appendix ii (see paragraph 6) form -1 a (only for...
TRANSCRIPT
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
APPENDIX II
(See paragraph 6)
FORM -1 A (only for construction projects listed under item 8 of the Schedule)
CHECK LIST OF ENVIROMENTAL IMPACTS
(Project proponents are required to provide full information and wherever necessary attach
explanatory notes with the form and submit along with proposed environmental management
plan & monitoring programme)
1. LAND ENVIRONMENT
(Attach panoramic view of the project site and the vicinity)
1.1 Will the existing land use get significantly altered from the project that is not consistent
with the surroundings? (Proposed land use must conform to the approved Master Plan /
Development Plan of the area. Change of land use if any and the statutory approval from
the competent authority be submitted) Attach Maps of (i) site location, (ii) surrounding
features of the proposed site (within 500 meters) and (iii) the site (indicating levels &
contours) to appropriate scales. If not available attach only conceptual plans.
The proposed project is located in developing municipal area of Jaipur. Plot is allotted by JDA
for Group Housing purpose. The area is having single land use pattern comprising of
residential establishments. There will be no change in land use, which will not be in consistent
with the existing surroundings. The proposed land use is as per approval of JDA.
Please refer the following maps available as annexure.
Google Map showing surrounding features of the proposed site as Annexure- IX.
Conceptual Plan/Site Plan as Annexure- XXIII-1
1.2 List out all the major project requirements in terms of the land area, built up area, water
consumption, power requirement, connectivity, community facilities, parking needs etc.
a) Name & Location:
“Ashadeep Rainbow”
Proposed Group Housing Project
Promoted by Regalia Builders
At Plot No.-GH-1, Ashadeep Kings Court Scheme, Village- Jirota, Tehsil - Sanganer,
District- Jaipur, Rajasthan
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
b)
Details of Proposed Construction
1. Total Plot Area 23887.39 Sq. m
2. Gross Built up Area 40033.77 Sq. m
3. Permissible F.A.R 31770.23 Sq. m
4. Achieved F.A.R 29094.56 Sq. m
5. Permissible Ground
Coverage
8360.59 Sq. m (35 % of plot area)
6. Achieved Ground
Coverage
7259.25 Sq. m (30.39 % of plot area)
7. Permissible Height 47.50 m (up to Machine level)
8. Achieved Height 39.70 m (up to Terrace Level)
9. Permissible Green
Area
2388.74 Sq. m (10.00 % of Plot Area)
10. Achieved Green
Area
2441.90 Sq. m (10.22 % of Plot Area)
11. Flat Details 348 Flats
120 Villa
c) Water Consumption:-
A. During Construction: 10.60 KLD
Supervisory & construction labour = 80 Persons @ 45 LPCD = 3.60 KLD
Curing & mixing of mortar & cement = 3.40 KLD
Dust Control = 3.60 KLDs
Total = 10.60 KLD
B. During Post Construction:
Water Demand Details of water used during post construction:-
Total No. of Flats = 384 Flats
Total No. of Villas= 120 Villas
Estimated population = 2400 Persons (Considering 5 persons in flat and 4 per
Villa)
Rate of water consumption- 86 LPCD
i) Total domestic Water Demand @86 LPCD 206.40 KLD
a) For Flushing @21 LPCD 50.40 KLD
b) For other domestic uses like-Drinking, Cooking,
Bathing and Washing etc @ 65 LPCD 156.00 KLD
ii) Water requirement for Club House 3.60 KLD
iii) Water requirement for Green Area 30.00 KLD
TOTAL WATER DEMAND 240.00 KLD
Out of total water requirement of 240.00 KLD, 158.00 KLD will be met from PHED Supply
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
and remaining 82.00 KLD will be met from treated effluent of in-house STP
* Water requirement for Landscape Area:
Total Achieved Landscape Area = 2441.9 Sq. m (10.22 % of Plot Area)
Water Requirement for Trees:
Canopy Area = 25 Sq. m.
Plant factor = 1
Evapo-transpiration = 0.75 m per annum
Irrigation efficiency- 0.70
Total 156 trees will be planted along the boundary of plot in single row at minimum distance
of 6 meter between two consecutive trees.
As per manual of norms and standards for environment clearance of large construction projects
article 2.3.4.1 Page 66.
Water requirement (LPD) can be calculated as:-
= {Canopy area (sq.m) × Evapo-transpiration (mpd) × Plant factor ×1000}
÷ Irrigation efficiency
= {25×156 × (0.75÷365) ×1 ×1000} ÷ 0.7
=11.44 KLD say 12.00 KLD
Water Requirement for Lawn Area:
Water Requirement for Lawn Area = 17.00 KLD
Total Water Requirement for green belt development including Large Trees and Lawn Area =
12.00 KLD +17.00 KLD =29.00 KLD
Provisions Made = 30.00 KLD
d) Wastewater Generation:-
Rate of wastewater generation = 85% of water consumed except Landscaping
Expected wastewater generation = 0.85 x (240.00 – 30) = 178.50 KLD
Total sewage generated will be 178.50 KLD. After treatment about 90% i.e. 160.65 KLD will
be available. Out of which 82.00 KLD will be used for flushing and green belt development.
The excess treated effluent (78.65 KLD) will be used in a manner to reduce the pressure on
fresh water demand in surroundings areas. We are committed to provide our excess treated
water to any individual/organization free of cost for their use. We are also willing to adopt
Road/parks in the area for development at the appropriate land. In case there is no
demand/requirement of treated water, we will discharge it in sewer system provided by
JDA/PHED/Municipal Corporation of Jaipur after taking necessary permission from
authorities.
e) Power Requirements:-
The total power demand of the project will be 2102.01 KW, which shall be met through power
grid of JVVNL.
The power will be received from JVVNL at 33 KV supply voltage, it will be stepped down to
0.433 KV through one transformers of 3150 kVA capacitiy. To supplement above during
power failure, it is proposed to provide one D.G. Set of capacity 250 kVA.
f) Connectivity:-
The proposed site is well connected:
Jaipur Junction Railway Station is about 15.18 Kms towards SW.
