RCC Scope
Mr. Schiavone reported that the changes received for the RCC included minor editorial
changes and the following clarification to Responsibility No. 12:
12. Revisions to NPCC Regional Guidelines (‘B’ Documents) that have not been incorporated into a
Directory and retirement of those ‘B’ Documents which have had their guideline principles
incorporated into a Reliability Directory.
He said the Scope would be sent to the NPCC Board following the RCC’s recommendation
for their approval of the changes.
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 7
Approval of the “Addendum to the 2015 NPCC Overall Transmission Reliability
Assessment: Sensitivity Study on the Impact of Distributed Generation”
Mr. Schiavone reported that by electronic ballot ending 5:00 pm on Thursday, March 31,
2016, the RCC approved the “Addendum to the 2015 NPCC Overall Transmission Reliability
Assessment: Sensitivity Study on the Impact of Distributed Generation.”
The RCC’s quorum (two-thirds of 43) was satisfied by 38 submitted votes; approval was
achieved with 37 votes for, with one abstention.
Consent Agenda The Reliability Coordinating Committee unanimously approved the following Consent
Agenda items (written proxy in favor).
March 2, 2016 Meeting Minutes
The Draft-For-Approval Minutes of the March 2, 2016 Reliability Coordinating Committee
were approved, as provided in the Agenda package, with the corrections noted.
RCC Membership Changes
The following changes to RCC Membership were approved:
Sector 1, Transmission Owners
Mr. Brad Bentley has left Eversource Energy. No replacement has been named.
Mr. Jonathan Appelbaum has left the United Illuminating Company. Ms. Silvia Valerio of
the United Illuminating Company succeeds Mr. Jonathan Appelbaum as the alternate.
Sector 2, Reliability Coordinators
Mr. Franҫois Brassard of Hydro-Québec TransÉnergie succeeds Mr. Pierre Paquet (formerly
of Hydro-Québec TransÉnergie) as the member.
Mr. Stéphane Desbiens succeeds Ms. Caroline Dupuis as the alternate, both of Hydro-Québec
TransÉnergie.
Sector 4, Generator Owners
Mr. Sean Bodkin succeeds Ms. Connie Lowe as the member, both of Dominion Resources
Services, Inc.
Ms. Connie Lowe succeeds Mr. Lou Oberski as the alternate, both of Dominion Resources
Services, Inc.
Sector 6 – State and Provincial Regulatory and/or Governmental Authorities
Mr. Humayun Kabir succeeds Mr. Richard Quimby as the alternate, both of the New York
State Department of Public Service.
Task Force Roster Changes
The following changes to Task Force and Working Group memberships were approved:
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 8
Task Force on Coordination of Planning
Mr. Robert Russo of Eversource Energy as the member, succeeding Mr. Brad Bentley, who
has left the company.
Task Force on System Studies
Mr. Vincent Fihey succeeds Mr. Sylvain Bastien as the member, both of Hydro-Québec
TransÉnergie.
Task Force on Infrastructure Security and Technology
Mr. Victor Costanza of the New York Power Authority to serve as the alternate.
IST-2 Telecommunications Working Group
Mr. Troy Wells of the New Brunswick Power Corporation to serve as the member.
SP-7 Working Group on Protection System Misoperation Review
Mr. Anthony Napikoski of the United Illuminating Company to serve as the member.
Mr. Peter Larochelle of NextEra Energy Resources to serve as the member.
SP-9 (Ad Hoc) Working Group on Telecommunication Circuits Used for Teleprotection
and Remedial Action Schemes
Mr. David Lambert from Hydro-Québec TranÉnergie to serve as the Chairman.
Mr. Delavar Khomarlou from Hydro One Networks to serve as the member.
Mr. Nghia (Mike) H. Lac from National Grid USA to serve as the member.
Mr. Martine Lalancette from Hydro-Québec TransÉnergie to serve as the member.
Mr. Daniel M. Markis from National Grid USA to serve as the member.
Mr. Frank Parker from the New York Power Authority to serve as the member.
Mr. Jean-Luc Robichaud from Hydro-Québec TransÉnergie to serve as the member.
