appendix p cnr crossing application - port of … · appendix p. cnr crossing application. aecom...

9
Appendix P CNR Crossing Application

Upload: votuong

Post on 09-Sep-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Appendix P

CNR Crossing Application

AECOM

3292 Production Way, Floor 4 604 444 6400 tel

Burnaby, BC, Canada V5A 4R4 604 294 8597 fax

www.aecom.com

© 2017 AECOM Canada Ltd. All Rights Reserved. This proposal may contain confidential information and may not be provided to anyone other than the addressee and its employees without AECOM’s written consent.

L_2017-05-16_CN Permitting_R1 (2).Docx

May 17, 2017

British Columbia Railway Company 600-221 West Esplanade North Vancouver BC V7M 3J3 Email: [email protected] Attention: Richard K. Myhill-Jones Director, Real Estate

CN Acquisition Limited

10229 -127 Avenue 2 Floor,

Building “B” Edmonton, AB, T5E 0B9

Attention: Sara Lovegrove

CN Design and Construction/Prairie Utilities Coordinator

Dear Sirs and Mesdames:

Regarding: North Shore Wastewater Treatment Plant - Conveyance System

Utility Crossing Application

We write with respect to the following railway line lands which are owned by the British Columbia

Railway Company (“BCR”) and leased to CN Acquisition Limited (“CN”):

PID: 015-861-881

Legal Description:

DISTRICT LOT 4286 (REFERENCE PLAN 1270) GROUP 1 NEW WESTMINSTER

DISTRICT,

EXCEPT PART IN REFERENCE PLAN 3863

(the “Railway Line”).

The Greater Vancouver Sewage and Drainage District (“GVS&DD”) is undertaking a secondary

treatment upgrade program on the North Shore of Burrard Inlet, which is required by Metro

Vancouver's Integrated Liquid Waste and Resource Management Plan (ILWRMP), as approved

pursuant to the Environmental Management Act, and the new federal Wastewater Systems Effluent

Regulations (“WSER”). The North Shore Wastewater Treatment Plant (NSWWTP) is being

constructed within the District of North Vancouver and will replace the existing Lions Gate Wastewater

Treatment Plant (LGWWTP), which is located within the District of West Vancouver and which was

commissioned in 1961. The LGWWTP provides primary waste water treatment to the 200,000

residents of the North Shore municipalities of West Vancouver, the City of North Vancouver and

Page 2

May 17, 2017

© 2017 AECOM Canada Ltd. All Rights Reserved. This proposal may contain confidential information and may not be provided to anyone other than the addressee and its employees without AECOM’s written consent.

L_2017-05-16_CN Permitting_R1 (2).Docx

the District of North Vancouver as well as the Squamish Nation and the Tsleil-Waututh Nation. The

NSWWTP Program comprises design and construction of the new secondary wastewater treatment

plant, design and construction of interconnection works between the LGWWTP and the NSWWTP

(the “conveyance system”), and decommissioning of the existing LGWWTP. The NSWWTP must be

operational by the end of 2020 per the ILWRMP and the WSER.

The conveyance system to and from the NSWWTP includes the following:

• a wastewater pump station

• a new 900mm diameter forcemain extending from the new pump station to the NSWWTP (the “forcemain”),

• a 2100 mm secondary effluent pipe extending from a chamber upstream of the marine outfall at LGWWTP to the NSWWTP (the “effluent pipe”),

• a 1200mm diameter extension of the trunk sewer system from the LGWWTP to the new pump station, and

• various other sewer connections and trunk sewer extensions to facilitate the conveyance of wastewater from the District of North Vancouver and the Squamish Nation to the NSWWTP

The proposed alignment of the forcemain and effluent pipe (“Utility Line”) extends east from the

LGWWTP generally parallel to and north of the existing Canadian National Railway (“CNR”) tracks

within the Railway Line. The Utility Line will cross beneath the CNR tracks under the Lions Gate Bridge.

We propose constructing the Utility Line at Mile MP 1.90 of the Railway Line, Squamish Subdivision

which is within District of West Vancouver boundary, on the east side of the Bridge Road and the

existing LGWWTP and approximately 16.2m east of the Lions Gate Bridge piers. According to the

proposed design, both the Utility Line will be encased in steel casings and installed by trenchless

techniques.

GVS&DD plans to procure the conveyance system work through a Design-Build methodology.

GVS&DD will engage in a competitive selection process in order to retain a single entity (“Project

Co”) to design, build and commission the work. To meet GVS&DD deadline to achieve secondary

effluent treatment of December 31, 2020, the Design-Build approach is necessary to meet the

schedule constraints of the project.