Jagatpura Railway Station is about 4.90 Kms towards SW.
Khatipura Railway Station is about 5.35 Kms towards NW
NH -12 is about 3.65 Km towards SE.
Sanganer Airport is about 4.35 Kms towards SW
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
g) Parking Details:-
Required Parking:
Required Parking = Achieved F.A.R / 75 = 25419.37 /75 = 338.92 E.C.U
Add 25% Visitors Parking = 338.92 x 0.25 = 84.73 E.C.U
Total = 338.92 E.C.U + 84.73 E.C.U = 423.65 E.C.U say 424 E.C.U
TOTAL E.C.U Required = 424.00 E.C.U
Parking Provided:
Total Parking Provided = 504.00 E.C.U
Provision for Parking of 504.00 E.C.U. has been made as follows:
Floor
Provided
Total E.C.U CARS TWO WHEELERS
E.C.U SCOOTERS E.C.U
STILT 64.00 0.00 0.00 64
OPEN GROUND 368.00 57.00 19.00 387
BASEMENT 72.00 0.00 0.00 72
TOTAL 504.00 57.00 19.00 523
1.3 What are the likely impacts of the proposed activity on the existing facilities adjacent to
the proposed site? (Such as open spaces, community facilities, details of the existing
landaus, disturbance to the local ecology).
The proposed project is coming up in developing area of Jaipur district. It has land use pattern
of residential establishments and is well connected with roads. There will be no impact on
existing facilities such as open spaces, community facilities. It will not cause any disturbance
to the local ecology as the land in this area is slowly being used for urban use.
1.4 Will there be any significant land disturbance resulting in erosion, subsidence &
instability? (Details of soil type, slope analysis, vulnerability to subsidence, seismicity etc.
may be given).
No, there will not be significant land disturbance resulting in erosion, subsidence &
instability.
1.5 Will the proposal involve alteration of natural drainage systems? (Give details on a
contour map showing the natural drainage near the proposed project site)
The project site is not having any natural drainage route. No perennial or non perennial
drainage system is intersecting the project site therefore no drainage system will be obstructed
by the proposed project. Well designed storm water system is proposed for management of
internal storm water drainage. Thus, no impact on the natural drainage system is expected.
1.6 What are the quantities of earthwork involved in the construction activity-cutting, filling,
reclamation etc. (Give details of the quantities of earthwork involved, transport of fill
materials from outside the site etc?)
There will be earthwork involved. Expected quantity of earthwork involved is about 8000 M3.
The same earth will be used for back filling, correcting the ground slopes, raising the ground
level and road level, no earth would be required from outside before starting the project, top 30
cm soil will be stored in a corner and it will be used to form the top soil of the landscaped area.
1.7 Give details regarding water supply, waste handling etc during the construction period.
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
During Construction phase, Water requirement will be met from authorized suppliers/surplus
treated water after disinfection from other commercial/residential project while fresh water
needed for domestic activities will be taken from authorized suppliers.
There will be no significant solid waste generated except the waste produced at the time of
construction. The saleable construction waste will be sold to authorized vendors and utilizable
construction waste will be used in backfilling and road embankments.
1.8 Will the low lying areas & wetlands get altered? (Provide details of how low lying and
wetlands are getting modified from the proposed activity)
No. There is no low lying or wetlands in the project site.
1.9 Whether construction debris & waste during construction cause health hazard? (Give
qualities of various types of wastes generated during construction including the
construction labor and the means of disposal)
Hazardous materials like Respirable silica, lead, used lubricating oil from DG Sets, aluminum
sections etc will be generated during construction of the building which can cause health
hazard.
Measures to minimize the effects are given below:-
S. No. Type of waste Mitigation measures
1. Respirable dust Regular sprinkling of water
2. Lead
Utmost care will be taken to ensure no spillage of
paint. Empty cans will be cleaned with thinner and this
paint solute will be used as thinner. Cleaned cans will
be sold to authorized vendors recyclers.
3. Used lubricating oil
from DG Sets
Waste oil will be properly stored and sold to
authorized recyclers.
4.
Aluminum sections
for doors and
windows.
The workers will wear mask whenever aluminum
cutting will be done and dust generated during cutting
will be collected at a designated place and sold to
authorized vendors / recyclers along with other
aluminum waste.
2. WATER ENVIRONMENT
2.1.
Give the total quantity of water requirement for the proposed project with the breakup
of requirements for various uses. How will the water requirement met? State the sources
& quantities and furnish a water balance statement.
S.
No. Particulars
Fresh Water
Demand
Flushing Water
Demand
Total Water
Demand
1. Water Demand in Housing
Facility 156.00 50.40 206.40
2. Water Requirement for Club
House 2.00 1.60 3.60
3. Water Requirement for
- 30.00 30.00
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Gardening
TOTAL 158.00 82.00 240.00
*Note all values are in KLD
Source: Fresh water- PHED supply; Recycled Water – STP Treated Water
Water Balance
Flushing in
Residential Block
50.40 KLD
39.00 KLD
Flushing in Clubhouse
1.60 KLD
Total Water Demand= 240.00 KLD
Daily Fresh Water Demand= 158.00 KLD
Daily Recycled Water Demand= 82.00 KLD
Daily Fresh Water Demand
158.00 KLD
Daily Recycled Water
Demand
82.00 KLD
In
Residential
Block
156.00 KLD
In Clubhouse
2.00 KLD
Gardening
30.00 KLD
For Flushing
52.00 KLD
15 % Loss
Waste Water Generated
178.50 KLD in STP
Treated Water from STP
(90% of Sewer)
160.65 KLD
78.65 KLD, Supplied to
Farmers/ Organization / JDA/
Greenbelt/Parks /discharged in
Sewer System after taking
necessary permission from
regulatory authorities.
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Total sewage generated will be 178.50 KLD. After treatment about 90% i.e. 160.65 KLD
will be available. Out of which 82.00 KLD will be used for flushing and green belt
development.
