aoc sediment update_part 1

42
Contaminated Sediment Management Roger Santiago – Environment Canada 2012 RAP Implementation Workshop Getting the Job Done !

Upload: lake-superior-binational-forum

Post on 06-May-2015

598 views

Category:

Documents


0 download

DESCRIPTION

2012 update on sediment management at Areas of Concern across the Great Lakes. Excellent information about the north harbour section of Thunder Bay, Ontario

TRANSCRIPT

Page 1: Aoc sediment update_part 1

Contaminated Sediment

Management

Roger Santiago – Environment Canada

2012 RAP Implementation Workshop Getting the Job Done !

Page 2: Aoc sediment update_part 1
Page 3: Aoc sediment update_part 1

Priority Sediment Remediation Sites

Contaminated Site Overview •  Thunder Bay N. Harbour – Hg, Organic material – 350,000 m3 •  Peninsula Harbour – Hg, PCBs – 256,000 m2 •  St. Marys River – PAHs – 50,000 m3 (app.) •  St. Clair River – Hg – 61,000 m3 •  Hamilton Harbour – PAHs, metals – 675,000 m3 •  Niagara River – PCBs – 20,000 m3 (MoNR)

Page 4: Aoc sediment update_part 1

Conceptual Implementation Schedule and Estimated Costs (in $1000)

Implementation estimate based on sediment risk assessment

Implementation estimate based on SMO

Implementation estimate based on Engineering Design

AOCs 2012/13 2013/14 2014/15 2015/16 2016/17 2017/18 2018/19 Total

TB $21,600 $21,600 $21,600 $65,000

PH $7,300 $7,300

SM $5,000 $5,000 $10,000

SC $8,750 $8,750 $17,500

Total Cost (without RR)

$99,800

RR (to 2022) $105,000

TOTAL COST (with RR)

$204,800

Page 5: Aoc sediment update_part 1

Stages of Sediment Projects (7) Post Construction

(6) During Construction

(5) Tender Award

(4) Detailed Engineering Design

(3) Preliminary Engineering Design

(2) Conceptual Design

(1) Sediment Assessment

Sediment Remediation Challenges Cost Estimate Increases

Increasing Certainty in Estimate

Page 6: Aoc sediment update_part 1

Sediment Remediation Challenges

•  Ability to secure1/3 local funding –  Depressed local markets –  Local industry bankruptcy issues –  Lack of interest/responsibility

•  Project lead (Contracting Authority) •  Future Liability for in-situ remediation •  Site Access/Ownership Issues •  Coordinating stakeholder (funding parties) interest •  Cost overruns during implementation •  Cost estimate increases

Page 7: Aoc sediment update_part 1

Science Challenges to GL Sediment Remediation

  Great Lakes Areas of Concern •  Lack of Chemical Guidelines for COC in Sediment •  Absence of confirmed dose-response information for COC •  Development of innovative techniques to identify and manage debris •  Develop and implement feasible pore water sampling methods •  Develop approaches to reduce uncertainty related to identification of

contamination layer •  Understanding the dynamics of natural recovery and recovery post

remediation and the ability to to predict through modelling when short and long term goals will be achieved

•  Addressing temporal variability in benthic community structure related to stressors such as invasive species, climate change, change in abundance of native taxa, watershed disturbance etc.

Page 8: Aoc sediment update_part 1

Thunder Bay North Harbour Sediment Management

RAP Workshop February 8, 2012

Page 9: Aoc sediment update_part 1

Thunder Bay Area of Concern

Page 10: Aoc sediment update_part 1

Thunder Bay Project Site

Page 11: Aoc sediment update_part 1

Thunder Bay North Harbour - Contaminated Sediment Management

Page 12: Aoc sediment update_part 1

Contamination Overview

Page 13: Aoc sediment update_part 1

Contaminated Sediment

Page 14: Aoc sediment update_part 1

Mercury Concentrations in Surficial Sediments

Page 15: Aoc sediment update_part 1

Mercury Concentrations at Depth

Page 16: Aoc sediment update_part 1

Enriched Organic Sediment

Page 17: Aoc sediment update_part 1

Toxicity and Biomagnification

Page 18: Aoc sediment update_part 1

•  Monitored natural recovery

•  Capping (sand or reactive cap)