The following table correlates the checklist requirements provided by CNR and entitled “CN a Guide

to the Pipe and Wire Process – Water/Sewer Pipelines”:

Page 3

May 17, 2017

© 2017 AECOM Canada Ltd. All Rights Reserved. This proposal may contain confidential information and may not be provided to anyone other than the addressee and its employees without AECOM’s written consent.

L_2017-05-16_CN Permitting_R1 (2).Docx

Checklist

Item

Description Included in

this

Submission

1 Plans for Effluent and Forcemain crossings including :

• Site Plan and Profile

• Location Plan

• Land Description

• Specifications for carrier pipe and casing pipes included in

plan

Yes

2 Geotechnical Recommendation Letter Yes

This application package is submitted under “Indicative Design Phase” of the project with the purpose

of negotiating an agreement relating to the construction, maintenance and apportionment of the costs

of utility crossings for the forcemain and effluent pipelines. We have addressed this package to

both BCR and CN because we understand that under the terms of its lease, CN cannot offer

GVSDD any rights to occupy or use the Railway Line for underground work. During the Design

–Build phase either the Project Co or GVS&DD will provide detailed design plans for the utility

crossings.

Please do not hesitate to contact me (604-444-6465) if you have any questions or concerns.

Sincerely,

AECOM Canada Ltd.

Tatiana Irimia, P.Eng.

Senior Project Engineer

[email protected]

cc: Joan Liu, Senior Project Engineer – Metro Vancouver

SH17-04

1219mm O.D. STEEL CASING PIPE ASTM

A252 GRADE 2 STEEL

(MIN. YIELD STRENGTH 241 MPA) WALL

THICKNESS 12.7mm

L=46.5m

900Ø HDPE SAN FM

OWNER - METRO VANCOUVER

INSTALLATION & MAINTENANCE TO BE IN ACCORDANCE WITH TC E10

CONTACT; JOAN LIU 604.451.6188

[email protected]

DATA CARRIER PIPE CASING PIPE

Contents to be handled RAW SEWAGE -

Outside Diameter 900mm 1219mm

Pipe Material HDPE Steel

Specification and Grade DR 17 ASTM A252 GRADE 2

Wall Thickness 5.3mm 12.7mm

Maximum Operating Pressure 30psi -

Maximum Surge & Test Pressure 60psi -

Maximum Operating Temperature 21 DEGREES -

Type of Joint BUTT FUSION Welded, End Seals

Coating NiL

Method of Installation Trenchless Trenchless

Length 46.5m 46.5m

CANADIAN NATIONAL RAILWAY

DIVISIONAL ENGINEER

REGIONAL ENGINEER

MANAGER

RAILWAY CHAINAGE

MILEAGE MP 1.90

SUBDIVISION SQUAMISH

NON-METALLIC CASING

SPACERS RACI TYPE

NOTES:

1. HYDROVAC TO CONFIRM DEPTH AND LOCATIONS

OF EXISTING UTILITIES PRIOR TO CONSTRUCTION.

2. ENDS OF CASING TO BE PROVIDED WITH END

SEALS.

SH17-04

2428mm O.D. STEEL CASING PIPE ASTM

A252 GRADE 2 STEEL

(MIN. YIELD STRENGTH 241 MPA) WALL

THICKNESS 12.7mm

L=46.5m

2133Ø STEEL SAN PIPE

DATA CARRIER PIPE CASING PIPE

Contents to be handled TREATED EFFLUENT -

Outside Diameter 2133mm 2428mm

Pipe Material Steel Steel

Specification and Grade ASTM A572 GR.42 ASTM A252 GRADE 2

Wall Thickness 9.5mm 12.7mm

Maximum Operating Pressure 4psi -

Maximum Surge & Test Pressure 8psi -

Maximum Operating Temperature 14 DEGREES -

Minimum Operating Temperature 10 DEGREES -

Type of Joint Welded Welded, End Seals

Coating Polyurethane to AWWA

C222

-

Method of Installation Trenchless Trenchless

CANADIAN NATIONAL RAILWAY

DIVISIONAL ENGINEER

REGIONAL ENGINEER

MANAGER

RAILWAY CHAINAGE

MILEAGE MP 1.90

SUBDIVISION SQUAMISH

OWNER - METRO VANCOUVER

INSTALLATION & MAINTENANCE TO BE IN ACCORDANCE WITH TC E10

CONTACT; JOAN LIU 604.451.6188

[email protected]

NOTES:

1. HYDROVAC TO CONFIRM DEPTH AND LOCATIONS

OF EXISTING UTILITIES PRIOR TO CONSTRUCTION.

2. ENDS OF CASING TO BE PROVIDED WITH END

SEALS.

NON-METALLIC CASING

SPACERS RACI TYPE