annual report 2016 17 - oil india · 4.1 budget performance capital budget target for 2016-2017 was...

60
1 ANNUAL REPORT 2016 – 17 RAJASTHAN PROJECT, JODHPUR OIL INDIA LIMITED

Upload: others

Post on 15-Mar-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

1

ANNUAL REPORT 2016 – 17

RAJASTHAN PROJECT, JODHPUR OIL INDIA LIMITED

Page 2: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

1

1.0 INTRODUCTION:

During the year 2016-17 Rajasthan Project achieved a Natural Gas production of 232.019 MMSCUM and Sales of 227.071 MMSCUM against the revised target of 211.00 MMSCUM and 209.00 MMSCUM respectively. Additionally, with respect to the quantum of production vis-à-vis total sale quantity, both were higher than the respective quantity in the previous year i.e. 2015-2016 which were 206.188 MMSCUM & 201.17 MMSCUM. The percentage achieved for production of Natural Gas was 109.96% and sale 108.65 % against RE target. Rajasthan Project continued its endeavour for production and supply of Natural Gas to Rajasthan Rajya Vidyut Utpadan Nigam Limited (RRVUNL) through the pipeline of M/s GAIL (India) Ltd. in an efficient manner and thus contributed towards overall annual performance of OIL INDIA LIMITED.

OIL (Rajasthan Project) bagged the following eight prizes in the 30th Mines Safety Week 2016, organised by M/s. FCI Aravali Gypsum and Minerals India limited, Jodhpur, under the aegis of Director of Mines Safety, Ajmer region.

Installation Prize Category

1 Production DND-GPC First Fire Fighting Drill

2 Production DND-GPC First Statutory records keeping

3 Production DND-GPC Third Overall performance

4 Workover Rig (GTC 100-03) First Electrical equipment, lighting and wiring.

5 Workover Rig (GTC 100-03) First Safety features & Records

6 Workover Rig (GTC 100-03) First Overall performance

7 Workover Rig (GTC 100-03) Second Publicity propaganda and house keeping

8 Workover Rig (GTC 100-03) Second Drilling & Maintenance

Project has also achieved success in the field of energy conservation by adopting measures like reducing vehicle movements, using energy efficient lights, maintaining solar lighting system etc. in the field which resulted in saving of considerable amount of HSD.

Page 3: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

2

2.1 TARGETS AND ACHIEVEMENTS : Activity Target

Achievem

ent Excess / Short-fall

1. Drilling (MTRS) Exploratory 1250

1278

Excess by 0.24 %

Development

8000

8054

Excess by 0.67 %

2.Natural Gas (MMSCUM) Production 211 232.019 Excess by

9.96% Sales 209 227.071 Excess by

8.65%

2.2 STATUS OF PEL / ML:

PEL AREAS: NELP IV BLOCK RJ-ONN-2002/1: As suggested by Director (E&D), a review study was

carried out on relinquished areas of this block. Few leads were identified within the block during G&G review and it was planned to validate the leads with additional seismic data before going for drilling . Accordingly, actions were initiated to carry out API of 600 GLKM of seismic to reconfirm the structural position and size of the leads and to upgrade to prospects but the same could not be carried out due to reason already discussed vide OCR dated 18.12.2009. It is worthwhile to mention here that one well (Nanuwala-1) drilled north of this block produced crude oil (API 30.33) during testing. The leads identified in the block are in up-dip direction with respect to Nanuwala-1 and fall in the same migration pathway. It is suggested to acquire 3D seismic of around 1000 sq.km covering the identified leads. Alternatively 600 GLKM 2D seismic (2x2 KM grid) can be acquired covering identified leads which was originally planned for the block. Based on the interpretation of suggested seismic data drilling may be planned in future.

NELP-VI Block RJ-ONN-2004/2: A review study was carried out on relinquished areas of

this block. Earlier, a G&G review was carried out after heavy oil discovery in Punam-1 well, one independent closure at Jodhpur Formation top level was identified in the south of Punam structure. The said structure is structurally up dip in respect to Punam structure and part of greater Baghewala-Punam structural high trend. One location (Loc.C) was proposed in the structural closure, however, location was not

Page 4: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

3

released and the structure could not be probed by exploratory drilling mainly due to time limitation to fulfill the MWP work and subsequently the area had to be relinquished (mandatory). As per G&G review to probe hydrocarbon prospects in the independent structural closure south of Punam structure by drilling an exploratory well, the same work program of drilling one exploratory well in the block is mooted again. A request of retaining of about 10.2SQ.KM area covering the discovery area of Block RJ-ONN-2004/2 for appraisal and Declaration of Commerciality (DOC) has been submitted to DG, DGH. However, DG, DGH in the meeting regarding “Monitoring of Nomination Blocks” indicated that OIL can avail the benefits of proposed OALP for further exploration and production activity in the block. PI Transfer: The process of 25% PI transfer to OIL , the matter is still under arbitration process. Next arbitration of hearing is expected in the month of May/June 2017. Received communication from DGH to extend the validity of BG till 30.09.2017 with claim period upto 30.11.2017.

NELP-VI Block RJ-ONN-2004/3:

Block relinquished w.e.f. 21.01.2012. Payment of Rs. 13,60,43,435/- has been made towards differential cost of un-finished MWP of the Block.

NELP-VII Block RJ-ONN-2005/2: 2nd Extension of Phase-I:

DGH made a communication in connection with our proposal to relinquish the entire Block. DGH has asked to submit the cost of unfinished MWP as per article 5.6 of PSC immediately as well as original and copy of data to DGH. Bank Guarantees was extended by one year for completion of Minimum work Programme in the Block. As suggested by Director (E&D), a review study was carried out on relinquished areas of this block. Out of the eleven prospects identified in-house as well as by consultancy services, two prospects are at much deeper depth than MWP well depths. Moreover, these new prospect horizons were not visible by old seismic data. Out of these eleven locations five locations were released by competent authority and out of these two locations have been drilled by the consortium. The deeper new prospect identified based on the last 3D seismic survey could not be probed by exploratory drilling as JV partners did not agree due to higher financial involvement for deeper target depth in comparison to MWP well Target and additional payment of 30% LD for the third extension requiring to complete the drilling of the well . There were also some concern about the reservoir type due to virgin nature of these prospects . However, subsequent G&G review indicates possible presence of carbonate reservoir at this depth.

MINING LEASE AREAS: a. 210 SQ KM ML AREA (BAGHEWALA BLOCK):

Page 5: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

4

ML is Valid up to 29.05.2023. Yearly Dead Rent was deposited for period 30.05.2016 to 29.05.2017 .

b. 250 SQ KM ML AREA (JAISALMER BLOCK): ML is valid up to 31.12.2035. Yearly Dead Rent was deposited for period 01.01.2017 to 31.12.2017. 3.0 BRIEF FINANCIAL SUMMARY:

3.0.1 Revenues Generated:

Page 6: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

5

3.0.2 Contribution to Exchequer:

4.1 Budget Performance

Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/

commitment have been made against ₹ 5,47,15,220.00.

4.2 Austerity Measures introduced:

The overtime in office jobs is reduced to almost zero.

The visits to the fields by different officials are clubbed to the extent possible.

With proper monitoring, control and clubbing of open tenders we could saved INR

23.44 Lakhs in the current financial year. The advertisement cost per tender is

reduced from last year’s cost of INR 3.35 Lakhs to INR 1.96 Lakhs.