•  On-site confined disposal facility

•  Dredging with disposal at an off-site confined disposal facility

•  Dredging with upland disposal

Page 19: Aoc sediment update_part 1

Conceptual Sediment Management Schedule

Additional Studies in support of SMO – 2012 Decision on preferred SMO – 2013 Engineering Design/ EA – 2014-2015 Construction (assume 2 to 5 years) – 2016-20?? Long-term monitoring – 15 years

Page 20: Aoc sediment update_part 1

Peninsula Harbour Sediment Management

RAP Workshop February 8, 2012

Page 21: Aoc sediment update_part 1

Peninsula Harbour Area of Concern

Page 22: Aoc sediment update_part 1

Project Description •  Elevated levels of Mercury and PCBs are

present in sediment in Peninsula Harbour with the highest concentration found in Jellicoe Cove.

•  Contaminated sediment in Jellicoe Cove is acting as a source of mercury and PCBs for the rest of the PH and posing risk to biota.

•  Results of Risk Assessment indicated that sediment management action is required

Peninsula Harbour Shoreline 2007

Page 23: Aoc sediment update_part 1

1. Sediment Sampling - Chemistry

Surface concentrations of mercury average 7 ppm, which is 3.5X higher than the guideline.

Average subsurface concentrations are 3X higher than average surface concentrations.

Sediment Core Sample

Page 24: Aoc sediment update_part 1

2.  In-Situ Tracer Measurements (6/05-7/06)

•  Divers applied a tracer (mineral) in slurry form to measure sediment mixing rate

•  Cores were initially collected to determine background levels

•  One year later, sampling revealed mixing of surface sediment to 8 cm

Conclusion: Mixing generally occurs in top 8 cm of sediment

Page 25: Aoc sediment update_part 1

3a. Rotating Circular Flume Tests

•  Tells us how the sediment resists bottom currents

•  Large diameter sediment cores collected and tested for erosional resistance in a rotating circular flume

Conclusion: Strong bottom currents are required to mobilize sediment that is deeper than 5 cm

Objective: Measure strength of bottom current needed to mobilize sediment

Page 26: Aoc sediment update_part 1

3b. In Situ Flume Experiments (9/07)

•  At 4 sites, flume was deployed in Jellicoe Cove to measure erosional resistance of surface sediments

•  Compared to subsurface sediment, surface fines erode with weaker bottom currents

Conclusion: Surface sediment (1-5 cm) erodes with bottom currents 10x weaker than for deeper sediment

Objective: Measure strength of bottom current needed to mobilize sediment

Page 27: Aoc sediment update_part 1

4. Wave Climate (6/05-7/06 and 11/06-5/07)

•  Bottom currents measured by a current meter (MAVS-3)

•  Year-round •  6 months in high energy

season

Objective: Measure bottom currents in Jellicoe Cove

Conclusion: Currents strong enough to move surface sediment are common. Currents strong enough to move subsurface sediment are rare.

Page 28: Aoc sediment update_part 1

Conclusions

1.  Thin layer capping will help manage the surface sediment that is currently mobile.

2.  Dredging is not required to address subsurface sediment mobility.

Page 29: Aoc sediment update_part 1

Sediment Management Option

•  Thin layer capping was selected to manage the contaminated sediments.