Mr. Chuck Victor from Nova Scotia Power Inc. to serve as the member.
SS-38 Working Group on Inter-Area Dynamic Analysis
Mr. Rudi Vega succeeds Mr. Kannan Sreenivasachar as the member, both of ISO-New
England.
Mr. Alexander Rost succeeds Mr. Anish Joshi and Mr. Shounak Abhyankar as alternates,
all of ISO-New England.
RCC Scope
Approved as provided in the Agenda package.
Revised New York A-10 list
Approved as provided in the Agenda package.
NPCC Regional Reliability Plan
Approved as provided in the Agenda package.
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 9
Task Force on Coordination of Operation Scope and Terms of Reference
Approved as provided in the Agenda package.
Task Force on Infrastructure Security and Technology Scope
Approved as provided in the Agenda package.
2015 Quebec Area Interim Transmission Review
Approved as provided in the Agenda package.
2015 Ontario Area Intermediate Transmission Review
Approved as provided in the Agenda package.
TransEnergie-Chateauguay BPS Risk Mitigation Extension Request Retirement of NPCC
Guideline B-27 – “Regional Critical Asset Identification”
Approved as provided in the Agenda package.
Reliability Coordinating Committee Actions
NYPA – Alcoa Type 1 Special Protection System (SPS) Removal (SPS #47)
Mr. Graham presented the material included in the Agenda package regarding the New York
Power Authority (NYPA) describing the proposed removal of the St. Lawrence/Alcoa 115
kV SPS (Type I SPS #47).
In 1991 NYPA Operations Planning conducted a study and determined that the SPS was no
longer needed and shortly after the study disabled the scheme. The wiring for the scheme
was left in place in case the scheme would be needed in the future. Since that time the Alcoa
SPS scheme was never required or implemented.
In accordance with the NPCC Regional Reliability Reference Directory No.7, “Special
Protection Systems,” the Task Force on System Studies reviewed the proposed removal of
the St. Lawrence/Alcoa 115 kV SPS and concurred with the removal.
The Task Force on Coordination of Planning reviewed this SPS removal and recommended
RCC approval of the retirement of this Type I SPS.
The RCC then unanimously approved the proposed removal of the St. Lawrence/Alcoa
115 kV SPS Type I SPS #47 (written proxy in favor).
NYPA – Type I Special Protection System (SPS) - Niagara Generator Rejection
Modification (SPS#50)
Mr. Hossain presented the materials included in the Agenda package regarding a proposed
modification to the Niagara Generation Rejection SPS (Type I SPS #50).
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 10
The Niagara 230 kV Generation Rejection System Special Protection System (NGRS SPS
#50) was originally installed to protect against a variety of Western New York and Eastern
Ontario contingencies under dynamic and steady-state operating conditions. System
improvements over the past 25 years have alleviated the majority of these conditions and the
NGRS SPS is rarely activated.
Thermal analysis showed no post-contingent thermal overloads for all studied system
configurations. Similarly, stability analysis showed stable system performance for all stuck
breaker faults. NYPA, therefore, recommended the removal of the “Niagara 345 kV breaker
failure” as an initiating incident from the NPCC SPS list.
Considering to the recommendations of the Task Force on System Studies, the Task Force on
System Protection and the Task Force on Coordination of Operation provided in the Agenda
package, the Task Force on Coordination of Planning reviewed this SPS modification for
conformance with NPCC Regional Reliability Reference Directory No. 1 “Design and
Operation of the Bulk Power System”, and recommended RCC for approval of this modified
Type I SPS.
The RCC then unanimously approved the proposed modification to remove 345 kV
breaker failure as an initiating event for the Niagara Generation Rejection SPS #50
(written proxy in favor).
2015 New York Area Comprehensive Area Transmission Review
Mr. DePugh presented the 2015 New York Comprehensive Area Transmission Review report
provided in the agenda package.
