appraisal- expansion of projects: 1. basic information of...
TRANSCRIPT
SEAC, Gujarat Page 1 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
Appraisal- Expansion of Projects:
1. Basic Information of the Project:
i Name & Address of the Project site (Complete details with plot no./Survey no., Landmark etc. )
M/s. Heubach Colour Pvt. Ltd. (Unit-1) Plot No. 9002-9010, GIDC Estate, Ankleshwar, Dist:-Bharuch, Gujarat.
ii Name of the Applicant Mr. D. K. Rana iii Address for
correspondence 102, Nathdwara, GIDC Ankleshwar-393002.
iv Contact no. and e-mail ID of the Applicant
Mo. no. : +919879533460 e-Mail: [email protected]
v Aerial distance of nearest Habitat (KM)
3 KM
vi Longitude & Latitude of the Project Site: (4 corners of the site)
Direction Corners Latitude Longitude
NW 1st 21°37'49.16"N 73° 2'44.97"E
NE 2nd 21°37'48.36"N 73° 2'57.03"E
East 3rd 21°37'40.69"N 73° 1'56.02"E
West 4th 21°37'40.99"N 73° 1'49.58"E
West 5th 21°37'34.23"N 73° 1'48.96"E
SW 6th 21°37'34.69"N 73° 1'43.83"E
vii Total cost of Proposed
Project
(Rs. in Crores):
Existing: 409.40 Proposed:216 Total: 625.40
viii
(1) Capital cost for EMS (Environmental Management System): 10.11 Crores
(2) Recurring cost towards the environmental protection measures: 24.12
Crores per Annum.
ix Total Plot area ( sq. meter)
Existing: 110385.40 sq. meter Proposed: 0 Total: 110385.40 sq. meter
x Green belt area,/Tree Plantation area ( sq. meter)
Existing:23633 Proposed: 9483 Total:33116
xi Category as per the Schedule to the EIA Notification 2006 i.e. 1(d), 2(b), 5(f) etc.
5(f)
xii Applicability of General Conditions of EIA Notification 2006: i.e. Ensure that
I. Protected areas notified under the Wildlife (Protection)
Not Applicable
SEAC, Gujarat Page 2 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
Act, 1972; II. CEPI areas
III. Eco-sensitive areas and
IV. Inter-state boundaries and international boundaries; are not located within 5 km or 10 km (as the case may be) area from the boundary of the proposed site.
2. Online application proposal no. : SIA/GJ/IND2/18607/2017
3. Date of application for EC: 14th September, 2017
4. Date of SEAC meeting for TOR: 30th March 2017
5. Date of TOR issued by SEIAA: 1st May 2017
6. Date of Public Hearing (If applicable): Not Applicable
7. Date of presentation for Appraisal: ---
8. Project status: Expansion
9. Product profile:
Sr. No.
Name of the Products
CAS no. Quantity MT/Month
End-use of product Existing Proposed Total
1 Organic Pigments -- 740 368 1108 Ink,
Paint,
Plastic,
Paint,
Refinery
&
Polymer
2 Inorganic
Chemicals
-- 900 -308 592
3 Pigment
Preparation
-- 900 0 900
4 Inorganic Stabilizer -- 0 100 100 Polymer
Total 2540 160 2700.00
5 Electricity* --
6.72 MW 5.9 MW 12.62
MW
* Unit will install 5.9 MW captive power plant. Unit will supply partial power to neighbouring
industry Heubach Colour Pvt. Ltd. (Unit -3).
LIST OF PRODUCTS AS PER TYPICAL PRODUCT MIX
Sr. No.