•  Area with > 3 ppm Hg will be covered with 15 to 20 cm of clean sand (approx. 20 hectares – about 40 football fields)

•  Area with >0.34 ppm PCB will be covered with 15 to 20 cm of clean sand (approx. 5 hectares – about 5 football fields)

Page 30: Aoc sediment update_part 1

Thin-Layer Capping

Sediment Profile Imaging Camera

Thin layer cap

Capped sediment

Page 31: Aoc sediment update_part 1

EA Findings

Results of the assessment indicate: • DFO Authorization under section 35(2) of the Fisheries Act is

required. • Town of Marathon may be subjected to truck traffic and noise

during the construction period • AECOM confirmed that local pits in the Marathon area have

suitable cap material. • There are no additional regulatory restrictions on dredging post

cap to allow access to larger vessels • The MPI water intake will be protected during construction.

Page 32: Aoc sediment update_part 1

Sediment Remediation Schedule

MERX Tender Posting – March 2012 Tender Award – April 2012 Mobilization – May 2012 Pilot Scale Demonstration – June 2012 Production Capping – June – Aug 2012 Demobilization – September 2012 Post Engineering Assessment 2013 Long Term Monitoring – 2014

Page 33: Aoc sediment update_part 1

Long Term Monitoring Plan Year Years after Cap Monitoring Component Survey Period 2013 1 Cap Movement and Submerged Aquatic Vegetation fall

Cap Thickness Study summer/fall

2015 3 Cap Movement and Submerged Aquatic Vegetation fall

2017 5 Cap Movement and Submerged Aquatic Vegetation fall Benthic Community/Benthic Tissue/Sediment Chemistry fall Fish Tissue Survey last week of June to end of August

2022 10 Cap Movement Survey fall Benthic Community/Benthic Tissue/Sediment Chemistry fall Fish Tissue Survey last week of June to end of August

2027 15 Cap Movement Survey fall Benthic Community/Benthic Tissue/Sediment Chemistry fall Fish Tissue Survey last week of June to end of August

2032 20 Cap Movement Survey fall Benthic Community/Benthic Tissue/Sediment Chemistry fall Fish Tissue Survey last week of June to end of August

Page 34: Aoc sediment update_part 1

St. Clair River – Sediment Management

RAP Workshop February 8, 2012

Page 35: Aoc sediment update_part 1

St. Clair River

Page 36: Aoc sediment update_part 1

St. Clair River – Contaminated Sediment Management

St. Clair River AOC

Page 37: Aoc sediment update_part 1

St. Clair River Sediment Remediation Project

•  Eddy Pump hydraulic dredge used to remove 13,000 m3 contaminated sediment (Hg, and organics) with physical dewatering and anaerobic bioremediation (biopile) and on-site disposal

Page 38: Aoc sediment update_part 1

Dow River Cleanup

Page 39: Aoc sediment update_part 1

Dow River Cleanup

Page 40: Aoc sediment update_part 1

Habitat Restoration - 2005

•  Restore the area to a state of granular sediment.

•  Enhance fisheries habitat and promote benthic macroinvertebrate recolonization.

Page 41: Aoc sediment update_part 1

Priority Zones for Sediment Management

Three priority zones for management;

1.  Volume near Suncor dock, (25,700m3)

2.  Volume near Shell dock (5,500m3), and

3.  Volume near Guthrie Park (3,750m3)

Suncor

Guthrie Park

Shell

These areas represent depositional areas downstream from the original source.

Page 42: Aoc sediment update_part 1

St. Clair River Priority Areas

1.  Sediment Chemistry •  61% of sediment samples more than

2 mg/kg Hg (Provincial SEL) •  Hg in buried sediment up to 5 times

higher than surface sediment in some places

3.  Sediment Toxicity •  No strong evidence of toxicity to Hg

5.  Changes to Benthic Community •  No strong evidence of community

changes due to Hg compared to reference sites

7.  Potential for Biomagnification •  Negligible risk to wildlife that eat fish •  Risks to some fish species •  Priority Areas identified based on

risk to fish

Management Goals Removal of Hg-contaminated sediment:

1.  as a source to downstream sites 2.  to promote local risk reduction 3.  for contaminant mass removal