The excess treated effluent (78.65 KLD) will be used in a manner to reduce the pressure
on fresh water demand in surroundings areas. We are committed to provide our excess
treated water to any individual/organization free of cost for their use. We are also willing
to adopt Road/parks in the area for development at the appropriate land. In case there is
no demand/requirement of treated water, we will discharge it in sewer system provided
by JDA/PHED/Municipal Corporation of Jaipur after taking necessary permission from
authorities.
2.2 What is the capacity (dependable flow or yield) of the proposed source of water?
During Construction phase, Water requirement will be met from authorized
suppliers/surplus treated water after disinfection from other commercial/residential
project while fresh water needed for domestic activities will be taken from authorized
suppliers.
2.3 What is the quality of water required in case the supply is not from a municipal
source? (Provide physical, chemical, biological characteristics with class of water
quality)
During Construction phase, Water requirement will be met from authorized
suppliers/surplus treated water after disinfection from other commercial/residential
project while fresh water needed for domestic activities will be taken from authorized
suppliers and during post construction water will be supplied by PHED. Although water
from nearby bore well was collected and analyzed and the quality of water supply is
conforming to IS 10500-2012. The water analysis report of well water near project site is
annexed.
2.4 How much of the water requirement can be met from the recycling of treated
wastewater? (Give the details of qualities, sources and usage).
Total sewage generated will be 178.50 KLD. After treatment about 90% i.e. 160.65 KLD
will be available. Out of which 82.00 KLD will be used for flushing and green belt
development.
2.5 Will there be diversion of water from other users? (Please assess the impacts of the
project on other existing uses and quantities of consumption)
During Construction phase, Water requirement will be met from tanker suppliers/surplus
treated water after disinfection from other commercial/residential project while fresh
water needed for domestic activities will be taken from authorized suppliers and during
post construction water will be supplied by PHED. The application to PHED has been
submitted for water supply.
2.6 What is the incremental pollution land from wastewater generated from the
proposed activity? (Give details of the quantities and composition of wastewater
generated from the proposed activity)
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Total sewage generated will be 178.50 KLD. After treatment about 90% i.e. 160.65 KLD
will be available. Out of which 82.00 KLD will be used for flushing and green belt
development.
Expected Raw Sewage Characteristics
S. No Parameters Units Numeric Values
1. Expected Flow KLD 178.50
2. pH - 6.5-8.5
3. BOD5 mg/ L 250-350
4 COD mg/ L 450-600
5. O & G mg/ L <50
6. SS mg/ L 400-500
Expected Treated Sewage Characteristics:
S. No Parameters Units Numeric Values
1. Expected Flow KLD 160.65
2. pH - 6.0-8.5
3. BOD5 mg/ L <10
4. COD mg/ L <50
5. O & G mg/ L Nil
6. SS mg/ L <10
Prescribed general standards for discharge of environmental pollutants as per
Environment Protection Act-1986
S.
No.
Parameters Standards
Inland
Surface water
Public
Sewers
Land for
Irrigation
Marine/Coastal
areas
1. pH 5.5-9 5.5-9 5.5-9 5.5-9
2. Suspended solids,
mg/L max
100 600 200
3. BOD (3 days at
27ºC), mg/L, max
30 350 100 100
4. Oil and Grease 10 20 10 20
5. COD mg/L, max 250 - - 250
Out of total treated effluent (160.65 KLD), 82.00 KLD will be re-circulated & the rest
78.65 KLD will be used in a manner to reduce the pressure on fresh water demand in
surroundings areas. We are committed to provide our excess treated effluent to any
individual/organization free of cost for their use. We are also willing to adopt Road/parks
in the area for development at the appropriate land. In case there is no demand/
requirement of treated water, we will discharge it in sewer system provided by JDA/
PHED/ Municipal Corporation of Jaipur (after taking necessary permission from
authorities) after disinfection and achieving prescribed standards permissible. Any
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
incremental pollution load of waste water is therefore not envisaged.
2.7 Give details of the water requirements met from water harvesting? Furnish details
of the facilities created.
The project proponents have proposed the roof top rainwater harvesting system. Storm
water from terrace is proposed to be collected treated and will be used in conjunction
with municipal water.
The collected water will be passed through filter bed and settling basin for removal of
dirt and other suspended solids. It will be treated with UV rays before pumping to
domestic supply.
The runoff from roads, paved roads and green belts will be passed through settling basin
and filter bed before discharging it into the recharge well.
2.8 What would be the impact of the land use changes occurring due to the proposed
project on the runoff characteristics (quantitative as well as qualitative) of the area
in the post construction phase on a long term basis? Would it aggravate the
problems of flooding or water logging in any way?
There will not be significant change in run off pattern. The surface runoff which was
going as waste till now will be captured and used for harvesting. The overflow during
heavy rainfall will follow the existing runoff pattern and routed into the municipal storm
water drains.
2.9 What are the impacts of the proposal on the ground water? (Will there be tapping
of ground water; give the details of ground water table, recharging capacity, and
approvals obtained from competent authority, if any)
There will be no significant negative impact on ground water as:
1. Total fresh water requirement for the proposed project will be 158.00 KLD which
will be met from PHED Supply. The application to PHED has been submitted for
water supply.
2. The Project Proponent is planning to recharge runoff on 100 % basis and also
propose to recycle treated waste water. The project proponent has proposed rain
water harvesting system. Storm water would be collected and recharged through
4 recharge structures.
3. Impact on ground water would be insignificant because through water harvesting
of water from road and parking, surface and green areas. Roof top water after
primary treatment & disinfection will be used in conjunction with PHED Supply.
The use of fresh water requirement will be reduced by using treated waste water
for gardening and flushing.
2.10 What precautions/measures are taken to prevent the run-off from construction
activities polluting land & aquifers? (Give details of quantities and the measures
taken to avoid the adverse impacts)
There will be no runoff from the construction activities.
2.11 How is the storm water from within the site managed? (State the provisions made to
avoid flooding of the area, details of the drainage facilities provided along with a
site layout indication contour levels)
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Storm Water Management:
Storms water drains will be constructed strictly in accordance with governing authority
regulations.