Completed three numbers of drilling wells and one Water Disposal Well in the stipulated time period.

Faster ILM in case of both drilling & work-over wells than the stipulated time-frame as per the provision of the Contract thereby increasing Rig utilization time leading to overall improvement of performance.

Optimum utilization of bit life in order to reduce quantity of drill bit consumption vis-à-vis number of bit trips in a well.

Use of integrated cementing set-up attached to Work-over Rig for cement plug/squeeze jobs in almost all the work-over wells.

------------ xx ------------

Page 7: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

6

Page 8: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

7

5.0 PRODUCTION

5.1.0 Introduction

Year 2016-2017 had been a better year for Team Production (RP) from the point of view of sale of natural gas produced from Dandewala(DND) and Bagitibba gas fields as well as the progress made towards heavy oil exploitation in comparison to previous year. Against the revised targets (RE) of 211.00 MMSCUM and 209.00 MMSCUM of gas production and sales respectively, the achievements were 232.019MMSCUM(109.96%) and 227.071MMSCUM(108.65%) respectively.

5.2.0 Targets & achievements (NATURAL GAS):

5.2.1 Details of Annual Targets & Achievement for the year 2016-2017 of Production Department are given below:

Target (RE)

Achievement % of achievement

Gas Production (MMSCUM)

211 232.019 109.96

Gas Sale (MMSCUM)

209 227.071 108.65

Frequent problems at RRVUNL’s turbines were reported during the year for which gas supply had to be either curtailed or stopped completely making it not possible to meet the budgeted target (BE) production of 240 MMSCUM though production capability was in hand.

5.2.2 A total quantum of 219.410 Kls of condensate was produced (+70 kls

carried over from previous year) and 240.00 Kls were sold to the customer during the year and another 32.00 kls was utilized at Baghewala– 5 & Bikampur#1 for chemical stimulation.

5.3.0 Gas production and sales, operation and maintenance of Production

Installation, gas wells:

Gas production and supply targets were planned as per the MOU with GAIL that the customer would lift gas @ 0.7 MMSCUMD during the year. However, due to various problems of the turbines of end user M/S. RRVUNL, gas production rate had to be curtailed as per actual gas off-take by the customer. A total of 5740 hours of turbine shut- down occurred during the year. As a result the production & supply of NG were

Page 9: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

8

marginally below the annual targets (BE). However , the average daily production was @ 0.64 MMSCUMD against that of @ 0.56 MMSCUMD in the previous year (2015-16) .

5.3.1 Wells on production during the year 2106-17:

Dandewala Field : 19 Nos. Bagitibba Field : 2 No.

CTU/NPU Deployment: A well activation contract was awarded to M/s. SES

Energy Services India Pvt Ltd, Mumbai to hire well activation and well testing

services on call out basis for 2 years period w.e.f. 18.02.2015 to 17.02.2017, which

was further extended by three months. The CTU/NPU was deployed in all

workover wells completed with permanent packer (DND#4, DND#6, DND#9,

DND#11, DND#14, DND#19, DND#24, DND#25, DND#26, DND#27, DND#28 &

BGT#1) . Loc RBAS(Well Bikampur–1) in Baghewala PML was also activated using

the hired CTU/NPU unit from the contractor.

Workover was also carried out at BGW#5 and hired CTU/NPU was deployed to activate the well.

5.3.2 Operation & Maintenance of DND-GPC:

The present gas handling capacity of the DND-GPC is 1.0 MMSCUMD. The plant is on continuous operation since 1996. Due to ingress of formation water in the produced fluid and continued operation of the plant, maintaining the equipments to its capacity has been a challenging job.

The overall operation and maintenance of the plant was carried out satisfactorily during the FY 2016-17.

5.3.3 Work-Over Operations:

Increase in water production and build up of annulus pressure in some of the wells is a matter of serious concern. Few wells are in production through N-80 tubing which is not desirable in CO2 environment. Hence, it was planned to carry out workover of 19 identified wells during FY 2015-16 & 2016-17. Three (3) wells (DND#6, DND#11 & BGT#1) ) having water ingress and four (4) wells (DND#4, DND#9, DND#14, DND#19)having annulus pressure buildup were undertaken for workover operation. Also five (5) new wells previously drilled (DND#24, DND#25, DND#26, DND#27, DND#28) were undertaken for workover for production testing. In total, workover was carried out successfully in twelve (12) nos of gas wells of Jaisalmer PML of Rajasthan and one (1) heavy oil well (BGW#5) of Baghewala during the year.

5.3.4 Drilling and Field Development:

Page 10: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

9

It was proposed to drill five wells in Dandewala field to sustain the gas production potential from the Jaisalmer Basin. Two development wells namely, DND#24(Loc.RJBH) & DND#25 (Loc. RJBJ) were completed successfully in 2015-16. The production testing of these wells was carried out with workover outfit in the year 2016-17. Drilling of DND#26(Loc. RJBI) was completed in 2016-17 along with DND#27 & DND#28. Production testing for these wells was also carried out during this period. Moreover a water disposal well(WDW) was also drilled during this period for disposal of effluent water. The contract for laying SS flow lines for these wells is already in place and job is under progress. Already work is completed for BGT#1 and the well is flowing through the new layed line .

5.3.5 Production & Disposal of Formation Water:

Total quantity of Formation Water Produced: 35253.39 Kls. Total quantity of Formation Water stored in evaporation pit: 35253.39 Kls. The produced formation water is stored in a concrete evaporation Pit near adjacent to the plant.

5.4.0 Heavy Oil Production/Exploitation :

5.4.1 New well completion:

In the year 2016-17, drilling of one well Loc RBAS (Bikampur-1) was completed and production testing is presently under progress.

5.4.2 Exploitation of heavy oil from BGW # 1, BGW#4 & BGW#5 At BGW#4, a surface unit of SRP was installed (shifted from Punam#1) for artificial lift and experimental production started in the month of November, 2016 after installation of a reducer gear box.

After workover operation at BGW#1 in the year 2015-16, the well was bought into production with the help of artificial lift (SRP). The surface unit was received from field Headquaters, Duliajan and installed in the month of December, 2016 and experimental production was started after installation of a reducer gear box. Workover operation was carried out at BGW#5 in January, 2017 and a hired unit of SRP was installed to bring the the well into production. Experimental production from the well started since the month of February, 2017. The details of the production of heavy oil from the wells are as under :

Page 11: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

10

WELL NO PRODUCTION (BBLS) PRODUCTION (Kls)

BGW#1 672.00 112.0

BGW#4 1097.3 183.0

BGW#5 36 6.0

Out of the total production, we have dispatched 249.2 bbls of heavy oil to M/s

ONGCL, Mehsana through hired bowser services.

5.4.3 Exploitation of Heavy oil from Baghewala Field:

Based on the results of the experimentation, it was decided to drill one no of vertical well and one no of horizontal well as pilot wells at Baghewala field. As a part of the project it was decided to hire consultancy services having adequate knowledge and past experience in the field of Heavy Oil production. Accordingly, a contract was awarded to M/s. Belgrave Oil and Gas Corporation (BOGC) from Canada. A final report was submitted by the consultant and the same is under review at present. A timeline has been prepared for the pilot project and accordingly various services and material procurement have been either initiated or completed. We intend to use Progressive Cavity Pump & Electric Down Hole Heater in the proposed horizontal well for which procurement process is almost complete. Necessary actions have also been initiated for revival and relocation of the boilers at Baghewala for hot production from the proposed wells.