The 2015 New York Comprehensive Area Transmission Review (the ‘Review’) provides a
five-year-ahead reliability assessment of the Independent Electricity System Operator
controlled grid and its conformance to the NPCC Design and Operation of the Bulk Power
System (Directory No.1). The forecast and conclusions made in the Review are based on the
integrated results from expected changes in load, transmission and generation up to summer
2020.
The Task Force on System Studies conducted a review and approved the Review.
The Task Force on Coordination of Planning (TFCP) agreed that the Bulk Power System in
New York, as planned through the 2020, will remain in conformance with the NPCC
Directory No. 1 criteria and the NERC Transmission Planning standards TPL-001 to TPL-
004. The Review was conducted in conformance with the TPL standards currently in effect
and the Bulk Electric System definition. The TFCP recommended RCC approval of the 2015
New York Comprehensive Area Transmission.
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 11
Mr. Presume asked about the impact of loop flows the New York to New England interface
limits. Mr. DePugh explained that the loop flows modeled were in New England going from
north to south; some of that flow came through New York, and affected the import/export
limits.
Mr. Kula asked if transfers on the western end of the state (from Ontario to New York) are
limited by New York transmission internal restrictions. Mr. DePugh responded that in order
to bring power from the western area to the rest of the state, internal New York constraints
are limiting, unless the western New York generation is correspondingly reduced.
He further explained that generation retirements on the New York 230 kV system, coupled
with load growth and loop flows have made the 230 kV system more constraining than the
345 kV system. Mr. Conroy mentioned that the New York Public Service Commission
(PSC) has identified a public policy need to increase transfer capability west to east; multiple
projects have been proposed that the New York ISO is evaluating. Mr. Smith added that the
New York ISO recently issued their final Viability and Sufficiency Assessment that evaluated
various projects submitted for Western New York through their public policy process (Order
1000); the New York Public Service Commission will be reviewing those projects; a
transmission project will likely be selected next year to address those issues.
The RCC then unanimously approved the 2015 New York Comprehensive Area
Transmission (written proxy in favor).
Nova Scotia Power Inc. - Maritime Link Type I Special Protection System (SPS)
Modification (SPS #119)
Mr. Huynh presented the materials included in the Agenda package regarding Nova Scotia
Power Inc.’s proposed modification to the Type I SPS #119 - "NS 345 kV SPS."
In Nova Scotia, major generation is located in the eastern part of the province while the load
center is located in the central part of the province. The transmission corridor from east to
west consists of 345kV, 230 kV and 138 kV lines. Loss of a 345 kV line in the corridor
requires generation runback in the east utilizing the Type I SPS No. 119, “NS 345 kV SPS.”
The present generation rejection target for SPS# 119 consists of one or two thermal units at
Lingan and Point Aconi. Lingan has four units with net operating of 153 MW each and Point
Aconi has one unit with net operating of 171 MW. By 2017, Nova Scotia will be connected
to the province of Newfoundland via a new VSC HVDC link in a bi-polar configuration.
The Maritime Link will have a 500 MW capability.
This HVDC link provides Nova Scotia with the opportunity to select the HVDC for
generation runback target instead of tripping thermal plants at Lingan or Point Aconi when
the HVDC is in-service. The response characteristics and versatility of HVDC runback are
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 12
superior to tripping thermal plants. The HVDC runback by the SPS #119 will be limited to
330 MW net, which is equivalent to the existing generation rejection amount.
Considering to the recommendations of the Task Force on System Studies, the Task Force on
System Protection and the Task Force on Coordination of Operation (provided in the Agenda
package) the Task Force on Coordination of Planning reviewed this SPS modification for
conformance with NPCC Regional Reliability Reference Directory No. 1 “Design and
Operation of the Bulk Power System,” and recommended RCC for approval of this modified
Type I SPS #119.
The RCC then unanimously approved the proposed modification to the Type I SPS#
119 - "NS 345 kV SPS" (written proxy in favor).
SS-37 Working Group – Geo-magnetically Induced Current (GIC) Modeling White
Paper
Mr. Lal explained that the SS-37 Working Group GIC Modeling Data Collection White
Paper provides general information and guidance to aid in the collection of GIC data for
required for facilities that include power transformer(s) with a high side, wye grounded
winding with terminal voltage greater than 200 kV. Siemens PSS®E provides a template to
create a GIC data file; the template is divided into the following sections: Substation (and Bus) Data;
Transformer Data;
Bus Fixed Shunt Data;
Branch Data; and,
Earth Model Data.