Design Details:
Runoff coefficient for various types of surfaces
Parks, Lawns and garden : 0.10
Paver block on sand bed open jointed : 0.40
Water tight roof surface : 0.75
(i) Total Runoff: Roof Top
C = 0.75
I = 50 mm/hr
A = 7259.25 m²
Q = 272.22 M3 /hr
Storm duration 15 Minutes
Volume of water available will be 68.06 M3 /
storm
(ii) Runoff generated from other surfaces
(a) Roads and Parking area- Parking area will be paved (open jointed paved
blocks on sand bed)
C = 0.40
A = 14186.24 m²
I = 50 mm / hr
Q = 283.72M3 /hr
Storm duration 15 Minutes
Volume of water available will be: 70.93 M3
/storm
(b) From open spaces and garden
C = 0.10
A = 2441.9 m²
I = 50 mm / hr
Q = 12.21 M3
/ hr
Storm duration 15 Minutes
Volume of water available will be: 3.05 M3
/storm
Total = 68.06 + 70.93 + 3.05 = 142.04 say 142 M3
/storm
It will be diverted to 4 Rain water harvesting pits.
2.12 Will the deployment of construction laborers particularly in the peak period lead to
unsanitary conditions around the project site (Justify with proper explanation)
During construction phase sewage generated will be treated through the septic tank and
soak pit. Hence it will not lead to unsanitary conditions around the project site.
Septic Tank Details
Total domestic water requirement during construction= 3.60 KLD.
It is assumed that 40 % (1.44 KLD) of total water will be used for flushing and 60%
(2.16 KLD) will be used for domestic purposes. Considering 15 % as losses, total
Sewage generated will be 3.06 KLD.
For 3.06 KLD sewage as per Manual on Sewerage and Sewage Treatment, Ministry of
Urban Development, New Delhi, page no. 334-
Size = 5 m× 2 m × 1m depth (0.2 m freeboard)
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
It will require cleaning once in 2 years.
The septic tank will be supported by a soak pit 0.60 m diameter and 6 m depth.
2.13 What on-site facilities are provided for the collection, treatment & safe disposal of
sewage? (Give details of the quantities of wastewater generation, treatment
capacities with technology & facilities for recycling and disposal).
Total sewage generation from the project will be 178.50 KLD. The sewage will be
treated in a full fledged sewage treatment plant of capacity 200 KLD based on SBR
Technology. Treated sewage will be reused for flushing and gardening within premises.
The sewage treatment unit will consist of following unit processes:
1. Primary treatment
Screen Chamber
Oil & Grease Trap
Equalization Tank
2. Secondary Treatment
Sequencing Batch Reactor (SBR)
3. Tertiary treatment
Treated Effluent holding Tank
Sewage Filtration
Activated Carbon Filter
Disinfection
Sludge Treatment
Process Flow Chart
2.14 Give details of dual plumbing system if treated waste used is used for flushing of
Screen Oil &
Grease
Equalization
Tank
Sequencing
Batch
Reactor
Sludge
Treatment
Disinfection
Filtration
Unit
Irrigation and
Flush Water
Storage Tank
Flushing Gardening
Treated Effluent
Holding Tank
ACF
Used in JDA Greenbelt/Parks /discharged in
Sewer System after taking necessary
permission from regulatory authorities
Filter Press Dried Sludge
used as
Manure
Leachate
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
toilets or any other use.
Two separate pipelines one for fresh water supply and other for treated water will be laid.
3. VEGETATION
3.1 Is there any threat of the project to the biodiversity? (Give a description of the local
ecosystem with its unique features, if any)
No. Presently site is located in the urban ecosystem and does not comprise any unique
feature. Moreover, all the species reported from the study area were common to the urban
ecosystem. So biodiversity will remain unaffected. Therefore there will be no threat to
biodiversity due to proposed project.
3.2 Will the construction involve extensive clearing or modification of vegetation?
(Provide a detailed account of the trees & vegetation affected by the project)
The Group Housing Project site is devoid of any significant vegetation. It is proposed to
plant 156 large trees in open ground area along the boundary of plot.
3.3 What are the measures proposed to be taken to minimize the likely impacts on
important site features (Give details of proposal for tree plantation, landscaping,
creation of water bodies etc along with a layout plan to an appropriate scale?)
It is proposed to plant 156 large trees along the boundary of plot and grasses and other
small decorative plants in Lawn area at podium. Total Green Area provided is 10.22 % of
plot area (2441.9 Sq. m).
4. FAUNA
4.1 Is there likely to be any displacement of fauna –both terrestrial and aquatic or
creation of barriers for their movement? Provide the details.
No significant terrestrial fauna is present. Proposed project site does not contain any
water bodies, hence no aquatic fauna.
4.2 Any direct or indirect impacts on the existing avifauna of the area? Provide
details.
There will not be any direct or in direct impacts on the avifauna of the area. However,
with proposed green cover and additional 60 trees, the project premises may offer
nesting & growing space to avifauna in operational phase.
4.3 Prescribe measures such as corridors, fish ladders etc to mitigate adverse
impacts on fauna.
Not applicable.
5. AIR ENVIRONMENT
5.1 Will the project increase atmospheric concentration of gases & result in heat
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
island? (Give details of background air quality levels with predicted values
based on dispersion models taking into account the increased traffic generation
as a result of the proposed constructions)
No, there is influx of only 2400 Persons and this number will not materially affect the
ambient air quality as clean fuel will be used for cooking.
The development of heat island effect due to this project alone is not envisaged, however,
cluster development in the area can lead to such effect. The proper orientation, intensive
green belt development inside the project & outside wall will minimize it. Moreover,
achieving 30.39 % ground coverage and leaving large open spaces negate the
development of Heat Island Effect. As the proposed project will have only about 2400
persons, air pollution is not expected to be a major concern. But impact on air quality has
been predicted using ambient air quality data collected during the monitoring. The
predicted results depict that there will not be significant negative impact on the existing
ambient air quality of locality around project site.
5.2 What are the impacts on generation of dust, smoke, odorous fumes or other
hazardous gases? Give details in relation to all the meteorological parameters.
During construction phase dust emissions are expected due to excavation activity. All
other emission sources are intermittent, including emission from movement of heavy
vehicle for material transport, unloading of material. However, all necessary measures
will be taken to control the impact by spraying water at dust generation sources, shielding
the construction activity with tarpaulin so as to prevent the dust emission to travel etc.