Name of the Products
CI/CAS no. Quantity MT/Month
End-use of product
Existing Proposed Total 1. CPC Green 74260/1328-
53-6 250 275 525 Paint, Ink &
Plastic
SEAC, Gujarat Page 3 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
2. Beta Blue 74160/147-14-8
320 113 333
3. Crude Blue 74160/147-14-8
100
4. Alpha Blue 74160/147-14-8
100 0 100
5. Dispersion/ Flushes/ Pigments Preparations
(for paints, Inks, Plastics)
-- 900 0 900
6. Aluminium Hydroxide
21645-51-2 400 192 292 Pharmaceucal & chemical
7. Hydrotalcite 12304-65-3 250 Polymer
8. Boehmite 1318-23-6 50 Paint, Refinery & Polymer
9. Crude Pigment Blue- 60(Vat Blue 4) / Pigment Blue- 60 Finished
69800/81-77-6 50 0 50 Paint, Ink & Plastic
10. Inorganic Stabilizer
NA 0 100 100 Polymer
11. Polycyclic Pigment
20 -20 0
12 Alum Solution 500 -500 0
The project falls under Category B of project activity 5(f) as per the schedule of EIA Notification 2006.
10. Product wise Raw material consumption:
Sr.
No.
Name of
Product
Name of Raw
Material
CAS No. Existing
Quantity
in
MT/Mon
th
Proposed
Quantity
in
MT/Month
Quantity
After
Expansio
n in
MT/Month
1. CPC Blue Phthalic Anhydride 85-44-9 10 90 100
Urea 57-13-6 11 99 110
Cuprous Chloride 7758-89-6 2 18 20
Ammonium
Molybdate
12027-67-7 0.03 0.27 0.3
Alkyl
Benzene(Solvent)
68855-24-3 0.35 3.15 3.5
Spent Sulphuric
Acid (20 %)
7664-93-9 19 171 190
Total 42.38 381.42 423.8
SEAC, Gujarat Page 4 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
Sr.
No.
Name of
Product
Name of Raw
Material
CAS No. Existing
Quantity
in
MT/Mon
th
Proposed
Quantity
in
MT/Month
Quantity
After
Expansio
n in
MT/Month
2. ALFA BLUE Phthalic Anhydride 85-44-9 90 0 90
Urea 57-13-6 96 0 96
Cuprous Chloride 7758-89-6 20 0 20
Ammonium
Molybdate
12027-67-7 0.2 0 0.2
Alkylbenzene(Solv
ent)
68855-24-3 3 0 3
Spent Sulphuric
Acid (20 %)
7664-93-9 170 0 170
Sulphuric Acid 7664-93-9 484 0 484
Additive-1 NA 3 0 3
Caustic soda Lye
(100%)
1310-73-2 1 0 1
Additive-2 NA 1.3 0 1.3
Total 880.2 0 880.2
3. BETA BLUE Phthalic Anhydride 85-44-9 322.4 23.92 346.32
Urea 57-13-6 334.8 24.84 359.64
Cuprous Chloride 7758-89-6 55.8 4.14 59.94
Ammonium
Molybdate
12027-67-7 0.93 0.069 0.999
Spent Sulphuric
Acid (20 %)
7664-93-9 682 50.6 732.6
Alkylbenzene(Solv
ent)
68855-24-3 9.3 0.69 9.99
Additive-1 NA 3.1 0.23 3.33
Caustic soda Lye
(100%)
1310-73-2 24.8 1.84 26.64
Additive-2 NA 6.2 0.46 6.66
Additive-3 NA 12.4 0.92 13.32
Isobutanol 78-83-1 43.4 3.22 46.62
Total 1495.13 110.929 1606.059
4. CPC Green Phthalic Anhydride 85-44-9 150 165 315
Urea 57-13-6 150 165 315
Cuprous Chloride 7758-89-6 25 27.5 52.5
Ammonium
Molybdate
12027-67-7 0.25 0.275 0.525
Alkyl
Benzene(Solvent)
68855-24-3 5 5.5 10.5
Spent Sulphuric
Acid (20 %)
7664-93-9 275 302.5 577.5
Aluminium Chloride 7446-70-0 450 495 945
SEAC, Gujarat Page 5 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
Sr.
No.
