Appendix D

COST ESTIMATION

Page 2: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each
Page 3: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

ALTERNATIVE COST ESTIMATES FOR COMPARISON

2008 DOLLARS

CALCASIEU RIVER AND PASS, LOUISIANA DREDGED MATERIAL MANAGEMENT PLAN

Contract No. DACW27-03-D-0005

Delivery Order No. CZ03 GEC Project No. 27321CZ03

Prepared for:

U.S. Army Corps of Engineers

New Orleans District New Orleans, Louisiana

Prepared by:

GAHAGAN & BRYANT ASSOCIATES, INC.

10631 SOUTH SAM HOUSTON PARKWAY WEST SUITE 190 HOUSTON, TEXAS 77071-3140 PHONE (832) 518-2112 FAX (832) 518-1496

Page 4: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each
Page 5: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-i

TABLE OF CONTENTS Page

1 INTRODUCTION.........................................................................................................D-1 2 GENERAL BASIS OF ESTIMATE AND ASSUMPTIONS .......................................D-27 2.1 Placement Areas (CDFs) ..............................................................................D-27 2.2 Beneficial Use Sites ......................................................................................D-30 2.3 Hydraulic Dredging Costs..............................................................................D-31 2.4 Shore Protection Costs .................................................................................D-34 2.5 Alternatives B and C......................................................................................D-34 2.6 Alternative D - Hopper Dredging ...................................................................D-35 3 SITE SPECIFIC INFORMATION ..............................................................................D-39 3.1 Alternative B - Emphasis on Placement at Currently Available Site ......D-39 3.1.1 Reach 34-36 ......................................................................................D-39 3.1.2 Reach 30-34, Clooney Island and Turning Basin ..............................D-40 3.1.3 Reach 26-30 ......................................................................................D-40 3.1.4 Reach 22-26 ......................................................................................D-42 3.1.5 Reach 21-22 ......................................................................................D-43 3.1.6 Reach Devil’s Elbow..........................................................................D-44 3.1.7 Reach 16-21 ......................................................................................D-44 3.1.8 Reach 12-16 ......................................................................................D-48 3.1.9 Reach 9.5-12 .....................................................................................D-50 3.1.10 Reach 5-9.5 .......................................................................................D-51 3.2 Alternative C - Emphasis on Placement at Beneficial Use Sites ............D-52 3.2.1 Miles 36 to 22 ....................................................................................D-52 3.2.2 Reach Devil’s Elbow..........................................................................D-52 3.2.3 Reach 16-21 ......................................................................................D-53 3.2.4 Reach 12-16 ......................................................................................D-56 3.2.5 Reach 9.5-12 .....................................................................................D-57 3.2.6 Reach 5-9.5 .......................................................................................D-57 3.3 Alternative D - Placement of Material in the Ocean Disposal Management Site (ODMDS) ........................................................................D-57 3.3.1 Miles 26 to 22 ....................................................................................D-57 3.3.2 Reach 21-22 ......................................................................................D-57 3.3.3 Reach Devil’s Elbow..........................................................................D-58 3.3.4 Reach 16 - 21 ....................................................................................D-58 3.3.5 Reach 12 - 16 ....................................................................................D-58 3.3.6 Reach 9.5 to 12 .................................................................................D-58 4 BAR CHANNEL........................................................................................................D-58 5 COSTS FOR EACH SITE..........................................................................D-59 to D-144

Page 6: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-ii

LIST OF TABLES Number Page D-1 Alternative B Cost Estimate ........................................................................................D-3 D-2 Alternative C Cost Estimate ......................................................................................D-11 D-3 Option D Cost Estimate.............................................................................................D-21 D-4 Site Management Costs............................................................................................D-29 D-5 Beneficial Use Site Parameters and Shore Protection Costs....................................D-31 D-6 Hydraulic Cutterhead Dredge Cost and Production Analysis....................................D-33 D-7 Industry Hopper Fleet Analysis for Mobile District Hopper Dredge Rental Contract .............................................................................................D-37

Page 7: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-1

1 INTRODUCTION The following cost estimates are considered planning level estimates used for determining the

cost of various alternatives. The estimates demonstrate the relative cost to one another. The

estimates are not intended to identify final projected cost of the project. A further defined cost

estimate based on the selected alternative will be developed in the future.

Cost estimates were developed for Options B, C and D that considered dredging, placement

area construction, shore protection, site management, lands easements rights of ways and

relocations (LERRs) engineering and design, and supervision and administration. Each option

divided the channel from river mile 5 to mile 36 into 10 segments in addition to the Bar Channels

for which the costs were estimated. The costs for each cycle over the 20 year term of the

DMMP were adjusted for escalation per 1110-2-1304 Civil Works Construction Cost Index

System. While these planning level estimates were made to primarily provide an order of

magnitude cost of an option and an annual estimated funding requirement, they also provide a

basis for comparison of the options. An overall 15% contingency was applied to all estimates

for the first 5 years and 20% for the remaining years due to the breadth of uncertaintainties

surrounding the options and the advice of the ITR process. Fuel costs were estimated at $3.76

per gallon for off-road diesel as of May 2009. South East Labor and Benefit rates for the Local

25 southern dredging union were used to establish unit costs, production, and rates. Alternative

B, the Recommended Plan, is estimated at a total of $788 million. Approximately $628 million is

estimated for Mile 5 to 36 and $160 million for the Bar Channel Sections. Alternative C is

estimated at $800 million. Approximately $640 million is estimated for Mile 5 to 36 and $160

million for the Bar Channel Sections. Alternative D is estimated at over $1 Billion over the life of

the DMMP and has been eliminated from further consideration as a viable plan.

The cost estimates and assumptions listed in this Appendix have been used to evaluate and

compare the costs for each alternative.

The estimates prepared under this appendix have been used in the DMMP for the cost estimate

as the separable items relating to cost sharing, and operation and maintenance are more easily

separated.

Page 8: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-2

Tables D-1 to D-3 provides a summary of the costs for all three options by year, river reach and

site. The amounts in the tables also indicate the cost sharing values for elements per law and

policy at the time the estimate was made.

Page 9: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-3

Table D-1. Alternative B Cost Estimate Year Total

Section Placement Sites Type Cost

Share 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Local 25% 181 54

Federal 75% 543 163 O&M 1,416 31 32 471 35 1,731 38

1

Total 724 1,416 31 32 0 471 35 0 0 217 1,731 38 0 0 0 0 0 0 0 0 4,695Local 25% 131 47

Federal 75% 392 140 O&M 1,416 27 28 1,731 34 562 37

34 to 36

2

Total 523 1,416 27 28 0 0 0 0 0 187 1,731 34 0 0 0 562 37 0 0 0 4,545Local 25% 233 115

Federal 75% 698 345 O&M 5,112 70 71 1,515 80 3,180 87

3

Total 931 5,112 70 71 0 461 1,515 80 0 0 0 3,180 87 0 0 0 0 0 0 0 11,506Local 25% 192 48

Federal 75% 575 144 O&M 77 78 3,180 98 1,917 108

30 to 34

7

Total 77 78 0 767 0 0 0 0 0 0 0 3,180 98 0 192 0 1,917 108 0 0 6,417Local 25% 192 48

Federal 75% 575 144 O&M 77 78 3,659 87 88 98 4,645 106

7

Total 77 78 0 767 3,659 87 88 0 0 0 0 0 98 0 192 4,645 106 0 0 0 9,798Local 25% 396 99

Federal 75% 1,187 297 O&M 3,659 131 133 4,174 143

8

Total 0 0 0 1,583 3,659 131 133 0 397 4,174 143 0 0 0 0 0 0 0 0 0 10,219Local 25% 398 96

Federal 75% 1,194 288 O&M 4,174 125 127 4,645 139

26 to 30

9

Total 0 0 0 0 0 0 0 0 1,592 4,174 125 127 0 0 385 4,645 139 0 0 0 11,187Local 25% 342 51

Federal 75% 1,026 152 O&M 2,332 87 92 1,870 105 2,008 112

10

Total 0 0 1,368 2,332 87 92 0 0 0 0 203 1,870 105 0 0 2,008 112 0 0 0 8,176Local 25% 320 50

Federal 75% 960 151 O&M 1,502 84 86 2,612 97 1,870 105 2,008 112

11

Total 1,280 1,502 84 86 0 0 0 2,612 97 0 201 1,870 105 0 0 2,008 112 0 0 0 9,958Local 25% 407 60

Federal 75% 1,220 180 O&M 2,332 103 110 2,612 116 1,870 125 2,008 134

12A

Total 0 0 1,627 2,332 103 110 0 2,612 116 0 240 1,870 125 0 0 2,008 134 0 0 0 11,276Local 25% 951 132

Federal 75% 2,853 396 O&M 3,006 267 272 5,040 300 5,414 322 5,814 346 6,242 371 6,458

22 to 26

12B

Total 0 3,006 267 272 0 5,040 300 0 3,804 5,414 322 0 0 5,814 346 0 528 6,242 371 6,458 38,183

Page 10: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-4

THIS PAGE LEFT BLANK

Page 11: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-5

Table D-1. Alternative B Cost Estimate Continued

Local 25% 1,783 140

Federal 75% 5,350 421

O&M 1,571 110 112 1,665 123 1,866 132 2,004 142 2,152 152 15

Total 1,571 110 112 7,134 1,665 123 0 0 1,866 132 0 0 2,004 142 0 561 2,152 152 0 0 17,725

Local 25% 1,329 110

Federal 75% 3,988 329

O&M 1,607 105 107 1,801 117 1,934 126 2,077 135 2,228 145

21 to 22

16N

Total 0 5,317 1,607 105 107 0 1,801 117 0 438 1,934 126 0 0 2,077 135 0 0 2,228 145 16,138

Local 25% 492 120

Federal 75% 1,477 360

O&M 3,631 219 223 3,850 242 4,314 260 4,634 279 4,976 299 13A

Total 5,601 0 219 223 3,850 242 0 480 4,314 260 0 0 4,634 279 0 0 4,976 299 0 0 25,377

Local 25% 492 124

Federal 75% 1,477 373

O&M 3,716 223 227 4,163 251 4,471 269 4,802 289 5,152 310

Devil's Elbow

13B

Total 1,970 0 3,716 223 227 0 4,163 251 0 497 4,471 269 0 0 4,802 289 0 0 5,152 310 26,339

Local 25% 1,101 248

Federal 75% 3,304 744

O&M 1,830 3,592 261 4,215 285 17

Total 0 0 0 0 0 0 0 0 0 0 0 6,236 3,592 261 0 0 993 4,215 285 0 15,582

Local 25% 1,567 312 218

Federal 75% 4,700 935 653

O&M 2,208 4,929 184 3,556 201 1,994 208 19

Total 0 0 0 8,475 0 4,929 184 0 1,247 0 3,556 1,072 1,994 208 0 0 0 0 0 0 21,665

Local 25% 1,778 579 278

Federal 75% 5,334 1,738 833

O&M 217 4,929 239 3,665 262 5,585 271 5,899 286 22

Total 0 0 0 7,330 0 4,929 239 2,317 0 3,665 1,373 5,585 271 0 5,899 286 0 0 0 31,895

Local 25% 114 116 133 153 159

Federal 75% 341 349 399 460 477

O&M 7,553 7,729 8,816 10,160 13,452

Meracantel (BU50)

Total 8,008 0 8,195 0 0 0 0 9,348 0 0 0 0 0 0 0 10,773 0 14,088 0 0 50,413

Local 25% 1,819

Federal 75% 5,457

O&M 4,378 181 4,480 187 5,109 213 3,556 225

16 to 21

Foreshore Dike (FSD)

Total 11,654 181 4,480 187 0 0 0 5,109 213 0 3,556 225 0 0 0 0 0 0 0 0 25,605

Page 12: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-6

THIS PAGE LEFT BLANK

Page 13: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-7

Table D-1. Alternative B Cost Estimate (Continued)

Local 25% 2,887 1,027 Federal 75% 8,662 3,081 O&M 377 4,828 415 10,006 430 10,556 454 3,587 470

D,E Expanded (DEX)

Total 0 0 0 11,927 0 4,828 415 10,006 430 4,108 10,556 454 3,587 470 0 0 0 0 0 0 46,782Local 25% 1,151

Federal 75% 3,452 O&M 4,828 206 1,883 233 5,771 246 4,247 255

Foreshore Dike (FSD)

Total 0 0 0 0 0 4,828 206 0 0 4,602 0 0 1,883 233 0 5,771 246 4,247 255 0 22,272Local 25% 73 73 93 98 101

Federal 75% 218 218 278 294 304 O&M 13,411 13,724 8,671 9,147 12,156

12 to 16

Sabine (BU5)

Total 13,701 0 14,015 0 0 0 0 0 0 0 0 0 9,042 0 0 9,538 0 12,562 0 0 58,858Local 25% 119 131 138

Federal 75% 356 392 414 O&M 8,260 2,796 5,163

Cameron SB (BU49)

Total 0 0 0 474 8,260 0 523 2,796 0 551 5,163 0 0 0 0 0 0 0 0 0 17,768Local 25% 114 131 138 145 153 162

Federal 75% 341 392 414 436 460 485 O&M 7,695 6,816 4,976 9,922 10,468 11,022

9.5 to 12

Sabine (BU18)

Total 455 7,695 0 0 0 0 523 6,816 0 551 4,976 0 582 9,922 0 614 10,468 0 647 11,022 54,271Local 25% 249

Federal 75% 746 O&M 2,751 88 89 2,129 114

H

Total 994 2,751 88 89 0 0 0 0 0 0 0 0 0 2,129 114 0 0 0 0 0 6,165Local 25% 710 163

Federal 75% 2,129 490 O&M 2,895 266 271 3,362 296 4,965 312 7,483 329 3,940

M

Total 0 0 0 2,839 2,895 266 271 0 0 0 3,362 296 0 4,965 312 653 7,483 329 0 3,940 27,612Local 25% 500 152

Federal 75% 1,500 456 O&M 2,751 137 139 3,362 168 3,940

N

Total 2,000 2,751 137 139 0 0 0 0 0 0 3,362 168 0 0 0 0 0 0 608 3,940 13,103Local 25% 91

Federal 75% 273 O&M 6,780

Cameron WR (BU19)

Total 0 0 0 0 0 0 364 6,780 0 0 0 0 0 0 0 0 0 0 0 0 7,144Local 25% 83

Federal 75% 248 O&M 5,134

5 to 9.5

Cameron WR (BU20)

Total 0 0 0 331 5,134 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5,465 Local 25% 4,717 1,329 938 9,706 0 115 352 253 2,339 2,788 161 1,597 238 0 192 708 380 260 314 0 26,389 Federal 75% 14,151 3,988 2,813 29,118 0 345 1,057 759 7,018 8,364 483 4,791 715 0 577 2,125 1,141 781 941 0 79,166 O&M 30,699 26,096 32,291 8,918 29,645 26,076 9,350 45,996 7,038 14,153 48,653 15,998 32,569 24,696 7,651 47,276 28,169 41,201 8,291 25,815 510,583 LER's 4,726 3,630 1,859 1,203 0 0 151 25 293 0 2 360 0 0 0 0 0 0 0 0 12,249

Total Project Mile 5-36 Option B

Total 54,293 35,043 37,901 48,945 29,645 26,537 10,910 47,033 16,688 25,305 49,300 22,746 33,522 24,696 8,420 50,109 29,690 42,243 9,546 25,815 628,387

Page 14: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-8

THIS PAGE LEFT BLANK

Page 15: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-9

Table D-1. Alternative B Cost Estimate (Continued)

Year Section Placement Sites Type Cost

Share 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Total

Local 25% Federal 75% O&M 6,373 6,500 6,631 6,763 7,199 7,343 7,490 7,640 7,793 7,948 8,107 8,270 8,435 8,604 8,776 8,951 9,130 9,312 9,499 9,689 160,453LER's

Bar Channel

ODMDS/ Agitation

Total 6,373 6,500 6,631 6,763 7,199 7,343 7,490 7,640 7,793 7,948 8,107 8,270 8,435 8,604 8,776 8,951 9,130 9,312 9,499 9,689 160,453 Local 25% 4,717 1,329 938 9,706 0 115 352 253 2,339 2,788 161 1,597 238 0 192 708 380 260 314 0 26,389 Federal 75% 14,151 3,988 2,813 29,118 0 345 1,057 759 7,018 8,364 483 4,791 715 0 577 2,125 1,141 781 941 0 79,166 O&M 37,072 32,596 38,922 15,681 36,844 33,419 16,840 53,636 14,831 22,101 56,760 24,268 41,004 33,300 16,427 56,227 37,299 50,513 17,790 35,504 671,036 LER's 4,726 3,630 1,859 1,203 0 0 151 25 293 0 2 360 0 0 0 0 0 0 0 0 12,249

Total Project Mile 5-36 and Bar Channel

Option B Total 60,666 41,543 44,532 55,708 36,844 33,880 18,400 54,673 24,481 33,253 57,407 31,016 41,957 33,300 17,196 59,060 38,820 51,555 19,045 35,504 788,840

Page 16: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-10

THIS PAGE LEFT BLANK

Page 17: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-11

Table D-2. Alternative C Cost Estimate

Year Section Placement Sites Type Cost

Share 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Total

Local 25% 181 54

CG 75% 543 163

O&M 1,416 31 32 471 35 1,731 38 1

Total 724 1,416 31 32 0 471 35 0 0 217 1,731 38 0 0 0 0 0 0 0 0 4,695

Local 25% 131 47

CG 75% 392 140

O&M 1,416 27 28 1,731 34 562 37

34 to 36

2

Total 523 1,416 27 28 0 0 0 0 0 187 1,731 34 0 0 0 562 37 0 0 0 4,545

Local 25% 233 115

CG 75% 698 345

O&M 5,112 70 71 1,515 80 3,180 87 3

Total 931 5,112 70 71 0 461 1,515 80 0 0 0 3,180 87 0 0 0 0 0 0 0 11,506

Local 25% 192 48

CG 75% 575 144

O&M 77 78 3,180 98 1,917 108

30 to 34

7

Total 77 78 0 767 0 0 0 0 0 0 0 3,180 98 0 192 0 1,917 108 0 0 6,417

Local 25% 192 48

CG 75% 575 144

O&M 77 78 3,659 87 88 98 4,645 106 7

Total 77 78 0 767 3,659 87 88 0 0 0 0 0 98 0 192 4,645 106 0 0 0 9,798

Local 25% 396 99

CG 75% 1,187 297

O&M 3,659 131 133 4,174 143 8

Total 0 0 0 1,583 3,659 131 133 0 397 4,174 143 0 0 0 0 0 0 0 0 0 10,219

Local 25% 398 96

Federal 75% 1,194 288

O&M 4,174 125 127 4,645 139

26 to 30

9

Total 0 0 0 0 0 0 0 0 1,592 4,174 125 127 0 0 385 4,645 139 0 0 0 11,187

Page 18: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-12

THIS PAGE LEFT BLANK

Page 19: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-13

Table D-2. Alternative C Cost Estimate (Continued) Local 25% 1,783 140 Federal 75% 5,350 421 O&M 1,571 110 112 1,665 123 1,866 132 2,004 142 2,152 152

15

Total 1,571 110 112 7,134 1,665 123 0 0 1,866 132 0 0 2,004 142 0 561 2,152 152 0 0 17,725 Local 25% 1,329 110 Federal 75% 3,988 329 O&M 1,607 105 107 1,801 117 1,934 126 2,077 135 2,228 145

21 to 22

16N

Total 0 5,317 1,607 105 107 0 1,801 117 0 438 1,934 126 0 0 2,077 135 0 0 2,228 145 16,138 Local 25% 496 124 Federal 75% 1,489 373 O&M 3,716 219 223 4,314 260 4,551 279 4,976 299

13A

Total 0 1,985 3,716 219 223 0 0 0 4,314 260 0 497 4,551 279 0 0 4,976 299 0 0 21,320 Local 25% 496 133 Federal 75% 1,489 400 O&M 3,782 242 238 4,471 264 4,802 289 5,152 310

13B

Total 0 1,985 0 0 3,782 242 238 0 0 0 4,471 264 0 534 4,802 289 0 0 5,152 310 22,068 Local 25% 114 131 Federal 75% 341 392 O&M 6,401 7,338

Devil's Elbow

West of Black Lake(BU50)

Total 6,856 0 0 0 0 0 7,861 0 0 0 0 0 0 0 0 0 0 0 0 0 14,717 Local 25% 865 Federal 75% 2,594 O&M 0 8,546 125

17

Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3,459 8,546 125 0 12,130 Local 25% 146 164 166 182 Federal 75% 439 499 499 546 O&M 14,374 6,849 8,506 10,162

W. Palermo (BU48)

Total 0 585 14,374 0 0 7,512 666 8,506 0 0 0 728 10,162 0 0 0 0 0 0 0 42,532 Local 25% 114 126 133 Federal 75% 341 378 399 O&M 14,309 9,266 7,887

West of Black Lake (BU50)

Total 14,765 0 0 0 0 9,770 0 8,419 0 0 0 0 0 0 0 0 0 0 0 0 32,954 Local 25% 138 Federal 75% 414 O&M 4,269

E. Palermo (BU52)

Total 0 0 0 0 0 0 0 0 0 551 4,269 0 0 0 0 0 0 0 0 0 4,821 Local 25% 146 Federal 75% 439 O&M 12,698

Palermo (BU4)

Total 0 0 0 0 0 0 0 0 0 586 12,698 0 0 0 0 0 0 0 0 0 13,284 Local 25% 223 236 125 Federal 75% 670 707 374 O&M 9,115 19,622 7,133

16 to 21

BU24

Total 0 0 0 0 0 0 0 0 0 0 0 893 9,115 0 942 19,622 0 7,631 0 0 38,204

Page 20: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-14

THIS PAGE LEFT BLANK

Page 21: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-15

Table D-2. Alternative C Cost Estimate (Continued)

Local 25% 1,819 1,183

Federal 75% 5,457 3,550

O&M 8,574 156 11,541 214

Foreshore Dike (FSD)

Total 15,849 156 0 0 0 0 0 0 0 0 0 0 0 0 4,733 11,541 214 0 0 0 32,494

Local 25%

Federal 75%

O&M 0

Shore Protect D&E Lakeside

Total 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Local 25% 74 80 85 44

Federal 75% 223 241 255 132

O&M 13,724 14,837 15,653 8,219 Sabine (BU5)