5.5.0 Instrumentation:

Major Activities:

1. Maintenance & calibration of all field instruments of DND-GPC carried out as per schedule.

2. Calibration of Portable Explosive Gas Detectors of Production installations under Rajasthan Project carried out as per schedule.

3. Preventive Maintenance of SCADA (Supervisory Control & Data Acquisition) system of DND-GPC, TOT-GGS, TVC & Jodhpur consisting of Remote Terminal Units (RTU), Engineering Stations, Operator Display Stations, Servers carried out by M/s Yokogawa India Limited as per AMC . A new Annual Maintenance Contract for SCADA system for another 3 years was put into force with M/s Yokogawa w.e.f. 01.10.2016.

4. Joint calibration of the field instruments of Custody Transfer carried out with GAIL (India) Ltd. as per calibration schedule.

5. One no. of Turbine Flowmeter for Condensate Sale measurement of DND-GPC calibrated at NABL accredited Laboratory.

6. Two nos. of Turbine Flowmeter of Gas Custody Transfer calibrated at NABL accredited Calibration Laboratory in presence of GAIL’s representative as per provision under Gas Sale Agreement with GAIL (India) Ltd.

Page 12: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

11

7. Validation & Preventive Maintenance of two nos. of Flow Computer of Gas Custody Transfer carried out on 16.11.2016 in presence of GAIL (India) Limited.

8. All the Master Test Equipments including Sound Level Meter of DND-GPC calibrated at M/s EQDC, Vadodara (NABL accredited Calibration Laboratory).

9. New Online Dew Point Transmitter (Make: GE) installed & commissioned successfully by using the existing sampling system of old Dew Point Meter. The same is hooked up with SCADA system.

10. Reboiler Burner Management System was successfully hooked up with SCADA system for monitoring & operation of the boiler remotely from SCADA.

11. Implementation of Security Access Control System for OIL House. 12. Actions taken to revive the boilers & ancillaries at Baghewala for proposed

pilot project towards exploitation of Heavy Oil. 5.6.0 Mines Safety Week Celebration :

30th Mines Safety Week 2017 was organised by Ajmer Zone of Directorate General of Mines Safety from 19th to 24th Dec, 2016 with the final day function at Jodhpur, on 13.01.2017. Installation, DND GPC won various prizes in the categories as mentioned below:

Installation Prize Category DND-GPC First Fire Fighting Drill DND-GPC First Statutory records

keeping DND-GPC Third Overall performance

5.7.0 Promotions & Transfers:

SL. No. Item Description Number

1 Promotion 1 2 Transferred from RP 1 3 Transferred to RP 2

5.8.0 Conservation of Energy:

1. Production department has achieved success in the field of energy conservation by adopting measures like reducing vehicle movements, using energy efficient lights, maintaining solar lighting system etc. in the field which resulted in saving of considerable amount of HSD. During the year under review the consumption of HSD is as follows:

Page 13: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

12

Sl.No Location HSD Consumed (Liters)

1 TVC 20989 2 DND – GPC 12447 3 RANAO WATER POINT 10485 4 WELL LOGGING 9470 Total 53391

2. Two numbers of acoustic Gen sets has been ordered to replace the existing ones to

reduce diesel consumption. 3. Gas flaring has been reduced as compared to last year. 4. Consumption of HSD has come down as compared to previous year.

5.9.0 Cost saving measures:

1. All out efforts were made to control operational cost by taking timely action on maintaining production equipments.

2. In spite of having shortage of manpower in the department, all jobs were carried out within the optimum period, thereby reducing the downtime, overtime etc.

3. Consumption of HSD for running generator-set etc was maintained within the stipulated limit and there was considerable reduction in consumption of HSD with availability of RSEB power to DND GPC. During the year under review a total of 53391 Liters of HSD has been consumed. Moreover installation of two numbers of acoustic Gen sets are in progress to replace the existing ones and likely to reduce diesel consumption substantially.

4. Gas Flaring was kept at bare minimum level. The NG flared during the year under review is 0.470353 MMSCUM.

5.10.0 Safety Audits:

1. During the year under review, Safety audits like Internal Safety Audits & Fire

safety audits were carried out. Inspection team nominated by Directorate General of Mines Safety Ajmer region inspected Production Mines on 24.12.2016. External Safety Audits of DND – GPC installations by DDMS (Mechanical) was carried out in the month of March-2017. Besides the above Safety Audits, regular inspection of the installations helped in improvement of the safety standards. Regular mock fire drill in every month is conducted at DND GPC.

5.11.0 HSE policy Implementations:

Page 14: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

13

Systematic effort to generate a general awareness to Safety is the best tool to achieve outstanding HSE performance. With this in mind, the department has initiated actions at the grass root level to develop safety awareness on the entire spectrum of people in the department. In pursuance towards this we went beyond compliance with existing regulation to meet or exceed accepted good practice in health, safety and environmental management. Some notable actions initiated for the compliance are mentioned below: Prepared bridging document with service provider of DND GPC where

responsibilities demarcated without any ambiguity. Monthly safety committee meeting held where contract employees were

encouraged to raise issues related to safety. Mock fire drills conducted even in odd hours. Tool box meetings conducted regularly. Communication facilities provided at the processing area so that instructions can

be passed down to operator from control room as and when required without any time loss.

Walkie-talkies provided to operators to communicate with field personnel. Near miss reporting encouraged. Workmen inspector was appointed to visit the field frequently and reports back

safety related issues. All records maintained in the desired formats Testing of all surface equipments along with SRVS carried out Emergency Response: The Disaster Management Plan & Contingency plan of

Dandewala- GPC, Pipelines & Drilling Rig of Oil India Limited was updated during the current year. QRA & ERDMP for DND-GPC as per ERDMP regulations 2010 by PNGRB is under preparation.

During the current year the mutual aid scheme agreement for firefighting aid

between M/s. Oil India Limited, Jodhpur & M/s. ONGCL, Jodhpur was renewed for a period of five years.

5.12.0 Man-Power:

In spite of serious shortage of executive manpower in the department, all out efforts were made to complete all planned activities within the stipulated time. Followings are the details of manpower in the department during the year under review.

Executives Qty. Break-up

Production 7 L-3/4: 1 and L-1:6 Instrumentation 2 L-1:2 (One new executive trainee joined on

Page 15: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

14

20.02.2017)

Workmen 14

5.13.0 Training & Seminars:

In-House In Country Abroad Executives 3 2 NIL Workmen NIL 2 NIL

5.14.0 Transfers & Superannuation:

1. An executive in L1 was transferred and replaced by another executive. 2. An Executive Trainee has joined Instrumentation dept. 3. An employee is transferred to another dept. within the Project.