Name of
Product
Name of Raw
Material
CAS No. Existing
Quantity
in
MT/Mon
th
Proposed
Quantity
in
MT/Month
Quantity
After
Expansio
n in
MT/Month
Cupric Chloride 7447-39-4 10 11 21
Sodium Chloride 7647-14-5 75 82.5 157.5
Chlorine/Bromine
7782-50-5 /
7726-95-6
300 330 630
Xylene/Mono
Chlorobenzene
95-47-6 /
108-90-7
25 27.5 52.5
Additives NA 7.5 8.25 15.75
Caustic Soda Lye
(100%)
1310-73-2 100 110 210
Total 1572.75 1730.03 3302.78
5. Crude Blue-
60
Amino
Anthraquinone
82-45-1 51 0 51
Dimethyl-2-
imidazolidinone (
Solvent)
80-73-9 8.5 0 8.5
Potassium
Hydroxide
1310-58-3 19 0 19
Total 78.5 0 78.5
6. Pigment
Blue-60
Amino
Anthraquinone
82-45-1
51 0 51
Dimethyl-2-
imidazolidinone (
Solvent)
80-73-9
8.5 0 8.5
Potassium
Hydroxide (100%)
1310-58-3
19 0 19
Sodium dithionite 7775-14-6 35 0 35
Sodium Hydroxide 1310-73-2 85 0 85
Sulphuric Acid 7664-93-9 502.5 0 502.5
Additive-1 NA 5 0 5
Nitrobenzene 98-95-3 1 0 1
Sodium sulphate 7757-82-6 2 0 2
Sodium
bicarbonate
144-55-8
5 0 5
Total 714 0 714
7. Solid
Dispersions
-I
Pigment press-
cake
NA
291 0 291
Resin NA 145 0 145
Additive NA 5 0 5
Total 441 0 441
8. Solid
Dispersions
Pigment NA 45 0 45
Polymer NA 90 0 90
SEAC, Gujarat Page 6 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
Sr.
No.
Name of
Product
Name of Raw
Material
CAS No. Existing
Quantity
in
MT/Mon
th
Proposed
Quantity
in
MT/Month
Quantity
After
Expansio
n in
MT/Month
–II Wax NA 13.5 0 13.5
Additive NA 1.5 0 1.5
Total 150 0 150
9. Solid
Dispersions
-I
Pigment NA 75 0 75
Polymer/wax NA 67.5 0 67.5
Additive NA 7.5 0 7.5
Total 150 0 150
10. Liquid
Dispersion
Pigments NA 90 0 90
Additives NA 15 0 15
Surfactants NA 45 0 45
Filler NA 6 0 6
Biocide NA 3 0 3
Water 7732-18-5 141 0 141
Total 300 0 300
11. Aluminium
Hydroxide
Aluminium Chloride
Soln. from CPC
green plant
7446-70-0 2831.4 1344.2 4175.6
Soda ash solution
20 % /Soda ash
Powder
497-19-8 1782 846 2628
Sodium Sulphide 1313-82-2
11.88 5.64 17.52
Sodium Hydroxide 1310-73-2 3.96 1.88 5.84
Total 4629.24 2197.72 6826.96
12. Hydrotalcite Caustic soda Lye
(100 %)
1310-73-2 110.88 54.12 165
Aluminium
Hydroxide Press
cake
21645-51-2
221.76 108.24 330
Magnesium
Chloride
7786-30-3 403.2 196.8 600
Additive NA 6.72 3.28 10
Alkaline Solution 1310-73-2 840 410 1250
Total 1582.56 772.44 2355
13. Boehmite Aluminium
Hydroxide Press
cake
21645-51-2 136 64 200
Total 136 64 200
14. Inorganic
Stabilizer
Hydrotelsite 12304-65-3 0 50 50
Fatty acid 57-11-4 0 30 30
Filler NA 0 15 15
Additive NA 0 5 5
SEAC, Gujarat Page 7 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
Sr.
No.
Name of
Product
Name of Raw
Material
CAS No. Existing
Quantity
in
MT/Mon
th
Proposed
Quantity
in
MT/Month
Quantity
After
Expansio
n in
MT/Month
Anti-oxidant NA 0.0 5 5
Total 0 105 105
11. Compliance status of the existing project:
Sr. no.