Total 0 297 13,724 0 0 15,159 0 15,992 0 0 8,395 0 0 0 0 0 0 0 0 53,567

Local 25% 44 46

Federal 75% 132 137

O&M 8,139 6,775 Bell (BU6)

Total 0 0 0 0 0 0 0 0 0 0 8,314 0 6,957 0 0 0 0 0 0 0 15,271

Local 25% 394 51

Federal 75% 1,183 152

O&M 10,175 19,197

12 to 16

Bell (BU7)

Total 0 0 0 0 0 0 0 0 0 0 0 0 11,752 0 0 0 0 19,400 0 0 31,152

Local 25% 114 131 138 145 153 162

Federal 75% 341 391.965 414 436 460 485

O&M 7,695 6,816 4,976 9,922 10,468 11,022

Sabine (BU18)

Total 455 7,695 0 0 0 0 523 6,816 0 551 4,976 0 582 9,922 0 614 10,468 0 647 11,022 54,271

Local 25% 119 131 138

Federal 75% 356 392 414

O&M 8,260 2,796 5,163

9.5 to 12

Cameron SB (BU49)

Total 0 0 0 474 8,260 0 523 2,796 0 551 5,163 0 0 0 0 0 0 0 0 0 17,768

Page 22: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-16

THIS PAGE LEFT BLANK

Page 23: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-17

Table D-2. Alternative C Cost Estimate (Continued)

Local 25% 249

Federal 75% 746

O&M 2,751 88 89 2,129 114 H

Total 994 2,751 88 89 0 0 0 0 0 0 0 0 0 2,129 114 0 0 0 0 0 6,165

Local 25% 710 163

Federal 75% 2,129 490

O&M 2,895 266 271 3,362 296 4,965 312 7,483 329 3,940 M

Total 0 0 0 2,839 2,895 266 271 0 0 0 3,362 296 0 4,965 312 653 7,483 329 0 3,940 27,612

Local 25% 500 152

Federal 75% 1,500 456

O&M 2,751 137 139 3,362 168 3,940 N

Total 2,000 2,751 137 139 0 0 0 0 0 0 3,362 168 0 0 0 0 0 0 608 3,940 13,103

Local 25% 91

Federal 75% 273

O&M 6,780

Cameron WR (BU19)

Total 0 0 0 0 0 0 364 6,780 0 0 0 0 0 0 0 0 0 0 0 0 7,144

Local 25% 83

Federal 75% 248

O&M 5,134

5 to 9.5

Cameron WR (BU20)

Total 0 0 0 331 5,134 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5,465 Local 25% 3,773 2,542 749 3,474 0 485 649 218 1,448 770 249 530 585 133 1,611 457 997 175 314 0 19,160 Federal 75% 11,320 7,626 2,246 10,421 0 1,464 1,948 654 4,345 2,311 747 1,589 1,756 400 4,834 1,371 2,991 526 941 0 57,490 O&M 31,009 26,072 34,237 5,703 29,573 37,513 11,718 53,860 6,394 14,153 60,644 13,022 43,399 23,251 7,651 47,463 27,851 42,007 7,876 25,815 549,212 LER's 2,428 6,276 1,788 1,090 166 0 135 0 253 420 301 908 0 0 0 0 0 520 0 0 14,285

Total Project Mile 5-36 Option C

Total 48,531 42,516 39,019 20,688 29,739 39,463 14,451 54,732 12,440 17,655 61,941 16,048 45,741 23,785 14,096 49,291 31,839 43,228 9,131 25,815 640,147

Page 24: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-18

THIS PAGE LEFT BLANK

Page 25: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-19

Table D-2. Alternative C Cost Estimate (Continued)

Year Section Placement Sites Type Cost Share

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Total

Local 25%

Federal 75%

O&M 6,373 6,500 6,631 6,763 7,199 7,343 7,490 7,640 7,793 7,948 8,107 8,270 8,435 8,604 8,776 8,951 9,130 9,312 9,499 9,689 160,453

LER's

Bar Channel ODMDS/Agitation

Total 6,373 6,500 6,631 6,763 7,199 7,343 7,490 7,640 7,793 7,948 8,107 8,270 8,435 8,604 8,776 8,951 9,130 9,312 9,499 9,689 160,453 Local 25% 3,773 2,542 749 3,474 0 485 649 218 1,448 770 249 530 585 133 1,611 457 997 175 314 0 19,160 Federal 75% 11,320 7,626 2,246 10,421 0 1,464 1,948 654 4,345 2,311 747 1,589 1,756 400 4,834 1,371 2,991 526 941 0 57,490 O&M 37,382 32,572 40,868 12,466 36,772 44,856 19,208 61,500 14,187 22,101 68,751 21,292 51,834 31,855 16,427 56,414 36,981 51,319 17,375 35,504 709,665 LER's 2,428 6,276 1,788 1,090 166 0 135 0 253 420 301 908 0 0 0 0 0 520 0 0 14,285

Total Project Mile 5-36 and Bar Channel

Option C

Total 54,904 49,016 45,650 27,451 36,938 46,806 21,941 62,372 20,233 25,603 70,048 24,318 54,176 32,389 22,872 58,242 40,969 52,540 18,630 35,504 800,600

Page 26: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-20

THIS PAGE LEFT BLANK

Page 27: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-21

Table D-3. Option D Cost Estimate

Year Section Placement Sites Type Cost

Share 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Total

Local 25% 182 57 CG 75% 547 170

O&M 1,444 32 33 485 36 1,802 39 1

Total 730 1,444 32 33 0 485 36 0 0 226 1,802 39 0 0 0 0 0 0 0 0 4,827Local 25% 132 49 CG 75% 395 146

O&M 1,444 28 28 1,802 36 591 39

34 to 36

2

Total 527 1,444 28 28 0 0 0 0 0 194 1,802 36 0 0 0 591 39 0 0 0 4,689Local 25% 235 119 CG 75% 704 356

O&M 5,214 71 74 1,565 82 3,317 91 3

Total 938 5,214 71 74 0 475 1,565 82 0 0 0 3,317 91 0 0 0 0 0 0 0 11,827Local 25% 197 51 CG 75% 591 152

O&M 79 79 3,317 102 2,019 113

30 to 34

7

Total 79 79 0 788 0 0 0 0 0 0 0 3,317 102 0 202 0 2,019 113 0 0 6,699Local 25% 197 51 CG 75% 591 152

O&M 78 79 2,822 89 91 102 3,662 111 7

Total 78 79 0 788 2,822 89 91 0 0 0 0 0 102 0 202 3,662 111 0 0 0 8,024Local 25% 406 103 CG 75% 1,219 309

O&M 2,822 135 138 3,252 149 8

Total 0 0 0 1,625 2,822 135 138 0 412 3,252 149 0 0 0 0 0 0 0 0 0 8,533Local 25% 413 101

Federal 75% 1,238 303 O&M 3,252 131 133 3,662 147

26 to 30

9

Total 0 0 0 0 0 0 0 0 1,651 3,252 131 133 0 0 404 3,662 147 0 0 0 9,380Local 25% 350 53

Federal 75% 1,051 159 O&M 2,395 90 95 1,950 109 2,111 118

10

Total 0 0 1,401 2,395 90 95 0 0 0 0 212 1,950 109 0 0 2,111 118 0 0 0 8,481Local 25% 323 52

Federal 75% 968 157 O&M 2,301 86 88 2,703 100 1,950 109 2,111 118

11

Total 1,291 2,301 86 88 0 0 0 2,703 100 0 209 1,950 109 0 0 2,111 118 0 0 0 11,066Local 25% 417 63

Federal 75% 1,250 188 O&M 2,395 106 114 2,703 121 1,950 131 2,111 142

12A

Total 0 0 1,667 2,395 106 114 0 2,703 121 0 250 1,950 131 0 0 2,111 142 0 0 0 11,690Local 25% 986 139

Federal 75% 2,958 417 O&M 2,301 273 278 5,196 309 5,624 335 6,088 362 6,589 392 6,855

22 to 26

12B

Total 0 2,301 273 278 0 5,196 309 0 3,944 5,624 335 0 0 6,088 362 0 556 6,589 392 6,855 39,102

Page 28: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-22

THIS PAGE LEFT BLANK

Page 29: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-23

Table D-3. Alternative D Cost Estimate Continued

Year Section Placement Sites Type Cost

Share 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Total

Local 25% 0 Federal 75% 0

O&M 5,487 15

Total 0 0 0 5,487 0 0 0 0 0 0 0 0 0 0 0 0 0 0 5,487Local 25% 0

Federal 75% 0 O&M 3,819

16N

Total 0 3,819 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3,819Local 25%

Federal 75% O&M 3,414 3,552 3,696 4,011 4,173 4,341 4,517 4,699 4,889 5,086

21 to 22

ODMDS

Total 3,414 0 3,552 0 3,696 0 4,011 0 4,173 0 4,341 0 4,517 0 4,699 0 4,889 0 5,086 0 42,378Local 25%

Federal 75% O&M 8,160 8,490 8,833 9,589 9,977 10,380 10,799 11,236 11,689 12,161

Devil's Elbow ODMDS

Total 8,160 0 8,490 0 8,833 0 9,589 0 9,977 0 10,380 0 10,799 0 11,236 0 11,689 0 12,161 0 101,314Local 25%

Federal 75% O&M 19,004 19,773 21,894 22,778 24,173 25,150 26,688 27,766

ODMDS

Total 19,004 0 19,773 0 0 21,894 0 22,778 0 0 24,173 0 25,150 0 0 26,688 0 27,766 0 0 187,226Local 25% 0 0

Federal 75% 0 0 O&M 34,314 26,372 10,438

16 to 21

17-19-22

Total 0 0 0 0 0 0 34,314 26,372 10,438 0 0 0 0 0 0 0 0 0 0 0 71,124Local 25%

Federal 75% O&M 18,511 19,259 21,326 22,187 23,545 24,497 25,995 27,045

12 to 16 ODMDS

Total 18,511 0 19,259 0 0 21,326 0 22,187 0 0 23,545 0 24,497 0 0 25,995 0 27,045 0 0 182,365Local 25%

Federal 75% O&M 10,220 10,846 12,011 12,746 13,526 14,354 15,232

9.5 to 12 ODMDS

Total 0 10,220 0 0 10,846 0 0 12,011 0 0 12,746 0 0 13,526 0 0 14,354 0 0 15,232 88,935Local 25%

Federal 75% O&M 11,944 12,676 14,036 14,895 15,807 16,774 17,801

5 to 9.5 ODMDS

Total 0 11,944 0 0 12,676 0 0 14,036 0 0 14,895 0 0 15,807 0 0 16,774 0 0 17,801 103,933 Local 25% 871 0 767 800 0 119 0 0 1,502 105 168 0 0 0 202 0 139 0 0 0 4,673 Federal 75% 2,614 0 2,301 2,401 0 356 0 0 4,505 315 503 0 0 0 606 0 417 0 0 0 14,019 O&M 49,246 38,845 51,564 10,778 41,891 49,334 50,053 102,872 24,809 12,128 94,299 12,692 65,607 35,421 16,297 66,931 50,400 61,513 17,639 39,888 892,207 LER's 367 2,933 1,904 11 0 0 340 0 304 0 0 0 0 0 0 0 0 0 0 0 5,860

Total Project Mile 5-36 Option D

Total 52,731 38,845 54,632 13,979 41,891 49,809 50,053 102,872 30,816 12,548 94,970 12,692 65,607 35,421 17,105 66,931 50,956 61,513 17,639 39,888 916,758

Page 30: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-24

THIS PAGE LEFT BLANK

Page 31: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-25

Table D-3. Alternative D Cost Estimate (Continued)

Year Section Placement Sites Type Cost Share 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Total

Local 25% Federal 75%

O&M 6,373 6,500 6,631 6,763 7,199 7,343 7,490 7,640 7,793 7,948 8,107 8,270 8,435 8,604 8,776 8,951 9,130 9,312 9,499 9,689 160,453LER's

Bar Channel ODMDS/Agitation

Total 6,373 6,500 6,631 6,763 7,199 7,343 7,490 7,640 7,793 7,948 8,107 8,270 8,435 8,604 8,776 8,951 9,130 9,312 9,499 9,689 160,453 Local 25% 871 0 767 800 0 119 0 0 1,502 105 168 0 0 0 202 0 139 0 0 0 4,673 Federal 75% 2,614 0 2,301 2,401 0 356 0 0 4,505 315 503 0 0 0 606 0 417 0 0 0 14,019 O&M 55,619 45,345 58,195 17,541 49,090 56,677 57,543 110,512 32,602 20,076 102,406 20,962 74,042 44,025 25,073 75,882 59,530 70,825 27,138 49,577 1,052,660 LER's 367 2,933 1,904 11 0 0 340 0 304 0 0 0 0 0 0 0 0 0 0 0 5,860

Total Project Mile 5-36 and Bar Channel

Option D Total 59,472 48,279 63,167 20,753 49,090 57,152 57,883 110,512 38,913 20,496 103,077 20,962 74,042 44,025 25,881 75,882 60,086 70,825 27,138 49,577 1,077,211

COSTS SHOWN REFLECT CONDITIONS AND ESTIMATES FROM 2007. DUE TO THE EXCESSIVE COSTS OF THIS OPTION, IT WAS NOT CARRIED THROUGH COST COORDINATION.

Page 32: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-26

THIS PAGE LEFT BLANK

Page 33: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-27

2 GENERAL BASIS OF ESTIMATE AND ASSUMPTIONS 2.1 Placement Areas (CDF’s) • Costs do not have as much variability or uncertainty as the Beneficial Use sites. Costs

are based on considerable experience with numerous projects supported by historical

data from the Corps. There is assumed little or no environmental issues or mitigation

requirements affecting costs or implementation.

• Site Management costs are for minimum required efforts to insure that there is sufficient

dry material for dike raising needed to support the schedule and meet capacity

requirements. Initial efforts are repeated over 2 years to compensate for poor existing

site conditions and provide better stability and more available material for dike raising.

Following subsequent dredged material fill events, a single year effort is applied.

• Rehabilitation includes perimeter and interior ditching to obtain dry material for dike

raising. Second lift dike raising assumes site management has been done in the interim

and sufficient dry material is available and therefore does not include any ditching.

• Typical dike sections include 3:1 slopes and a 12 ft crown width. Dikes will be

constructed/raised by side-casting material from the site interior.

• The dikes on the lakeside of CDFs 17, 19, 22, and D/E will be constructed with a 25’

crown and 4:1 side slopes.

• Dike raising (initial and second lift) does not include any grassing or other stabilization.

These costs are considered to be relatively minor.

• No interior training dikes are included, only perimeter containment dikes are constructed

or raised.

• Site dimensions were estimated from aerial photos.

• Weir costs are current pricing data from USACE, Mobile for 16 ft (4 each, 4 ft long bay)

weirs, 8 feet tall, including outfall pipes, installed; $35,000 each.

• Due to wet conditions, dikes are constructed in two lifts; the total width of the 20-year

dike is constructed in the initial construction to provide long term settlement and

consolidation.

• Dike volume calculation for the bottom half of the 20-year dike: first sequence calculates

the area of the trapezoid, and then compresses the area under the crown and 1/2 of the

side slope length, simulating the "iceberg" effect of a displacement dike.

Page 34: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-28

• Two passes on a perimeter dewatering ditch around the exterior and one interior pass of

the rotary ditcher is included in the initial rehabilitation costs. Perimeter ditches all

around the site are included in the initial effort. Perimeter ditches are shortened to two

dike lengths for subsequent events to new weirs.

• The second lift volumes assume the site is managed in the interim; the material is dried

and available as a result of management.

• Side-cast borrow costs are based on current costs of $3.50/cy that includes side-casting,

dressing and grassing where usable materials may be present adjacent to or near the

existing dike alignment.

• In areas where longer haul efforts are required and the possiblility of double or triple

handling materials is required to achieve the dike template, the CY unit costs increase to

$6.00 and $8.00 per/cy. This occurs on PAs 17, 19, 22, D/E.

• Side slopes for the dike are based on slope stability analyses and qualitative reviews of

shear vane tests as discussed in the Geotechnical Report Appendix.

• Costs assume dredged material placed strategically around the site to provide dike

stability and width for haul roads.

• The estimated remaining capacities of the CDFs subtract 2 feet for required site

freeboard and 1 foot for ponding. For example, a site with 4 foot of remaining freeboard

was estimated to have 1 foot of available dredged material capacity.

Table D-4, Site Management Costs, lists the assumptions made to determine the site

management costs.

Page 35: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-29

Table D-4. Site Management Costs

Perimeter Ditching; Initial Effort

$ 250.00 Hourly Cost for Marshbuggy Backhoe 40 feet per hour production first pass 35 feet per hour production second pass

$ 6.25 per foot first pass

$ 7.14 per foot second pass

Interior Ditching; Initial Effort $ 4,000 daily cost for rotary ditcher

8000 feet per day

$ 0.50 per foot interior ditch

100 center spacing for ditches 3 lines per acre @ 200 ft long

$ 300.00 per acre Event Dry and Drain Costs

100 - Acres 2,100 - feet on each side

22 - lines for 100 ft spacing 46,200 - linear ft internal ditching

8,000 - feet per day production

4,000 - $ per day for ditcher

5.78 - days of work $23,100 - sub-total, cost of interior ditching

$231 - cost per acre to do internal ditching

4200 - perimeter ditch on two sides (ft)

$6.25 - cost per ft, one pass

$26,250 - sub-total cost perimeter ditch $3,000 - sub-total, cost to excavated sumps at weirs

$52,350 - total DAMP cost $ 436.25 - per acre

Data Sources: J. Simmons Group, Disposal Area Management Contractor for the Port of Houston US Army Corps of Engineers, Mobile District, Irvington Area Office Assumptions: Two passes are required for the initial perimeter ditches One internal pass of the rotary ditcher Perimeter ditches all around the site for the initial effort Perimeter ditches shortened to two dike lengths for subsequent events to new weirs

Page 36: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-30

2.2 Beneficial Use Sites • Costs have variability and uncertainty due to site conditions and access impediments,

possible marsh dike stability issues, owner requirements and adjacent property impacts.

Planning, engineering, permitting, access and coordination efforts could also be greater

than estimated.

• Site management, planting or other habitat restoration efforts are not included; nor is

removal or degrading of marsh containment dikes upon completion.

• Site dimensions were estimated from aerial photos and property maps.

• Available capacities (based on property acreage) were reduced by a third to a half to

allow for open water areas and circulation in the marshes.

• Typical marsh dikes are assumed to be constructed to a height of 5-7 feet, using

adjacent side cast borrow at an estimated unit price of $55/lf.

• Typical site preparation does not include water control structures.

• Pipeline lengths were scaled from aerial photos from center of reach to center of site.

Unit price to lay and remove shore pipeline was estimated at $12/lf. Unit price to lay and

remove marsh pipeline was estimated at $16/lf.

Table D-5, Beneficial Use Site Parameters and Shore Protection Costs, details the assumptions

made to determine the Beneficial Use Costs.

Page 37: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-31

Table D-5. Beneficial Use Site Parameters and Shore Protection Costs Shore Event Laying Event Total Site Prot. Dike Line Misc Pipeline Containment Event Designation Length Length Length Cost Cost Cost Cost (ft) (ft) (ft) ($1000) ($1000) ($1000) ($) Cameron Pr WR 4,000 18,000 252 230 $ 482,000.00 (19) Cameron Pr WR 4,000 31,000 455 230 $ 684,666.67 (20) Cameron SB 6,000 27,000 432 330 $ 762,000.00 (BU 49) NWR 18 6,000 23,000 322 330 $ 652,000.00 (BU 18) Bell (6) 6,000 5,000 80 80 210 $ 370,000.00 Bell (7) 13,000 24,000 384 910 $ 1,294,000.00 NWR (5) 6,000 8,000 128 210 $ 338,000.00 BU (48) 6,000 24,000 384 420 $ 804,000.00 West Palermo E. Palermo (52) 3,000 4,000 64 330 $ 394,000.00 W. Black Lake (50) 6,000 36,000 576 330 $ 906,000.00 BU 24 8,000 48,000 75 768 440 $ 1,283,000.00 Palermo (4) 6,000 8,000 20 128 330 $ 478,000.00

Assumptions:

$ 12.00 per ft to lay and pick up shore pipe

$ 16.00 per ft to lay and pick up pipe in a marsh

$ 55.00 per linear foot of 5 ft high marsh dike using adjacent borrow $ 35.00 per linear foot of 5 ft high dike built with an 8 cy bucket dredge

8 tons per ft rock shore protection for lake side expansions $ 80.00 per ton of graded rock installed on earth fill, with filter fabric

$640 per ft shore protection Miscellaneous costs are for drainage and water control structures on the sites that drain to adjacent properties. Data Sources: US Army Corps of Engineers, Mobile District US Army Corps of Engineers, Galveston District US Army Corps of Engineers, New Orleans District

2.3 Hydraulic Dredging Costs • Dredging cost estimates are supported by historical prices for the region and by Corps

data. Costs were estimated by developing production tables for various dredge plant

configurations as applicable for the various site conditions and locations. Booster pump

costs and mobilization/demobilization are included in the unit prices for dredging.

Dredging costs were developed for 27 and 30 inch discharge hydraulic cutterhead

dredges operating alone or utilizing 1 or 2 booster pumps depending on the pipeline

lengths required for placement. Production estimates were produced utilizing data and

Page 38: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-32

information from the Corps and dredging contractors as well as software systems

specifically designed for estimating dredging production that consider pump size and

power, dredge material characteristics and other factors. Operating and ownership

costs including overhead, bond and profit were developed from data and information

obtained from the Corps and dredging contractors for dredges that could be reasonably

be expected to bid and perform the work resulting from implementation of the DMMP.

For the CDF dredging costs, pipeline costs were assumed in the mobilization and

demobilization as most of the CDFs used are adjacent. For BU costs the pipline costs

were added.

Table D-6, Hydraulic Cutterhead Dredge Cost and Production Analysis, details the analysis and

assumptions made to determine the dredging and pipeline costs.