The RCC then unanimously approved the GIC Modeling Data Collection White Paper
(written proxy in favor).
Status Reports Mr. Schiavone referred the RCC to the materials provided in the Agenda package; the RCC
discussed the following Agenda items:
NPCC Regional Standards Committee Report
Mr. Zito referred the RCC to the Regional Standards Committee report provided in the
Agenda package, and highlighted the following activities: the current activity to “grade” 24 Standards (and their corresponding Requirements) with
respect to their quality and content;
revision of NPCC Regional Standard PRC-006- NPCC-1, Automatic Underfrequency Load
Shedding against the continent-wide Standard;
revision of an existing regional variance (Quebec) appearing in the NERC PRC-006-2
Automatic Underfrequency Load Shedding Standard;
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 13
Filing for the retirement of the NPCC Regional Standard for Disturbance Monitoring (PRC-
002-NPCC-1). FERC approval of the continent wide NERC PRC-002-2 Disturbance
Monitoring and Reporting Requirements Standard and its enforceable date of July 1, 2016
renders the Regional Standard unnecessary; and,
Task Force on Coordination of Operation’s technical comparison between the criteria in
Directory No. 9 and Directory No. 10 against the NERC requirements in MOD-025-2
Verification and Data Reporting of Generator Real and Reactive Power Capability and
Synchronous Condenser Reactive Power Capability.
NPCC Compliance Committee
Mr. Kopman referred the RCC to the Compliance and Enforcement materials provided in the
Agenda package and highlighted the following three items: development of a feedback mechanism to provide recommendations to improve Reliability
Standards based on CMEP implementation and review of events analysis;
outreach seminars designed to present a comprehensive analysis to registered entities related
to the top violated NERC Reliability Standards in NPCC. These seminars provide an in-
depth description of root-cause analysis, factors contributing to violations, lessons learned
and risk assessment training. The first seminar covered CIP-007, PRC-005 and CIP-004;
and,
the Spring NPCC Standards and Compliance Workshop, and plans for the November
Workshop concentrating on Standards that become enforceable in 2016.
Mr. Buffamante then highlighted the following activities provided in the Agenda package: CIP version 5 outreach activities;
on track to complete an Inherent Risk Assessment for every entity registered with NPCC by
the end of the year; and,
the 2016 NPCC Physical Security outreach that analyzing gaps in the Transmission Owner’s
and Transmission Operator’s Physical Security.
Task Force on System Protection SP-7 Working Group Review of Protection Systems Misoperations
Mr. Wegh summarized the activities of the SP-7 Working Group provided in the Agenda
package. as completed through the Fourth Quarter of 2015. He reported that the combined
misoperations caused by Incorrect Setting/Logic/Design Errors and by Relay
Failures/Malfunctions ranges between 40-50% of all the misoperations. By relay technology,
the majority of these are microprocessor-based relays. This is expected as the installed base
of BES relays has grown and changed over time reflecting an increasing population of
microprocessor-based technology.
The SP-7 Working Group also reviewed submittals for Special Protection System (SPS)
operations and misoperations for the Fourth Quarter of 2015 as requested by NERC using the
new SPS reporting Template. There was no reported SPS misoperation during this Quarter.
The SP-7 working Group will be reviewing the First Quarter 2016 Protection System and
SPS Misoperations data and will be reporting the data to NERC by July 15, 2016.
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 14
In response to a question from Mr. Mongeon, Mr. Le described NPCC’s involvement in the
development of the NERC Misoperation Information Data Analysis System (MIDAS); Mr.
Sahiholamal described how the MIDAS process will be implemented in NPCC.
SP-9 Working Group on Telecommunication Circuits Used for Teleprotection and
Remedial Action Schemes
Mr. Wegh reported that the SP-9 Working Group is planning its first meeting in June 2016 to
start work on the development of a new NPCC guideline for telecommunication circuits used
for teleprotection and remedial action schemes.
