On Thursday 16th October 2014, John Chapman and Andrew Gray presented at the APM Project Management in Practice Event, where the subject area was an Introduction to Programme Management. Theirs was an interactive session where John provided the theoretical side of programme management, whilst Andrew explained how this worked using a real life example from the UK MOD where a Programme Management approach was adopted using the Managing Successful Programmes (MSP) framework. The Programme Lifecycle gave a structure to the presentation covering seven areas 1. What is a programme? 2. Why do a programme? 3. What makes up a programme? 4. How do we run a programme? 5. Who is in the programme? 6. When does a programme end? 7. What challenges are faced? It was important to show how Programme Management called upon the specialisms from the other Specific Interest Groups. An example of this relates to Benefits Management. Early on in the programme the questions to be asked, and answered, include: 1. Is there a vision of a change future? 2. Is this a shared single vision? 3. Is it in line with what is needed? 4. What are the benefits to be gained? 5. Who benefits, what do they benefit, how much benefit, when do they benefit? Andrew commented that an important area to consider was the area of stakeholder management. With a high profile programme, there are many diverse stakeholder groups and interfaces including • An external advisory group • Local representatives and committees • Regulators & policy holders • UK & Scottish governments • Press coverage • Wide ranging public consultations Consultation and communication (two way) would then provide inputs and influences to the decision making process within the Programme. At the end of the presentation Andrew noted the lessons learned (so far) on the adoption of a programme management approach as: A Programme Management approach is not for everything - Split change element of the objectives from long-term business as usual Bring clarity & focus - Projects need to know how they fit into ‘big change picture’ Get senior commitment - Have the approach endorsed by the Programme Board Co-ordinate stakeholder engagement - Communications must be co-ordinated and consistent across the projects Scale the management investment that is needed - Do not swamp with bureaucracy Efficient pooling of resources - A small programme team benefits from pooling common central activities Cope with geographically dispersed team - Programme Management approach is the glue to hold things togetherTRANSCRIPT
![Page 1: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/1.jpg)
Joining the DotsProgramme Management in action
Introduction
![Page 2: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/2.jpg)
Introduction
![Page 3: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/3.jpg)
Approach
We want to give an overview of the elements of programme management and how they integrate together.
We will illustrate some of these elements or principles with case study material from an ongoing programme.
The elements and case study will be explored using an dialogue style with interview questions. We welcome any additional questions from the floor as we proceed.
![Page 4: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/4.jpg)
Joining the Dots
One key theme of programmes is co-ordination and integration of interdependencies.
Even in programme management itself there are many dots to join...
What is a programme
?
Why do a programme
?What
makes up a programme
?
How do we run a
programme?Who runs a
programme?
When does a
programme end
?
What challenges are faced
?
![Page 5: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/5.jpg)
What is a programme?
Why do a programme? What makes
up a programme?
How do we run a
programme?
Who runs a programme?
When does a
programme end
?
What challenges are
faced?
![Page 6: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/6.jpg)
DevelopmentManaging the TranchesConcept
Identifying a
programme
DefinitionDefining a
programme
ClosureClosing a
programme
Benefits RealisationRealising Benefits
Project Delivery
Delivering the
capability
MSP is a registered trademark of Axelos Ltd.
![Page 7: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/7.jpg)
Enabling Change
PortfolioBenefits
Value
Assurance
Governance
PMC
PMO
ProgM
Risk
People
Knowledge
WIPM
Contracts &Procurement
![Page 8: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/8.jpg)
Who are we?
Programme Director for Touchstone EnergyExperienced programme/project director & manager in international environmentsAuthor and co-author, including Gower Handbook of Programme ManagementContributor to Managing Successful ProgrammesCommittee member of ProgM and PMC SIGs
John Chapman
Andrew GrayPrincipal Consultant at BMT Hi-Q Sigma
Experienced programme/project manager in engineering product development and introduction
Programme advisor to MOD Submarine Dismantling ProjectCommittee member of ProgM SIG
& member of APM / INCOSE Joint Working Group
![Page 9: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/9.jpg)
The Case Study
Description of case study
UK MOD Submarine Dismantling Project
![Page 10: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/10.jpg)
![Page 11: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/11.jpg)
Definitions & ContextAPMA group of related projects and change management activities that together achieve beneficial change for an organisation.