Page 39: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-33

Table D-6. Hydraulic Cutterhead Dredge Cost and Production Analysis Production Ownership & Operating Cost 27 inch dredge 30 inch dredges dredge with booster Line Length (ft) 23,500 40,300 41,500 T James or Geo D. Wms & aux. plant addedLine Length (mi) 4 8 8 Monthly Ownership Cost $232,555 $265,315 Dredge Production (cy/hr) 1,266 Monthly Operating Cost $2,887,750 $3,164,132 with one booster (cy/hr) 947 931 Total Monthly Cost $3,120,305 $3,429,447 with two boosters (cy/hr 1,146 1,130 incl. OH & Bond(s)&contingency $3,749,251 $4,163,169 30-inch dredge incl. Profit $4,068,660 $4,535,789 Line Length (ft) 23500 40300 41500 Line Length (mi) 4.45 7.63 7.86 27 inch dredges dredge with booster Dredge Production (cy/hr) 2350 Mike Hooks and Dredge 32 & aux. plant addedwith one booster (cy/hr) 1840 1800 Monthly Ownership Cost $232,555 $265,315 Monthly Operating Cost $1,924,344 $2,259,730 Total Monthly Cost $2,156,899 $2,525,045 incl. OH & Bond(s)&contin $2,624,084 $3,071,970 incl. Profit $2,861,343 $3,349,725 Developed Unit Cost 27-inch 27-inch 27-inch 30-inch 30-inch

dredge with booster

2 boosters dredge w/ booster

Run Hours dredge 18 18 18 18 Run Hours w/ booster 16.5 16.5 15 16.5 16.5 Days per month 30.4 30.4 30.4 30.4 30.4

Monthly Production 692755.2 475015.2 515280 128592

0 922944 Unit Price $4.13 $7.05 $7.28 $3.16 $4.91 M&D / 2.0 million cys $0.25 $0.38 $0.50 $0.28 $0.40 $4.38 $7.43 $7.78 $3.44 $5.31 rounded unit /cy $3.44 $5.31 $5.31 $3.44 $5.31 max pipeline length 23,000 41,000 45,000

The 30” dredge cost is the goverData Sources:

Gahagan & Bryant Dredge Production Analysis Program US Army Corps of Engineers, Mobile District, Irvington Area Office US Army Corps of Engineers, New Orleans District CUTPRO; ERDC Production Gahagan & Bryant Cost Database Production Analysis Program Historic Data Set from USACE, Weeks Marine and Mike Hooks Inc.

Page 40: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SIES ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-34

2.4 Shore Protection Costs • Traditional shore protection costs are based on top elevation of 8 ft, a bottom elevation

of -2 ft, side slopes at 3:1, with an application of 0.27 tons/sf/lf at $80/ton resulting in a

unit cost of $640/lf.

2.5 Alternatives B and C Cutterhead Dredging • General: Total volumes include non-pay excess dredging quantities. Pay volumes in

estimate are reduced by dividing by 135%. Historical volumes used were from the 1995

to 2005 dredging contracts for all reaches except Reach 30-36, the Turning Basin, and

Clooney Island Loop, which did not include 2005.

• General: Costs include 10% Engineering and Design, 8% Supervision and

Administration for Construction and 15% Contingency for the first five years of the plan

and a 20% contingency thereafter. A contingency is applied to cover minor variations

and incidental costs through the planning, design and construction phases. This is not

intended to cover variations in market factors such as dredge plant supply and demand,

inflation fluctuations, spikes in fuel costs, etc.

• Reach 34-36: The channels are dredged on a 10 yr cycle. The Port/Non-federal quantity

of 88,000cy is dredged every 5 years.

• Reach 30-34: Costs for Site 7 are split with Reach 26-30. DAMP is applied at Site 7 in

years 0 and 1 due to wet existing conditions, in preparation for Rehabilitation and dike

raising in year 3.

• Reach 26-30: Costs for Site 7 are split with Reach 30-34. DAMP is applied at Site 7 in

years 0 and 1 due to wet existing conditions, in preparation for Rehabilitation and dike

raising in year 3.

• Reach 21-22: Shore Protection is applied along the channel side of sites 15 and 16N.

• Reach 16-21: Shore Protection and Rehabilitation of Sites 17, 19, and 22 would likely

take 2 years and should be initiated in year 3 to be ready to accept material in the

combined site in year 5. The DAMP at the Foreshore Dike site is applied only for 1 year

initially, as opposed to the typical 2-year application, since the site is new and the initial

placement will not be much above the water table. Subsequent applications following fill

events are also applied for 1 year only.

• Reach 12-16: Expansion of Sites D and E would likely take 2 years and should be

initiated in year 3 to be ready to accept material in the combined site in year 5. The

DAMP at the Foreshore Dike site is applied only for 1 year initially, as opposed to the

Page 41: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SIES ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-35

typical 2-year application, since the site is mostly new and relatively dry and

consolidated. Subsequent applications following fill events are also applied for 1 year

only.

• Reach 9.5-12: No DAMP or Shore Protection is applied in this reach since only non-

adjacent Beneficial Use sites are utilized.

• Reach 5-9.5: Utilizes a combination of CDF rehabilitation and levee raising with

beneficial use.

2.6 Alternative D – Hopper Dredging • Reach 34-36, Reach 30-34, Reach 26-30, and Reach 22-26 are the same as in

Alternatives B and C. Offshore disposal is not cost effective above Mile 22 because of

the excessive travel distance to the disposal area.

• Dredging costs are based on a typical rental contract rate of $1,600 per hour. Hourly

rates are based on historical prices from New Orleans and Mobile District hopper rental

contracts and include Mobilization/Demobilization allocations.

• Rental Costs include hopper dredge, survey vessel, survey plots and silent inspector

telemetry.

• The estimate is primarily based on cycle time including dredging, travel to offshore

disposal area, unloading, turning and return to dredging reach.

• Total time for dredging, unloading, and turning offshore is estimated to be 45 minutes.

Due to the curvature in the channel through the Devils Elbow reach, the dredging time

was increased to 1 hour.

• The distance to the offshore area is estimated at 7 miles beyond the channel entrance

(Mile 0).

• Travel time to the disposal area is based on a typical loaded speed of 10.89 mph.

• Travel time to return to the dredging reach is based on a typical unloaded speed of

11.88 mph. The return time includes travel to turn around at Devils Elbow (Mile 23).

• An allowance of 1.1 hours was added to account for wait time for LNG traffic in the

channel.

• A typical hopper dredge capacity of 6,300 (Eagle, now Terrapin Island and the Glen

Edwards) cubic yards is used. This includes a reduction of 100 cubic yards to account

for residual material after unloading.

• A load factor of 58% was applied to convert gross capacity of the hopper to the effective

volume of dredged material.

Page 42: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SIES ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-36

• An efficiency factor of 95% was applied to the operating time to account for traffic,

fueling, maintenance and repairs.

• The quantity of material to be dredged is the same as the quantities evaluated for

Options B and C for purposes of comparison and calculation of costs and comparison of

options.

Tables D-7, Industry Hopper Fleet Analysis for Mobile District Hopper Dredge Rental Contract,

provide the parameters used for the basis of estimates for Hopper Dredging and placement at

the ODMDS.

Page 43: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SIES ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-37

Table D-7. Industry Hopper Fleet Analysis for Mobile District Hopper Dredge Rental Contract

Effective Capacity = 6300 cy 57% Load Factor Hopper EAGLE Rate = 3,500 $/hr 95% Production Efficiency

Comparative Analysis Reach Pass Speed Speed Dump Trav to L&D LNG Turn DE Turn DE Unit Unit Larger

Start Stop to Dmp Light Loaded to Cut Dump Time wait Time & retn Cyc Cy Price Price Unit Mile Mile (mi) (mph) (mph) (hr) (hr) (hr) (hr) (hr) (hr) (hr) (hr) to turn to DE Price

5 9.5 7 11.88 10.89 1.389 1.4233 0.75 1.1 0.5 2.473 5.162 7.135 5.30 7.32 $7.32 9.5 12 7 11.88 10.89 1.599 1.6529 0.75 1.1 0.5 2.052 5.602 7.154 5.75 7.34 $7.34 12 16 7 11.88 10.89 1.936 2.0202 0.75 1.1 0.5 1.378 6.306 7.185 6.47 7.37 $7.37 16 21 7 11.88 10.89 2.357 2.4793 0.75 1.1 0.5 0.537 7.186 7.223 7.37 7.41 $7.41 21 22 7 11.88 10.89 2.441 2.5712 0.75 1.1 0.368 6.862 7.231 7.04 7.42 $7.42 22 22 7 11.88 10.89 2.441 2.5712 1 1.1 0.368 7.112 7.481 7.30 7.67 $7.67

Effective Capacity = 13372 cys 57% Load Factor GLENN EDWARDS Rate = 3,200 $/hr 95% Production Efficiency

To Comparative Analysis Reach Pass Speed Speed Dump Trav to L&D LNG Turn DE Turn DE Unit Unit Larger

Start Stop to Dmp Light Loaded to Cut Dump Time wait Time & retn Cyc Cy Price Price Unit Mile Mile (mi) (mph) (mph) (hr) (hr) (hr) (hr) (hr) (hr) (hr) (hr) to turn to DE Price

5 9.5 7 13.56 11.24 1.217 1.379 1 1.1 0.5 1.991 5.196 6.687 2.30 2.96 $2.96 9.5 12 7 13.56 11.24 1.401 1.6014 1 1.1 0.5 1.622 5.603 6.725 2.48 2.97 $2.97 12 16 7 13.56 11.24 1.696 1.9573 1 1.1 0.5 1.032 6.253 6.786 2.76 3.00 $3.00 16 21 7 13.56 11.24 2.065 2.4021 1 1.1 0.5 0.295 7.067 6.862 3.12 3.03 $3.12 21 22 7 13.56 11.24 2.139 2.4911 1 1.1 0.5 0.147 7.23 6.877 3.20 3.04 $3.20 22 22 7 13.56 11.24 2.139 2.4911 1.25 1.1 0.5 0.147 7.48 7.127 3.31 3.15 $3.31

Notes & Assumptions Devils Elbow is from 22 to 23 L&D is load and dump time The dredges are 300 ft long and could turn empty in the channel with thrusters, costs are both ways, used larger cost Used turning in the channel vs going to Devils Elbow for turning Several places for the dredge to leave the channel for LNG if anchorages constructed. Assumed hopper rental contract, digging on channel toes only. Travel time from ODMDS is to the top of the cut Rental Costs include hopper dredge, survey vessel, survey plots and silent inspector telemetered data to PM Hourly rates are from New Orleans and Mobile District hopper rental contracts and include Mob/Demob allocation

Page 44: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-38

THIS PAGE LEFT BLANK

Page 45: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-39

3 SITE SPECIFIC INFORMATION 3.1 Alternative B – Emphasis on Placement at Currently Available Sites Site specific assumptions for the cost estimate are provided by reach and site in the

following subsections.

3.1.1 Reach 34-36 Site 1:

• Estimated dimensions: 50 acres surrounded by 6,300 lf of perimeter dike

• Typical dike section variance: N slope = 3.5:1, E slope = 3:1, W slope = 3:1 due to poor

existing conditions/materials in these areas

• Initial dike raising/construction variance: short haul materials for N dike = 800 lf, E dike =

800 lf due to poor existing materials in these areas negating the option of side-casting

• Existing capacity: 97,000 cy based on an estimated remaining freeboard of 3 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 5 ft

• Total Capacity with vertical expansion = 887,700 cy

• Vertical Capacity/Ft = 80,700 cy

• Number of weirs, locations: 2, N and W

• Estimated dike foundation displacement/compaction: N = 2 ft, E = 0.5 ft, S = 0.5 ft, W =

0.5 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site 2:

• Estimated dimensions: 44 acres surrounded by 5,400 lf of perimeter dike

• Typical dike section variance: N slope = 3:1, S slope = 3:1, W slope = 3.5:1 due to poor

existing conditions/materials in these areas

• Initial dike raising/construction variance: short haul materials for N dike = 500 lf, S dike =

200 lf and long haul materials for W dike = 1,000 lf due to poor existing materials in

these areas negating the option of side-casting

• Existing capacity: 97,000 cy based on an estimated remaining freeboard of 3 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 5 ft

• Total Capacity with vertical expansion = 807,000 cy

• Number of weirs, locations: 1, S

Page 46: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-40

• Estimated dike foundation displacement/compaction: N = 0.7 ft, E = 0.5 ft, S = 0.7 ft, W =

1.5 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

3.1.2 Reach 30-34, Clooney Island and Turning Basin Site 3:

• Estimated dimensions: 113 acres surrounded by 11,100 lf perimeter dike

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: 364,600 cy based on an estimated remaining freeboard of 3 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 5 ft

• Total Capacity with vertical expansion = 2,187,600 cy

• Number of weirs, locations: 2, E and W

• Estimated dike foundation displacement/displacement/compaction: N = 1 ft, E = 1 ft, S =

1 ft, W = 1 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump).

Site 7 (shared with Reach 26-30):

• Estimated dimensions: 257 acres surrounded by 13,000 lf of perimeter dike

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: 414,600 cy based on an estimated remaining freeboard of 3 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 3 ft

• Total Capacity with vertical expansion = 3,731,400 cy

• Vertical Capacity = 414,600 cy/ft

• Number of weirs, location: 3, N and E and W

• Estimated dike foundation displacement/displacement/compaction: N = 1 ft, E = 1.3 ft,

S = 1.5 ft, W = 1 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump).

3.1.3 Reach 26-30 Site 7 (shared with Reach 30-34):

• Estimated dimensions: 257 acres surrounded by 13,000 lf of perimeter dike

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

Page 47: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-41

• Existing capacity: 414,600 cy based on an estimated remaining freeboard of 4 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 3 ft.

• Total Capacity with vertical expansion = 3,731,400 cy

• Number of weirs, location: 3, N and E and W

• Estimated dike foundation displacement/displacement/compaction: N = 1 ft, E = 1.3 ft,

S = 1.5 ft, W = 1 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site 8:

• Estimated dimensions: 192 acres surrounded by 14,400 lf perimeter dike

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: 0 cy based on an estimated remaining freeboard of 2 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 3 ft

• Total Capacity with vertical expansion = 2,478,400 cy

• Vertical Capacity: 309,800 cy/ft

• Number of weirs, locations: 3, E(2) and W

• Estimated dike foundation displacement/displacement/compaction: N = 1.4 ft, E = 1.7 ft,

S = 1.8 ft, W = 1 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site 9:

• Estimated dimensions: 170 acres surrounded by 12,500 lf perimeter dike

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: 0 cy based on an estimated remaining freeboard of 2 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 3 ft

• Total Capacity with vertical expansion = 2,194,400 cy

• Vertical Capacity: 274,00 cy/ft

• Number of weirs, locations: 3, NE and SE and SW

• Estimated dike foundation displacement/displacement/compaction: N = 1.1 ft, E = 1.5 ft,

S = 1.5 ft, W = 1 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Page 48: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-42

3.1.4 Reach 22-26 Site 10:

• Estimated dimensions: 135 acres surrounded by 10,100 lf of perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Initial dike raising/construction variance: n/a

• Existing capacity: 0 cy based on an estimated remaining freeboard of 2 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 3 ft

• Total Capacity with vertical expansion = 1,742,400 cy

• Vertical Capacity = 217,800 cy/ft

• Number of weirs, location: 3, N and E and W

• Estimated dike foundation displacement/displacement/compaction: N = 1.3 ft, E = 1.8 ft,

S = 1.3 ft, W = 1 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site 11:

• Estimated dimensions: 135 acres surrounded by 10,000 lf perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Initial dike raising/construction variance: n/a

• Existing capacity: 217,800 cy based on an estimated remaining freeboard of 4 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 3 ft

• Total Capacity with vertical expansion = 1,960,200 cy

• Vertical Capacity = 217,800 cy/ft

• Number of weirs, locations: 3, E(2) and S

• Estimated dike foundation displacement/displacement/compaction: N = 1.2 ft, E = 0.9 ft,

S = 1.2 ft, W = 1.8 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site 12A:

• Estimated dimensions: 160 acres surrounded by 12,000 lf perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Initial dike raising/construction variance: n/a

• Existing capacity: 0 cy based on an estimated remaining freeboard of 2 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 3 ft

Page 49: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-43

• Total Capacity with vertical expansion = 2,064,800 cy

• Vertical Capacity = 258,100 cy/ft

• Number of weirs, locations: 3, N and E and W

• Estimated dike foundation displacement/displacement/compaction: N = 1 ft, E = 1.5 ft,

S = 1 ft, W = 0.5 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site 12B:

• Estimated dimensions: 433 acres surrounded by 23,600 lf perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Initial dike raising/construction variance: n/a

• Existing capacity: 2,095,800 cy based on an estimated remaining freeboard of 5 ft

• Vertical Capacity = 698,600 cy/ft

• Dike raising required: Initial lift = 5 ft, Final height = 8 ft

• Total Capacity with vertical expansion = 7,684,600 cy

• Vertical Capacity = 698,600 cy/ft

• Number of weirs, locations: 6, E(3) and S(2) and W

• Estimated dike foundation displacement/displacement/compaction: N = 1 ft, E = 1.5 ft,

S = 1.2 ft, W = 0.7 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

3.1.5 Reach 21-22 Site 15:

• Estimated dimensions: 181 acres surrounded by 12,800 lf of perimeter dike

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: 584,000 cy based on an estimated remaining freeboard of 4 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 5 ft

• Total Capacity with vertical expansion = 3,504,000cy

• Vertical Capacity = 292,000 cy/ft

• Number of weirs, location: 2, E and S

• Estimated dike foundation displacement/displacement/compaction: N = 1 ft, E = 0.8 ft,

S = 1 ft, W = 1.4 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Page 50: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-44

Site 16N:

• Estimated dimensions: 168 acres surrounded by 11,100 lf perimeter dike

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: 0 cy based on an estimated remaining freeboard of 2 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 5 ft

• Total Capacity with vertical expansion = 2,710,000 cy

• Vertical Capacity = 271,000 cy/ft

• Number of weirs, locations: 2, N and E

• Estimated dike foundation displacement/compaction: N = 1.2 ft, E = 0.7 ft, S = 1.2 ft, W =

1.7 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

3.1.6 Reach Devil’s Elbow Site 13:

• Estimated dimensions: 710 acres surrounded by 23,000 lf of perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Initial dike raising/construction variance: site divided into 2 cells (13A & 13B)

• Existing capacity: 0 cy based on an estimated remaining freeboard of 2-3 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 5 ft

• Total Capacity with vertical expansion = 11,455,000 cy

• Vertical Capacity = 1.145,500 cy/ft

• Number of weirs, location: 6, N(add’l pipe costs) and E(add’l pipe costs) and S(2) and

W(2)

• Estimated dike foundation displacement/compaction: N = 1.2 ft, E = 1.5 ft, S = 1.2 ft, W =

0.7 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

3.1.7 Reach 16-21 Site BU50:

• Estimated dimensions: Approximately 6,000 LF of dike will be constructed each event.

• Dikes needed to contain the dredged materials are constructed using in-situ material in the same year of the dredging cycle to meet the capacity requirement of the dredging cycle.

Page 51: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-45

• Assumes dikes are existing on two sides

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity is estimated at 6,598,386 cy with a fill height of 6 ft assuming freeboard of

7 ft from top of dike to average bottom surface of site interior

• Number of weirs, location: n/a

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 36,000 ft (1 booster pump) for a 30” dredge.

Site FSD (shared with Reach 12-16):

• Estimated dimensions: 260 acres surrounded by 24,000 lf perimeter dike

• Typical dike section variance: all slopes = n/a

• Initial dike raising/construction variance: rock dike protection

• Site specific surveys for elevation of the adjacent dike/land on CDFs D and E were not available for this analysis. Existing LIDAR Data was used to estimate the adjacent dike heights. It is assumed that the existing adjacent dike heights are at +20 or greater.

• In order to contain materials in the new FSD for this site in a manner that allows for vertical expansion and contains the dredged materials from flowing through the rock dike, an earthen dike will be constructed by a combination of side cast materials and dried and hauled materials from within the land portions of the adjacent CDF.

• Dike construction assumes that a bucket dredge will be used to construct the first dike lift. It is assumed that the bucket dredge will enter through the currently existing breach and that the breach will be closed upon completion of the first dike construction.

• The second dike lift will be hauled and side cast.

• Dike raising required: Initial lift = 10 ft, Final height = 20 ft

• Approximately 4,549,000 CY of the 8,390,000 capacity will be utilized for this reach and the remaining capacity of approximately 3,841,000 will be utilized in the mile 12-16 reach.

• Number of weirs, locations: $70,000 included for drainage / water control structures

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Page 52: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-46

Site 17:

• Estimated dimensions: 160 acres surrounded by 13,070 lf perimeter dike

• Typical dike section variance: slopes on the north, south and west = 3.5:1 due to poor

existing conditions/materials

• Total Acres: 160

• Existing capacity: 309,700 cy

• Dike raising required: Initial lift = 5 ft

• Total Capacity with vertical expansion = 1,657,000 cy

• Number of weirs, locations: 2, E(2)

• Estimated dike foundation displacement/compaction: 17 - N = 3 ft, E = 3.0 ft, S = 1.2 ft,

W = 0.8 ft.

• Dikes on the upland portion of the site will be constructed in one five foot lift.

• Dikes in poor foundation and subject to significant erosion on the lakeside of the CDF will be constructed with a 25 foot crown and 4:1 side slopes (approximately 3,000 LF).

• The remaining dikes on the northeast, south, and west will be constructed with a standard 12 foot crown and 1:3.5 side slopes.

• In order to contain materials in the new FSD for this site in a manner that allows for vertical expansion and contains the dredged materials from flowing through the rock dike, an earthen dike will be constructed by a combination of side cast materials and dried and hauled materials from within the land portions of the CDF.

• Site specific surveys for elevation of the adjacent dike/land on in the vicinity of CDF 17 were not available for this analysis. Existing LIDAR Data was used to estimate the adjacent dike heights. It is assumed that the existing dike/land heights range from +15 to +20.

• It is assumed that the height of the FSD earthen dikes will be raised to +20 in two lifts.

• CDF 19 is utilized before 17 in order to raise it’s elevation closer to the existing elevations of CDF 17 so that the sites can be combined and utilized as one large site in the future.

• Approximately 2,100 LF of dike separates CDFs 17 and 19 and will be degraded in the future.

• Approximately 2,700 LF of the existing dikes will be degraded in front of the new CDF 17 FSD to allow the FSD and the upland site to be utilized as one area.

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site 19:

• Estimated dimensions: 149 acres surrounded by 15,954 lf perimeter dike

Page 53: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-47

• Existing capacity: n/a

• Dike raising required: Initial lift = 5 ft, Second lift = 5 ft.

• Total Capacity with vertical expansion = 2,507,000 cy

• Number of weirs, locations: 2, E(2)

• Estimated dike foundation displacement/compaction: N = 1.23 ft, E = 3.0 ft, S = 0 ft,

W = 3.0 ft.