Particulars Brief Information/Details Remarks
1 Earlier EC details No earlier EC Unit got NOC 2 Compliance of EC Not applicable -- 3 Status of inspection by RO-
MoEFCC, Bhopal. Not applicable --
4 Status of submission of half yearly return to concern authorities.
Not applicable --
5 Compliance of existing CC&A Given Below -- 6 Legal actions/Closure
directions/SCN etc. issued by GPCB.
Attached as Annexure in EIA report
--
7 Any Public Complaints No -- 8 Is there any litigation pending
before any court of Law against the Project ?
No --
12. Water, Air and Hazardous waste management:
Sr. no.
Particulars Details
A Water
i
Source of Water Supply (GIDC, Bore well, Surface water etc...)
GIDC
Status of permission from the concern authority. Granted
ii
Water consumption (KL/day)
Sr.
No.
Particular Water Consumption in KL/Day
Quantity as
per CCA-
AWH – 73997
in KLD
Proposed Quantity
in KLD
Total Quantity After
Expansion in KLD
Fresh Recycled Fresh Recycled
1. Domestic 125 75 0 200 0
2. Industrial
a) Process 2730 -317 1349 2413 1349
b) Washing
SEAC, Gujarat Page 8 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
*Partially steam will be consumed in Heubach Colour Pvt. Ltd. (Unit 3) and condensate will be return back in Heubach Colour Pvt. Ltd. (Unit 1).
c) Boiler 200 900 00 1100 00
d) Cooling 200 186 264 386 264
e) Gardening 100 -100 20 00 20
Total
(Domestic +
Industries)
3355 744 1436 4099 1633
iii
Waste water generation (KL/day)
Sr.
No.
Section Waste Water Generation
Existing
KL/Day
Proposed
KL/Day
Total
KL/Day
1 Domestic 125 55 180*
2 Industrial
2.1 Process & Washing 2337 1615 3952
2.2 Boiler 100 0 100
2.3 Cooling 100 0 100
2.4 Gardening 0 0 0
2.5 Other 0 0 0
Total (Industrial) 2537 1615 4152
Total
(Industrial + domestic)
2662 1670 4332
iv Treatment facility with capacity (ETP, CETP, MEE, STP etc).
ETP-4100 KLD FETP: 2662 KLD RO: 2246 & 200 KLD
v Mode of Disposal & Final meeting point
Domestic: STP treatment & reuse Industrial: ETP treatment, partially to NCT (FETP) and partially RO plant. RO reject to NCT.
vi Reuse/Recycle details (KL/day) 1634 KLD vii B Air [Existing & Proposed] i Flue gas emission details
No. of Boilers/TFH/Furnaces/DG sets etc. with capacities viz. TPH, Kcal/hr, MT/hr, KVA etc.
- SR
.
no.
Source
of
emission
With
Capacity
e.g.
Stack
Height
(meter
)
Name
of the
fuel
Quantit
y of
Fuel
MT/hr &
MT/Day
Type of
emission
s i.e. Air
Pollutant
s
APCM NAAQS
(National
Ambient
Air Quality
Standards
)
SEAC, Gujarat Page 9 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
Boiler (8
TPH)
Existing
1 Boiler
(16TPH)
(Bio
Fuel/Coal
based)
52 Biofuel
/
Coal
2.8/3.2
TPH
PM
SO2
NOx
ESP +
Water
Scrubbe
r
150
mg/Nm3
100 ppm
50 ppm
2 Hot Oil
Generato
r (50
Lack k
cal TFH)
(Bio
Fuel/Coal
based)
Biofuel
/
Coal
1.4/1.6
TPH
OR
3 Boiler
(10TPH &
6TPH)
(2 Nos.
