AECOM
3292 Production Way, Floor 4 604 444 6400 tel
Burnaby, BC, Canada V5A 4R4 604 294 8597 fax
www.aecom.com
© 2017 AECOM Canada Ltd. All Rights Reserved. This proposal may contain confidential information and may not be provided to anyone other than the addressee and its employees without AECOM’s written consent.
L_2017-05-16_CN Permitting_R1 (2).Docx
May 17, 2017
British Columbia Railway Company 600-221 West Esplanade North Vancouver BC V7M 3J3 Email: [email protected] Attention: Richard K. Myhill-Jones Director, Real Estate
CN Acquisition Limited
10229 -127 Avenue 2 Floor,
Building “B” Edmonton, AB, T5E 0B9
Attention: Sara Lovegrove
CN Design and Construction/Prairie Utilities Coordinator
Dear Sirs and Mesdames:
Regarding: North Shore Wastewater Treatment Plant - Conveyance System
Utility Crossing Application
We write with respect to the following railway line lands which are owned by the British Columbia
Railway Company (“BCR”) and leased to CN Acquisition Limited (“CN”):
PID: 015-861-881
Legal Description:
DISTRICT LOT 4286 (REFERENCE PLAN 1270) GROUP 1 NEW WESTMINSTER
DISTRICT,
EXCEPT PART IN REFERENCE PLAN 3863
(the “Railway Line”).
The Greater Vancouver Sewage and Drainage District (“GVS&DD”) is undertaking a secondary
treatment upgrade program on the North Shore of Burrard Inlet, which is required by Metro
Vancouver's Integrated Liquid Waste and Resource Management Plan (ILWRMP), as approved
pursuant to the Environmental Management Act, and the new federal Wastewater Systems Effluent
Regulations (“WSER”). The North Shore Wastewater Treatment Plant (NSWWTP) is being
constructed within the District of North Vancouver and will replace the existing Lions Gate Wastewater
Treatment Plant (LGWWTP), which is located within the District of West Vancouver and which was
commissioned in 1961. The LGWWTP provides primary waste water treatment to the 200,000
residents of the North Shore municipalities of West Vancouver, the City of North Vancouver and
Page 2
May 17, 2017
© 2017 AECOM Canada Ltd. All Rights Reserved. This proposal may contain confidential information and may not be provided to anyone other than the addressee and its employees without AECOM’s written consent.
L_2017-05-16_CN Permitting_R1 (2).Docx
the District of North Vancouver as well as the Squamish Nation and the Tsleil-Waututh Nation. The
NSWWTP Program comprises design and construction of the new secondary wastewater treatment
plant, design and construction of interconnection works between the LGWWTP and the NSWWTP
(the “conveyance system”), and decommissioning of the existing LGWWTP. The NSWWTP must be
operational by the end of 2020 per the ILWRMP and the WSER.
The conveyance system to and from the NSWWTP includes the following:
• a wastewater pump station
• a new 900mm diameter forcemain extending from the new pump station to the NSWWTP (the “forcemain”),
• a 2100 mm secondary effluent pipe extending from a chamber upstream of the marine outfall at LGWWTP to the NSWWTP (the “effluent pipe”),
• a 1200mm diameter extension of the trunk sewer system from the LGWWTP to the new pump station, and
• various other sewer connections and trunk sewer extensions to facilitate the conveyance of wastewater from the District of North Vancouver and the Squamish Nation to the NSWWTP
The proposed alignment of the forcemain and effluent pipe (“Utility Line”) extends east from the
LGWWTP generally parallel to and north of the existing Canadian National Railway (“CNR”) tracks
within the Railway Line. The Utility Line will cross beneath the CNR tracks under the Lions Gate Bridge.
We propose constructing the Utility Line at Mile MP 1.90 of the Railway Line, Squamish Subdivision
which is within District of West Vancouver boundary, on the east side of the Bridge Road and the
existing LGWWTP and approximately 16.2m east of the Lions Gate Bridge piers. According to the
proposed design, both the Utility Line will be encased in steel casings and installed by trenchless
techniques.
GVS&DD plans to procure the conveyance system work through a Design-Build methodology.
GVS&DD will engage in a competitive selection process in order to retain a single entity (“Project
Co”) to design, build and commission the work. To meet GVS&DD deadline to achieve secondary
effluent treatment of December 31, 2020, the Design-Build approach is necessary to meet the
schedule constraints of the project.