• Approximately 6,300 LF of existing land and old eroded dikes will be degraded in front of the new FSD to allow the FSD and the upland site to be utilized as one area.

• Dikes on the upland portion of the site will be constructed in two five foot lifts.

• Dikes in poor foundation and subject to significant erosion on the lakeside of the CDF will be constructed with a 25 foot crown and 4:1 side slopes (approximately 6,700 LF).

• The remaining dikes on the north, south, and west will be constructed with a standard 12 foot crown and 1:3.5 side slopes.

• In order to contain materials in the new FSD for this site in a manner that allows for vertical expansion and contains the dredged materials from flowing through the rock dike, an earthen dike will be constructed by a combination of side cast materials and dried and hauled materials from within the land portions of the CDF.

• Site specific surveys for elevation of the adjacent dike/land on in the vicinity of CDF 19 were not available for this analysis. Existing LIDAR Data was used to estimate the adjacent dike heights. It is assumed that the existing dike/land heights range from +4 to +8. The vertical expansion of the site will raise the dikes approximately 10 feet.

• It is assumed that the height of the FSD earthen dikes will be raised to +12 in two lifts.

• CDF 19 is utilized before 17 in order to raise it’s elevation closer to the existing elevations of CDF 17 so that the sites can be combined and utilized as one large site in the future.

• Approximately 2,900 LF of shore protection will be placed on the remaining unprotected ship channel side of the CDF to reduce further erosion. Shore protection will be placed to an elevation of +6.

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site 22:

• Estimated dimensions: 236 acres surrounded by 14,670 lf perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Initial dike raising/construction variance: 4:1 on the eastern slope due to poor existing

conditions/materials and erosion

• Existing capacity: 214,500 cy based on an estimated remaining freeboard of 3 ft

Page 54: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-48

• Dike raising required: Initial lift = 5 ft, Second lift = 5 ft.

• Total Capacity with vertical expansion = 4,575,000 cy

• Number of weirs, locations: 2

• Estimated dike foundation displacement/compaction: N = 1.2 ft, E = 3.0 ft, S = 0.9 ft,

W = 0.0 ft.

• Approximately 6,100 LF of existing land and existing dikes will be degraded in front of the new CDF 22 FSD to allow the FSD and the upland site to be utilized as one area.

• Dikes on the upland portion of the site will be constructed in two five foot lifts.

• Dikes in poor foundation and subject to significant erosion on the lakeside of the CDF will be constructed with a 25 foot crown and 4:1 side slopes (approximately 5,300 LF).

• The remaining dikes on the northeast, and west will be constructed with a standard 12 foot crown and 1:3.5 side slopes.

• In order to contain materials in the new FSD for this site in a manner that allows for vertical expansion and contains the dredged materials from flowing through the rock dike, an earthen dike will be constructed by a combination of side cast materials and dried and hauled materials from within the land portions of the CDF.

• Site specific surveys for elevation of the adjacent dike/land in the vicinity of CDF 22 were not available for this analysis. Existing LIDAR Data was used to estimate the adjacent dike heights. It is assumed that the existing dike/land heights range from +16 to +20.

• It is assumed that the height of the FSD earthen dikes will be raised to +20 in two lifts.

• Dredge pipeline length: less than 23,000 ft (no booster pump)

3.1.8 Reach 12-16 Site BU5:

• Estimated dimensions: 2,200 acres w/ 6,000 lf of marsh dikes constructed for each event

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity with vertical expansion = 8,873,000 cy with a fill height of 5 ft assuming

freeboard of 6 ft from top of dike to average bottom surface of site interior

• Number of weirs, location: n/a

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 8,000 ft of pipeline used in conjunction with the CWWPRA

pipeline.

Site D/E:

Page 55: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-49

• Estimated dimensions: 402 acres (D = 247 ac, E = 155 ac) surrounded by 41,300 lf

(D = 25,000 lf, E = 16,300 lf) perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials,

4:1 on the east dike due to poor foundation and high erosion.

• Initial dike raising/construction variance: combined use of sites D and E with initial

vertical expansion of both

• Existing capacity: 398,500 cy

• Dike raising required: two 5 foot lifts

• Total Capacity with vertical expansion = 6,884,500 cy

• Number of weirs, locations: 6, E(2) and W at both sites

• Estimated dike foundation displacement/compaction: N = 0.7 ft, E = 3.0 ft, S = .5 ft,

W = 0.0 ft.

• Dikes in poor foundation and subject to significant erosion on the lakeside of the CDF will be constructed with a 25 foot crown and 4:1 side slopes (approximately 18,500 LF).

• The remaining dikes on the north, south, and west will be constructed with a standard 12 foot crown and 1:3.5 side slopes.

• The dike between D&E will be degraded so that the site can be utilized as one site.

• It is assumed that once the FSD is filled to +20 that D&E will be combined with the FSD to be utilized as one facility in the future.

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site FSD (shared with Reach 16-21):

• Estimated dimensions: 260 acres surrounded by 24,000 lf perimeter dike

• Typical dike section variance: all slopes = n/a

• Initial dike raising/construction variance: rock dike protection

• Site specific surveys for elevation of the adjacent dike/land on CDFs D and E were not available for this analysis. Existing LIDAR Data was used to estimate the adjacent dike heights. It is assumed that the existing dike heights are at +20 or greater.

• In order to contain materials in the new FSD for this site in a manner that allows for vertical expansion and contains the dredged materials from flowing through the rock dike, an earthen dike will be constructed by a combination of side cast materials and dried and hauled materials from within the land portions of the CDF.

• Dike construction assumes that a bucket dredge will be used to construct the first dike lift. It is assumed that the bucket dredge will enter through the currently existing breach and that the breach will be closed upon completion of the first dike construction.

• The second dike lift will be hauled and side cast.

Page 56: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-50

• Dike raising required: Initial lift = 10 ft, Final height = 20 ft

• Approximately 3,841,000 CY of the 8,390,000 CY capacity will be utilized for this reach and the remaining capacity of approximately 4,549,014 CY will be utilized in the mile 16-21 Reach.

• Number of weirs, locations: $70,000 included for drainage / water control structures

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: less than 23,000 ft (no booster pump)

3.1.9 Reach 9.5-12 Site BU18:

• Estimated dimensions: Available 2,300 acres with adjacent properties protected by a

total of 30,000 lf of perimeter dike (2 sides), site divided into 1 cell for 6 placement

events w/ 6,000 lf of marsh dikes constructed for each event

• Typical dike section variance: all slopes = n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity with vertical expansion = 6,946,800 cy with a fill height of 5 ft assuming

freeboard of 6 ft from top of dike to average bottom surface of site interior

• Number of weirs, location: n/a

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 23,000 ft (1 booster pump)

Site BU49:

• Estimated dimensions: 600 acres with adjacent properties protected by a total of 18,000

lf of perimeter dike (2 sides), site divided into 3 – 200 acre cells for 3 placement events

w/ 6,000 lf of marsh dikes constructed for each event

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity with vertical expansion = 2,315,000 cy with a fill height of 5 ft assuming

freeboard of 6 ft from top of dike to average bottom surface of site interior

• Number of weirs, locations: n/a

Page 57: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-51

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 27,000 ft (1 booster pump)

3.1.10 Reach 5-9.5 Site H:

• Estimated dimensions: 142 acres surrounded by 13,000 lf of perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Initial dike raising/construction variance: no dike raising/construction on W side

• Existing capacity: 458,000 cy based on an estimated remaining freeboard of 4 ft

• Dike raising required: Initial lift = 4 ft, no 2nd lift

• Total Capacity with vertical expansion = 1,374,400 cy

• Vertical Capacity = 229,100 cy/ft

• Number of weirs, location: 3, NW and SW(2)

• Estimated dike foundation displacement/compaction: N = 1.2 ft, E = 0.8 ft, S = 1.2 ft,

W = 0.5 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site M:

• Estimated dimensions: 392 acres surrounded by 18,600 lf perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Initial dike raising/construction variance: n/a

• Existing capacity: 0 cy based on an estimated remaining freeboard of 2 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 3 ft

• Total Capacity with vertical expansion = 5,059,200 cy

• Vertical Capacity = 632,400 cy/ft

• Number of weirs, locations: 4, N and E and S and W

• Estimated dike foundation displacement/compaction: N = 1.2 ft, E = 1.8 ft, S = 1.3 ft,

W = 0.7 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site N:

• Estimated dimensions: 219 acres surrounded by 16,400 lf perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Initial dike raising/construction variance: n/a

• Existing capacity: 0 cy based on an estimated remaining freeboard of 2 ft

Page 58: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-52

• Dike raising required: Initial lift = 5 ft, Second lift = 3 ft

• Total Capacity with vertical expansion = 2,826,400cy

• Vertical Capacity = 219,300 cy/ft

• Number of weirs, locations: 3, N and S and W

• Estimated dike foundation displacement/compaction: N = 1.3 ft, E = 0.8 ft, S = 1 ft,

W = 1.5 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site BU19/20:

• Estimated dimensions: 600 acres with adjacent properties protected by a total of 8,000 lf

of perimeter dike (2 sides), site divided into 2 – 300 acre cells for 2 placement events w/

4,000 lf of marsh dikes constructed for each event

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity = 1,551,000 cy for BU 19 and 775,000 for BU 20 with a fill height of 6 ft

assuming freeboard of 7 ft from top of dike to average bottom surface of site interior

• Number of weirs, locations: n/a

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 18,000 ft (no booster pump)

3.2 Alternative C – Emphasis on Placement at Beneficial Use Sites

3.2.1 Miles 36 to 22

Same as Alternative B

3.2.2 Reach Devil’s Elbow Site 13:

• Estimated dimensions: 710 acres surrounded by 23,000 lf of perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Initial dike raising/construction variance: site divided into 2 cells (13A & 13B)

• Existing capacity: 0 cy based on an estimated remaining freeboard of 2-3 ft

• Dike raising required: Initial lift = 5 ft, Second lift = 5 ft

• Total Capacity with vertical expansion = 11,455,000 cy

Page 59: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-53

• Vertical Capacity = 1.145,500 cy/ft

• Number of weirs, location: 6, N (add’l pipe costs) and E (add’l pipe costs) and S(2) and

W(2)

• Estimated dike foundation displacement/compaction: N = 1.2 ft, E = 1.5 ft, S = 1.2 ft,

W = 0.7 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

Site BU50:

• Estimated dimensions: Approximately 6,000 LF of dike will be constructed each event.

• Dikes needed to contain the dredged materials are constructed using in-situ material in the same year of the dredging cycle to meet the capacity requirement of the dredging cycle.

• Dikes will only be constructed to meet the dredging need at the time. No additional capacity will be created.

• Assumes dikes are existing on two sides

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity is estimated at 7,158,000 cy with a fill height of 6 ft assuming freeboard of

7 ft from top of dike to average bottom surface of site interior.

• Approximately 2,062,000 cy will be used in this reach and the remainder in 16-21.

• Number of weirs, location: n/a

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 36,000 ft (1 booster pump) for a 30” dredge.

3.2.3 Reach 16-21 Site BU4:

• Estimated dimensions: 400 acres with adjacent properties protected by a total of 7,500 lf

of perimeter dike (2 sides), 1 placement event

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

Page 60: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-54

• Total Capacity with vertical expansion = 1,864,000 cy with a fill height of 6 ft assuming

freeboard of 7 ft from top of dike to average bottom surface of site interior

• Number of weirs, location: $20,000 included for drainage / water control structure

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 8,000 ft (no booster pump)

Site BU24:

• Estimated dimensions: 450 acres with adjacent properties protected by a total of 18,000

lf of perimeter dike (2 sides), site divided into 3 – 150 acre cells for 3 placement events

w/ 6,000 lf of marsh dikes constructed for each event

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity with vertical expansion = 4,350,000 cy with a fill height of 6 ft assuming

freeboard of 7 ft from top of dike to average bottom surface of site interior

• Number of weirs, location: $75,000 included for drainage / water control structure

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 48,000 ft (2 booster pumps)

Site BU48:

• Estimated dimensions: 650 acres with adjacent properties protected by a total of 14,000

lf of perimeter dike (2 sides), site divided into 2 – 325 acre cells for 2 placement events

w/ 7,500 lf of marsh dikes constructed for each event

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity with vertical expansion = 6,214,000 cy with a fill height of 6 ft assuming

freeboard of 7 ft from top of dike to average bottom surface of site interior

• Number of weirs, location: n/a

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 24,000 ft (1 booster pump)

Page 61: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-55

Site BU50:

• Estimated dimensions: Approximately 6,000 LF of dike will be constructed each event.

• Dikes needed to contain the dredged materials are constructed using in-situ material in the same year of the dredging cycle to meet the capacity requirement of the dredging cycle.

• Dikes will only be constructed to meet the dredging need at the time. No additional capacity will be created.

• Assumes dikes are existing on two sides

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity is estimated at 7,158,000 cy with a fill height of 6 ft assuming freeboard of

7 ft from top of dike to average bottom surface of site interior.

• Approximately 5,096,000 cy will be used in this reach and the remainder in Devil’s

Elbow.

• Number of weirs, location: n/a

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 36,000 ft (1 booster pump) for a 30” dredge.

Site BU52:

• Estimated dimensions: 150 acres with adjacent properties protected by a total of 8,000 lf

of perimeter dike (2 sides), 1 placement event

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity with vertical expansion = 621,000 cy with a fill height of 3 ft

• Number of weirs, location: n/a

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 4,000 ft (no booster pump)

Site 17

• Estimated dimensions: 147 acres surrounded by 17,600 lf perimeter dike

• Typical dike section variance: all slopes = 3.5:1 due to poor existing conditions/materials

• Existing capacity: 309,700 cy based on an estimated remaining freeboard of 3-4 ft,

Page 62: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-56

• Dike raising required: Initial lift = 6 ft, no 2nd lift

• Total Capacity with vertical expansion = 2,336,100 cy

• Number of weirs, locations: 2, E(1) and W(1)

• Estimated dike foundation displacement/compaction: 17 - N = 1.2 ft, E = 2.0 ft, S = 1.2 ft,

W = 0.8 ft

• Dredge pipeline length: less than 23,000 ft (no booster pump)

• This alternative only uses all available land for CDF17 and does not consider any

horizontal expansion as in Alternative B.

3.2.4 Reach 12-16 Site BU5:

• Estimated dimensions: 2,200 acres w/ 6,000 lf of marsh dikes constructed for each event

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity with vertical expansion = 8,873,000 cy with a fill height of 5 ft assuming

freeboard of 6 ft from top of dike to average bottom surface of site interior

• Number of weirs, location: n/a

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 8,000 ft of pipeline used in conjunction with the CWWPRA

pipeline.

Site BU6:

• Estimated dimensions: 12,000 lf of perimeter dike (2 sides), w/ 6,000 lf of marsh dikes

constructed for each event

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity with vertical expansion = 2,191,000 cy with a fill height of 2 ft

• Number of weirs, location: $48,000 included for drainage / water control structure

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 8,000 ft in conjunction with the CWWPRA Pipeline (1 booster

pump)

Page 63: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-57

Site BU7:

• Estimated dimensions: 13,000 lf of marsh dikes constructed for each event

• Typical dike section variance: n/a

• Initial dike raising/construction variance: n/a

• Existing capacity: n/a

• Dike required: Final height = 5 ft

• Total Capacity with vertical expansion = 3,895,000 cy with a fill height of 2 ft

• Number of weirs, location: n/a

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: 24,000 ft (1 booster pump)

Site FSD:

• Estimated dimensions: 260 acres surrounded by 24,000 lf perimeter dike

• Typical dike section variance: all slopes = n/a

• Initial dike raising/construction variance: rock dike protection

• Existing capacity: n/a

• Dike raising required: Initial lift = 10 ft, Final height = 20 ft

• Total Capacity with vertical expansion = 8,390,000 cy

• Number of weirs, locations: $70,000 included for drainage / water control structures

• Estimated dike foundation displacement/compaction: n/a

• Dredge pipeline length: less than 23,000 ft (no booster pump)

3.2.5 Reach 9.5-12 • Same as Alternative B

3.2.6 Reach 5 - 9.5 • Same as Alternative B

3.3 Alternative D – Placement of Material in the Ocean Disposal Management Site (ODMDS)

3.3.1 Miles 26 to 22 • Same as Alternative B

3.3.2 Reach 21-22 • Material to the ODMDS

• Shore Protection is applied along the channel side of sites 15 and 16N to minimize

erosion and subsequent channel shoaling.

Page 64: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-58

3.3.3 Reach Devil’s Elbow

• Material to the ODMDS.

3.3.4 Reach 16 – 21 • Material to the ODMDS.

• Shore Protection is applied along the channel side of sites 17 and 19 to minimize

erosion and subsequent channel shoaling.

3.3.5 Reach 12 - 16 • Material to the ODMDS.

3.3.6 Reach 9.5 to 12

• Material to the ODMDS.

• Shore Protection is applied along the channel side of site H to minimize erosion and

subsequent channel shoaling.

4 BAR CHANNEL The Bar Channel ranges from Mile 0 to approximate Mile -30 where it meets the natural deep

contour of the Gulf. Approximately 7 to 8 million cubic yards are dredged and agitated semi-

annually on an as needed basis, typically through a rental contract. An average of 6.7 million

cubic yards per year has been agitated in the channel and an average of 700,000 cubic yards

per year have been placed in the ODMDS annually. To determine the preliminary costs for

maintaining the Bar Channel, the average yearly cost over the last 5 years was determined at

$4.6 million. The costs were adjusted using a 10% Engineering and Design, 8% Supervision

and Administration and 15% Contingency for the first 5 years and 20% for the remaining years.

The costs for each cycle over the 20 year term of the DMMP were adjusted for escalation per

1110-2-1304 Civil Works Construction Cost Index System.

Page 65: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-59

Page 66: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-60

Page 67: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-61

Page 68: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-62

Page 69: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-63

Page 70: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-64

Page 71: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-65

Page 72: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-66

Page 73: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-67

Page 74: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-68

Page 75: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-69

Page 76: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-70

Page 77: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-71

Page 78: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-72

Page 79: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-73

Page 80: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-74

Page 81: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-75

Page 82: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-76

Page 83: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-77

Page 84: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-78

Page 85: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-79

Page 86: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-80

Page 87: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-81

Page 88: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-82

Page 89: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-83

Page 90: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-84

Page 91: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-85

Page 92: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-86

Page 93: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-87

Page 94: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-88

Page 95: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-89

Page 96: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-90

Page 97: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-91

Page 98: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-92

Page 99: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-93

Page 100: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-94

Page 101: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-95

Page 102: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-96

Page 103: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-97

Page 104: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-98

Page 105: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-99

Page 106: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-100

Page 107: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-101

Page 108: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-102

Page 109: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-103

Page 110: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-104

Page 111: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-105

Page 112: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-106

Page 113: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-107

Page 114: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-108

Page 115: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-109

Page 116: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-110

Page 117: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-111

Page 118: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-112

Page 119: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-113

Page 120: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-114

Page 121: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-115

Page 122: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-116

Page 123: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-117

Page 124: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-118

Page 125: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-119

Page 126: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-120

Page 127: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-121

Page 128: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-122

Page 129: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-123

Page 130: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-124

Page 131: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-125

Page 132: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-126

Page 133: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-127

Page 134: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-128

Page 135: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-129

Page 136: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-130

Page 137: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-131

Page 138: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-132

Page 139: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-133

Page 140: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-134

Page 141: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-135

Page 142: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-136

Page 143: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-137

Page 144: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-138

Page 145: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-139

Page 146: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP/SEIS ALTERNATIVE COST ESTIMATES FOR COST COMPARISON October 2010

Calcasieu River and Pass, LA DMMP and Supplemental EIS D-140

Page 147: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

New Orleans District Dredged Material Management Plan – Revised Plan B Calcasieu River and Pass, Louisiana

Cost Engineering Report - 2008 Dollars

September 2010

Page 148: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

Revised Plan B **** TOTAL PROJECT COST SUMMARY **** PAGE 1 OF 1

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

COST* CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLYEAR PROJECT DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

YEAR 00 CALCASIEU DMMP $47,605 $7,141 15% $54,746 $47,605 $7,141 $54,746 OCT 2009 1.86% $48,490 $7,274 $55,764YEAR 01 CALCASIEU DMMP $30,678 $4,602 15% $35,280 $30,678 $4,602 $35,280 OCT 2010 2.62% $31,482 $4,722 $36,204YEAR 02 CALCASIEU DMMP $33,448 $5,017 15% $38,465 $33,448 $5,017 $38,465 OCT 2011 4.24% $34,866 $5,230 $40,096YEAR 03 CALCASIEU DMMP $35,864 $5,380 15% $41,244 $35,864 $5,380 $41,244 OCT 2012 6.08% $38,045 $5,707 $43,751YEAR 04 CALCASIEU DMMP $23,119 $3,468 15% $26,587 $23,119 $3,468 $26,587 OCT 2013 7.99% $24,966 $3,745 $28,711YEAR 05 CALCASIEU DMMP $20,243 $4,049 20% $24,292 $20,243 $4,049 $24,292 OCT 2014 9.93% $22,253 $4,451 $26,704YEAR 06 CALCASIEU DMMP $8,133 $1,627 20% $9,760 $8,133 $1,627 $9,760 OCT 2015 11.91% $9,102 $1,820 $10,922YEAR 07 CALCASIEU DMMP $35,126 $7,025 20% $42,151 $35,126 $7,025 $42,151 OCT 2016 13.93% $40,019 $8,004 $48,023YEAR 08 CALCASIEU DMMP $12,631 $2,526 20% $15,157 $12,631 $2,526 $15,157 OCT 2017 15.98% $14,649 $2,930 $17,579YEAR 09 CALCASIEU DMMP $17,892 $3,578 20% $21,470 $17,892 $3,578 $21,470 OCT 2018 18.07% $21,125 $4,225 $25,350YEAR 10 CALCASIEU DMMP $34,851 $6,970 20% $41,821 $34,851 $6,970 $41,821 OCT 2019 20.19% $41,887 $8,377 $50,265YEAR 11 CALCASIEU DMMP $14,445 $2,889 20% $17,334 $14,445 $2,889 $17,334 OCT 2020 22.35% $17,673 $3,535 $21,208YEAR 12 CALCASIEU DMMP $22,531 $4,506 20% $27,037 $22,531 $4,506 $27,037 OCT 2021 24.56% $28,065 $5,613 $33,678YEAR 13 CALCASIEU DMMP $16,315 $3,263 20% $19,578 $16,315 $3,263 $19,578 OCT 2022 26.80% $20,687 $4,137 $24,825YEAR 14 CALCASIEU DMMP $5,711 $1,142 20% $6,853 $5,711 $1,142 $6,853 OCT 2023 29.08% $7,372 $1,474 $8,846YEAR 15 CALCASIEU DMMP $31,237 $6,247 20% $37,484 $31,237 $6,247 $37,484 OCT 2024 31.40% $41,045 $8,209 $49,255YEAR 16 CALCASIEU DMMP $18,324 $3,665 20% $21,989 $18,324 $3,665 $21,989 OCT 2025 33.77% $24,512 $4,902 $29,415YEAR 17 CALCASIEU DMMP $26,813 $5,363 20% $32,176 $26,813 $5,363 $32,176 OCT 2026 36.13% $36,501 $7,300 $43,801YEAR 18 CALCASIEU DMMP $5,878 $1,176 20% $7,054 $5,878 $1,176 $7,054 OCT 2027 38.49% $8,140 $1,628 $9,769YEAR 19 CALCASIEU DMMP $15,569 $3,114 20% $18,683 $15,569 $3,114 $18,683 OCT 2028 40.86% $21,930 $4,386 $26,317