Stack)
(Natural
Gas
Base)
30 Natural
Gas
1200
M3/hr
PM
SO2
NOx
---
150
mg/Nm3
100 ppm
50 ppm
4 Hot Oil
Generato
r (50
Lack k
cal TFH)
(Natural
Gas
Base)
PM
SO2
NOx
---
150
mg/Nm3
100 ppm
50 ppm
5 Hot Oil
Generato
r (Natural
Gas
Basis)
30
Natural
Gas
200
M3/hr PM
SO2
NOx
---
150
mg/Nm3
100 ppm
50 ppm
6
Power
Plant
Engines
(5Nos. of
stack)
(Natural
Gas
Base)
16
Natural
Gas
PM
SO2
NOx
---
150
mg/Nm3
100 ppm
50 ppm
SEAC, Gujarat Page 10 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
WHRB (5
Nos. of
Stack)
(Natural
Gas
Base)
16
Natural
Gas PM
SO2
NOx
----
150
mg/Nm3
100 ppm
50 ppm
Proposed
7 Boiler (40
TPH)
(coal
Based)
60
Coal 6 TPH PM
SO2
NOx
---
150
mg/Nm3
100 ppm
50 ppm
8. DG SET
(4000
KVA) 12
Diesel 1100
ltr/Hr
PM
SO2
NOx
ESP +
Water
Scrubbe
r
150
mg/Nm3
100 ppm
50 ppm
9. DG SET
(1500
KVA)
9 Diesel 400
ltr/Hr
PM
SO2
NOx
---
150
mg/Nm3
100 ppm
50 ppm
- ii Process gas i.e. Type of pollutant gases (SO2, HCl, NH3, Cl2, NOx etc.)
[Existing & Proposed] -
Sr. no.
Source of emission
Type of emission
Stack/Vent Height (meter)
APCM
NAAQS (National Ambient
Air Quality Standards)
Existing 1 Blue Plant
Spin Flash Dryer (5 Nos. of Stack)
PM 12 Bag Filter
150 mg/NM3
Synthesis Vessel (3 Nos. of Stack)
Ammonia 12 Scrubber 175 mg/NM3
2 Green Plant Spin Flash
Dryer (3 Nos. of Stack)
PM 18 Bag Filter
150 mg/NM3
Chlorination Vessel (2 Nos. of Stack)
HCL CL2
18 Water & Alkali Scrubber
20 mg/NM3
09 mg/NM3
3 Aluminum Hydroxide
SEAC, Gujarat Page 11 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
Spin Flash Dryer (2 Nos. of Stack)
PM 20 Bag Filter
150 mg/NM3
Purification Vessel (1 Nos. of stack)
H2S 27 Alkali Scrubber
45 mg/NM3
Proposed 1 Blue Plant Spin Flash
Dryer (5 Nos. of Stack)
PM 12 Bag Filter
150 mg/NM3
Synthesis Vessel (2 Nos. of Stack)
Ammonia 12 Scrubber 175 mg/NM3
2 Green Plant Spin Flash
Dryer (2 Nos. of Stack)
PM 18 Bag Filter
150 mg/NM3
Chlorination Vessel (3 Nos. of Stack)
HCL CL2
18 Water & Alkali Scrubber
20 mg/NM3
09 mg/NM3
3 Aluminum Hydroxide
Spin Flash Dryer (4 Nos. of Stack)
PM 20 Bag Filter
150 mg/NM3
Purification Vessel (3 Nos. of stack)
H2S 27 Alkali Scrubber
45 mg/NM3
- v Fugitive emission details with its mitigation measures.
[Existing & Proposed] Sr.
No. Source Probable Pollutant
Emission Control Measures/ APCM
FUGITIVE EMISSION
1 Solvent storage tank Air pollutant (VOC)
i) Carry out work place area monitoring to find out concentration level in ambient air
Close handling system.
ii) Provision of breather valve cum flame arrester.
2 Solvent recovery system
Air pollutant (VOC)
i) Solvent recovery system with steam condensation system.
ii) Pumps & motors are
SEAC, Gujarat Page 12 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
mechanical seal type. 3 Handling of raw
material bags in storage area
Air pollutant (PM)
i) Provision of exhaust ventilation
Provision of PPE.
ii) Provision of Job rotation to reduce exposure.