**********************************************************************************

Page 16: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

15

6.0 GEOSCIENCE DEPT:

6.1.0 Jaisalmer Mining Lease (250 Sq. Km) & Baghewala Mining Lease (210 Sq. Km ) a) Gas field Maintenance and Monitoring: The cumulative gas production in the year 2016-17 from three gas fields (viz Tanot, Dandewala & Bagitibba) was 232.019 MMSCM with an average gas production rate of 0.64 MMSCMD during the year. The cumulative condensate production in the year 2016-17 from Dandewala, Bagitibba & Tanot fields was 219.410 KLs along with cumulative water production of around 35253.390 KLs. Well-wise, reservoir-wise gas, condensate and water production rates were maintained regularly in the data base. Pressure-production plots of each pool was prepared and maintained. The performance of all gas pools of different field were regularly monitored to ensure optimum production from each well/pool. b) Workover Operations: Oil India Limited engaged a 500 HP Mobile Workover Rig from M/s GTC, Ahmedabad to carry out workover operations since 06.02.2015. On completion of the contracted period, the rig was de-hired on 05.02.2017 after completing a total of 28 number of workover jobs. During the FY 2016-17, a total of thirteen numbers of workover jobs have been completed in thirteen wells in Jaisalmer PML and Baghewala PML, resulting in a gas production potential gain of 0.18 MMSCMD. As on 31.03.2017, available production potential of the gas fields is estimated at 0.95 MMSCMD post workover & drilling operations. Selection of well, issuing & finalization of workover program, monitoring the operation and course correction during the job execution etc were carried out in the following wells.

Srl. Well No. Start date Completion date 1 DND-14 20/03/2016 01/05/2016 2 DND-19 01/05/2016 18/06/2016 3 DND-11 18/06/2016 15/07/2016 4 DND-9 15/07/2016 14/08/2016 5 DND-8 14/08/2016 30/08/2016 6 DND-25 30/08/2016 09/09/2016 7 DND-24 09/09/2016 04/10/2016 8 DND-22 04/10/2016 18/11/2016

9 DND-26 18/11/2016 04/12/2016 10 DND-4 04/12/2016 23/12/2016 11 BGT-1 23/12/2016 13/01/2017 12 DND-6 13/01/2017 21/01/2017 13 BGW-5 21/01/2017 05/02/2017

c) Wire-Line Logging:

i) Logging Operations: The well logging operation of Rajasthan Project has been monitored by Geoscience Department. Well Logging section in Geoscience Department provides all the essential wire-line logging services of Rajasthan Project except advance services like CAST and RMT were provided by the Contractor, HLSA . Due to non-availability of the advance tool, CAST and RMT Jobs were done by HLSA using in-house Logging unit with their personnel. Apart from field job monitoring, crew movement, explosives requirement/storage, WL Truck related documents preparation etc. were also executed by Geoscience Department.

Page 17: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

16

During the Financial Year 2016-17 total number of 198 logging jobs were done. Out of this 182 jobs were done by Well Logging Section and remaining 16 no of jobs were done by the Contractor (HLSA) using in house Well Logging Unit.

The details of In-house Logging Operations is shown in detail below:

- Open –hole Services = 65 nos. (Fig-1) - Cased –hole Services = 117 nos. (Fig-2)

ii) Well Log Interpretation: Log Interpretation is being regularly carried out using ULTRA software by the FHQ, Interpretation team. The PETROSITE processing software is also used for processing advance tools such as WSTT and XRM.

iii) Equipment Available: Following major equipment are available at the TVC workshop for carrying out Logging jobs and maintenance of tools.

- Logging Unit – 01 no. with open hole and cased hole tools with accessories. - Pressure control system for Through Tubing Operation = 01 set. - LOGIQ Lab System = 01 no.

iv) Health, Safety & Environment: Use of highly hazardous materials like explosives and radioactive source in our operation requires strict adherence to safety norms, which were followed meticulously. Necessary measures for environmental protection and pollution control with respect to radioactive sources and explosives were adopted and monitored strictly.

Necessary safety briefing were given to all the field going Executives and Employees on regular basis. No untoward incident calling for immediate remedial action took place during this period.

Page 18: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

17

FIG-1

FIG-2

d) Mud logging Unit : Mud logging jobs were carried out in Wells DND – 26, DND-27, DND28,

and BKM-1 with M/s Geologging India Limited . Mud logging contract with M/s Geologging India Limited expired on 28/03/2017. For the new tender for Mud logging services, six (6) offers received. Price bid opened on 27.03.2017. The L1 party is M/s. Cyratron Techmation & Oilex syestem Ltd.

Page 19: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

18

e) Drilling Locations:

i) DND-26 (Loc. RJBI): The well was spudded-in on 30.03.2016. The well was drilled down to 2115.3 m and cemented 5.1/2" casing with shoe at 2105.37 m. The rig was released on 10.05.2016 for ILM to next forward loc. WDW-1. The well testing was carried out by deploying the workover outfit from M/s GTC from 17.11.2016 and ended on 15.12.2016. ii) WDW 1: The well was spudded-in on 20.05.2016 and drilled down to 1053 m and cemented 5.1/2" casing with shoe at 1046.82 m. The rig was released on 06.06.2016. iii) DND-27 (Loc. RJBG): The well was spudded-in on 20.06.2016. The well was drilled down to 2131 m and cemented 5.1/2" casing with shoe at 2123.70 m. The rig was released on 09.08.2016 for ILM to next forward loc. DND 28. iv) DND-28 (Loc. RJBF): The well was spudded-in on 19.08.2016. The well was drilled down to 2865m and cemented 5.1/2" casing with shoe at 2826.30 m. The rig was released on 11.12.2016 for ILM to next forward loc. BKM 1. v) BKM-1 (Loc. RBAS): The well was spudded-in on 26.12.2016. The well was drilled down to 1278 m and cemented 5.1/2" casing with shoe at 1269.06 m. The rig was released on 16.03.2017.

f) Environmental Clearance:

i)Jaisalmer PML: Consent to Establish (CTE) for the drilling of Six (6) wells in Jaisalmer PML from RSPCB, Jaipur was received and Consent to operate (CTO) is yet to be received. ii)Baghewala PML: Consent to Establish (CTE) and Consent to operate (CTO) for the drilling of Six (3) wells in Baghewala PML from RSPCB, Jaipur were received.

6.2.0 NELP IV BLOCK RJ-ONN-2002/1: As suggested by Director (E&D), a review study

was carried out on relinquished areas of this block. Few leads were identified within the block during G&G review and it was planned to validate the leads with additional seismic data before going for drilling . Accordingly, actions were initiated to carry out API of 600 GLKM of seismic to reconfirm the structural position and size of the leads and to upgrade to prospects but the same could not be carried out due to reason already discussed vide OCR dated 18.12.2009. It is worthwhile to mention here that one well (Nanuwala-1) drilled north of this block produced crude oil (API 30.33) during testing. The leads identified in the block are in up-dip direction with respect to Nanuwala-1 and fall in the same migration pathway. It is suggested to acquire 3D seismic of around 1000 sq.km covering the identified leads. Alternatively 600 GLKM 2D seismic (2x2 KM grid) can be acquired covering identified leads which was originally planned for the block. Based on the interpretation of suggested seismic data drilling may be planned in future.

Page 20: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

19

6.3.0 NELP-VI Block RJ-ONN-2004/2: A review study was carried out on relinquished

areas of this block. Earlier, a G&G review was carried out after heavy oil discovery in Punam-1 well, one independent closure at Jodhpur Formation top level was identified in the south of Punam structure. The said structure is structurally up dip in respect to Punam structure and part of greater Baghewala-Punam structural high trend. One location (Loc.C) was proposed in the structural closure, however, location was not released and the structure could not be probed by exploratory drilling mainly due to time limitation to fulfill the MWP work and subsequently the area had to be relinquished (mandatory). As per G&G review to probe hydrocarbon prospects in the independent structural closure south of Punam structure by drilling an exploratory well, the same work program of drilling one exploratory well in the block is mooted again. A request of retaining of about 10.2SQ.KM area covering the discovery area of Block RJ-ONN-2004/2 for appraisal and Declaration of Commerciality (DOC) has been submitted to DG, DGH. However, DG, DGH in the meeting regarding “Monitoring of Nomination Blocks” indicated that OIL can avail the benefits of proposed OALP for further exploration and production activity in the block.