_________________________________ _________ _________ _________ _________ _________ _________ _________

TOTAL PROJECT COSTS ========> $456,413 $82,747 $539,160 $456,413 $82,747 $539,160 $532,811 $97,670 $630,481

Revised Plan BTOTAL COSTS ==============> 630,481

*INCLUDES FUNTIONAL COSTS ASSOCIATED WITH LANDS AND DAMAGES, PLANNING ENGINEERING & DESIGN AND CONSTRUCTION MANAGEMENT

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 149: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 00 **** TOTAL PROJECT COST SUMMARY **** PAGE 1 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $22,634 $3,395 15% $26,029 $22,634 $3,395 $26,029 OCT 2009 1.86% $23,055 $3,458 $26,513C-12-05 DRAINAGE AREA MANAGEMENT $128 $19 15% $147 $128 $19 $147 OCT 2009 1.86% $130 $20 $150C-12-06 DIKE CONST, REHAB AND LIFT $13,738 $2,061 15% $15,799 $13,738 $2,061 $15,799 OCT 2009 1.86% $13,994 $2,099 $16,093C-16-01 SHORELINE PROTECTION 15% OCT 2009 1.86% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $36,500 $5,475 15% $41,975 $36,500 $5,475 $41,975 OCT 2009 1.86% 37,179 $5,577 $42,756

P-01 LANDS AND DAMAGES $4,535 $680 15% $5,215 $4,535 $680 $5,215 OCT 2009 1.86% $4,619 $693 $5,312

P-30 PLANNING, ENGINEERING & DESIGN $3,650 $548 15% $4,198 $3,650 $548 $4,198 OCT 2009 1.86% $3,718 $558 $4,276

P-31 CONSTRUCTION MANAGEMENT $2,920 $438 15% $3,358 $2,920 $438 $3,358 OCT 2009 1.86% $2,974 $446 $3,420

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $47,605 $7,141 15% $54,746 $47,605 $7,141 $54,746 48,490 $7,274 $55,764

YEAR 00TOTAL COSTS ==============> 55,764

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 150: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 01 **** TOTAL PROJECT COST SUMMARY **** PAGE 2 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $18,597 $2,790 15% $21,387 $18,597 $2,790 $21,387 OCT 2010 2.62% $19,084 $2,863 $21,947C-12-05 DRAINAGE AREA MANAGEMENT $367 $55 15% $422 $367 $55 $422 OCT 2010 2.62% $377 $56 $433C-12-06 DIKE CONST, REHAB AND LIFT $1,346 $202 15% $1,548 $1,346 $202 $1,548 OCT 2010 2.62% $1,381 $207 $1,588C-16-01 SHORELINE PROTECTION $2,556 $383 15% $2,939 $2,556 $383 $2,939 OCT 2010 2.62% $2,623 $393 $3,016

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $22,866 $3,430 15% $26,296 $22,866 $3,430 $26,296 OCT 2010 2.62% 23,465 $3,520 $26,985

P-01 LANDS AND DAMAGES $3,692 $554 15% $4,246 $3,692 $554 $4,246 OCT 2010 2.62% $3,789 $568 $4,357

P-30 PLANNING, ENGINEERING & DESIGN $2,290 $344 15% $2,634 $2,290 $344 $2,634 OCT 2010 2.62% $2,350 $352 $2,703

P-31 CONSTRUCTION MANAGEMENT $1,830 $275 15% $2,105 $1,830 $275 $2,105 OCT 2010 2.62% $1,878 $282 $2,160

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $30,678 $4,602 15% $35,280 $30,678 $4,602 $35,280 31,482 $4,722 $36,204

YEAR 01TOTAL COSTS ==============> 36,204

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 151: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 02 **** TOTAL PROJECT COST SUMMARY **** PAGE 3 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $22,634 $3,395 15% $26,029 $22,634 $3,395 $26,029 OCT 2011 4.24% $23,594 $3,539 $27,133C-12-05 DRAINAGE AREA MANAGEMENT $831 $125 15% $956 $831 $125 $956 OCT 2011 4.24% $866 $130 $996C-12-06 DIKE CONST, REHAB AND LIFT $3,215 $482 15% $3,697 $3,215 $482 $3,697 OCT 2011 4.24% $3,351 $503 $3,854C-16-01 SHORELINE PROTECTION 15% OCT 2011 4.24% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $26,680 $4,002 15% $30,682 $26,680 $4,002 $30,682 OCT 2011 4.24% 27,811 $4,172 $31,983

P-01 LANDS AND DAMAGES $1,958 $294 15% $2,252 $1,958 $294 $2,252 OCT 2011 4.24% $2,041 $306 $2,347

P-30 PLANNING, ENGINEERING & DESIGN $2,670 $401 15% $3,071 $2,670 $401 $3,071 OCT 2011 4.24% $2,783 $417 $3,201

P-31 CONSTRUCTION MANAGEMENT $2,140 $321 15% $2,461 $2,140 $321 $2,461 OCT 2011 4.24% $2,231 $335 $2,565

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $33,448 $5,017 15% $38,465 $33,448 $5,017 $38,465 34,866 $5,230 $40,096

YEAR 02TOTAL COSTS ==============> 40,096

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 152: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 03 **** TOTAL PROJECT COST SUMMARY **** PAGE 4 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $3,217 $483 15% $3,700 $3,217 $483 $3,700 OCT 2012 6.08% $3,413 $512 $3,925C-12-05 DRAINAGE AREA MANAGEMENT $1,269 $190 15% $1,459 $1,269 $190 $1,459 OCT 2012 6.08% $1,346 $202 $1,548C-12-06 DIKE CONST, REHAB AND LIFT $20,182 $3,027 15% $23,209 $20,182 $3,027 $23,209 OCT 2012 6.08% $21,409 $3,211 $24,620C-16-01 SHORELINE PROTECTION $4,907 $736 15% $5,643 $4,907 $736 $5,643 OCT 2012 6.08% $5,205 $781 $5,986

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $29,575 $4,436 15% $34,011 $29,575 $4,436 $34,011 OCT 2012 6.08% 31,373 $4,706 $36,079

P-01 LANDS AND DAMAGES $959 $144 15% $1,103 $959 $144 $1,103 OCT 2012 6.08% $1,017 $153 $1,170

P-30 PLANNING, ENGINEERING & DESIGN $2,960 $444 15% $3,404 $2,960 $444 $3,404 OCT 2012 6.08% $3,140 $471 $3,611

P-31 CONSTRUCTION MANAGEMENT $2,370 $356 15% $2,726 $2,370 $356 $2,726 OCT 2012 6.08% $2,514 $377 $2,891

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $35,864 $5,380 15% $41,244 $35,864 $5,380 $41,244 38,045 $5,707 $43,751

YEAR 03TOTAL COSTS ==============> 43,751

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 153: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 04 **** TOTAL PROJECT COST SUMMARY **** PAGE 5 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $18,958 $2,844 15% $21,802 $18,958 $2,844 $21,802 OCT 2013 7.99% $20,473 $3,071 $23,544C-12-05 DRAINAGE AREA MANAGEMENT $406 $61 15% $467 $406 $61 $467 OCT 2013 7.99% $438 $66 $504C-12-06 DIKE CONST, REHAB AND LIFT 15% OCT 2013 7.99% $0C-16-01 SHORELINE PROTECTION 15% OCT 2013 7.99% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $19,364 $2,905 15% $22,269 $19,364 $2,905 $22,269 OCT 2013 7.99% 20,911 $3,137 $24,048

P-01 LANDS AND DAMAGES $265 $40 15% $305 $265 $40 $305 OCT 2013 7.99% $286 $43 $329

P-30 PLANNING, ENGINEERING & DESIGN $1,940 $291 15% $2,231 $1,940 $291 $2,231 OCT 2013 7.99% $2,095 $314 $2,409

P-31 CONSTRUCTION MANAGEMENT $1,550 $233 15% $1,783 $1,550 $233 $1,783 OCT 2013 7.99% $1,674 $251 $1,925

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $23,119 $3,468 15% $26,587 $23,119 $3,468 $26,587 24,966 $3,745 $28,711

YEAR 04TOTAL COSTS ==============> 28,711

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 154: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 05 **** TOTAL PROJECT COST SUMMARY **** PAGE 6 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $15,975 $3,195 20% $19,170 $15,975 $3,195 $19,170 OCT 2014 9.93% $17,561 $3,512 $21,074C-12-05 DRAINAGE AREA MANAGEMENT $768 $154 20% $922 $768 $154 $922 OCT 2014 9.93% $844 $169 $1,013C-12-06 DIKE CONST, REHAB AND LIFT $400 $80 20% $480 $400 $80 $480 OCT 2014 9.93% $440 $88 $528C-16-01 SHORELINE PROTECTION 20% OCT 2014 9.93% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $17,143 $3,429 20% $20,572 $17,143 $3,429 $20,572 OCT 2014 9.93% 18,845 $3,769 $22,614

P-01 LANDS AND DAMAGES 20% OCT 2014 9.93% $0

P-30 PLANNING, ENGINEERING & DESIGN $1,720 $344 20% $2,064 $1,720 $344 $2,064 OCT 2014 9.93% $1,891 $378 $2,269

P-31 CONSTRUCTION MANAGEMENT $1,380 $276 20% $1,656 $1,380 $276 $1,656 OCT 2014 9.93% $1,517 $303 $1,821

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $20,243 $4,049 20% $24,292 $20,243 $4,049 $24,292 22,253 $4,451 $26,704

YEAR 05TOTAL COSTS ==============> 26,704

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 155: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 06 **** TOTAL PROJECT COST SUMMARY **** PAGE 7 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $4,689 $938 20% $5,627 $4,689 $938 $5,627 OCT 2015 11.91% $5,247 $1,049 $6,297C-12-05 DRAINAGE AREA MANAGEMENT $1,136 $227 20% $1,363 $1,136 $227 $1,363 OCT 2015 11.91% $1,271 $254 $1,526C-12-06 DIKE CONST, REHAB AND LIFT $943 $189 20% $1,132 $943 $189 $1,132 OCT 2015 11.91% $1,055 $211 $1,266C-16-01 SHORELINE PROTECTION 20% OCT 2015 11.91% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $6,768 $1,354 20% $8,122 $6,768 $1,354 $8,122 OCT 2015 11.91% 7,574 $1,515 $9,089

P-01 LANDS AND DAMAGES $135 $27 20% $162 $135 $27 $162 OCT 2015 11.91% $151 $30 $181

P-30 PLANNING, ENGINEERING & DESIGN $680 $136 20% $816 $680 $136 $816 OCT 2015 11.91% $761 $152 $913

P-31 CONSTRUCTION MANAGEMENT $550 $110 20% $660 $550 $110 $660 OCT 2015 11.91% $616 $123 $739

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $8,133 $1,627 20% $9,760 $8,133 $1,627 $9,760 9,102 $1,820 $10,922

YEAR 06TOTAL COSTS ==============> 10,922

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 156: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 07 **** TOTAL PROJECT COST SUMMARY **** PAGE 8 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $28,669 $5,734 20% $34,403 $28,669 $5,734 $34,403 OCT 2016 13.93% $32,663 $6,533 $39,195C-12-05 DRAINAGE AREA MANAGEMENT $315 $63 20% $378 $315 $63 $378 OCT 2016 13.93% $359 $72 $431C-12-06 DIKE CONST, REHAB AND LIFT $772 $154 20% $926 $772 $154 $926 OCT 2016 13.93% $880 $176 $1,056C-16-01 SHORELINE PROTECTION 20% OCT 2016 13.93% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $29,756 $5,951 20% $35,707 $29,756 $5,951 $35,707 OCT 2016 13.93% 33,901 $6,780 $40,681

P-01 LANDS AND DAMAGES 20% OCT 2016 13.93% $0

P-30 PLANNING, ENGINEERING & DESIGN $2,980 $596 20% $3,576 $2,980 $596 $3,576 OCT 2016 13.93% $3,395 $679 $4,074

P-31 CONSTRUCTION MANAGEMENT $2,390 $478 20% $2,868 $2,390 $478 $2,868 OCT 2016 13.93% $2,723 $545 $3,268

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $35,126 $7,025 20% $42,151 $35,126 $7,025 $42,151 40,019 $8,004 $48,023

YEAR 07TOTAL COSTS ==============> 48,023

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 157: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 08 **** TOTAL PROJECT COST SUMMARY **** PAGE 9 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $3,739 $748 20% $4,487 $3,739 $748 $4,487 OCT 2017 15.98% $4,336 $867 $5,204C-12-05 DRAINAGE AREA MANAGEMENT $496 $99 20% $595 $496 $99 $595 OCT 2017 15.98% $575 $115 $690C-12-06 DIKE CONST, REHAB AND LIFT $6,322 $1,264 20% $7,586 $6,322 $1,264 $7,586 OCT 2017 15.98% $7,332 $1,466 $8,799C-16-01 SHORELINE PROTECTION 20% OCT 2017 15.98% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $10,557 $2,111 20% $12,668 $10,557 $2,111 $12,668 OCT 2017 15.98% 12,244 $2,449 $14,693

P-01 LANDS AND DAMAGES $164 $33 20% $197 $164 $33 $197 OCT 2017 15.98% $190 $38 $228

P-30 PLANNING, ENGINEERING & DESIGN $1,060 $212 20% $1,272 $1,060 $212 $1,272 OCT 2017 15.98% $1,229 $246 $1,475

P-31 CONSTRUCTION MANAGEMENT $850 $170 20% $1,020 $850 $170 $1,020 OCT 2017 15.98% $986 $197 $1,183

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $12,631 $2,526 20% $15,157 $12,631 $2,526 $15,157 14,649 $2,930 $17,579

YEAR 08TOTAL COSTS ==============> 17,579

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 158: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 09 **** TOTAL PROJECT COST SUMMARY **** PAGE 10 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $6,936 $1,387 20% $8,323 $6,936 $1,387 $8,323 OCT 2018 18.07% $8,189 $1,638 $9,827C-12-05 DRAINAGE AREA MANAGEMENT $267 $53 20% $320 $267 $53 $320 OCT 2018 18.07% $315 $63 $378C-12-06 DIKE CONST, REHAB AND LIFT $7,949 $1,590 20% $9,539 $7,949 $1,590 $9,539 OCT 2018 18.07% $9,385 $1,877 $11,263C-16-01 SHORELINE PROTECTION 20% OCT 2018 18.07% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $15,152 $3,030 20% $18,182 $15,152 $3,030 $18,182 OCT 2018 18.07% 17,890 $3,578 $21,468

P-01 LANDS AND DAMAGES 20% OCT 2018 18.07% $0

P-30 PLANNING, ENGINEERING & DESIGN $1,520 $304 20% $1,824 $1,520 $304 $1,824 OCT 2018 18.07% $1,795 $359 $2,154

P-31 CONSTRUCTION MANAGEMENT $1,220 $244 20% $1,464 $1,220 $244 $1,464 OCT 2018 18.07% $1,440 $288 $1,729

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $17,892 $3,578 20% $21,470 $17,892 $3,578 $21,470 21,125 $4,225 $25,350

YEAR 09TOTAL COSTS ==============> 25,350

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 159: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 10 **** TOTAL PROJECT COST SUMMARY **** PAGE 11 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $28,381 $5,676 20% $34,057 $28,381 $5,676 $34,057 OCT 2019 20.19% $34,111 $6,822 $40,934C-12-05 DRAINAGE AREA MANAGEMENT $596 $119 20% $715 $596 $119 $715 OCT 2019 20.19% $716 $143 $860C-12-06 DIKE CONST, REHAB AND LIFT $544 $109 20% $653 $544 $109 $653 OCT 2019 20.19% $654 $131 $785C-16-01 SHORELINE PROTECTION 20% OCT 2019 20.19% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $29,521 $5,904 20% $35,425 $29,521 $5,904 $35,425 OCT 2019 20.19% 35,481 $7,096 $42,578

P-01 LANDS AND DAMAGES 20% OCT 2019 20.19% $0

P-30 PLANNING, ENGINEERING & DESIGN $2,960 $592 20% $3,552 $2,960 $592 $3,552 OCT 2019 20.19% $3,558 $712 $4,269

P-31 CONSTRUCTION MANAGEMENT $2,370 $474 20% $2,844 $2,370 $474 $2,844 OCT 2019 20.19% $2,849 $570 $3,418

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $34,851 $6,970 20% $41,821 $34,851 $6,970 $41,821 41,887 $8,377 $50,265

YEAR 10TOTAL COSTS ==============> 50,265

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 160: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 11 **** TOTAL PROJECT COST SUMMARY **** PAGE 12 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $6,865 $1,373 20% $8,238 $6,865 $1,373 $8,238 OCT 2020 22.35% $8,399 $1,680 $10,079C-12-05 DRAINAGE AREA MANAGEMENT $1,036 $207 20% $1,243 $1,036 $207 $1,243 OCT 2020 22.35% $1,268 $254 $1,521C-12-06 DIKE CONST, REHAB AND LIFT $2,935 $587 20% $3,522 $2,935 $587 $3,522 OCT 2020 22.35% $3,591 $718 $4,309C-16-01 SHORELINE PROTECTION $1,377 $275 20% $1,652 $1,377 $275 $1,652 OCT 2020 22.35% $1,685 $337 $2,022

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $12,213 $2,443 20% $14,656 $12,213 $2,443 $14,656 OCT 2020 22.35% 14,943 $2,989 $17,931

P-01 LANDS AND DAMAGES $22 $4 20% $26 $22 $4 $26 OCT 2020 22.35% $27 $5 $33

P-30 PLANNING, ENGINEERING & DESIGN $1,230 $246 20% $1,476 $1,230 $246 $1,476 OCT 2020 22.35% $1,505 $301 $1,806

P-31 CONSTRUCTION MANAGEMENT $980 $196 20% $1,176 $980 $196 $1,176 OCT 2020 22.35% $1,199 $240 $1,439

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $14,445 $2,889 20% $17,334 $14,445 $2,889 $17,334 17,673 $3,535 $21,208

YEAR 11TOTAL COSTS ==============> 21,208

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 161: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 12 **** TOTAL PROJECT COST SUMMARY **** PAGE 13 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $18,049 $3,610 20% $21,659 $18,049 $3,610 $21,659 OCT 2021 24.56% $22,482 $4,496 $26,978C-12-05 DRAINAGE AREA MANAGEMENT $397 $79 20% $476 $397 $79 $476 OCT 2021 24.56% $495 $99 $594C-12-06 DIKE CONST, REHAB AND LIFT $640 $128 20% $768 $640 $128 $768 OCT 2021 24.56% $797 $159 $957C-16-01 SHORELINE PROTECTION 20% OCT 2021 24.56% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $19,086 $3,817 20% $22,903 $19,086 $3,817 $22,903 OCT 2021 24.56% 23,774 $4,755 $28,528

P-01 LANDS AND DAMAGES $5 $1 20% $6 $5 $1 $6 OCT 2021 24.56% $6 $1 $8

P-30 PLANNING, ENGINEERING & DESIGN $1,910 $382 20% $2,292 $1,910 $382 $2,292 OCT 2021 24.56% $2,379 $476 $2,855

P-31 CONSTRUCTION MANAGEMENT $1,530 $306 20% $1,836 $1,530 $306 $1,836 OCT 2021 24.56% $1,906 $381 $2,287

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $22,531 $4,506 20% $27,037 $22,531 $4,506 $27,037 28,065 $5,613 $33,678

YEAR 12TOTAL COSTS ==============> 33,678

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 162: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 13 **** TOTAL PROJECT COST SUMMARY **** PAGE 14 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $12,928 $2,586 20% $15,514 $12,928 $2,586 $15,514 OCT 2022 26.80% $16,393 $3,279 $19,672C-12-05 DRAINAGE AREA MANAGEMENT $887 $177 20% $1,064 $887 $177 $1,064 OCT 2022 26.80% $1,125 $225 $1,350C-12-06 DIKE CONST, REHAB AND LIFT 20% OCT 2022 26.80% $0C-16-01 SHORELINE PROTECTION 20% OCT 2022 26.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $13,815 $2,763 20% $16,578 $13,815 $2,763 $16,578 OCT 2022 26.80% 17,517 $3,503 $21,021

P-01 LANDS AND DAMAGES 20% OCT 2022 26.80% $0

P-30 PLANNING, ENGINEERING & DESIGN $1,390 $278 20% $1,668 $1,390 $278 $1,668 OCT 2022 26.80% $1,763 $353 $2,115

P-31 CONSTRUCTION MANAGEMENT $1,110 $222 20% $1,332 $1,110 $222 $1,332 OCT 2022 26.80% $1,407 $281 $1,689

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $16,315 $3,263 20% $19,578 $16,315 $3,263 $19,578 20,687 $4,137 $24,825

YEAR 13TOTAL COSTS ==============> 24,825

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 163: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 14 **** TOTAL PROJECT COST SUMMARY **** PAGE 15 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $3,739 $748 20% $4,487 $3,739 $748 $4,487 OCT 2023 29.08% $4,826 $965 $5,792C-12-05 DRAINAGE AREA MANAGEMENT $481 $96 20% $577 $481 $96 $577 OCT 2023 29.08% $621 $124 $745C-12-06 DIKE CONST, REHAB AND LIFT $611 $122 20% $733 $611 $122 $733 OCT 2023 29.08% $789 $158 $947C-16-01 SHORELINE PROTECTION 20% OCT 2023 29.08% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $4,831 $966 20% $5,797 $4,831 $966 $5,797 OCT 2023 29.08% 6,236 $1,247 $7,483