4 Flange joints of pipeline, pump & motors
Air pollutant (VOC)
i) Routine &periodic inspection to check leakage.
ii) Preventive maintenance, Follow SOP for maintenance.
iii) Pumps & motors will be mechanical seal type.
iv) LDAR program will be followed.
Provision of Flange guard. 5 Solid raw material
transferring to reactor Air pollutant (PM)
Hopper will be provided with powder transfer system.
6 Liquid raw material transferring to reactor
Air pollutant (VOC)
Feeding of liquid raw material will be carried out by closed pipeline and mechanical seal pump.
7 Loading /unloading at storage area
Air pollutant (VOC)
Unloading through pipeline to tank in a close system.
C Hazardous waste (as per the Hazardous and Other Wastes (Management and Transboundary Movement) Rules 2016. [Existing & Proposed]
i Sr. no.
Type/Name of Hazardous waste
Source of generation
Category and Schedule as per HW Rules.
Quantity (MT/Annum)
Disposal Method
Existing
Proposed
Total
1 ETP Sludge
ETP plant 33.5
10950
14800 25750
Collection, storage, Transportation & Disposal by send to TSDF-BEIL/SEEPL Kutch/sell Authorized to Cement Industries.
2 Discarded
Bags/Drums/Liner
Storage & transportation
33.3
24 36 60
Collection, Storage, Reuse & Decontamination, Disposal
SEAC, Gujarat Page 13 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
to TSDF, or send to GPCB authorized Re-processor.
3 Spent Oil
Lubrication
5.1
3000 Lit
600 Lit 3600 Lit
Collection, storage, Transportation & Disposal by sell CPCB authorized Re-Processors
4 Copper Salt
Fom Process
B3/II
240 -240 0
Collection, storage, Transportation & Disposal by sold to authorize industrial users.
5 Dust From Air
Filteration System
From Air Filteration System
26.3
24 6 30
Collection, storage, Transportation Recovered & Reprocessed.
6 Spent carbon
Dust From ETP
From ETP
24 36 60
Collection, storage, Transportation & Disposal at TSDF-BEIL/SEPPL Kutch for land Fill.
7 Used
Membrane
35.1
0.12 0.024 0.14
4
Collection, storage, Transportation & Disposal at TSDF-BEIL for land Fill.
8
Used Granular Activated Carbon
35.2
3650 0 3650
Collection, storage, Transportation & Disposal by send to GPCB approved industry for regeneration / reactivation.
9 Gypsum
From process
26.1
18000
0 18000
Collection, storage, Transportation & Disposal at TSDF-BEIL/SEPPL, Kutch/sell to
SEAC, Gujarat Page 14 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
authorized Cement Manufacturers.
10
Spent sulphuric Acid
From process
D2
10950 KL
0 10950 KL
Collection, storage, Transportation & Disposal By Sell to Authorized industrial Reusers/neutralise and sold as Gypsum.
11
Used Batteries
---
25 Nos.
5 Nos. 30
Nos.
Collection, storage, Transportation & Disposal by return back to supplier.
12
Used Insulation Material
---
10 5 15
Collection, storage, Transportation & Disposal by Return back to Supplier.
13
Contaminated papers, plastics,
cotton etc
Storage 33.3 0 60 60 Collection, storage, and transportation & final disposal by incineration at BEIL
14
Sodium Hypo Chloride
Process -- 0 1200 1200
Collection, storage, Transportation & Disposal by selling to actual end user having rule-9 permission/use in ETP for COD/ Ammonical Nitrogen reduction.
15
Ammonium Carbonate
From CPC Blue
C4 0 9000 9000
Collection, storage, Conversion to Ammonia liquor and soda ash solution.
SEAC, Gujarat Page 15 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
Quantity of discarded containers must be in MT/Annum.
ii Membership details of CETP, TSDF, CHWIF, Common MEE etc.