The gaseous emissions from vehicle will be controlled by avoiding traffic congestion
through proper parking arrangements. Traffic circulation and parking plans are enclosed
as Annexure- XXIII-2 to Annexure- XXIII-3
The fuels used in this residential complex will be clean fuel like bottled liquefied
petroleum gas, which will minimize air pollution.
Hence there will not be significant negative impact on the Air environment due to
project.
As this will be residential building with 2400 persons, air pollution is not expected to be
a major concern. Hence, the air quality predictions have been carried out. Data on
ambient air quality have been collected during the study period and the predicted results
depict that there will not be significant negative impact on the existing ambient air
quality of locality around project site.
5.3 Will the proposal create shortage of parking space for vehicles? Furnish details of
the present level of transport infrastructure and measures proposed for
improvement including the traffic management at the entry & exit to the project
site.
The project proponent has proposed to provide well organized parking. The provided
parking details are as under:
Required Parking:
Required Parking = Achieved F.A.R / 75 = 29094.56 /75 = 387.92 E.C.U
Add 25% Visitors Parking = 387.92 x 0.25 = 96.92 E.C.U
Total = 387.92 E.C.U + 96.92 E.C.U = 484.84 E.C.U say 485 E.C.U
TOTAL E.C.U Required = 485.00 E.C.U
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Parking Provided:
Total Parking Provided = 523.00 E.C.U
Provision for Parking of 523.00 E.C.U. has been made as follows:
Floor
Provided
Total E.C.U CARS TWO WHEELERS
E.C.U SCOOTERS E.C.U
STILT 64.00 0.00 0.00 64
OPEN GROUND 368.00 57.00 19.00 387
BASEMENT 72.00 0.00 0.00 72
TOTAL 504.00 57.00 19.00 523
5.4 Provide details of the movement patterns with internal roads, bicycle tracks,
pedestrian pathways, footpaths etc., with areas under each category.
Parking plan showing traffic movement is Annexure- XXIII-2 to Annexure- XXII-3.
5.5 Will there be significant increase in traffic noise & vibrations? Give details of the
sources and the measures proposed for mitigation of the above.
The source of noise will be vehicular noise only. A well organized parking is proposed,
which will help in reducing noise level due to vehicular movement in parking area.
Sufficient no. of trees (156 large trees in addition to shrubs and other small plants) will
be planted to act as noise buffer and reducing noise level within the site.
5.6 What will be the impact of DG sets & other equipment on noise levels & vibration
in & ambient air quality around the project site? Provide details.
It is proposed to provide 1 D.G. Sets of capacity 250 kVA for common facilities. The
D.G. set will provide power only in case of power failure or emergency. The emissions
from D.G. set will be discharged through vent of proper height.
Total power requirement of project is 2102.01 KW. The power will be received from
JVVNL at 33 KV supply voltage, it will be stepped down to 0.433 KV through one 3150
kVA transformer.
D.G. sets will be enclosed in acoustic enclosure (as per GSR7, Dated Dec22, 1998) to
mitigate effect of their noise during operation.
The emissions from D.G. sets will be in conformity with standards prescribed under
Environment (protection) Act- 1986.
6. AESTHETICS
6.1 Will the proposed constructions in any way result in the obstruction of a view,
scenic amenity or landscapes? Are these considerations taken into account by the
proponents?
No, the project is well planned and is developed keeping local aesthetics in mind.
6.2 Will there be any adverse impacts from new constructions on the existing
structures? What are the considerations taken into account?
No. There is no any existing structure.
6.3 Whether there are any local considerations of urban form & urban design
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
influencing the design criteria? They may be explicitly spelt out.
No. There are no such local considerations
6.4 Are there any anthropological sites or utilized nearby? State if any other significant
features in the vicinity of the proposed site have been considered.
No.
7. SOCIO-ECONOMIC ASPECTS
7.1 Will the proposal result in any changes to the demographic structure of local
population? Provide the details.
The proposed project is residential. There will be influx of people around 2400 persons.
It will not cause significant change in demographic pattern. The project may however,
create jobs for unskilled and skilled labour both during construction phase as well as
during operation phase which will benefit local populace.
7.2 Give details of the existing social infrastructure around the proposed project.
The project is located in residential area cum commercial area under jurisdiction of
Jaipur Development Authority with all basic facilities like roads, electricity, water
supply, transportation, educational institute, hospitals, market etc.
7.3 Will the project cause adverse effects on local communities, disturbance to sacred
sites or other cultural values? What are the safeguards proposed?
No, on the contrary it may open job opportunities for local people. The options are
domestic help, gardeners, watch and ward staff, cooks etc. It will also create additional
business for local shops.
8. BUILDING MATERIALS
8.1 May involve the use of building materials with high-embodied energy. Are the
construction materials produced with energy efficient processes? (Give details of
energy conservation measures in the selection of building materials and their energy
efficiency)
Cement, aluminum, paints, floor tiles etc used in the project are purchased from branded
companies and it is also ensured that these bear IS mark.
8.2 Transport and handling of materials during construction may result in pollution,
noise& public nuisance. What measures are taken to minimize the impacts?
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
During construction phase following measures will be taken to prevent pollution due to
transportation and handling of material-
1. Covering the site on all four sides to prevent dust and other pollutants to the
surrounding environment.
2. Water spraying to prevent dust from different sources.
3. Speed restriction to all vehicles approaching the site and within site.
4. All vehicles used for transportation of materials will be covered with tarpaulin.
5. Overloading of vehicles will be avoided.
8.3 Are recycled materials used in roads and structures? State the extent of savings
achieved?
Yes, approx. 5000 m³ of construction debris and 8,000 m³ (approx.) earth as recycled
material is available and will be used in road construction resulting in saving of Rs.10.00
Lacs (approx)
8.4 Give details of the methods of collection, segregation & disposal of the garbage
generated during the operation phases of the project.
According to the building construction manual of MoE&F the rate of waste generation in
residential building is 0.41 Kg/day/person. In the Residential Section of project, out of
total domestic waste, 40 % will be the wet garbage and rest (60 %) will be dry garbage.