Status of NPCC Directory No. 11 “Disturbance Monitoring Equipment Criteria”
Mr. Wegh stated that the new NPCC Directory No. 11 was developed following the approval
of the NERC standard PRC-002-02 “Disturbance Monitoring and Reporting Requirements”
and the determination by NPCC that PRC-002-NPCC-1 could be retired. The NPCC
Directory No. 11 was developed to address identified differences in Disturbance Monitoring
Equipment coverage requirements between PRC-002-2 and PRC-002-NPCC-1.
He explained that the draft NPCC Directory No. 11 provided in the Agenda package has been
posted in the NPCC Open Process for comments through May 29, 2016. All comments
received will be addressed by Task Force on System Protection at their July meeting. If there
are no significant comments that require another Open Process posting, the draft new NPCC
Directory No. 11 will be submitted for approval at the September 2016 RCC meeting.
Task Force on Infrastructure Security & Technology
Mr. Helme reviewed the Cyber and Physical Security information provided in the Agenda
package.
Task Force on System Studies SS-38 Working Group - Load Modeling Working Group (LMWG)
Mr. Couture-Gagnon summarized the activities of the LMWG provided in the Agenda
package. He noted that representatives on the LMWG were also actively participating on the
NERC Load Modeling Task Force. In addition, LMWG representatives continue to provide
support to Transmission Planners and Planning Coordinators regarding the use of dynamic
load models in NERC Standard TLP-001-4.
SS-38 Working Group
Mr. Le summarized the SS-38 Working Group activities provided in the Agenda package
regarding the assessment of the impact of Distributed Generation under other stressed transfer
scenarios in several areas of the NPCC.
As part of emerging reliability risk and the reliability assessments of distributed generation,
he added that the SS-38 WG will also be conducting additional studies this year to measure
the static & dynamic reactive capability on the transmission system if time permits, and to
determine any potential reliability risks resulting from lower system inertia. This effort is
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 15
expected to be completed this fall and a report will be provided at the December RCC
meeting.
Task Force on Coordination of Planning (TFCP) Review of NPCC Document A-10
Mr. Smith summarized the review of NPCC Document A-10 “Classification of Bulk Power
System Elements” currently being undertaken by the TFCP; initial discussions have included:
identification of differences between NPCC BPS and NERC BES applicability;
understanding how the A-10 methodology is applied in each NPCC Area;
reviewing the current list of BPS facilities; and,
reviewing each Area’s interpretation of “significant adverse impact outside of the
local area.”
He explained that members of the newly constituted CP-11 Working Group, with input from
the other Task Forces, plan to develop a detailed scope of this review over its upcoming
meetings. Although not procedurally required, the TFCP plans to bring the CP-11 Working
Group Scope of Work to the RCC for approval before starting work.
2016-2017 Work Plan Progress
Mr. Schiavone referred the RCC to the materials provided in the Agenda package.
NPCC Reliability Assessment Program (NRAP) Highlights Report
Mr. Fedora reported at the NRAP Highlights Report was updated as of May 27, 2016 and has
been posted on the NPCC website.
NERC Agenda Items Operating Committee
Mr. Rufrano reviewed the following Draft June 2016 NERC Operating Committee Agenda
items for approval: the revised PJM RTO Reliability Plan;
archiving the NERC Backup Control Center – A Reference Document;
the Dynamic Transfer Reference Document (Version 3); and,
the Time Monitoring Reference Document (Version 4).
He also mentioned that the Functional Model Advisory Group is in the process of revising
the NERC Functional Model, “to ensure the model correctly reflects the industry today and
evaluates and incorporates new and emergent reliability related tasks.”
Planning Committee
Mr. Fedora reviewed the following approval items on the Draft March Planning Committee
Agenda: the 2016 Summer Reliability Assessment;
the Reliability Guideline for Initial Review: Reactive Power Planning and Operations;
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 16
the Reliability Guideline for Initial Review: Power Plant Model Verification using PMUs;
and,
Phase Angle Monitoring Technical Report.
