applying the nec contracts in new zealand · 2015-12-17 · introduction •can i use nec unamended...

16
Applying the NEC Contracts in New Zealand Charlotte Fox, Senior Associate, Simpson Grierson 5 November 2015

Upload: others

Post on 11-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Applying the NEC Contracts in New Zealand

Charlotte Fox, Senior Associate, Simpson Grierson

5 November 2015

Page 2: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Overview of the Session

• Introduction

• Y(NZ)1 and Y(NZ)2

• Potential Z clauses

• Potential Schedules

• Warranties and Guarantees

• Amending NEC to comply with the Health & Safety at Work

Act 2015

• Amending NEC to comply with the Construction Contracts

Amendment Act 2015

12/11/2015 © NEC Contracts 2

Page 3: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Introduction

• Can I use NEC unamended in New Zealand?

– NO:

• If the contract is for construction work, need to select

Y(NZ)1 to comply with the Construction Contracts Act

2002

• Will be necessary to make amendments to ensure

compliance with the Health & Safety at Work Act 2015

• Terminology needs to be introduced (GST, RMA, HSEA)

12/11/2015 © NEC Contracts 3

Page 4: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Y(NZ)1 – Construction Contracts Act 2002

• Only select where there is “construction work”

• Incorporated into the contract by reference to Y(NZ)1 in the

Contract Data Part 1

• Supplements the payment provisions to ensure compliance

with the CCA and aligns the dispute resolution provisions

12/11/2015 © NEC Contracts 4

Page 5: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Y(NZ)2 – Contracts (Privity) Act 1982

• Only select where the project is carried out in New Zealand

or the law of the contract is New Zealand

• Incorporated into the contract by reference to Y(NZ)2 in the

Contract Data Part 1

• Include the names of the third parties who can benefit from

the Y(NZ)2 clause

12/11/2015 © NEC Contracts 5

Page 6: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Potential Z clauses

• Definitions

• Assignment

• Subcontracting

• Novation

• Confidentiality

• Public Relations

12/11/2015 © NEC Contracts 6

Page 7: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Potential Z clauses cont.

• Insurance

• Environmental Compliance

• Dispute Resolution – Option W1 or something else?

12/11/2015 © NEC Contracts 7

Page 8: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Potential Schedules

• Form of Contract Agreement

• Form of Bond

• Bond in Lieu of Retentions

• Deed of Novation

12/11/2015 © NEC Contracts 8

Page 9: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Warranties and Guarantees

• Parent Company Guarantee

• Continuity Guarantee

• Contractor/Subcontractor Warranty

• Weathertightness Warranty

12/11/2015 © NEC Contracts 9

Page 10: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Health & Safety at Work Act 2015

• Comes into force on 4 April 2016

• PCBU – primary duty:

– to ensure so far as is reasonably practicable the health

and safety of workers who work for the PCBU and

workers whose activities are influenced or directed by the

PCBU while carrying out the work

12/11/2015 © NEC Contracts 10

Page 11: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Health & Safety at Work Act 2015 cont.

• Duty to consult with other PCBUs

• So far as is reasonably practicable need to:

Consult

Co-operate

Co-ordinate

12/11/2015 © NEC Contracts 11

Page 12: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Health & Safety at Work Act 2015 cont.

• Need Z clauses to cover:

– PCBU’s primary duty of care

– Overlapping duties of PCBUs

– Health & Safety in general to ensure:

• risks to health and safety are eliminated so far as is

reasonably practicable; and

• where not reasonably practicable to eliminate then the

risks are minimised so far as is reasonably practicable

12/11/2015 © NEC Contracts 12

Page 13: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Construction Contracts Amendment Act

2015

• Construction Contracts Amendment Act 2015

– Sections 6 and 11 in force 1 September 2016

– Sections 4(3) and 18 in force 31 March 2017

– Rest of the Act 1 December 2015

12/11/2015 © NEC Contracts 13

Page 14: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Construction Contracts Amendment Act

2015 cont.

• Contracts involving design or engineering work, or quantity

surveying work

• Unclear exactly who will be included and what “engineering

work” is

12/11/2015 © NEC Contracts 14

Page 15: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Construction Contracts Amendment Act

2015 cont.

• Retention money defined as:

“…an amount withheld by a party to a construction contract

(party A) from an amount payable to another party to the

contract (party B) as security for the performance of party

B’s obligations under the contract.”

12/11/2015 © NEC Contracts 15

Page 16: Applying the NEC Contracts in New Zealand · 2015-12-17 · Introduction •Can I use NEC unamended in New Zealand? –NO: •If the contract is for construction work, need to select

Questions

12/11/2015 © NEC Contracts 16