Attached in EIA report
ii Details of Non-Hazardous waste & its disposal (MSW and others)
Sr.No. Waste Quantity Mode Of Disposal
1. Glass Waste ( Z 13) 0.1MT/Month TSDF Site
2. Paper waste (Z44) 3 MT/Month To notified collection system
3. Wooden Waste 5 MT/Month Authorized Scrap Vendors
4. Fly ash 368 MT/Month Collection, storage, transportation, disposal to brick manufacturer/ Cement & Its Article.
D i Solvent management (If any)
Details of Solvent recovery (As per respective ToR) Given in Chapter-2
ii VOC emission sources and its mitigation measures Given in chapter-8
13. Details of Environmental Consultants:
Sr. no.
Particulars Details
i Name of the Consultant M/s. Jyoti Om Chemical Research Centre Pvt. Ltd.
ii Validity of Certificate of accreditation issued by the NABET, QCI
High Court Stay Order
iii Accreditation for the categories -- iv Any other details --
14. Details regarding EIA report:
Sr. no.
Particulars Details Page no. of EIA report
a Ensure that there is no change in EIA report compared to ToR application i.e. Form-1 & PFR
No Change ----
b Baseline environmental monitoring period
January-2017 to March-2017
c Baseline study area (5 km or 10 km) 10 km d No. of AAQM stations including project
site 8
e Parameters considered for AAQM & ensure that project specific parameters are considered.
PM10, PM2.5, SO2, NOx, VOC, HCl, H2S, HBr, Br2, Cl2 and NH3
Page No. 3.12 to 3.15 of Chapter-
SEAC, Gujarat Page 16 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
3 f Conclusion of the Monitoring (Baseline
study) Air, Water & Land Air: the results of AAQM is within the norms prescribed in NAAQS. Water: Analysis of
collected samples
reveals that rest of the
parameters satisfy the
permissible limits as
per IS 10500:2012
specified for drinking
water and hence are
suitable for drinking,
however it is
suggested that the
water may disinfected
by boiling or by use of
chlorine tablets before
use.
From the table above,
it can be observed that
surface water qualities
in terms of various
essential and
desirable
characteristics are
found within the limits
specified by IS
10500:2012.
Land: the soil quality around site is appropriate and no abnormality in terms of soil contaminants is reported.
Page No.3.15, 3.19, 3.22 & 3.29 of chapter-3
g Parameters considered for AAQM including project specific parameters.
- Sr. no. Parameters Range of
Concentrations (μg/m3
Remarks
SEAC, Gujarat Page 17 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
) 1 PM10, 75 - 94 The results of AAQM
is within the norms prescribed in NAAQS.
2 PM2.5, 32-43 3 SO2, 20 - 35 4 NOx, 35-49 5 VOC, 1.2 – 4.4 6 HCl, 1-5 7 H2S, BDL 8 HBr, BDL 9 Br2, BDL 10 Cl2 BDL 11 NH3 400 12 CO 0.2-0.8
- h Whether the results of AAQM is within the
norms prescribed in NAAQS ? Yes Page No.
3.12 to 3.15 of Chapter-3
i Comments for AAQM results w.r.t. NAAQS The results of AAQM is within the norms prescribed in NAAQS.
Page No. 3.12 to 3.15 of Chapter-3
j Software used for the mathematical Modelling for anticipated incremental GLCs (Ground Level Concentrations)
Industrial Source Complex Short Term (ISCST-3)
Page No. 4.12 of chapter-4
k The resultant concentrations w.r.t. NAAQS and its conclusion.