P-01 LANDS AND DAMAGES 20% OCT 2023 29.08% $0

P-30 PLANNING, ENGINEERING & DESIGN $490 $98 20% $588 $490 $98 $588 OCT 2023 29.08% $632 $126 $759

P-31 CONSTRUCTION MANAGEMENT $390 $78 20% $468 $390 $78 $468 OCT 2023 29.08% $503 $101 $604

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $5,711 $1,142 20% $6,853 $5,711 $1,142 $6,853 7,372 $1,474 $8,846

YEAR 14TOTAL COSTS ==============> 8,846

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 164: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 15 **** TOTAL PROJECT COST SUMMARY **** PAGE 16 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $24,243 $4,849 20% $29,092 $24,243 $4,849 $29,092 OCT 2024 31.40% $31,855 $6,371 $38,227C-12-05 DRAINAGE AREA MANAGEMENT $260 $52 20% $312 $260 $52 $312 OCT 2024 31.40% $342 $68 $410C-12-06 DIKE CONST, REHAB AND LIFT $1,959 $392 20% $2,351 $1,959 $392 $2,351 OCT 2024 31.40% $2,574 $515 $3,089C-16-01 SHORELINE PROTECTION 20% OCT 2024 31.40% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $26,462 $5,292 20% $31,754 $26,462 $5,292 $31,754 OCT 2024 31.40% 34,771 $6,954 $41,726

P-01 LANDS AND DAMAGES $5 $1 20% $6 $5 $1 $6 OCT 2024 31.40% $7 $1 $8

P-30 PLANNING, ENGINEERING & DESIGN $2,650 $530 20% $3,180 $2,650 $530 $3,180 OCT 2024 31.40% $3,482 $696 $4,179

P-31 CONSTRUCTION MANAGEMENT $2,120 $424 20% $2,544 $2,120 $424 $2,544 OCT 2024 31.40% $2,786 $557 $3,343

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $31,237 $6,247 20% $37,484 $31,237 $6,247 $37,484 41,045 $8,209 $49,255

YEAR 15TOTAL COSTS ==============> 49,255

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 165: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 16 **** TOTAL PROJECT COST SUMMARY **** PAGE 17 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $14,400 $2,880 20% $17,280 $14,400 $2,880 $17,280 OCT 2025 33.77% $19,263 $3,853 $23,116C-12-05 DRAINAGE AREA MANAGEMENT $714 $143 20% $857 $714 $143 $857 OCT 2025 33.77% $955 $191 $1,146C-12-06 DIKE CONST, REHAB AND LIFT $400 $80 20% $480 $400 $80 $480 OCT 2025 33.77% $535 $107 $642C-16-01 SHORELINE PROTECTION 20% OCT 2025 33.77% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $15,514 $3,103 20% $18,617 $15,514 $3,103 $18,617 OCT 2025 33.77% 20,753 $4,151 $24,904

P-01 LANDS AND DAMAGES 20% OCT 2025 33.77% $0

P-30 PLANNING, ENGINEERING & DESIGN $1,560 $312 20% $1,872 $1,560 $312 $1,872 OCT 2025 33.77% $2,087 $417 $2,505

P-31 CONSTRUCTION MANAGEMENT $1,250 $250 20% $1,500 $1,250 $250 $1,500 OCT 2025 33.77% $1,672 $334 $2,007

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $18,324 $3,665 20% $21,989 $18,324 $3,665 $21,989 24,512 $4,902 $29,414

YEAR 16TOTAL COSTS ==============> 29,414

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 166: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 17 **** TOTAL PROJECT COST SUMMARY **** PAGE 18 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $21,368 $4,274 20% $25,642 $21,368 $4,274 $25,642 OCT 2026 36.13% $29,088 $5,818 $34,906C-12-05 DRAINAGE AREA MANAGEMENT $525 $105 20% $630 $525 $105 $630 OCT 2026 36.13% $715 $143 $858C-12-06 DIKE CONST, REHAB AND LIFT $815 $163 20% $978 $815 $163 $978 OCT 2026 36.13% $1,109 $222 $1,332C-16-01 SHORELINE PROTECTION 20% OCT 2026 36.13% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $22,708 $4,542 20% $27,250 $22,708 $4,542 $27,250 OCT 2026 36.13% 30,912 $6,182 $37,095

P-01 LANDS AND DAMAGES $5 $1 20% $6 $5 $1 $6 OCT 2026 36.13% $7 $1 $9

P-30 PLANNING, ENGINEERING & DESIGN $2,280 $456 20% $2,736 $2,280 $456 $2,736 OCT 2026 36.13% $3,104 $621 $3,725

P-31 CONSTRUCTION MANAGEMENT $1,820 $364 20% $2,184 $1,820 $364 $2,184 OCT 2026 36.13% $2,478 $496 $2,973

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $26,813 $5,363 20% $32,176 $26,813 $5,363 $32,176 36,501 $7,300 $43,801

YEAR 17TOTAL COSTS ==============> 43,801

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 167: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 18 **** TOTAL PROJECT COST SUMMARY **** PAGE 19 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $3,739 $748 20% $4,487 $3,739 $748 $4,487 OCT 2027 38.49% $5,178 $1,036 $6,214C-12-05 DRAINAGE AREA MANAGEMENT $444 $89 20% $533 $444 $89 $533 OCT 2027 38.49% $615 $123 $738C-12-06 DIKE CONST, REHAB AND LIFT $795 $159 20% $954 $795 $159 $954 OCT 2027 38.49% $1,101 $220 $1,322C-16-01 SHORELINE PROTECTION 20% OCT 2027 38.49% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $4,978 $996 20% $5,974 $4,978 $996 $5,974 OCT 2027 38.49% 6,894 $1,379 $8,273

P-01 LANDS AND DAMAGES 20% OCT 2027 38.49% $0

P-30 PLANNING, ENGINEERING & DESIGN $500 $100 20% $600 $500 $100 $600 OCT 2027 38.49% $692 $138 $831

P-31 CONSTRUCTION MANAGEMENT $400 $80 20% $480 $400 $80 $480 OCT 2027 38.49% $554 $111 $665

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $5,878 $1,176 20% $7,054 $5,878 $1,176 $7,054 8,140 $1,628 $9,769

YEAR 18TOTAL COSTS ==============> 9,769

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 168: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 19 **** TOTAL PROJECT COST SUMMARY **** PAGE 20 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 25 SEP 2010 AUTHORIZ./BUDGET YEAR: 2009 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: JUL 2008 EFFECT. PRICING LEVEL: 1 OCT 08

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $12,929 $2,586 20% $15,515 $12,929 $2,586 $15,515 OCT 2028 40.86% $18,212 $3,642 $21,855C-12-05 DRAINAGE AREA MANAGEMENT $260 $52 20% $312 $260 $52 $312 OCT 2028 40.86% $366 $73 $440C-12-06 DIKE CONST, REHAB AND LIFT 20% OCT 2028 40.86% $0C-16-01 SHORELINE PROTECTION 20% OCT 2028 40.86% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $13,189 $2,638 20% $15,827 $13,189 $2,638 $15,827 OCT 2028 40.86% 18,578 $3,716 $22,294

P-01 LANDS AND DAMAGES 20% OCT 2028 40.86% $0

P-30 PLANNING, ENGINEERING & DESIGN $1,320 $264 20% $1,584 $1,320 $264 $1,584 OCT 2028 40.86% $1,859 $372 $2,232

P-31 CONSTRUCTION MANAGEMENT $1,060 $212 20% $1,272 $1,060 $212 $1,272 OCT 2028 40.86% $1,493 $299 $1,792

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $15,569 $3,114 20% $18,683 $15,569 $3,114 $18,683 21,930 $4,386 $26,317

YEAR 19TOTAL COSTS ==============> 26,317

REVISED PLAN B_TPCS-Calcasieu_20100925.xls Printed: 9/27/2010

Page 169: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP – Revised Plan B Calcasieu River and Pass, Louisiana Cost Narrative

Tetra Tech 1 September 2010

Dredged Material Management Plan (DMMP) Calcasieu River and Pass, Louisiana

Cost Narrative 1. Project Description

A. General: The Calcasieu River and Pass, Louisiana, project spans 36 miles from Lake

Charles, Louisiana, to the Gulf of Mexico, and 32 miles offshore. The Calcasieu Ship Channel handles about 50 million tons of cargo every year. The existing dredged material disposal capacity is not adequate for maintaining the channel over the long term. Existing disposal sites are at or near capacity. Other disposal sites have been lost to commercial development. The DMMP identified areas for the placement of dredged material for the 20-year life of the project.

B. Purpose: The purpose of the DMMP is to develop a plan for the placement of material

dredged from the maintenance of the Calcasieu Ship Channel, and anticipated improvements for the next 20 years.

C. Design Features: To prepare the disposal areas to receive the dredged material, site

rehabilitation, dike raising, dike construction, shore protection, and site management will occur. The various disposal area placement sites are shown in the project’s site plan which is included in Appendix A.

2. Basis of Estimate

A. Basis of Design: “Calcasieu River and Pass, Louisiana, Dredged Material Management Plan,

Appendix D – Cost Estimates,” dated February 2008. “Calcasieu River and Pass, Louisiana, Dredged Material Management Plan,

Supplemental Environmental Impact Statement, Volume I,” dated May 2008. B. Basis of Quantities: The estimate is based on the overall quantities for Revised Plan B

provided by the designer. The overall quantities are presented in Appendix B. The quantity estimates include loss factors as listed below: Dredge Material Pay Volume Reduction 35% Dike Construction Shrinkage 15% to 40%

3. Design, and Construction Schedule

Sign PCA February 2009. Initiate Planning, Engineering, and Design February 2009. Advertise August 2009. Initiate Construction October 2009. Complete Construction October 2029.

Page 170: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP – Revised Plan B Calcasieu River and Pass, Louisiana Cost Narrative

Tetra Tech 2 September 2010

The estimate is based on construction and operation and maintenance occurring over a 20-year period. The tentative project schedule and implementation schedule are presented in Appendix C.

A. Overtime:

Typical construction, crew (1 shift) working 12hr/day, and 7 day weeks.

Typical dredge construction, crew (2 shifts) working 12hr/shift/day, and 7 day weeks.

B. Construction Windows: Continuous construction activity is anticipated. 4. Contracting Plan The dredging portion of the project will likely be contracted to one prime construction contractor. The dike rehabilitation and lifting will likely be assigned to a second prime construction contractor. No subcontractors are anticipated. For estimating purposes, one prime construction contractor was used for the entire project to reflect prime contractor mark-ups only to the costs. 5. Project Construction

A. Borrow Areas: The project is self sufficient in terms of borrow material, except for the

rock shore protection. B. Construction Methodology: The construction activities proposed at the various placement

sites include site rehabilitation, and initial dike raising (RLIFT), active dredging, and placement (PUMP), disposal area management (DAMP), secondary dike raising (LIFT), new dike construction (CONST), and shore protection (SP).

RLIFT includes rehabilitating, and raising existing dikes and installing weirs at confined disposal facilities (CDF). The total width of the dike will be raised during RLIFT. Dikes will be raised by side-casting material from construction activities including perimeter, and interior ditching to obtain dike lifting material. To create the perimeter, and interior drainage ditches two passes will be made around the exterior by a marshbuggie backhoe, and one around the interior by a rotary ditcher. At some CDFs the degrading of dikes will occur. After RLIFT has occurred, PUMP, and DAMP will occur. DAMP construction activities include perimeter, and interior ditching to obtain future dike lifting material. To create the perimeter, and interior drainage ditches two passes will be made around the exterior by a marshbuggie backhoe, and one around the interior by a rotary ditcher. PUMP includes dredging and pumping the material from the river to the placement sites. Dredging will be performed by a 27-inch discharge hydraulic cutter head dredge operating alone or utilizing 1 or 2 booster pumps depending on the pipeline lengths required for placement.

Page 171: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP – Revised Plan B Calcasieu River and Pass, Louisiana Cost Narrative

Tetra Tech 3 September 2010

LIFT will not include any ditching as fill material will have been previously made available during DAMP. LIFT is the secondary lifting of the dikes. After LIFT has occurred, PUMP, and DAMP will typically occur again. At locations along the river where no dikes exist, typically beneficial use (BU) sites, new dikes will be constructed. This process is referred to as CONST. These dikes will be 5 feet high constructed using adjacent borrow material with a marshbuggie backhoe an 8-cubic yard (CY) bucket dredge if in marsh conditions . There are two types of SP that will be used: traditional SP will have an 8-foot top elevation, a -2-foot bottom elevation, 3:1 side slopes, and 0.27-tons of rock/square foot (SF)/linear foot (LF). Rock dike SP will have a 6-foot top elevation, a -3-foot bottom elevation, 2.5:1 side slopes, and 0.27-tons of rock/SF/LF. The site specific construction activities that will occur along river miles 5 to 36 are listed below:

1) River Reach (Reach) 34-36: Reach 34-36’s dredged material will be disposed of at

Placement Sites (Sites) 1, and 2. Sites 1 and 2 both have an existing perimeter dike with lengths of 6,300-linear feet (LF), and 5,400-LF, and interior areas of 50-acres, and 44-acres, respectively. The construction activities that will occur at these sites are given below:

RLIFT: Site 1, and 2’s dikes will be rehabilitated, and raised 5-feet. PUMP: Three PUMP events will occur at Sites 1 and 2 each over the 20-year

construction period. A total volume of 1,359,020-CY will be dredged from Reach 34-36, and disposed of at these placement sites. The dredged material will be side-cast to the placement site. No booster pumps will be required.

DAMP: Perimeter, and interior ditches will be constructed at both sites over their entire areas.

CONST: None. LIFT: The dikes at Sites 1, and 2 will be raised another 5-feet after RLIFT has

occurred. SP: None.

2) Reach 30-34: Reach 30-34’s dredged material will be disposed of at Sites 3, and 7.

Both sites have an existing perimeter dikes with lengths of 11,000-LF, and 13,000-LF, and interior areas of 113-acres, and 129-acres, respectively. 6,500-feet of Site 7’s dike will be rehabilitated, and raised in conjunction with Reach 30-34, and the remaining 6,500-LF will be rehabilitated, and raised in conjunction with Reach 26-30. Costs for Site 7 are split between the two reaches. Detailed construction activities are given below:

RLIFT: Site 3 and 7’s dikes will be rehabilitated, and raised 4-feet.

Page 172: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP – Revised Plan B Calcasieu River and Pass, Louisiana Cost Narrative

Tetra Tech 4 September 2010

PUMP: Three PUMP events will occur at Site 3, and two will occur at Site 7 over the 20-year construction period. A total volume of 2,690,210-CY will be dredged from Reach 30-34, and disposed of at these placement sites. The dredged material will be side-cast to the placement site. No booster pumps will be required.

DAMP: Perimeter, and interior ditches will be constructed at both sites over their entire areas. DAMP will be applied at Site 7 initially in preparation for rehabilitation, and dike raising due to wet existing conditions.

CONST: None. LIFT: Sites 3 and 7’s dikes will be raised another 6-feet, and 4-feet, respectively,

after RLIFT has occurred. SP: None.

3) Reach 26-30: Reach 26-30’s dredged material will be disposed of at Sites 7, 8, and 9.

Sites 8, and 9 have exterior dikes with lengths of 14,400-LF, and 12,500-LF, respectively. Sites 7, 8, and 9 have areas of 129-acres, 192-acres, and 170-acres, respectively. Detailed construction activities are given below:

RLIFT: Site 7, 8, and 9’s dikes will be rehabilitated, and raised 4-feet. The second

half of Site 7’s 13,000-LF dike will be rehabilitated, and raised as that portion was left undone from Reach 30-34.

PUMP: Two PUMP events will occur at Sites 7, 8, and 9 each over the 20-year construction period. A total volume of 3,264,240-CY will be dredged from Reach 26-30, and disposed of at these placement sites. The dredged material will be side-cast to the placement site. No booster pumps will be required.

DAMP: Perimeter, and interior ditches will be constructed at the three sites over their entire areas.

CONST: None. LIFT: The three sites’ dikes will be raised another 4-feet after RLIFT has

occurred. SP: None.

4) Reach 22-26: Reach 22-26’s dredged material will be disposed of at Sites 10, 11,

12A, and 12B. Sites 10, 11, 12A, and, 12B have existing perimeter dikes with lengths of 10,100-LF, 10,000-LF, 12,000-LF, and 23,600-LF, respectively. Sites 10, 11, 12A, and 12B have areas of 135-acres, 135-acres, 160-acres, and 433-acres, respectively. Detailed construction activities are given below:

RLIFT: The dikes at Sites 10, 11, 12A, and 12B will be rehabilitated, and raised

5-feet. PUMP: Three PUMP events will occur at Site 10, four will occur at Sites 11, and

12A, and six will occur at Site 12B. A total volume of 9,412,800-CY will be dredged from Reach 22-26, and disposed of at these placement sites. The dredged material will be side-cast to the placement site. No booster pumps will be required.

DAMP: Perimeter and interior ditches will be constructed at the four sites over their entire areas.

Page 173: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP – Revised Plan B Calcasieu River and Pass, Louisiana Cost Narrative

Tetra Tech 5 September 2010

CONST: None. LIFT: The four sites’ dikes will be raised another 3-feet after RLIFT has occurred. SP: None.

5) Reach 21-22: Reach 21-22’s dredged material will be disposed of at Sites 15, and

16N. Sites 15, and 16N consist of existing dikes with lengths of 12,800-LF, and 11,100-LF, respectively. Sites 15, and 16 have areas of 181-acres, and 168-acres, respectively. Detailed construction activities are given below:

RLIFT: The dikes at Sites 15, and 16N will be rehabilitated, and raised 5-feet. PUMP: Five PUMP events will occur at each site. A total volume of 3,302,800-

CY will be dredged from Reach 21-22, and disposed of at these placement sites. The dredged material will be side-cast to the placement site. No booster pumps will be required.

DAMP: Perimeter, and interior ditches will be constructed at both sites over their entire areas.

CONST: None. LIFT: The two sites’ dikes will be raised another 5-feet after RLIFT has occurred. SP: 5,800-LF and 4,200-LF of SP will be applied along the channel side of Sites

15, and 16N, respectively.

6) Devil’s Elbow: Devil Elbow’s dredged material will be disposed of at Sites 13A, and 13B. Both sites have existing perimeter dikes with lengths of 11,500-feet. Both sites have areas of 355-acres. Detailed construction activities are given below:

RLIFT: The dikes at Sites 13A, and 13B will be rehabilitated, and raised 5-feet. PUMP: Five PUMP events will occur at both sites. A total volume of 7,636,100-

CY will be dredged from Reach Devil’s Elbow, and disposed of at these placement sites. The dredged material will be side-cast to the placement site. No booster pumps will be required.

DAMP: Perimeter, and interior ditches will be constructed at both sites over their entire areas.

CONST: None. LIFT: The two sites’ dikes will be raised another 5-feet after RLIFT has occurred. SP: None.

7) Reach 16-21: Reach 16-21’s dredged material will be disposed of at Sites 17, 19, 22,

Mercantel (BU 50), Garrison (BU 3), and Foreshore Dike (FSD). Sites 17, 19, and 22 consist of existing dikes with lengths of 39,200-LF, and 11,600-LF, respectively. Sites BU 50 and FSD have no existing dikes, but will have new ones constructed. Their lengths will be 30,000-LF and 24,000-LF each, respectively. Sites 17, 19, 22, and FSD have areas of 160-acres, 149-acres, 236-acres, and 300-acres, respectively. Detailed construction activities are given below:

Page 174: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP – Revised Plan B Calcasieu River and Pass, Louisiana Cost Narrative

Tetra Tech 6 September 2010

RLIFT: The typical 12-FT wide crown dike at Sites 17, 19 and 22 will be rehabilitated and raised 5-feet. Dikes with poor foundation and prone to erosion on the lakeside will be constructed with a 25-FT wide crown and 4:1 side slopes. Additionally existing land and existing dikes along the west side of the Sites will be degraded to allow the FSD and upland sites to be utilized as one area.

PUMP: Two PUMP events will occur at Site 17, three will occur at site 19, four will occur at Site 22, five will occur at BU 50, and four will occur at FSD within the 20-year construction period. A total volume of 14,730,700-CY will be dredged from Reach 16-21, and disposed of at these placement sites. The dredged material will be side-cast to the placement site, and will not require booster pumps. Site BU 50 dredge pipeline length will be 36,000-feet, and will require a booster pump.

DAMP: The DAMP at Site FSD is applied for 1-year initially. Subsequent applications following fill events will occur for the first year only.

CONST: Sites BU 50 will have a 5-feet high dike constructed. FSD will have 10-feet high dike constructed in two 5-foot lifts.

LIFT: The dikes at Sites 17, 19, and 22 will be raised another 5-feet respectively. SP: 2,953-LF of traditional SP will be applied to Site 17, and 2,953-LF of SP will

be applied at Site 19.

8) Reach 12-16: Reach 12-16’s dredged material will be disposed of at Sites D/E, FSD, and Sabine (BU 5). Site BU 5 doesn’t have dikes, but will have a new one constructed. The length will be 30,000-LF. No work will be done to Site FSD’s dike. Sites FSD, and BU 5 have areas of 300-acres, and 2,200-acres, respectively. Site D/E has an area of 403-acres. Detailed construction activities are given below:

RLIFT: The dikes at Site D/E will be rehabilitated. The typical 12-FT wide crown

dikes will be rehabilitated and raised 5-feet. Dikes with poor foundation and prone to erosion on the lakeside will be constructed with a 25-FT wide crown and 4:1 side slopes. Additionally existing land and existing dikes along the west side of the Sites will be degraded to allow the FSD and upland sites to be utilized as one area.

PUMP: Four PUMP events will occur at Site D/E, five will occur at BU 5, and four will occur at Site FSD over the 20-year construction period. A total volume of 14,426,700-CY will be dredged from Reach 12-16, and disposed of at these placement sites. The dredged material will be side-cast to the placement site. No booster pumps will be required. Site BU 5 will utilize an 8,000-foot pipeline in conjunction with the CWWPRA pipeline totaling 42,000-feet and two booster pumps.