The solid waste so generated will be first segregated as plastic, glass, paper and other
waste separately and disposed off as per MSW Rules, 2000 (amended up to date).
Generation of Waste from Project (kg/day) = 0.41 X Estimated Population
= 0.41 x 2400
= 984 kg/day
Dry waste @ 60% Total Waste Generated = 590.40 kg/day
Wet Garbage @40% Total Waste Generated = 393.60 Kg/day
Management of Solid Waste during Operation Phase:-
Collection and Segregation of waste
I. A door to door collection system will be provided for collection of domestic waste
in colored bins from the different blocks.
II. For waste collection, adequate number of colored bins (Green and Blue & dark
grey bins– Separate for Bio-degradable and Non Bio-degradable) are proposed to
be provided at the strategic locations of the area.
III. Litter bin will also be provided in open areas like parks etc.
Handling of Waste:
Recyclable wastes
I. Grass Recycling – The cropped grass will be spread on the green area. It will act
as manure after decomposition.
II. The saleable waste like paper, plastic, metals etc segregated during collection will
be sold off to recyclables.
Disposal
Non-recyclable wastes will be disposed through Govt. approved agency. Hence, the
Municipal Solid Waste Management will be conducted as per the guidelines of Municipal
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Solid Waste
Biodegradable Waste
Recyclable Waste
Green Bins
Non Biodegradable Waste
Non- Recyclable Waste
Dark Gray Bins Blue Bins
Sold to Respective
Recyclers/Buyers
Final Disposal through Municipal Corporation of City
Segregation during Waste Collection
Remaining
Solid Wastes (Management and Handling) Rules, 2000 amended up to date). A Solid
waste management Scheme is depicted in the following figure for the project-
Solid Waste Management Scheme During Operational Phase.
9. ENERGY CONSERVATION
9.1 Give details of the power requirements, source of supply, backup source etc. what is
the energy consumption assumed per square foot of built-up area? How have you
tried to minimize energy consumption?
The power will be received from JVVNL at 33 KV supply voltage, it will be stepped
down to 0.433 KV through one transformer of 3150 kVA capacity.The power
requirements of the project will be met by Jaipur Vidyut Vitaran Nigam during
construction and operation phase.
9.2 What type of, and capacity of, power back up you plan to provide?
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
D.G. set and transformer shall be provided in case of power failure for Lifts, lighting of
roads and circulation area.
Type Capacity No. Specification
DG Sets
Transformers
250 kVA
3150 kVA
33 KV to 0.433 KV
1
1
To confirm emission Limits as
prescribed under E P Act-1986 and
having acoustic arrangement as per
EP act-1986. The DG sets will carry
„Type approval Certificate‟.
9.3 What are the characteristics of the glass you plan to use? Provide specifications of
its characteristics related to both short wave and long wave radiation?
Saint Gobain Glass, Shade- Neutral, Single Glazed (Dew Drop) will be used for
windows.
Properties:
Visible Light
Transmission 51%
Reflection Outside 18%
Reflection inside 17%
Solar Energy
Direct Transmission 45%
Reflection Outside 14%
Absorption 41%
UV Value: 5.7 W/ (m2.K
0)
9.4 What passive solar architectural features are being used in the building?
Illustrate the applications made in the proposed project.
Jaipur comes under composite zone according to the classification of climate zones. Solar
passive architectural features that are used in the building are-
1) Low exposed surface to volume ratio: - This is obtained through optimized building
shape, form, correct orientation and multistoried building.
2) Increased thermal resistance and thermal capacity which is achieved through
insulating roof and using thick external walls.
3) Increase buffer zones to protect the building mass from direct exposure to solar
radiation. This achieved through incorporating verandas and balconies in the design,
especially if, openings are provided in west direction.
4) Decrease outside air exchange rate during day time while increase air exchange rate
during night time through windows and ventilations.
5) Increase shading, by protecting glazed surfaces through overhangs, louvers and trees.
6) Increase external surface reflectivity through selecting light or pale colour finish of
the building envelope and heat proofing the roof.
7) In summer months, increase the humidity, which could be obtained through
plantation of trees and also through evaporative cooling.
8) Glazed windows are located to face the south (in the northern hemisphere) to receive
maximum sunlight in winter.
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
9.5 Does the layout of streets & buildings maximize the potential for solar energy
devices? Have you considered the use of street lighting, emergency lighting and solar
hot water systems for use in the building complex? Substantiate with details.
Methods Used To Conserve Energy:
1. Use of CFL Lamps in Lighting
2. Use of Solar Powered Lights In Landscape & Street Lighting
3. Use of Solar Hot Water Generators for Water Heating
S.
No. Energy Conservation Measures
Operation at
load (KW)
i
Total Flats Light Load- 1320 KW can be reduced by
11.78 % if we use CFL Lamps in place of Flourescent/
Incandescent Lamp
155.52
ii Total Landscape & Street load -20 KW can be reduced by
100% if we use solar powered fixtures. 10.00
iii
Total Common area light load- 30 KW can be reduced by
16% if we use led lamps in place of
flourescent/incandescent lamps
4.80
iv Total Power load - 1692 KW can be reduced by 10 % if
solar hot water generator is used 252.00
v Total energy conservation achieved 422.32
vi Total energy conservation achieved in percentage 20.09 %
Light & power load saving calculation
S.
No. Energy Conservation Measures
Operation at
load
i Total Light Load in W (55W each light) 213840 W
ii Total Light Load in W (55W each light) 58320W
iii Watts saved by using LED lights in place 155520W
iv KW saved in light load 155.52KW
v KW saved in light load 172.80KVA
vi Total KVA load after saving in lights 2162.76KVA
vii % Light load saving 11.78
viii % Power load saving 14.89
9.6 Is shading effectively used to reduce cooling/heating loads? What principles have
been used to maximize the shading of walls on the East and the West and the Root?
How much energy saving has been effected?