The results of AAQM is within the norms prescribed in NAAQS
Page No. 3.12 to 3.15 of Chapter-3
l Suggested mitigation measures w.r.t. Air The NH3 will be absorbed in Acid Scrubber before venting out to achieve GPCB norms. The HCl, Cl-2, and H2S will be absorbed in Alkali Scrubber before venting out to achieve GPCB norms. Bag filter is provided with spin flash drier to control particulate matter. Adequate stack height will further help in dispersion of pollutants. Closed feeding and transferring system, proper local and
Page No. 4.11 of chapter-4
SEAC, Gujarat Page 18 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
exhaust ventilation and more solvent recovery efficiency will control fugitive emission. The installation of water scrubber followed by carbon absorption tower will control VOC going into the atmosphere. The air quality impact of source is evaluated by use of model. The model simulates the relationship between air pollutants emission, meteorology and air chemistry, all of which are determined by formulating impact scenario.
m Conclusion of the Monitoring during baseline study of water
Analysis of collected
samples reveals
that rest of the
parameters satisfy
the permissible
limits as per IS
10500:2012
specified for
drinking water and
hence are suitable
for drinking,
however it is
suggested that the
water may
disinfected by
boiling or by use of
chlorine tablets
before use.
From the table
above, it can be
3.19 & 3.22 of chapter-3
SEAC, Gujarat Page 19 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
observed that
surface water
qualities in terms of
various essential
and desirable
characteristics are
found within the
limits specified by IS
10500:2012.
n Suggested mitigation measures w.r.t.
Water Proper care will be taken to prevent any spillage/leakage. Proper storage facility will be provided for raw material and hazardous waste.
Page No. 4.10 of chapter-4.
o Conclusion of the Monitoring during baseline study of Land
The soil quality around site is appropriate and no abnormality in terms of soil contaminants is reported.
Page No. 3.22 of chaper-3
p Suggested mitigation measures w.r.t. Land The unit has closed
hazardous waste
storage area with
impervious flooring.
Transportation of
hazardous waste to
the TSDF site is
governed as per the
Hazardous Waste
(Management,
Handling and Trans
Boundary
Movement) Rules-
2016.
Separate collection
system is provided
Page 4.46 of chapter-4
SEAC, Gujarat Page 20 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
for collection of
spillage material.
Impervious layer,
RCC roads and
flooring is provided
to area, where the
chemical storage
and handling
activities will be
involved.
Separate storm
water collection
system is provided
to prevent
contamination of soil
through
contaminated water.
. q Conclusion of the Monitoring during
baseline study of Noise
r Suggested mitigation measures w.r.t. Noise
• Adequate noise control measures such as mufflers, silencers at the air inlet/outlet, anti-vibration pad for equipment with high vibration etc. shall be provided. •Housing/casing shall be provided for all noise generating machines. •Job rotation will reduce exposure to some extent. Moreover, PPE like earmuff and ear plugs will be provided to the operators/worker exposed to high noise. •The proposed green belt will further be helpful in
Page 4.45 of chapter-4
SEAC, Gujarat Page 21 of 21
SEAC, Gujarat [Appraisal- Expansion projects]
reducing the ambient noise level.
s Main issues in Public hearing (If applicable)
Not Applicable
t Brief description of Public hearing Main Issues raised by stake holders
Commitments by Project proponent and action plan.
-- -- -- -- -- --
- u Major hazardous chemicals and worst
case scenario considered in Risk Analysis report.
Detail given in topic 6.3 of Chaper-6
Page 6.7 to 6.32 of Chapter-6
Comments/Suggestions/mitigation measures in brief
Detail given in topic 6.4 of Chaper-6
Page 6.32 of Chapter-6
v An undertaking by the Project Proponent
on the ownership of the EIA report as per
the OM of MoEF&CC dated 05/10/2011
and an undertaking by the Consultant
regarding the prescribed TORs have been
complied with and the data submitted is
factually correct as per the OM of
MoEF&CC dated 04/08/2009.
Attached in EIA report.
w Any other details: -- --
Name & designation of the Applicant: ______________
Stamp & Signature of Applicant: __________
Date:
General Instructions
• Format shall be in WORD Format (Font type- Arial, Font size- 11)
• Provide authenticated (with stamp & Signature) hard copy during presentation.
• Kindly mail to : [email protected] and copy to all members.
• Above data should be as per application Form-1 & PFR.
• Incorporate relevant details in respective column in the Format. Do not attach
Annexure in Format.