Managing Successful Programmes (MSP)A temporary, flexible organisation created to coordinate, direct and oversee the implementation of a set of related projects and activities in order to deliver outcomes and benefits related to the organisations strategic objectives.
![Page 12: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/12.jpg)
Satisfying Business Needs
Is there a need for change?Is there an ability and culture for change?Is there a wider perspective of change?
Is there a business need?
... address complexity and uncertainty?
... manage tensions between corporate objectives, business as usual and change delivery?
How can we…
• Transformational Change• Specification-Led Change• Emergent Change
![Page 13: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/13.jpg)
Change environment in the DE&S submarine portfolio
Defence Reform
Business as usual New operational capabilities
![Page 14: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/14.jpg)
![Page 15: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/15.jpg)
Programme vs Project
![Page 16: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/16.jpg)
So why change?
![Page 17: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/17.jpg)
![Page 18: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/18.jpg)
Identify
Is there a vision of a changed future?Is this a shared single vision?Is it in line with what is needed?
What are the benefits to be gained?Who benefits, what do they benefit, how much benefit, when do they benefit?
What is going to change?How are we going to bridge the gap from now to then?
Define a blueprint for the future
Where (and how) is transition to steady state to be achieved?
![Page 19: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/19.jpg)
The Need
SDP Single Statement of User Need
![Page 20: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/20.jpg)
Change vs Steady-State
![Page 21: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/21.jpg)
The SDP Change Vision
![Page 22: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/22.jpg)
![Page 23: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/23.jpg)
![Page 24: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/24.jpg)
Define a programme
Benefits
Outcomes
Tranches – step changes in capability
Define a dossier of projects
Do the right projects, do the projects right
What benefits can we achieve & when? Any quick wins?
What elements of the future state need to be put in place - is there a sequence?
What are the intermediate steps to achieve? Are there funding or decision gates? Are we driving down uncertainty?
What do we need to produce, how, when and who by?
![Page 25: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/25.jpg)
Identifying SDP projects
![Page 26: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/26.jpg)
Defining the Tranches
![Page 27: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/27.jpg)
![Page 28: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/28.jpg)
![Page 29: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/29.jpg)
How it works together
Managing the Tranches
![Page 30: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/30.jpg)
Create a clear structure in SDP
![Page 31: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/31.jpg)
Manage SDP Interdependencies
![Page 32: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/32.jpg)
![Page 33: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/33.jpg)
![Page 34: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/34.jpg)
Responsibilities, roles & actorsGovernance and leadership
Making the change
Managing integration & relationships
Engaging with stakeholders
An effective PMO
Need strong integrated leadership and boundary scanning: Sponsor(ing Group), Senior Responsible Owner, Board
Must be able to transition effectively to new practices:Business Change Manager(s)
No programme exists in isolation:Know your stakeholders and their objectives; keep them informed
The ringmaster around whom the performers interact:The Programme Manager
Nobody notices a smooth running machine
![Page 35: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/35.jpg)
Engaging the public
![Page 36: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/36.jpg)
![Page 37: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/37.jpg)
![Page 38: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/38.jpg)
Transition and Realisation
Generating outcomes & value
Transitioning to the new state
Embedding change in business-as-usual
Realising the benefits
![Page 39: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/39.jpg)
SDP Verification and Validation
![Page 40: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/40.jpg)
![Page 41: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/41.jpg)
![Page 42: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/42.jpg)
Potential barriers
• Insufficient support• Weak leadership• Unrealistic expectation of capability & capacity• Insufficient focus on benefits• No real idea of future capability & how to get there• Little understanding or control over interdependencies• Poorly defined for communicated vision• Failure to change culture• Insufficient engagement of stakeholders• No boundary scanning
A typical programme may have to consider how to address
![Page 43: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/43.jpg)
SDP External Forces
![Page 44: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/44.jpg)
![Page 45: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/45.jpg)
So what have we learnt?
![Page 46: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/46.jpg)
Joined the dots to make a picture
![Page 47: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/47.jpg)
SDP lessons to consider… so far
![Page 48: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/48.jpg)
More information
![Page 49: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/49.jpg)
Joining the DotsProgramme Management in action
Introduction
![Page 50: APM Presents - Joining the dots - Programme Management in action](https://reader035.vdocuments.mx/reader035/viewer/2022070312/553bb9a65503461c478b4759/html5/thumbnails/50.jpg)