DAMP: The DAMP at the Foreshore Dike site is applied only for 1 year initially, as opposed to the typical 2-year application, since the site is mostly new, and relatively dry, and consolidated. Subsequent applications following fill events are also applied for 1 year only.

CONST: Site BU 5 will have new dikes constructed to a height of 5-feet. LIFT: The dike at Site D/E will be raised another 5-feet. SP: None.

Page 175: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP – Revised Plan B Calcasieu River and Pass, Louisiana Cost Narrative

Tetra Tech 7 September 2010

9) Reach 9.5-12: Reach 9.5-12’s dredged material will be disposed of at Sites Cameron

SB (BU 49), and Sabine (BU 18). New dikes will be constructed at sites BU 49, and BU 18 with lengths of 18,000-feet, and 36,000-feet, respectively. The sites areas are 600-acres, and 2,300-acres, respectively. Detailed construction activities are given below:

RLIFT: None. PUMP: Three PUMP events will occur at Site BU 49, and six will occur at Site

BU 18 over the 20-year construction period. A total volume of 6,860,518-CY will be dredged from Reach 9.5-12, and disposed of at these placement sites. The sites will utilize a 27,000-feet pipeline, and 23,000-feet pipeline, respectively. One booster pumps will be required.

DAMP: None. CONST: Sites BU 49 and BU 18 will both have new dikes constructed to heights

of 5-feet. LIFT: None. SP: None.

10) Reach 5-9.5: Reach 5-9.5’s dredged material will be disposed of at Sites H, M, N,

Cameron WR (BU 19), and Cameron WR (BU 20). Sites H, M, and N have existing dikes with lengths of 13,000-foot, 18,600-foot, and 16,400-foot, respectively. Sites BU 19 and BU 20 don’t have dikes, but will have new ones constructed each with a length of 4,000feet. Sites H, M, N, BU 19, and BU 20 have areas of 142-acres, 392-acres, 219-acres, 300-acres, and 300-acres, respectively. Detailed construction activities are given below:

RLIFT: Site H, M, and N’s dikes will be rehabilitated, and raised 4-feet. PUMP: Two PUMP events will occur at Site H, five will occur at Site M, three

will occur at Site N, and one will occur at Sites BU 19, and BU 20 over the 20-year construction period. A total volume of 8,039,476-CY will be dredged from Reach 5-9.5, and disposed of at these placement sites. The dredged material will be side-cast to the placement site, and no booster pumps. Site BU 19, and BU 20 will utilize an 18,000-feet, and 31,000-feet pipeline, respectively. They will not require booster pumps.

DAMP: Perimeter, and interior ditches will be constructed at Sites H, M, and N over their entire areas.

CONST: Sites BU 19 and BU 20 will both have new dikes constructed to heights of 5-feet.

LIFT: The dikes at Sites M, and N will be raised another 4-feet after RLIFT has occurred.

SP: None.

C. Unusual Conditions: Unusual conditions that might influence construction costs all sites include unusually wet weather conditions, flooding and river currents. Unusual

Page 176: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP – Revised Plan B Calcasieu River and Pass, Louisiana Cost Narrative

Tetra Tech 8 September 2010

conditions that might influence construction costs of the beneficial use sites include marsh stability issues, unforeseen owner requirement, and unforeseen property impacts.

D. Unique Construction Techniques: The dredging will be performed by hydraulic

cutterhead dredges with pipelines to the placement sites. The dredge area management ditching will be performed by marshbuggie backhoes and rotary ditchers. The dike construction will be performed by marshbuggie backhoes or bucket dredges depending on the marsh site conditions. The rock shore protection will be placed by barge mounted cranes.

E. Equipment/Labor Availability and Distance Traveled: All equipment is assumed to be

available in the Calcasieu area. Some labor may have to come from other parts of the country.

6. Environmental Concerns

There is assumed little or no environmental issues or mitigation requirements affecting costs or implementation.

7. Effective Dates for Labor, Equipment, and Material Pricing The labor, equipment, and material pricing were developed using the MCACES 2006 English Unit Cost Library, Local 25 Southern Labor Rates, and the 2005 Equipment Library (Region III) for the base estimate. The index pricing data has been prepared in July 2008 dollars. The labor rates from the MCACES 2006 National Labor Library were compared with the current Davis-Bacon Wage rates (General Decision County Index LA20080011, and LA20080015) and actual wage rates (provided by New Orleans District), and Local 25 Southern Rates, Effective Through 30 September 2008 (see Appendix D). The Local 25 Southern Rates are higher than Davis-Bacon Wage Rates. Using current Davis-Bacon Wage Rates may not be appropriate for this market due to the extended period of construction duration in an area that is planned to be saturated with construction activity. Therefore the higher Local 25 Southern Labor Rates were used in the estimate. The higher rates along with the overtime will likely be needed to attract labor to this market. The base estimate has been updated with current quoted fuel prices of $3.76/gal for off-road diesel (provided by the Designer and approved by the Corps), $4.59/gal for on-road diesel and $3.90/gal for gasoline costs in the Calcasieu Louisiana area.

Labor and Equipment Crews Production Output: Production rates for the construction crews have also been estimated based on project conditions. See Appendix E for the Estimated Production Rates and General Assumptions.

Page 177: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP – Revised Plan B Calcasieu River and Pass, Louisiana Cost Narrative

Tetra Tech 9 September 2010

8. Project Markups

Escalation: Escalation has been calculated in two steps. Price levels were to be first escalated from effective price levels of the construction cost estimate for July 2008 to an effective price level for October 2008 to match the authorized budget year (FY2009). Since this initial escalation was calculated to be negative based on current OMB data, a zero escalation factor was used per the direction of Walla Walla District Corps of Engineers. Price levels are then escalated again from the budget year to an effective price level for year of construction (i.e. Year 00 price level = October 2009. The escalation cost factors for CWBS Feature Code 12 Navigation Ports and Harbors were taken from EM 1110-2-1304 Civil Works Construction Cost Index System (tables revised 31 March, 2009). Contingency: Contingencies represent allowances to cover unknowns, uncertainties and/or unanticipated conditions that are not possible to adequately evaluate from the data on hand at the time the cost estimate is prepared but must be represented by a sufficient cost to cover the identified risks. A 15% contingency has been used for construction years YR00 thru YR04 to cover design changes and uncertainties in quantities and unit prices. The 15% contingency is based on engineering judgment and ER 1110-2-1302, for a Project/Feature Design Memorandum level project. A 20% contingency has been used for construction years YR05 thru YR19 to cover unpredictable future economic trends as well as design changes and uncertainties in quantities and unit prices.

9. Functional Costs

Functional costs associated with this work were estimated as follows:

A. 01 Account – Lands and Damages: Costs for this account were provided by the U.S. Army Corps of Engineers, and are for Real Estate Costs. Real Estate Costs developed for this plan capture the 1 in 3 rule, which refers to the idea that at least one in every three land owners of both Confined Disposal Facilities and Beneficial Use sites will possibly be unwilling to participate in the disposal of dredged material on their site. These litigation costs have been provided via the Real Estate Plan that was prepared by the New Orleans District Real Estate team.

B. 30 Account - Planning, Engineering, and Design: Costs for this account were estimated at 10% of the construction cost. This account covers the preparation of Plans Specifications and Estimate for construction.

C. 31 Account - Construction Management: Costs for this account were estimated at 8% of

the construction cost. This account covers construction management during the construction contract.

Page 178: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

DMMP – Revised Plan B Calcasieu River and Pass, Louisiana Cost Narrative

Tetra Tech 10 September 2010

10. Project Cost Estimate

The construction cost estimate was developed using MCACES 2nd Generation (MII) estimating software in accordance with guidance contained in ER 1110-2-1302, Civil Works Cost Engineering. The MCACES construction cost estimate includes the Lands and Damages, Planning, Engineering and Design and the Construction Management costs, however it does not include the project markups noted in Section 8. See Appendix F for the MCACES output report. The Total Project Cost Summary (TPCS) was developed using an excel spreadsheet which incorporates the MCACES construction cost estimate, project mark-ups, and the functional costs.

Page 179: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

US Army Corps Of Engineers New Orleans District

Calcasieu River and Pass, Louisiana Dredged Material Management Plan

2010 Cost Estimate (MII) for the

Recommended Plan

2010 Dollars

U.S. Army Corps of Engineers, New Orleans District

November, 2010

Page 180: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each
Page 181: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each
Page 182: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each
Page 183: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each
Page 184: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each
Page 185: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

Revised Plan B **** TOTAL PROJECT COST SUMMARY **** PAGE 1 OF 1

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PREPARED: 5 NOV 2010 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2011 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 10

COST* CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLYEAR PROJECT DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

YEAR 00 CALCASIEU DMMP $52,438 $9,439 18% $61,877 0.5% $52,700 $9,486 $62,186 OCT 2012 2.60% $54,070 $9,733 $63,803YEAR 01 CALCASIEU DMMP $35,232 $6,342 18% $41,574 3.1% $36,324 $6,538 $42,863 OCT 2013 1.70% $36,942 $6,650 $43,591YEAR 02 CALCASIEU DMMP $37,011 $6,662 18% $43,673 4.9% $38,825 $6,988 $45,813 OCT 2014 1.70% $39,485 $7,107 $46,592YEAR 03 CALCASIEU DMMP $56,052 $10,089 18% $66,141 6.7% $59,807 $10,765 $70,573 OCT 2015 1.70% $60,824 $10,948 $71,773YEAR 04 CALCASIEU DMMP $30,043 $5,408 18% $35,451 8.5% $32,597 $5,867 $38,464 OCT 2016 1.80% $33,183 $5,973 $39,156YEAR 05 CALCASIEU DMMP $19,588 $3,526 18% $23,114 10.4% $21,625 $3,893 $25,518 OCT 2017 1.80% $22,014 $3,963 $25,977YEAR 06 CALCASIEU DMMP $15,815 $2,847 18% $18,662 12.4% $17,776 $3,200 $20,976 OCT 2018 1.80% $18,096 $3,257 $21,353YEAR 07 CALCASIEU DMMP $39,894 $7,181 18% $47,075 14.4% $45,639 $8,215 $53,854 OCT 2019 1.80% $46,460 $8,363 $54,823YEAR 08 CALCASIEU DMMP $15,716 $2,829 18% $18,545 16.5% $18,309 $3,296 $21,605 OCT 2020 1.80% $18,639 $3,355 $21,994YEAR 09 CALCASIEU DMMP $31,347 $5,642 18% $36,989 18.6% $37,178 $6,692 $43,869 OCT 2021 1.80% $37,847 $6,812 $44,659YEAR 10 CALCASIEU DMMP $33,533 $6,036 18% $39,569 20.7% $40,474 $7,285 $47,760 OCT 2022 1.80% $41,203 $7,417 $48,619YEAR 11 CALCASIEU DMMP $20,727 $3,731 18% $24,458 22.9% $25,473 $4,585 $30,059 OCT 2023 1.80% $25,932 $4,668 $30,600YEAR 12 CALCASIEU DMMP $22,920 $4,126 18% $27,046 25.1% $28,673 $5,161 $33,834 OCT 2024 1.80% $29,189 $5,254 $34,443YEAR 13 CALCASIEU DMMP $18,955 $3,412 18% $22,367 27.3% $24,130 $4,343 $28,473 OCT 2025 1.80% $24,564 $4,422 $28,986YEAR 14 CALCASIEU DMMP $9,208 $1,657 18% $10,865 29.6% $11,934 $2,148 $14,082 OCT 2026 1.80% $12,148 $2,187 $14,335YEAR 15 CALCASIEU DMMP $35,960 $6,473 18% $42,433 31.9% $47,431 $8,538 $55,969 OCT 2027 1.80% $48,285 $8,691 $56,976YEAR 16 CALCASIEU DMMP $29,467 $5,304 18% $34,771 34.3% $39,574 $7,123 $46,698 OCT 2028 1.80% $40,287 $7,252 $47,538YEAR 17 CALCASIEU DMMP $34,510 $6,212 18% $40,722 36.7% $47,175 $8,492 $55,667 OCT 2029 1.80% $48,024 $8,644 $56,669YEAR 18 CALCASIEU DMMP $9,511 $1,712 18% $11,223 39.2% $13,239 $2,383 $15,622 OCT 2030 1.80% $13,478 $2,426 $15,904YEAR 19 CALCASIEU DMMP $18,527 $3,335 18% $21,862 41.7% $26,253 $4,725 $30,978 OCT 2031 1.80% $26,725 $4,811 $31,536

_________________________________ _________ _________ _________ _________ _________ _________ _________

TOTAL PROJECT COSTS ========> $566,454 $101,962 $668,416 $665,136 $119,725 $784,861 $677,395 $121,931 $799,327

Revised Plan BTOTAL COSTS ==============> 799,327

*INCLUDES FUNTIONAL COSTS ASSOCIATED WITH LANDS AND DAMAGES, PLANNING ENGINEERING & DESIGN AND CONSTRUCTION MANAGEMENT

CHIEF, COST ENGINEERING, THOMAS D. MURPHY, P.E.

PROJECT MANAGER, PAUL VARNADO

CHIEF, REAL ESTATE, LINDA LABURE

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 186: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 00 **** TOTAL PROJECT COST SUMMARY **** PAGE 1 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2012 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 11

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $26,189 $4,714 18% $30,903 0.50% $26,320 $4,738 $31,058 OCT 2012 2.60% $27,004 $4,861 $31,865C-12-05 DRAINAGE AREA MANAGEMENT $167 $30 18% $197 0.50% $168 $30 $198 OCT 2012 2.60% $172 $31 $203C-12-06 DIKE CONST, REHAB AND LIFT $14,239 $2,563 18% $16,802 0.50% $14,310 $2,576 $16,886 OCT 2012 2.60% $14,682 $2,643 $17,325C-16-01 SHORELINE PROTECTION 18% 0.50% OCT 2012 2.60% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $40,595 $7,307 18% $47,902 $40,798 $7,344 $48,142 OCT 2012 2.60% 41,859 $7,535 $49,393

P-01 LANDS AND DAMAGES $4,535 $816 18% $5,351 0.50% $4,558 $820 $5,378 OCT 2012 2.60% $4,676 $842 $5,518

P-30 PLANNING, ENGINEERING & DESIGN $4,060 $731 18% $4,791 0.50% $4,080 $734 $4,815 OCT 2012 2.60% $4,186 $754 $4,940

P-31 CONSTRUCTION MANAGEMENT $3,248 $585 18% $3,833 0.50% $3,264 $588 $3,852 OCT 2012 2.60% $3,349 $603 $3,952

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $52,438 $9,439 18% $61,877 $52,700 $9,486 $62,186 54,070 $9,733 $63,803

YEAR 00TOTAL COSTS ==============> 63,803

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 187: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 01 **** TOTAL PROJECT COST SUMMARY **** PAGE 2 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2013 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 12

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $22,997 $4,139 18% $27,137 3.10% $23,710 $4,268 $27,978 OCT 2013 1.70% $24,113 $4,340 $28,453C-12-05 DRAINAGE AREA MANAGEMENT $293 $53 18% $346 3.10% $302 $54 $356 OCT 2013 1.70% $307 $55 $363C-12-06 DIKE CONST, REHAB AND LIFT $1,073 $193 18% $1,266 3.10% $1,106 $199 $1,305 OCT 2013 1.70% $1,125 $203 $1,328C-16-01 SHORELINE PROTECTION $2,366 $426 18% $2,792 3.10% $2,439 $439 $2,878 OCT 2013 1.70% $2,481 $447 $2,927

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $26,729 $4,811 18% $31,540 $27,558 $4,960 $32,518 OCT 2013 1.70% 28,026 $5,045 $33,071

P-01 LANDS AND DAMAGES $3,692 $665 18% $4,357 3.10% $3,806 $685 $4,492 OCT 2013 1.70% $3,871 $697 $4,568

P-30 PLANNING, ENGINEERING & DESIGN $2,673 $481 18% $3,154 3.10% $2,756 $496 $3,252 OCT 2013 1.70% $2,803 $504 $3,307

P-31 CONSTRUCTION MANAGEMENT $2,138 $385 18% $2,523 3.10% $2,204 $397 $2,601 OCT 2013 1.70% $2,242 $404 $2,645

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $35,232 $6,342 18% $41,574 $36,324 $6,538 $42,863 36,942 $6,650 $43,591

YEAR 01TOTAL COSTS ==============> 43,591

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 188: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 02 **** TOTAL PROJECT COST SUMMARY **** PAGE 3 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2014 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 13

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $26,189 $4,714 18% $30,903 4.90% $27,472 $4,945 $32,417 OCT 2014 1.70% $27,939 $5,029 $32,968C-12-05 DRAINAGE AREA MANAGEMENT $531 $96 18% $627 4.90% $557 $100 $657 OCT 2014 1.70% $566 $102 $668C-12-06 DIKE CONST, REHAB AND LIFT $2,986 $537 18% $3,523 4.90% $3,132 $564 $3,696 OCT 2014 1.70% $3,186 $573 $3,759C-16-01 SHORELINE PROTECTION 18% 4.90% OCT 2014 1.70% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $29,706 $5,347 18% $35,053 $31,162 $5,609 $36,771 OCT 2014 1.70% 31,691 $5,704 $37,396

P-01 LANDS AND DAMAGES $1,958 $352 18% $2,310 4.90% $2,054 $370 $2,424 OCT 2014 1.70% $2,089 $376 $2,465

P-30 PLANNING, ENGINEERING & DESIGN $2,971 $535 18% $3,506 4.90% $3,117 $561 $3,678 OCT 2014 1.70% $3,170 $571 $3,740

P-31 CONSTRUCTION MANAGEMENT $2,376 $428 18% $2,804 4.90% $2,492 $449 $2,941 OCT 2014 1.70% $2,535 $456 $2,991

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $37,011 $6,662 18% $43,673 $38,825 $6,988 $45,813 39,485 $7,107 $46,592

YEAR 02TOTAL COSTS ==============> 46,592

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 189: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 03 **** TOTAL PROJECT COST SUMMARY **** PAGE 4 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2015 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 14

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $6,041 $1,087 18% $7,129 6.70% $6,446 $1,160 $7,606 OCT 2015 1.70% $6,555 $1,180 $7,735C-12-05 DRAINAGE AREA MANAGEMENT $758 $136 18% $894 6.70% $809 $146 $954 OCT 2015 1.70% $823 $148 $971C-12-06 DIKE CONST, REHAB AND LIFT $34,287 $6,172 18% $40,459 6.70% $36,584 $6,585 $43,169 OCT 2015 1.70% $37,206 $6,697 $43,903C-16-01 SHORELINE PROTECTION $5,603 $1,009 18% $6,612 6.70% $5,978 $1,076 $7,055 OCT 2015 1.70% $6,080 $1,094 $7,174

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $46,689 $8,404 18% $55,093 $49,817 $8,967 $58,784 OCT 2015 1.70% 50,664 $9,120 $59,784

P-01 LANDS AND DAMAGES $959 $173 18% $1,132 6.70% $1,023 $184 $1,207 OCT 2015 1.70% $1,041 $187 $1,228

P-30 PLANNING, ENGINEERING & DESIGN $4,669 $840 18% $5,509 6.70% $4,982 $897 $5,879 OCT 2015 1.70% $5,067 $912 $5,979

P-31 CONSTRUCTION MANAGEMENT $3,735 $672 18% $4,407 6.70% $3,985 $717 $4,703 OCT 2015 1.70% $4,053 $730 $4,783

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $56,052 $10,089 18% $66,141 $59,807 $10,765 $70,573 60,824 $10,948 $71,773

YEAR 03TOTAL COSTS ==============> 71,773

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 190: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 04 **** TOTAL PROJECT COST SUMMARY **** PAGE 5 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2016 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 15

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $24,924 $4,486 18% $29,411 8.50% $27,043 $4,868 $31,910 OCT 2016 1.80% $27,529 $4,955 $32,485C-12-05 DRAINAGE AREA MANAGEMENT $311 $56 18% $367 8.50% $337 $61 $398 OCT 2016 1.80% $344 $62 $405C-12-06 DIKE CONST, REHAB AND LIFT 18% 8.50% OCT 2016 1.80% $0C-16-01 SHORELINE PROTECTION 18% 8.50% OCT 2016 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $25,235 $4,542 18% $29,777 $27,380 $4,928 $32,308 OCT 2016 1.80% 27,873 $5,017 $32,890

P-01 LANDS AND DAMAGES $265 $48 18% $313 8.50% $288 $52 $339 OCT 2016 1.80% $293 $53 $345

P-30 PLANNING, ENGINEERING & DESIGN $2,524 $454 18% $2,978 8.50% $2,739 $493 $3,231 OCT 2016 1.80% $2,788 $502 $3,290

P-31 CONSTRUCTION MANAGEMENT $2,019 $363 18% $2,382 8.50% $2,191 $394 $2,585 OCT 2016 1.80% $2,230 $401 $2,631

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $30,043 $5,408 18% $35,451 $32,597 $5,867 $38,464 33,183 $5,973 $39,156

YEAR 04TOTAL COSTS ==============> 39,156

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 191: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 05 **** TOTAL PROJECT COST SUMMARY **** PAGE 6 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2017 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 16

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $15,731 $2,832 18% $18,563 10.40% $17,367 $3,126 $20,493 OCT 2017 1.80% $17,680 $3,182 $20,862C-12-05 DRAINAGE AREA MANAGEMENT $498 $90 18% $588 10.40% $550 $99 $649 OCT 2017 1.80% $560 $101 $660C-12-06 DIKE CONST, REHAB AND LIFT $371 $67 18% $438 10.40% $410 $74 $483 OCT 2017 1.80% $417 $75 $492C-16-01 SHORELINE PROTECTION 18% 10.40% OCT 2017 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $16,600 $2,988 18% $19,588 $18,326 $3,299 $21,625 OCT 2017 1.80% 18,656 $3,358 $22,014

P-01 LANDS AND DAMAGES $0 18% $0 10.40% $0 $0 $0 OCT 2017 1.80% $0 $0 $0

P-30 PLANNING, ENGINEERING & DESIGN $1,660 $299 18% $1,959 10.40% $1,833 $330 $2,163 OCT 2017 1.80% $1,866 $336 $2,201

P-31 CONSTRUCTION MANAGEMENT $1,328 $239 18% $1,567 10.40% $1,466 $264 $1,730 OCT 2017 1.80% $1,493 $269 $1,761

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $19,588 $3,526 18% $23,114 $21,625 $3,893 $25,518 22,015 $3,963 $25,977