He also highlighted the following informational items: topics for the next NERC Short-Term Special Assessment;
the Reliability Assessment Subcommittee 2016 Long Term Reliability Assessment schedule,
the Probabilistic Assessment Improvement Task Force recommendations;
status update for the Essential Reliability Services Working Group & Distributed Energy
Resources Task Force activities; and,
revisions to the NERC Functional Model.
Critical Infrastructure Protection Committee
Mr. Hogue highlighted the following items on the Draft June 2016 NERC Critical
Infrastructure Committee Agenda; RedTeam Security video (link in the E-ISAC presentation);
Remote Access Study update;
Functional Model Advisory Group update; and,
EMP-Rated Control Room Rebuild.
Informational Items Mr. Schiavone referred the RCC to the materials included in the Agenda package. The
following Informational Items were discussed at the meeting:
Event Analysis Program Status
Mr. Rufrano provided an overview status of the Event Analysis Program provided in the
Agenda package.
NERC/FERC Data Requests
Mr. Fedora noted that the NERC Synchronized Measurements Subcommittee (SMS)
requested Reliability Coordinators provide synchrophasor data from Phasor Measurement
Units (PMUs) or other Dynamic Disturbance Recorders to assess the oscillation behavior of
the Eastern Interconnection for selected events. This is a test Section 800 data request for
PMU data to be used for a Special Reliability Assessment on Oscillation Analysis to be
performed by NERC staff and the NERC SMS. Data was requested to be submitted
electronically by May 10, 2016. NERC indicated it would treat this data as Confidential
Information pursuant with its Rules of Procedure, Section 1500.
Eastern Interconnection Reliability Assessment Group Activities
Mr. Roman reviewed the Eastern Interconnection Reliability Assessment Group Activities
provided in the Agenda package. He noted that the six Eastern Interconnection Regions now
have a signed Agreement with NERC to be the Designee under Requirement 4 of MOD-032-
NORTHEAST POWER COORDINATING COUNCIL
Reliability Coordinating Committee Minutes
June 1, 2016
June 1, 2016 17
1 through ERAG, and will follow the NERC requirements for the Designee to compile and
produce the annual sets of Eastern Interconnection power flow and dynamic simulation base
cases. Mr. Lombardi added that the agreement was discussed at the Task Force and System
Studies and the SS-37 Working Group; ISO-New England agreed to be the Data Coordinator
for the NPCC Planning Coordinators.
Other Matters Mr. Clayton asked if the new Type III NYPA - Marcy-South Series Compensation SPS was
temporary. Mr. DePugh said the SPS would be considered temporary until a more
permanent solution is found. Mr. Smith added that the NYPA proposed the SPS to eliminate
the possibility of Sub Synchronous Resonance at the Fitzpatrick plant; that plant has recently
announced its intent to deactivitate. If the plant deactiviates, there would be no need for this
SPS; the SPS would be retired at that point.
With no other matters to consider, the RCC meeting was adjourned.
Next RCC Meeting Date Location
Wednesday, September 7, 2016
Toronto Marriott Downtown Eaton Centre
Hotel
Distribution of Approved Minutes
NPCC Full & General Member Representatives and Alternates
Members, NPCC Board of Directors
Members, NPCC Reliability Coordinating Committee
Members, NPCC Public Information Committee
Members, NPCC Compliance Committee
Members, NPCC Regional Standards Committee
Members, NPCC Task Force on Coordination of Operation
Members, NPCC Task Force on Coordination of Planning
Members, NPCC Task Force on Infrastructure Security and Technology
Members, NPCC Task Force on System Protection
Members, NPCC Task Force on System Studies
NPCC Officers
NPCC Staff
Ruta Skucas, Esq.
and
Federal Energy Regulatory Commission – Mike Bardee, David O’Connor, Juan Villar
La Régie de L’Énergie – Daniel Soulier
Ontario Energy Board – Peter Fraser
United States Department of Energy – David Meyer
New Brunswick Department of Energy and Mines – David Sallows
Nova Scotia Utility & Review Board – S. Bruce Outhouse, Q.C.