PI Transfer: The process of 25% PI transfer to OIL , the matter is still under arbitration process. Next arbitration of hearing is expected in the month of May/June 2017. Received communication from DGH to extend the validity of BG till 30.09.2017 with claim period upto 30.11.2017.

6.4.0 NELP-VI Block RJ-ONN-2004/3:

Block relinquished w.e.f. 21.01.2012. Payment of Rs. 13,60,43,435/- has been made towards differential cost of un-finished MWP of the Block.

6.5.0 NELP-VII Block RJ-ONN-2005/2: 2nd Extension of Phase-I:

DGH made a communication in connection with our proposal to relinquish the entire Block. DGH has asked to submit the cost of unfinished MWP as per article 5.6 of PSC immediately as well as original and copy of data to DGH. Bank Guarantees was extended by one year for completion of Minimum work Programme in the Block. As suggested by Director (E&D), a review study was carried out on relinquished areas of this block. Out of the eleven prospects identified in-house as well as by consultancy services, two prospects are at much deeper depth than MWP well depths. Moreover, these new prospect horizons were not visible by old seismic data. Out of these eleven locations five locations were released by competent authority and out of these two locations have been drilled by the consortium. The deeper new prospect identified based on the last 3D seismic survey could not be probed by exploratory drilling as JV partners did not agree due to higher financial involvement for deeper target depth in comparison to MWP well Target and additional payment of 30% LD for the third extension requiring to complete the drilling of the well . There were also some

Page 21: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

20

concern about the reservoir type due to virgin nature of these prospects . However, subsequent G&G review indicates possible presence of carbonate reservoir at this depth.

6.6.0 Publication of Notes/Reports:

REGN 64: Prospect Evaluation of Relinquished NELP Blocks in Rajasthan. By RS Ram & SS Deb

Depth Data Drilling Policy (DDDP) & GTO of wells WDW 1, DND 27 (Loc. RJBG), DND 28( Loc. RJBF), BKM 1( Loc. RBAS)

Reserve Appraisal Note No. 50: A Report on Oil and Gas Reserves of Oil India Limited as on 01.04.2016 (Assam, Arunachal Pradesh and Rajasthan). Co-author: S. Gupta

Potential Note No. 3: Well - Wise Details and Production Potential of Oil India Limited’s fields in Rajasthan Project as on 01.04.2016. Author: S. Gupta.

RGON-129: Initial Well Testing Programme Of DND-25 (LOC. RJBJ)

RGON-130: Initial Well Testing Programme Of DND-24 (LOC. RJBH).

RGON-131: Initial Well Testing Programme Of DND-26 (LOC. RJBI).

RGON-132: Initial Well Testing Programme Of DND-28 (LOC. RJBF).

RGON-134: Initial Well Testing Programme of BKM-1(RBAS).

Sri S. Gupta, S E (Reservoir) presented a Paper and a Poster titled "Well Integrity Diagnostics and Reservoir Monitoring in Ageing Completions to Arrest Decline in Gas Production: Experience from Dandewala Gas Field, Rajasthan, India" in the 4th SPWLA-India Symposium held in Mumbai.

6.7.0 Reserve Appraisal:

The estimation of Crude Oil, Natural Gas and Condensate Reserves of Oil India Limited in its operational areas in Assam, Arunachal Pradesh and Rajasthan as on 01.04.2016 was carried out in compliance with the SPE PRMS reserve definition and guidelines. The estimation was jointly carried out by G&R Department, Duliajan and Geosciences Department, Rajasthan Project in a time bound manner and a joint report for the same titled “Reserves Appraisal Note (RAN) No. 50 was published. Gas Position of Rajasthan Project as on 01.04.2016 as estimated vide Reserves Appraisal Note (RAN) No. 50 is given below:

Gas Position of Rajasthan Project As On 01.04.2016

Natural Gas (All Figures in MMSCM)

LE BE HE

Gas-Initially-in-place (GIIP) 7834 11350 16071

Estimated Ultimate Recovery (EUR) 5386 8425 12624 Remaining Producible Volume (RPV) 1909 4948 9148

Page 22: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

21

The Field/structure wise heavy oil in-place contingent resources of Jodhpur Sandstone formation as estimated vide Reserves Appraisal Note (RAN) No. 50 is given below:

Heavy Oil In-place Volume of Jodhpur Sandstone As On 01.04.2016

Field/Structures Contingent Resources (All Figures in MMT)

1P 2P 3P

Baghewala 10.75 12.53 14.42

Tavriwala-2 0.79 1.01 1.26

Grand Total 11.54 13.54 15.68 The Annual estimation of Oil and Gas Reserves of Oil India Limited as on 01.04.2017 is presently under progress . The report is being prepared jointly by G&R Department, Duliajan and Geosciences Department, Rajasthan Project on ‘Oil and Gas Reserves of Oil India Limited as on 01.04.2017 (Assam, Arunachal Pradesh and Rajasthan)’ and shall be presented as Reserves Appraisal Note (RAN) No. 51.

6.8.0 Service Contract monitoring: Total six (06) numbers of service contracts have been initiated, executed and monitored by the department.

6.9.0 Unconventional Hydrocarbon Exploration: i) Coal Bed Methane gas exploration: Collection of data from different coal /lignite mines

in west Rajasthan area by visiting different active mines and findings were presented in a geo-scientific note.

ii) Shale gas/oil exploration: Detail analysis of available data for shale gas potential

available in OIL's operational area of Rajasthan and findings were presented in a geo-scientific note.

6.10.0 Jobs carried out in other sphere: Wellsite Duty: Geoscientist from RP has performed well site duty in KG basin and Cauvery

basins for drilling operation.

6.11.0 Other Jobs: Preparation of Presentation for OC, MC and Review meeting for the NELP blocks. Conduct OC/TC meetings for NELP blocks. Preparation of OC/MC minutes and incorporation of JV partners view/comments and final submission to DGH/MoP&NG after obtaining JV partners signature. Proposal for approval of LD, BG from competent authority and subsequent correspondence with DGH/MoP&NG/JV partners. Preparation of Cash call for payments and related quarries from JV pertaining to expenditure. Preparation of presentations for VIPs /guests on OIL's activities and future planning etc were carried out by Geoscience Department from time to time . Reply for numbers of Parliamentary questions was also prepared by Geoscience Department . Additionally a number of quarries from Auditors, CAG, Internal Audit, Directorate of Petroleum ; Govt. of Rajasthan, DGH, MoP&NG and Ministry of Environment & Forest were also addressed by Geoscience Department (RP) . In absence of separate Planning Department number of planning related (ML license, ML/PEL fee advice, legal documentation with State Govt. etc) jobs were carried out by Geoscience Department.

Page 23: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

22

6.12.0 Manpower Position: Manpower position of Geoscience Department as on 31.03.2017 is as follows:

Category Level/Grade Nos. Total

Executives:

Level 4 1

9 Level 3 1

Level 2 1 Level 1 6

*Workmen:

EG Grade IV 3

11

EG Grade III 2

EG Grade II -

Grade VIII 2

Grade VII -

Grade V 2

Grade IV 2 Grand Total 20

Note: * 2 (Two) WCL’s are working in Geoscience Department in addition to the above.