The following table correlates the checklist requirements provided by CNR and entitled “CN a Guide
to the Pipe and Wire Process – Water/Sewer Pipelines”:
Page 3
May 17, 2017
© 2017 AECOM Canada Ltd. All Rights Reserved. This proposal may contain confidential information and may not be provided to anyone other than the addressee and its employees without AECOM’s written consent.
L_2017-05-16_CN Permitting_R1 (2).Docx
Checklist
Item
Description Included in
this
Submission
1 Plans for Effluent and Forcemain crossings including :
• Site Plan and Profile
• Location Plan
• Land Description
• Specifications for carrier pipe and casing pipes included in
plan
Yes
2 Geotechnical Recommendation Letter Yes
This application package is submitted under “Indicative Design Phase” of the project with the purpose
of negotiating an agreement relating to the construction, maintenance and apportionment of the costs
of utility crossings for the forcemain and effluent pipelines. We have addressed this package to
both BCR and CN because we understand that under the terms of its lease, CN cannot offer
GVSDD any rights to occupy or use the Railway Line for underground work. During the Design
–Build phase either the Project Co or GVS&DD will provide detailed design plans for the utility
crossings.
Please do not hesitate to contact me (604-444-6465) if you have any questions or concerns.
Sincerely,
AECOM Canada Ltd.
Tatiana Irimia, P.Eng.
Senior Project Engineer
cc: Joan Liu, Senior Project Engineer – Metro Vancouver
SH17-04
1219mm O.D. STEEL CASING PIPE ASTM
A252 GRADE 2 STEEL
(MIN. YIELD STRENGTH 241 MPA) WALL
THICKNESS 12.7mm
L=46.5m
900Ø HDPE SAN FM
OWNER - METRO VANCOUVER
INSTALLATION & MAINTENANCE TO BE IN ACCORDANCE WITH TC E10
CONTACT; JOAN LIU 604.451.6188
DATA CARRIER PIPE CASING PIPE
Contents to be handled RAW SEWAGE -
Outside Diameter 900mm 1219mm
Pipe Material HDPE Steel
Specification and Grade DR 17 ASTM A252 GRADE 2
Wall Thickness 5.3mm 12.7mm
Maximum Operating Pressure 30psi -
Maximum Surge & Test Pressure 60psi -
Maximum Operating Temperature 21 DEGREES -
Type of Joint BUTT FUSION Welded, End Seals
Coating NiL
Method of Installation Trenchless Trenchless
Length 46.5m 46.5m
CANADIAN NATIONAL RAILWAY
DIVISIONAL ENGINEER
REGIONAL ENGINEER
MANAGER
RAILWAY CHAINAGE
MILEAGE MP 1.90
SUBDIVISION SQUAMISH
NON-METALLIC CASING
SPACERS RACI TYPE
NOTES:
1. HYDROVAC TO CONFIRM DEPTH AND LOCATIONS
OF EXISTING UTILITIES PRIOR TO CONSTRUCTION.
2. ENDS OF CASING TO BE PROVIDED WITH END
SEALS.
SH17-04
2428mm O.D. STEEL CASING PIPE ASTM
A252 GRADE 2 STEEL
(MIN. YIELD STRENGTH 241 MPA) WALL
THICKNESS 12.7mm
L=46.5m
2133Ø STEEL SAN PIPE
DATA CARRIER PIPE CASING PIPE
Contents to be handled TREATED EFFLUENT -
Outside Diameter 2133mm 2428mm
Pipe Material Steel Steel
Specification and Grade ASTM A572 GR.42 ASTM A252 GRADE 2
Wall Thickness 9.5mm 12.7mm
Maximum Operating Pressure 4psi -
Maximum Surge & Test Pressure 8psi -
Maximum Operating Temperature 14 DEGREES -
Minimum Operating Temperature 10 DEGREES -
Type of Joint Welded Welded, End Seals
Coating Polyurethane to AWWA
C222
-
Method of Installation Trenchless Trenchless
CANADIAN NATIONAL RAILWAY
DIVISIONAL ENGINEER
REGIONAL ENGINEER
MANAGER
RAILWAY CHAINAGE
MILEAGE MP 1.90
SUBDIVISION SQUAMISH
OWNER - METRO VANCOUVER
INSTALLATION & MAINTENANCE TO BE IN ACCORDANCE WITH TC E10
CONTACT; JOAN LIU 604.451.6188
NOTES:
1. HYDROVAC TO CONFIRM DEPTH AND LOCATIONS
OF EXISTING UTILITIES PRIOR TO CONSTRUCTION.
2. ENDS OF CASING TO BE PROVIDED WITH END
SEALS.
NON-METALLIC CASING
SPACERS RACI TYPE