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
The following precautions will be taken to minimize weather effects within the buildings-
1. Care is taken to have minimum exposed area of the building. Maximum heat
enters a building from roof & west walls. In a multistory building only the top
roof will be exposed & it will be insulated. Minimum openings in the west wall
will be kept. When openings in the west wall become unavoidable the openings
will be properly shaded.
2. The external walls will have minimum thickness of 200 mm. where feasible
hollow building blocks for external walls will be used.
3. For dissipation of heat cut outs open to sky in the buildings will be provided.
4. Size of the windows will be kept smaller to decrease air exchange rate and
provide ventilation during day time.
5. Properly designed sun shades will be used.
6. External paints will be of reflective type.
7. Minimum glazing would be provided in west side.
9.7 Do the structures use energy-efficient space conditioning, lighting and mechanical
systems? Provide technical details. Provide details of the transformers and motor
efficiencies, lighting intensity and air-conditioning load assumptions? Are you using
CFC and HCFC free chillers? Provide specifications.
Natural ventilation will be used to get maximum advantage of nature. CFL lighting in all
common areas will be used although LED is more energy efficient but its cost is high in
comparison to CFL. DG Set will be in acoustic enclosure. Proponent will provide only
power points for air conditioners and further responsibility of installation of air
conditioner will be of buyers. Central air conditioning of the building is proposed.
9.8 What are the likely effects of the building activity in altering the micro-climates?
Provide a self assessment on the likely impacts of the proposed construction on
creation of heat island & inversion effects?
Measure to minimize the effects of DG set emissions in altering the microclimate are
given below:-
1) Genset will be furnished with turbochargers to reduce consumption of diesel
consequently reducing the generated heat.
2) Genset will be installed in well ventilated area to ensure quick dissipation of heat.
3) Genset will be provided with vent/ stack as per CPCB rules.
4) DG Set will be used in case of power failure.
9.9 What are the thermal characteristics of the building envelope? (a) roof; (b) external
walls; and (c) fenestration? Give details of the material used and U-values or the R-
values of the individual components.
It is proposed that the roof of these buildings to minimize the heat gain and turn save the
energy.
S. No. Specification U values
[W/(m2.K]
Wall
1 1.25 cm PL + 11.25 cm brick + 1.25 cm PL 3.00
2 1.25 cm PL + 22.25 cm brick + 1.25 cm PL 2.13
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Roof
3 10cm RCC + 10 cm lime concrete 2.78
4 10 cm + 7.5 cm cin +5 cm brick tile 1.76
The roof will be further insulated by using foam concrete having high thermo insulation
properties. The technical specifications are:
1 Density (Kg/m3) 704.0
2 Thermal Conductivity (W/mK) 0.149
3 Specific Heat Capacity (kJ/Kg.K) 0.92
These values have been taken from Handbook on “Functional Requirement of
Buildings (other than Industrial Building)”- Bureau of Indian Standards- SP: 41
(S & T) – 1987.
9.10 What precautions & safety measures are proposed against fire hazards? Furnish
details of emergency plans.
9.11 If you are using glass as wall material provides details and specifications including
emissivity and thermal characteristics
No
9.12 What is the rate of air infiltration into the building? Provide details how you are
mitigating the effects of infiltration.
Typical air infiltration rate is 0.1 ACH (air change /hr). It will be reduced further to 0.07
ACH by properly designed doors and windows to ensure air tightness.
The buildings intended to be air conditioned are designed for low air exchanges achieved
by air tight windows and doors. Generally air conditioners are designed for 0.1 ACH.
In well insulated buildings, heat is lost mostly as a result of mass and energy transfer
during ventilation by fresh air takes place.
Disaster Management Plan
Fire Water Earthquake
Rain water will be
recharged to ground.
Excess storm water
will be routed to
natural drainage
system
The structural
design is as per
BIS codes for
Seismic Zone II
All arrangements as per
regulations of CFO will be
made. Necessary permission
from competent authority
will be obtained
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Careful consideration should be given to the following:
1. An airtight construction with controllable means of ventilation to minimize
unwanted infiltration of outdoor air while providing an adequate supply of fresh
air.
2. In summer during day time windows and doors will be kept mostly in closed
position to avoid flow of hot air from outside into the building.
3. In summer during night windows will be opened to admit cool night air into the
house.
During winter windows and doors would be opened optimally to keep the house well
ventilated without creating draft of chill winds in the house.
9.13 To what extent the non-conventional energy technologies are utilized in the overall
energy consumption? Provide details of the renewable energy technologies used.
It is proposed to use solar energy based lights for the common passages and
driveways.
10. ENVIRONMENT MANAGEMENT PLAN
The Environment Management Plan would consist of all mitigation measures for each
item wise activity to be undertaken during the construction, operation and the entire life
style to minimize adverse environmental impacts as a result of the activities of the
project. It would also delineate the environmental monitoring plan for compliance of
various environmental regulations. It will state the steps to be taken in the case of
emergency such as accidents at the site including fire.
Environmental
component
Phase Project Activity Potential Impact Mitigation Measure
Air
Constructi
on
Phase
Site Clearance/
Operation
Dust Pollution Sprinkling of water
above the area before
Clearing. Covering the
site on all four sides to
prevent dust and other
pollutants to the
surrounding
environment.
Heavy Vehicle
Maintenance/
Operation
Air Pollution
Dust Generation
Vehicles used for
transportation of
material shall be
covered with tarpaulin.
All vehicles shall be
asked to have valid
PUC Certificate.
Construction of
structure and
earth work
Dust due to
cutting and filling
Wetting of area before
clearing. All vehicles
shall be asked to have
valid PUC.
Operation
Phase
Traffic
movement
on Road
Increased
concentration of
air pollution at
some location
Temporary internal
roads, loading and
unloading will be
designed to have
smooth flow of traffic,
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Regulation of air
pollution
by legislation and
public awareness.
DG set
operation
Air Pollution DG set adhering to
CPCB Norms.
Proper maintenance of
DG set.DG set will be
enclosed in acoustic
enclosure.
Noise
Constructi
on
Phase
Heavy Vehicle
Maintenance
Increased
vehicular noise
The vehicles used for
Construction work shall
be regularly maintained
and shall be asked to
adhere to CPCB norms
Construction of
structure and
earth work
Noise from
vibrators,
Concrete
batching
plants etc.