6.13.0 Induction of New Technology: Land Mark Decision Space Software was installed for

Interpretation.

6.14.0 Training / Workshop:

Sr. No.

Name of Executive Course Title Period Venue

1 Sh N. R Hazarika, GM-Geoscience

Senior Management Program

7 – 12 Nov, 2016 IIM Bangalore

2 Sh N. R Hazarika, GM-Geoscience

Disha – A new journey post retirement

13 – 14 February, 2017

MTDC Duliajan

3 Sh. S.S. Deb DGM Geoscientist

Petrotech Conference 4 – 7 Dec, 2016 New Delhi

4 Sh. Pankaj K Chetia Suptg. Geologist

Effective Interpersonal Skills for Team Building Development Program

11-12 July, 2016 Jodhpur

5 Sh. Pankaj K Chetia Suptg. Geologist

Petrophysics for professions

17-19 Oct'16 New Delhi

6 Sh. Bhola Kumar, Sr. Engineer (Well Logging)

Effective Interpersonal Skills for Team Building Development Program

11-12 July, 2016 Jodhpur

7 Sh. S Gupta, Suptg. Engineer (R)

Presented technical paper & poster.

11-12 Feb, 2017 SPWLA, Mumbai

6.15.0 Cost Cutting & Energy Conservation: Completion of drilling well during the financial

year 2016-17 was done successfully. With an idea to achieve cost control it was decided to

Page 24: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

23

carry out production testing in the drilling wells using workover outfit instead of the drilling rig . Additionally, based on the current p roduction behavior and neighboring well correlation, we were able to cut down drilling depths instead of drilling down to earlier planned objective depths in one well which saved us drilling time as well as drilling cost of the reduced metreage . All possible measures were adopted in the Department to cut down cost and conserve energy consumption. Electrical appliances were used judiciously only when required .

**********************************************************************************

Page 25: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

24

7.0 CHEMICAL DEPTARTMENT:

Chemical Department continued to support Drilling as well as Production activity of the Project by providing various services like Drilling Fluid Engineering , Laboratory facilities and Reservoir Data Acquisition .

7.1 Targets and achievements and reason for shortfall, if any, along with remedial measures adopted during the year.

Chemical Department (RP) carried out the following field and laboratory activities in Rajasthan Project during the period April 2016 to March 2017. The department provided the required services in fields as well as in the laboratory as per the job demand and apparently there was no shortfall in achieving the various targets .

Field Activities: a) Drilling fluid services were provided to 3 (Three) Development Wells viz.; Loc. RJBI

(DND#26), Loc. RJBG (DND#27) & Loc. RJBF (DND#28) and 1(one) water disposal well viz. WDW#1 at Dandewala field with a cumulative drilling meterage of 8054m for Development well . All the Development wells were completed without any drilling fluid related problem .

b) Provided drilling fluid services to 1 (One) Exploratory Well viz.; Loc. RBAS (Bikampur#1) at Bikaner Nagur Basin with a drilling meterage of 1278m . During drilling of exploratory well, Loc. RBAS, severe loss circulation was encountered throughout the drilling of isolation and oil string stage. However, the well was completed successfully.

c) Total drilling meterage during the year vis-à-vis target was as follows: Type of Well No. of Wells Target (m) Achievement (m) Exploratory 01 1250 1278 Development 04 8000 8054 Total Cumulative drilling meterage 9332

d) Provided Work-over fluid services to 14 (Fourteen) no of jobs including

abandonment of one difficult well (DND#09). Except Loc. DND#19 (fishing problem), all other Work-over wells were completed without any difficulties. Sodium format solution was incorporated for all the Work-over wells as Packer fluid.

e) Designed cement formulations for the wells in association with M/s WEAFRI, Nigeria and carried out the primary/secondary cementation jobs successfully using cementing unit of M/s WEAFRI .

f) As a part of Gas Field Development Program and Heavy Oil Exploration Project, BHP contract has been awarded to M/s Naithani Oil & Gas Services Pvt. Ltd.

Page 26: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

25

Laboratory Activities: a) Analysis of custody transfer composite gas samples from OIL’s DND-GPC were carried

out fortnightly for determination of composition and calorific value for billing to M/s GAIL(India) Limited .

b) Analysis of natural gas samples from OIL’s Gas Processing Centre, Dandewala (DND-GPC) and from different gas producing wells were carried out regularly for monitoring gas composition and determination of calorific value.

c) Planning and procurement of various drilling fluid additives and work over fluid additives continued as per requirement and phasing.

d) Total numbers of various samples analyzed in the laboratory during the year are:

Sl. No. Type of Sample No. of Sample analyzed 2016-17 2015-16 1 Natural Gas Sample

(Custody Transfer) 24 24

2 Natural Gas Sample (Individual Well)

40 36

3 Crude Oil Sample 08 14 4 Tender Sample 22 0 5 Glycol Sample 72 38 6 Condensate Sample 12 8 7 Water Sample 134 40

e) Analyzed total 312 nos of samples, 97% more than the last FY 15-16 (total analyzed

sample 158 nos) .

7.2.0 Adoption of all state-of-the art technologies, innovations and performance of excellence with resultant benefits attained there from.

a. The oil string stage drilling of Development well Loc. RJBF (well depth 2865m) where bottom hole temperature was higher than anticipated (218 degF), was carried out using 9.9 ppg KCl-polymer mud with proper mud parameters. The oil string hole was true gauge throughout and and there was no problem towards lowering oil string casing.

b. Designed and executed oil string cementation (thermal) with M/s Weafri at Loc: RJBF (BHT: 218 F) successfully, though there was no provision of high temperature cementing chemicals in the cementing contract.

c. Low density Bentonitic Cement slurry of controlled setting time was highly successful in controlling mud loss at Loc. RBAS.

d. DND#14, one cement plug was placed in an unconventional way to repair 5 ½” casing leakages and successfully set WF spool.

e. Incorporation of Sodium Format solution in Work Over wells as Packer fluid which itself is a Corrosion Inhibitor and also environment friendly. It is likely to resist Casing damage (Production Casing) by preventing Corrosion especially for Gas Wells.

7.3.0 All outstanding achievements and records made, breakthroughs achieved and milestone crossed.

Page 27: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

26

A notable breakthrough was achieved during drilling of Loc. RBAS, where severe loss circulation was encountered and well progress was very low for hole instability combined with hole cleaning. A unique High Concentration Unswelled Bentonite (HCUB) pill was developed and found to be highly successful in addressing hole instability and loss circulation problem and the well could be completed successfully. 7.4.0 Cost saving measures adopted and cost saved in terms of money.

Strict and round-the-clock monitoring had helped in controlling cost in terms of consumption of drilling fluid chemicals in drilling of the aforesaid wells . Minimized cost on travel to fields by combining with Drilling/ Geological Personnel . 7.5.0 Energy conservation measures adopted and resultant saving in terms of energy and money.

All possible measures were adopted in the department to contribute towards energy consumption. All electrical appliances were used judiciously. 7.6.0 Environmental protection and pollution control measures adopted with

resultant benefits attained there from. All drilling effluents were stored in HDPE lined effluent pit. No effluent was allowed

to flow out of effluent pits. 7.7.0 Other relevant points, viz. any significant seminars held, conferences

organized, awards won and recognitions received from any national or, international bodies of repute. None.