YEAR 05TOTAL COSTS ==============> 25,977

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 192: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 06 **** TOTAL PROJECT COST SUMMARY **** PAGE 7 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2018 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 17

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $6,890 $1,240 18% $8,130 12.40% $7,744 $1,394 $9,138 OCT 2018 1.80% $7,884 $1,419 $9,303C-12-05 DRAINAGE AREA MANAGEMENT $5,230 $941 18% $6,171 12.40% $5,879 $1,058 $6,937 OCT 2018 1.80% $5,984 $1,077 $7,062C-12-06 DIKE CONST, REHAB AND LIFT $1,168 $210 18% $1,378 12.40% $1,313 $236 $1,549 OCT 2018 1.80% $1,336 $241 $1,577C-16-01 SHORELINE PROTECTION 18% 12.40% OCT 2018 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $13,288 $2,392 18% $15,680 $14,936 $2,688 $17,624 OCT 2018 1.80% 15,205 $2,737 $17,941

P-01 LANDS AND DAMAGES $135 $24 18% $159 12.40% $152 $27 $179 OCT 2018 1.80% $154 $28 $182

P-30 PLANNING, ENGINEERING & DESIGN $1,329 $239 18% $1,568 12.40% $1,494 $269 $1,763 OCT 2018 1.80% $1,521 $274 $1,794

P-31 CONSTRUCTION MANAGEMENT $1,063 $191 18% $1,254 12.40% $1,195 $215 $1,410 OCT 2018 1.80% $1,216 $219 $1,435

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $15,815 $2,847 18% $18,662 $17,776 $3,200 $20,976 18,096 $3,257 $21,353

YEAR 06TOTAL COSTS ==============> 21,353

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 193: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 07 **** TOTAL PROJECT COST SUMMARY **** PAGE 8 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2019 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 18

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $32,719 $5,889 18% $38,609 14.40% $37,431 $6,737 $44,168 OCT 2019 1.80% $38,104 $6,859 $44,963C-12-05 DRAINAGE AREA MANAGEMENT $263 $47 18% $310 14.40% $301 $54 $355 OCT 2019 1.80% $306 $55 $361C-12-06 DIKE CONST, REHAB AND LIFT $826 $149 18% $975 14.40% $945 $170 $1,115 OCT 2019 1.80% $962 $173 $1,135C-16-01 SHORELINE PROTECTION 18% 14.40% OCT 2019 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $33,808 $6,085 18% $39,893 $38,676 $6,962 $45,638 OCT 2019 1.80% 39,373 $7,087 $46,460

P-01 LANDS AND DAMAGES 18% 14.40% OCT 2019 1.80% $0

P-30 PLANNING, ENGINEERING & DESIGN $3,381 $609 18% $3,990 14.40% $3,868 $696 $4,564 OCT 2019 1.80% $3,937 $709 $4,646

P-31 CONSTRUCTION MANAGEMENT $2,705 $487 18% $3,192 14.40% $3,095 $557 $3,652 OCT 2019 1.80% $3,150 $567 $3,717

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $39,894 $7,181 18% $47,075 $45,639 $8,215 $53,854 46,460 $8,363 $54,823

YEAR 07TOTAL COSTS ==============> 54,823

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 194: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 08 **** TOTAL PROJECT COST SUMMARY **** PAGE 9 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2020 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 19

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $6,889 $1,240 18% $8,129 16.50% $8,026 $1,445 $9,470 OCT 2020 1.80% $8,170 $1,471 $9,641C-12-05 DRAINAGE AREA MANAGEMENT $358 $64 18% $422 16.50% $417 $75 $492 OCT 2020 1.80% $425 $76 $501C-12-06 DIKE CONST, REHAB AND LIFT $5,933 $1,068 18% $7,001 16.50% $6,912 $1,244 $8,156 OCT 2020 1.80% $7,036 $1,267 $8,303C-16-01 SHORELINE PROTECTION 18% 16.50% OCT 2020 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $13,180 $2,372 18% $15,552 $15,355 $2,764 $18,119 OCT 2020 1.80% 15,631 $2,814 $18,445

P-01 LANDS AND DAMAGES $164 $30 18% $194 16.50% $191 $34 $225 OCT 2020 1.80% $194 $35 $230

P-30 PLANNING, ENGINEERING & DESIGN $1,318 $237 18% $1,555 16.50% $1,535 $276 $1,812 OCT 2020 1.80% $1,563 $281 $1,844

P-31 CONSTRUCTION MANAGEMENT $1,054 $190 18% $1,244 16.50% $1,228 $221 $1,449 OCT 2020 1.80% $1,250 $225 $1,475

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $15,716 $2,829 18% $18,545 $18,309 $3,296 $21,605 18,639 $3,355 $21,994

YEAR 08TOTAL COSTS ==============> 21,994

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 195: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 09 **** TOTAL PROJECT COST SUMMARY **** PAGE 10 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2021 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 20

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $10,922 $1,966 18% $12,888 18.60% $12,953 $2,332 $15,285 OCT 2021 1.80% $13,187 $2,374 $15,560C-12-05 DRAINAGE AREA MANAGEMENT $238 $43 18% $281 18.60% $282 $51 $333 OCT 2021 1.80% $287 $52 $339C-12-06 DIKE CONST, REHAB AND LIFT $15,405 $2,773 18% $18,178 18.60% $18,270 $3,289 $21,559 OCT 2021 1.80% $18,599 $3,348 $21,947C-16-01 SHORELINE PROTECTION 18% 18.60% OCT 2021 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $26,565 $4,782 18% $31,347 $31,506 $5,671 $37,177 OCT 2021 1.80% 32,073 $5,773 $37,846

P-01 LANDS AND DAMAGES 18% 18.60% OCT 2021 1.80% $0

P-30 PLANNING, ENGINEERING & DESIGN $2,657 $478 18% $3,135 18.60% $3,151 $567 $3,718 OCT 2021 1.80% $3,208 $577 $3,785

P-31 CONSTRUCTION MANAGEMENT $2,125 $383 18% $2,508 18.60% $2,520 $454 $2,974 OCT 2021 1.80% $2,566 $462 $3,027

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $31,347 $5,642 18% $36,989 $37,178 $6,692 $43,869 37,847 $6,812 $44,659

YEAR 09TOTAL COSTS ==============> 44,659

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 196: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 10 **** TOTAL PROJECT COST SUMMARY **** PAGE 11 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2022 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 21

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $27,505 $4,951 18% $32,456 20.70% $33,199 $5,976 $39,174 OCT 2022 1.80% $33,796 $6,083 $39,879C-12-05 DRAINAGE AREA MANAGEMENT $409 $74 18% $483 20.70% $494 $89 $583 OCT 2022 1.80% $503 $90 $593C-12-06 DIKE CONST, REHAB AND LIFT $504 $91 18% $595 20.70% $608 $109 $718 OCT 2022 1.80% $619 $111 $731C-16-01 SHORELINE PROTECTION 18% 20.70% OCT 2022 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $28,418 $5,115 18% $33,533 $34,301 $6,174 $40,475 OCT 2022 1.80% 34,918 $6,285 $41,203

P-01 LANDS AND DAMAGES 18% 20.70% OCT 2022 1.80% $0

P-30 PLANNING, ENGINEERING & DESIGN $2,842 $512 18% $3,354 20.70% $3,430 $617 $4,048 OCT 2022 1.80% $3,492 $629 $4,121

P-31 CONSTRUCTION MANAGEMENT $2,273 $409 18% $2,682 20.70% $2,744 $494 $3,237 OCT 2022 1.80% $2,793 $503 $3,296

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $33,533 $6,036 18% $39,569 $40,474 $7,285 $47,760 41,203 $7,417 $48,619

YEAR 10TOTAL COSTS ==============> 48,619

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 197: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 11 **** TOTAL PROJECT COST SUMMARY **** PAGE 12 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2023 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 22

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $10,045 $1,808 18% $11,853 22.90% $12,345 $2,222 $14,568 OCT 2023 1.80% $12,568 $2,262 $14,830C-12-05 DRAINAGE AREA MANAGEMENT $638 $115 18% $753 22.90% $784 $141 $925 OCT 2023 1.80% $798 $144 $942C-12-06 DIKE CONST, REHAB AND LIFT $5,518 $993 18% $6,511 22.90% $6,782 $1,221 $8,002 OCT 2023 1.80% $6,904 $1,243 $8,146C-16-01 SHORELINE PROTECTION $1,345 $242 18% $1,587 22.90% $1,653 $298 $1,951 OCT 2023 1.80% $1,683 $303 $1,986

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $17,546 $3,158 18% $20,704 $21,564 $3,882 $25,446 OCT 2023 1.80% 21,952 $3,951 $25,904

P-01 LANDS AND DAMAGES $22 $4 18% $26 22.90% $27 $5 $32 OCT 2023 1.80% $28 $5 $32

P-30 PLANNING, ENGINEERING & DESIGN $1,755 $316 18% $2,071 22.90% $2,157 $388 $2,545 OCT 2023 1.80% $2,196 $395 $2,591

P-31 CONSTRUCTION MANAGEMENT $1,404 $253 18% $1,657 22.90% $1,726 $311 $2,036 OCT 2023 1.80% $1,757 $316 $2,073

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $20,727 $3,731 18% $24,458 $25,473 $4,585 $30,059 25,932 $4,668 $30,600

YEAR 11TOTAL COSTS ==============> 30,600

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 198: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 12 **** TOTAL PROJECT COST SUMMARY **** PAGE 13 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2024 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 23

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $18,201 $3,276 18% $21,477 25.10% $22,769 $4,099 $26,868 OCT 2024 1.80% $23,179 $4,172 $27,352C-12-05 DRAINAGE AREA MANAGEMENT $306 $55 18% $361 25.10% $383 $69 $452 OCT 2024 1.80% $390 $70 $460C-12-06 DIKE CONST, REHAB AND LIFT $912 $164 18% $1,076 25.10% $1,141 $205 $1,346 OCT 2024 1.80% $1,161 $209 $1,371C-16-01 SHORELINE PROTECTION 18% 25.10% OCT 2024 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $19,419 $3,495 18% $22,914 $24,293 $4,373 $28,666 OCT 2024 1.80% 24,730 $4,451 $29,182

P-01 LANDS AND DAMAGES $5 $1 18% $6 25.10% $6 $1 $7 OCT 2024 1.80% $6 $1 $8

P-30 PLANNING, ENGINEERING & DESIGN $1,942 $350 18% $2,292 25.10% $2,429 $437 $2,867 OCT 2024 1.80% $2,473 $445 $2,918

P-31 CONSTRUCTION MANAGEMENT $1,554 $280 18% $1,834 25.10% $1,944 $350 $2,294 OCT 2024 1.80% $1,979 $356 $2,335

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $22,920 $4,126 18% $27,046 $28,673 $5,161 $33,834 29,189 $5,254 $34,443

YEAR 12TOTAL COSTS ==============> 34,443

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 199: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 13 **** TOTAL PROJECT COST SUMMARY **** PAGE 14 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2025 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 24

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $15,504 $2,791 18% $18,295 27.30% $19,737 $3,553 $23,289 OCT 2025 1.80% $20,092 $3,617 $23,708C-12-05 DRAINAGE AREA MANAGEMENT $560 $101 18% $661 27.30% $713 $128 $841 OCT 2025 1.80% $726 $131 $856C-12-06 DIKE CONST, REHAB AND LIFT 18% 27.30% OCT 2025 1.80% $0C-16-01 SHORELINE PROTECTION 18% 27.30% OCT 2025 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $16,064 $2,892 18% $18,956 $20,449 $3,681 $24,131 OCT 2025 1.80% 20,818 $3,747 $24,565

P-01 LANDS AND DAMAGES 18% 27.30% OCT 2025 1.80% $0

P-30 PLANNING, ENGINEERING & DESIGN $1,606 $289 18% $1,895 27.30% $2,044 $368 $2,412 OCT 2025 1.80% $2,081 $375 $2,456

P-31 CONSTRUCTION MANAGEMENT $1,285 $231 18% $1,516 27.30% $1,636 $294 $1,930 OCT 2025 1.80% $1,665 $300 $1,965

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $18,955 $3,412 18% $22,367 $24,130 $4,343 $28,473 24,564 $4,422 $28,986

YEAR 13TOTAL COSTS ==============> 28,986

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 200: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 14 **** TOTAL PROJECT COST SUMMARY **** PAGE 15 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2026 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 25

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $6,889 $1,240 18% $8,129 29.60% $8,928 $1,607 $10,536 OCT 2026 1.80% $9,089 $1,636 $10,725C-12-05 DRAINAGE AREA MANAGEMENT $350 $63 18% $413 29.60% $454 $82 $535 OCT 2026 1.80% $462 $83 $545C-12-06 DIKE CONST, REHAB AND LIFT $565 $102 18% $667 29.60% $732 $132 $864 OCT 2026 1.80% $745 $134 $880C-16-01 SHORELINE PROTECTION 18% 29.60% OCT 2026 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $7,804 $1,405 18% $9,209 $10,114 $1,821 $11,935 OCT 2026 1.80% 10,296 $1,853 $12,149

P-01 LANDS AND DAMAGES 18% 29.60% OCT 2026 1.80% $0

P-30 PLANNING, ENGINEERING & DESIGN $780 $140 18% $920 29.60% $1,011 $182 $1,193 OCT 2026 1.80% $1,029 $185 $1,214

P-31 CONSTRUCTION MANAGEMENT $624 $112 18% $736 29.60% $809 $146 $954 OCT 2026 1.80% $823 $148 $971

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $9,208 $1,657 18% $10,865 $11,934 $2,148 $14,082 12,148 $2,187 $14,335

YEAR 14TOTAL COSTS ==============> 14,335

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 201: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 15 **** TOTAL PROJECT COST SUMMARY **** PAGE 16 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2027 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 26

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $28,362 $5,105 18% $33,467 31.90% $37,409 $6,734 $44,144 OCT 2027 1.80% $38,083 $6,855 $44,938C-12-05 DRAINAGE AREA MANAGEMENT $235 $42 18% $277 31.90% $310 $56 $366 OCT 2027 1.80% $316 $57 $372C-12-06 DIKE CONST, REHAB AND LIFT $1,873 $337 18% $2,210 31.90% $2,470 $445 $2,915 OCT 2027 1.80% $2,515 $453 $2,968C-16-01 SHORELINE PROTECTION 18% 31.90% OCT 2027 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $30,470 $5,485 18% $35,955 $40,190 $7,234 $47,424 OCT 2027 1.80% 40,913 $7,364 $48,278

P-01 LANDS AND DAMAGES $5 $1 18% $6 31.90% $7 $1 $8 OCT 2027 1.80% $7 $1 $8

P-30 PLANNING, ENGINEERING & DESIGN $3,047 $548 18% $3,595 31.90% $4,019 $723 $4,742 OCT 2027 1.80% $4,091 $736 $4,828

P-31 CONSTRUCTION MANAGEMENT $2,438 $439 18% $2,877 31.90% $3,216 $579 $3,795 OCT 2027 1.80% $3,274 $589 $3,863

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $35,960 $6,473 18% $42,433 $47,431 $8,538 $55,969 48,285 $8,691 $56,976

YEAR 15TOTAL COSTS ==============> 56,976

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 202: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 16 **** TOTAL PROJECT COST SUMMARY **** PAGE 17 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2028 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 27

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $16,358 $2,944 18% $19,303 34.30% $21,969 $3,954 $25,924 OCT 2028 1.80% $22,364 $4,026 $26,390C-12-05 DRAINAGE AREA MANAGEMENT $8,243 $1,484 18% $9,727 34.30% $11,070 $1,993 $13,063 OCT 2028 1.80% $11,270 $2,029 $13,298C-12-06 DIKE CONST, REHAB AND LIFT $371 $67 18% $438 34.30% $498 $90 $588 OCT 2028 1.80% $507 $91 $599C-16-01 SHORELINE PROTECTION 18% 34.30% OCT 2028 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $24,972 $4,495 18% $29,467 $33,537 $6,037 $39,574 OCT 2028 1.80% 34,141 $6,145 $40,286

P-01 LANDS AND DAMAGES 18% 34.30% OCT 2028 1.80% $0

P-30 PLANNING, ENGINEERING & DESIGN $2,497 $449 18% $2,946 34.30% $3,353 $604 $3,957 OCT 2028 1.80% $3,414 $614 $4,028

P-31 CONSTRUCTION MANAGEMENT $1,998 $360 18% $2,358 34.30% $2,683 $483 $3,166 OCT 2028 1.80% $2,732 $492 $3,223

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $29,467 $5,304 18% $34,771 $39,574 $7,123 $46,698 40,287 $7,252 $47,538

YEAR 16TOTAL COSTS ==============> 47,538

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 203: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 17 **** TOTAL PROJECT COST SUMMARY **** PAGE 18 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2029 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 28

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $27,668 $4,980 18% $32,648 36.70% $37,822 $6,808 $44,631 OCT 2029 1.80% $38,503 $6,931 $45,434C-12-05 DRAINAGE AREA MANAGEMENT $373 $67 18% $440 36.70% $510 $92 $602 OCT 2029 1.80% $519 $93 $613C-12-06 DIKE CONST, REHAB AND LIFT $1,201 $216 18% $1,417 36.70% $1,642 $296 $1,937 OCT 2029 1.80% $1,671 $301 $1,972C-16-01 SHORELINE PROTECTION 18% 36.70% OCT 2029 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $29,242 $5,264 18% $34,506 $39,974 $7,195 $47,169 OCT 2029 1.80% 40,693 $7,325 $48,018

P-01 LANDS AND DAMAGES $5 $1 18% $6 36.70% $7 $1 $8 OCT 2029 1.80% $7 $1 $8

P-30 PLANNING, ENGINEERING & DESIGN $2,924 $526 18% $3,450 36.70% $3,997 $719 $4,717 OCT 2029 1.80% $4,069 $732 $4,802

P-31 CONSTRUCTION MANAGEMENT $2,339 $421 18% $2,760 36.70% $3,197 $576 $3,773 OCT 2029 1.80% $3,255 $586 $3,841

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $34,510 $6,212 18% $40,722 $47,175 $8,492 $55,667 48,024 $8,644 $56,669

YEAR 17TOTAL COSTS ==============> 56,669

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 204: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 18 **** TOTAL PROJECT COST SUMMARY **** PAGE 19 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2030 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 29

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $6,882 $1,239 18% $8,121 39.20% $9,580 $1,724 $11,304 OCT 2030 1.80% $9,752 $1,755 $11,508C-12-05 DRAINAGE AREA MANAGEMENT $331 $60 18% $391 39.20% $461 $83 $544 OCT 2030 1.80% $469 $84 $553C-12-06 DIKE CONST, REHAB AND LIFT $847 $152 18% $999 39.20% $1,179 $212 $1,391 OCT 2030 1.80% $1,200 $216 $1,416C-16-01 SHORELINE PROTECTION 18% 39.20% OCT 2030 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $8,060 $1,451 18% $9,511 $11,220 $2,020 $13,239 OCT 2030 1.80% 11,421 $2,056 $13,477

P-01 LANDS AND DAMAGES 18% 39.20% OCT 2030 1.80% $0

P-30 PLANNING, ENGINEERING & DESIGN $806 $145 18% $951 39.20% $1,122 $202 $1,324 OCT 2030 1.80% $1,142 $206 $1,348

P-31 CONSTRUCTION MANAGEMENT $645 $116 18% $761 39.20% $898 $162 $1,059 OCT 2030 1.80% $914 $165 $1,079

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $9,511 $1,712 18% $11,223 $13,239 $2,383 $15,622 13,478 $2,426 $15,904

YEAR 18TOTAL COSTS ==============> 15,904

2010 cost summary from District.xlsx Printed: 11/17/2010

Page 205: Appendix D COST ESTIMATION - United States Army · 2015-03-09 · The cost estimates and assumptions listed in this Appendix have been used to evaluate and compare the costs for each

YEAR 19 **** TOTAL PROJECT COST SUMMARY **** PAGE 20 OF 20

THIS ESTIMATE IS BASED ON THE SCOPE CONTAINED IN THE FEASIBILITY REPORT, DATED: FEB-2008 PROJECT: DMMP DISTRICT: NEW ORLEANS LOCATION: Calcasieu LA CALCASIEU RIVER AND PASS DMMP P.O.C.: Paul Varnado

CURRENT MCACES ESTIMATE PREPARED: 5 NOV 2010 AUTHORIZ./BUDGET YEAR: 2031 FULLY FUNDED ESTIMATE EFFECTIVE PRICING LEVEL: NOV 2010 EFFECT. PRICING LEVEL: 1 OCT 30

ACCOUNT COST CNTG CNTG TOTAL OMB COST CNTG TOTAL FEATURE OMB COST CNTG FULLNUMBER FEATURE DESCRIPTION ($K) ($K) (%) ($K) (%) ($K) ($K) ($K) CONST PT (%) ($K) ($K) ($K)

C-02-01 RELOCATIONS N/AC-12-04 HYDRAULIC DREDGING $15,466 $2,784 18% $18,250 41.70% $21,915 $3,945 $25,860 OCT 2031 1.80% $22,310 $4,016 $26,326C-12-05 DRAINAGE AREA MANAGEMENT $235 $42 18% $277 41.70% $333 $60 $393 OCT 2031 1.80% $339 $61 $400C-12-06 DIKE CONST, REHAB AND LIFT 18% 41.70% OCT 2031 1.80% $0C-16-01 SHORELINE PROTECTION 18% 41.70% OCT 2031 1.80% $0

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL CONSTRUCTION COSTS ===> $15,701 $2,826 18% $18,527 $22,248 $4,005 $26,253 OCT 2031 1.80% 22,649 $4,077 $26,726

P-01 LANDS AND DAMAGES 18% 41.70% OCT 2031 1.80% $0

P-30 PLANNING, ENGINEERING & DESIGN $1,570 $283 18% $1,853 41.70% $2,225 $400 $2,625 OCT 2031 1.80% $2,265 $408 $2,672

P-31 CONSTRUCTION MANAGEMENT $1,256 $226 18% $1,482 41.70% $1,780 $320 $2,100 OCT 2031 1.80% $1,812 $326 $2,138

_________________________________ _________ _________ _________ _________ _________ _ _________ _________

TOTAL PROJECT COSTS ========> $18,527 $3,335 18% $21,862 $26,253 $4,725 $30,978 26,725 $4,811 $31,536

YEAR 19TOTAL COSTS ==============> 31,536

2010 cost summary from District.xlsx Printed: 11/17/2010