Proper maintenance of
equipments.
Providing ear plugs to
workers employed in
close vicinity of noise
producing machine.
Operation
Phase
Vehicular
Traffic
Increased noise
due to vehicular
traffic
Ensuring smooth flow
of traffic.
Properly designed
parking.
Provision of rows of
trees to act as buffer.
DG set
operation
Increased noise
levels
DG set adhering to
CPCB norms
Proper maintenance of
DG Set.
DG set will be enclosed
in acoustic enclosure.
Water
Constructi
on
Phase
Construction
Staff Water
Requirement
Strain on local
water sources
Drinking water will be
purchased from
authorized water
supplier.
Operation
Phase
Building User
Water
Requirement
Strain on PHED Drinking water will be
supplied by PHED.
Recycled water from
treated effluent of STP
will be used for
flushing and green area
development and all
excess treated water
will be discharged in
drains maintained by
PHED after obtaining
necessary permissions.
Soil Storage of Pollution due to Storage of petroleum
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Constructi
on
Phase
petroleum and
other chemicals
mixing of
construction
Material.
and other chemicals on
Impervious floor viz
plain Concrete. Careful
handling of materials
will be ensured.
Construction
debris and earth
Material.
Pollution due to
mixing of
concrete with
soil.
Mixed Concrete and
such debris will be
unloading on
impervious metal
sheets, any waste or
spillage will be
collected and stored
properly used in making
road embankment and
sub base for parking
area.
Transportation
of hazardous
material
Accidental
spilling of
hazardous
material
Construction Process
does not involve
transportation of
hazardous material
except in very small
quantities, lubricant oil
and enamel paint. In
transportation of these
materials all precaution
as required by
regulation will be taken.
Residual paints
solvent,
bituminous
material
Contamination of
soil
Use of non hazardous
emulsion paints, cement
based putty shall be
done require water
thinner/solvent only.
Enamel paint/paint
solvent used in very
small quantity will be
sold and used with
waste generated, will be
handled to authorize
recyclers.
Heavy Vehicle
Maintenance/
Operation
Oil spillage Use of electrically
operated machines to
the possible extant. Oil
tray will be kept below
all potential oil spillage
points for final disposal
of spillage to authorized
recyclers.
Operation
Soil
contamination
due to surface
Oil & Grease trap shall
be provided at STP and
sludge from trap shall
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
Operation
Phase
run off / Oil and
grease dripping
from vehicle
be dumped at site
approved/authorized by
appropriate authority.
Solid waste
generation
Improper
disposal of
plastic/kitchen
waste.
Segregation of solid
waste at source shall be
practiced and
segregated waste shall
be handed over to
authorized agency of
Jaipur Nagar Nigam for
final disposal.
Ecology
Constructi
on
Phase
Construction of
Structure and
earth work
Migration of
fauna due to
construction
Use of electrically
operated machines to
the possible extent, and
proper maintenance of
machines to keep noise
level low.
Operation
Phase
Operation
Increased
exposure to
anthropogenic
activities.
Enactment and
enforcement of laws
regulating human
intrusion.
Projected Expenses on Environmental Management
S.
No.
Description Capital Cost
(Rs in lacs)
Recurring Cost/Year
(Rs in lacs)
1 STP 40 3
2 Landscaping 5 0.5
3 Ground Water Recharge Structure 5.0 0.50
4 Acoustic Enclosure 3 -
5 Dual Plumbing System 20 -
6 Solar Energy Utilization Application 10 3
7 Energy Efficient Lighting 3 2
8 Solid Waste Management 3 1.2
9 Efficient Fixtures 12 -
10 Monitoring of Air, Water, Noise &
Soil
- 2.2
11 Insulation of walls & roof 20 -
Total Rs. 111/- Lacs Rs. 12.40/- Lacs
Environmental Monitoring Schedule
S. No. Activity Frequency Annual Sample Budget (in Rs.)
Regalia Builders TEAM Institute of Science & Technology Pvt. Ltd.
Authorized Signatory Authorized Signatory
1. Ambient Air Quality
monitoring
2 Locations,
Quarterly
8@ Rs. 6000 48000
2. Noise Monitoring 2 Locations,
Quarterly
8@ Rs.2400 19200
3. Waste Water
Monitoring
2 Sample Per Month
(Inlet & Outlet)
24@ Rs. 2500 60000
4. Drinking Water
Monitoring
1 Sample,
Half Yearly
2@ Rs. 16000 32000
5. Soil Monitoring 2 Locations,
Half Yearly
4@ Rs. 2500 10000
6. Transportation
Charges
50000
Annual Budget for Environmental Monitoring Rs. 219200/-
Say 2.2 Lacs
Monitoring of Air, Water, Noise & Soil will be carried out by MoEF approved laboratory on
contract basis.
Budgetary Breakup for Labour
Fixed Explicit Investment:
S. No. Activity Fixed Capital
(in Rs.)
1. Temporary Houses to workers – 20 Nos.@ Rs. 25000 Rs. 5,00,000
2. Common Toilet- 4 Nos. @ 10,000 Rs. 40,000
3. Bathing Area- 4 Nos. @ 10,000 Rs. 40,000
4. Stoves to each family- 20 Nos. @ Rs. 2000 Rs. 40,000
5. A medical room will be provided for regular health
checkups and medical aid for which one doctor and
compounder will be hired.
Rs. 25,000
6. RO Plant (50 lpm) - 1 Nos. Rs. 50,000
Total Rs. 6,95,000
Running Expenses per Month:
S. No. Activity Running Capital (Rs.)
1. Kerosene Oil to workers- 40 l/month/family @ Rs. 35 Rs. 28,000
2. Medical Facility ( 1 Doctor + 1 Compounder) on visit
basis
Rs. 15,000
3. Electricity and general expenses Rs. 2,000
4. Proponent will encourage labour to send their children to
nearby school for which financial support will be made.
Rs. 12,000
Total Rs. 57,000
Details of CSR Activity
Proposal under Corporate Social Responsibility for Proposed Group Housing Project “Ashadeep