7.8.0 HR related issues: Manpower position, joining & separation, training, promotions etc. Manpower Position: Manpower position of Chemical Department at RP as on 31.03.2017 is as follows: Financial Year Position of

Executive No Position of

Employee No Total

Strength in Chemical (RP)

2015-16 Level-1 Level-2

02 01

EG Grade-IV EG Grade-II Grade-SR MP Grade-VII MP Grade-VI

01 01 01 01 01

Sub Total 03 Sub Total 05 Total 08 2016-17 Level-1

Level-2 02+02* 01

EG Grade-IV EG Grdae-II MP Grade-IX MP Grade-VII MP Grade-VII

01 01 01 01 01

Page 28: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

27

Sub Total 03+02* Sub Total 05 Total 08 * Two (02) nos. of Contract Chemists were deployed on temporary basis from

01.04.2016 to 29.11.2016. Training:

a) Sri Dhrubajyoti Bhuyan has attended “Effective Interpersonal Skills for Team Building Development Program” at Jodhpur on 11.07.16 & 12.07.16.

b) Sri Dhrubajyoti Bhuyan has attended “General Management cum leadership Program for Junior Level Executives of OIL” at ASCI, Hyderabad from 12.09.16 to 23.09.16.

c) Sri HK Barua has attended a training on “Leadership from Inside Out” at Noida on 13-14 June, 2016. Transfer/Joining:

a) Sri Bishnu Medhi, Suptdg. Chemist, S/code: 6072, transferred to Field Head Quarter Duliajan on 10.05.2016.

b) Sri Dhrubajyoti Bhuyan, Senior Chemist, S/code: 200583 joined Rajasthan Project on 02.05.2016 after his transfer from Field Head Quarter. Promotions:

a) Sri Subrata Kumar Biswas, S/code: 201249, promoted to Grade ‘C’ from Grade ‘B’ w.e.f. 01.01.2016.

b) Sri A. N. Asopa, OIL ID: 99469, promoted to Supervising Assistant (Grade-IX) w.e.f. 01.05.2016.

c) Sri. Dharmveer Singh, OIL ID: 109826, promoted to MP Grade-VII w.e.f 01.01.2017.

**********************************************************************************

Page 29: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

28

8.0 TECHNICAL SERVICES DEPARTMENT: During the year under review, different sections of TS department namely Civil, Electrical, Mechanical, Fire & Environment, provided all the required technical support and services to drilling and production activities of RP besides supporting/carrying out technical maintenance of OIL House, Guest House and other installations.

In addition, TS was in charge of Renewable Energy, generation from two wind farms and three solar plants. Some of the major jobs carried out during the year by the different sections of the department are high-lighted below:

8.1.0 CIVIL ENGINEERING SECTION:

During the year 2016-17, Civil Engineering Section played a key role in drilling and production processes, and other operations/ activities of Rajasthan Project by extending all the required civil engineering support. Civil personnel , leading from the front , performed in-house survey works and stacked location coordinates in the middle of sand dunes under hostile weather conditions.

Despite difficulties such as defence related restrictions by BSF in Dandewala area or villagers’ obstructions in Bikampur area from time to time, the section could deliver locations on time for drilling operations as per TDP of RP .

Necessary supports were provided for Work Over and other production related activities as and when required by the user department.

OIL’s operational roads, close the international border region, were maintained perennially to facilitate uninterrupted road connectivity to remote wells and installations, amidst the Thar desert.

General maintenance works at Wells, Installations, Stores, Office and Guest Houses were carried out from time to time ..

Some of the jobs execute during the year are as follows:

Field Works (Drilling / Work-Over):

a) Preparation of drilling site for Loc. RJBG (100% completed)

b) Preparation of drilling site for Loc. RJBF (100% completed)

c) Preparation of drilling site for Loc. RBAS (100% completed)

d) Preparation of drilling site for Loc. RBAT(95% completed)

e) Extending necessary support for Work-Over operations in wells.

f) Maintenance of OIL’s operational road network in Tanot, DND & Baghewala field.

g) Re-casting of cellar foundation at DND-9.

Other Civil Jobs:

Page 30: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

29

a) Construction of Boundary Wall at Hamira Godown including Security Room, Patrol Track, drainage etc.

This 1.2km long wall was a long pending requirement of the Hamira Stores. The installation had a porous fencing system since inception which made the godowns vulnerable with regard to security aspects.

b) Construction of 2 Nos Toilet blocks, Main Gate and a Piao under CSR Scheme for Govt. Model Hr. Sec. School, Village Raghwa, Ramgarh, Jaisalmer District.

This CSR project is in connection with the Renewal Energy Installations set up in Raghwa village of Jaisalmer district. This project goes a long way in providing decent wash-room facilities and drinking water to the boys and girls of the school. Also the construction of a main gate has added beauty to the school . This also paves the way for maintaining goodwill between OIL and the villagers of Raghwa.

c) Construction of Toilets, Resting Shed and underground 5KL tanks at locations BGW-1 and BGW-4.

d) Construction of 36KL crude oil tank at location BGW-5

e) Day to day maintenance works of OIL House, Guest House & Clubs premises in Jodhpur.

f) Carrying out repairing and maintenance works at Hamira Stores, DND-GPC and Tanot.

8.2.0 ELECTRICAL / MECHANICAL ENGINEERING SECTION:

This section was involved in the operation, upkeep and maintenance of all electrical and mechanical equipment at various field-installations, office, guest houses. Every attempt was made to ensure that power supply remained uninterrupted and that all equipment like AC systems, pumps, DG sets, etc. in various installations like DND GPC, TVC, OIL House, Ranau Water Point, Guest House, etc. functioned normally. In case of power supply disruption from the state grid, prompt action was initiated to restore supply either through rectification of faults or supply of power through stand-by generating sets.

Major activities of electrical section:

Carrying out electrical inspection during pre-spud racee at well sites.

Making power available for SRP units through DG sets.

Ensuring standby power availability at TVC, DND GPC, OIL House, Guest House.

Procurement, installation and commissioning of 62.5 KVA rating acoustic DG set at Guest House to replace the existing non-accoustic and ageing DG set .

Procurement, installation and commissioning of 30 KVA rating acoustic DG set at Hamira Stores to replace the existing ageing DG set .

Installation of two numbers of high-mast lights (each high-mast consisting of 8 x 2 x 400 watts =6.4KW lights) at Hamira Stores to provide adequate area-lighting and improve security aspects.

Page 31: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

30

Twelve numbers of new-generation split-type air conditioners installed at Guest House as replacement of old ACs and two numbers were also installed at Hamira Stores Office as replacement .

In order to provide adequate cooling in the open space meant for staff seating area within OIL House premises during the peak summer months when temperatures shoot up to around 50 degree centigrade, additional air conditioning using 80 TR VRV units were installed and commissioned during the year .

The registration of the Well Logging truck was transferred from Assam to Rajasthan. This long pending initiative will result in yearly savings of additional road taxes , besides meeting statutory requirements.

Maintenance of electrical equipment like motors, alternators, electrical panels at various field-installations, offices, guest house, etc.

Budgeting and procurement activities to meet requirement of electrical equipment for drilling, production processes and also for office/guest house installations.

8.3.0 RENEWABLE ENERGY:

Renewable Energy Projects : There are five existing Renewable Energy Projects , as under:

1. 13.6 MW Wind Power Plant at Ludharva near Jaisalmer : The plant comprising of 16 Wind turbines @ 850 KW each was installed & commissioned on 31.03.2012.

2. 54 MW Wind Power Plant at Dangri : The plant comprising of 27 Wind turbines @ 2.0 MW each was installed & commissioned on 30.03.2013.

3. 100KW Solar Power Plant at Tanot : The plant comprising of 416 SPV Poly Crystalline Modules @ 230 W each and electrical energy generated from the plant is directly connected to Tanot Village Complex for captive use. The plant was commissioned on 15.03.2013.

4. 5 MW Solar Photovoltaic Power Plant at Ramgarh : The plant, with generation from

solar SPV Poly Crystalline Modules was commissioned on 23.01.2014 and the electrical energy generated from the plant is evacuated through a transmission line to nearby Ramgarh GSS and fed into the state grid system.

5. 9 MW Solar Photovoltaic Power Plant at Ramgarh : The plant, with generation from

solar SPV Poly Crystalline Modules was commissioned on 25.02.2016 and the electrical energy generated from the plant is evacuated through a transmission line to nearby Ramgarh GSS and fed into the state grid system.

RENEWABLE ENERGY PLANT

TARGETED/ESTIMATED GENERATION FOR 2016-17

ACTUAL GENERATION FOR 2016-17

REMARKS

Page 32: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

31

1 13.6 MW Wind Power Plant at Ludharwa

2,72,33,463 KWh 1,99,83,915 KWh

73.38 % of Estimated Generation

2 54 MW Wind Power Plant at Dangri

10,97,02,964 KWh 7,69,23,718 KWh

70.12 % of Estimated Generation

3 5 MW Solar Power Plant at Ramgarh

89,15,346 KWh 91,32,880 KWh

102.44 % of targeted generation

4 9 MW Solar Power Plant at Ramgarh

1,49,60,522 KWh 1,64,58,070 KWh

110.01 % of targeted generation

REVENUE DETAILS FROM RE-PROJECTS: Revenue from the following RE Projects (except

100 KW Solar, which is for captive use) connected to the Grid Sub-Stations has generated substantial revenue under the provisions of Power Purchase Agreement(PPA) and other incentives. Revenue generation during the year 2016-17 by these projects is given below along with revenue figures for the year 2015-16 :

Sl No

Project name Revenue in Crores of Rupees for the

year 2016-17

Revenue in Crores of Rupees for the

year 2015-16

1 13.6 MW Wind Power Plant at Ludharva

As per PPA rate

8.83 8.07

2 54 MW Wind Power Plant at Dangri

As per PPA rate

39.33 34.79

GBI 3.70 3.36

3 5 MW Solar Power Plant at Ramgarh

As per PPA rate

2.92 3.40

REC sale 2.14 1.83

4 9 MW Solar Power Plant at Ramgarh

As per PPA rate

5.30 0.4571

REC Sale 0.19 --

Total Revenue 62.41 51.9

Status of Renewable Energy Certificates (RECs) as on 31st March 2017: In addition to the revenue earned from the state discoms through sale of power from OIL’s solar plants , Renewable Energy Certificates, (RECs) are also issued to OIL at the rate of 01 REC for every 1000 KWh of power injected into the state grid. The RECs are

Page 33: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

32

traded/redeemed in the Power Exchanges at the rate of INR 3,500.00 per REC for earning additional revenue .

RECs from 5 MW Plant

Total RECs issued since commissioning of plant 64,441 Nos.

Total number of RECs traded/redeemed as on 31.03.2017

12,445 Nos.

Balance RECs 51,996 Nos.

RECs from 9 MW Plant

Total RECs issued since commissioning of plant 9,594 Nos.

Total number of RECs traded/redeemed as on 31.03.2017

548 Nos.

Balance RECs 9,046 Nos.

8.4.0 FIRE and SAFETY

During the year, Fire Safety & Environment section of Rajasthan Project took all measures to ensure the highest levels of safety in our installations, operations and practices. There was monitoring of Occupational Health of the work persons exposed to Occupational Health Hazards , monitored & promoted clean environment at Rajasthan Project . Proactive approach was taken in HSE related issues for effective implementation of company’s HSE policies and guidelines. We strive for continuous development of the communities in which we operate.

Following are the achievements of the section in brief for the year under review :

8.4.1 SAFETY

During the year under review, the section continuously worked and has steadily taken some strategic steps for improving the safety standards in the company and for the benefit of all.

Page 34: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

33

Good standards of Safety for the people and processes have been established and maintained at Rajasthan Project. There was no Mining Accident (Zero Accident) reported at Rajasthan project during the year 2016-17. A total of 05 no. near misses were reported at DND-GPC and preventive measures were taken immediately to avoid the re-occurrence.

(a) Safety Audits

During the year under review, Safety Audits of Drilling Rig and DND – GPC were carried out. Inspection team nominated by Directorate General of Mines Safety Ajmer region inspected the Drilling & Production Mines on 16.04.2016 & 24.12.2016. Dy. Director Mines Safety (Mech) inspected Production Mine on 24.03.2017.

Besides the above inspections, regular audits of the installations have also helped in improvement of overall safety standards at Rajasthan Project.

(b) Statutory and other reporting

The following Statutory and other reports were compiled and sent:

I. Mines Annual Report to DGMS.

II. OISD Quarterly ESA status. III. Weekly HSE reports.

(c) Mines Safety Week

Mines Safety Week was observed at Rajasthan Project from 19th to 24th December 2016

under the aegis of “Director of Mines Safety, Ajmer Region” along with other mines of Ajmer region.

As a part of safety week celebration, safety slogan, safety poem & safety poster competitions were organized among the OIL employees / executives & their children at Rajasthan Project. Few numbers of safety drawings of our children were selected for publication in the Mines Safety Calendar. Trade Test examination for employees of Oil Mines in connection with 30th Mines Safety Week Celebration – 2016 was conducted at Oil India Limited, Jodhpur on 30.11.2016 for the following categories:

1. Knowledge of Operation 2. Knowledge of Maintenance 3. Conscious worker

Trade test competitions were held among participants from M/s. ONGCL, M/s. Cairn India & M/s. Oil India Limited. Fire Drill Competition: As a part of Mines Safety week, for the first time Fire Fighting Drill competition was organized at DND-GPC on 06.12.2016 amongst the fire fighting teams of M/s. ONGCL Gamnewala, M/s. NLC India Ltd, Barsinagar Project, M/s. Focus Energy, Jaisalmer & M/s. Oil India Limited DND-GPC.

OIL (Rajasthan Project) bagged the following eight prizes in the 30th Mines Safety Week

2016, organised by M/s. FCI Aravali Gypsum and Minerals India limited, Jodhpur, under the aegis of

Page 35: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

34

Director of Mines Safety, Ajmer region.

Installation Prize Category

1 Production DND-GPC First Fire Fighting Drill

2 Production DND-GPC First Statutory records keeping

3 Production DND-GPC Third Overall performance

4 Workover Rig (GTC 100-03) First Electrical equipment, lighting and wiring.

5 Workover Rig (GTC 100-03) First Safety features & Records

6 Workover Rig (GTC 100-03) First Overall performance

7 Workover Rig (GTC 100-03) Second Publicity propaganda and house keeping

8 Workover Rig (GTC 100-03) Second Drilling & Maintenance The prizes were distributed during the concluding function held at Jodhpur on 13.01.2017.

(d) Emergency Response: The Disaster Management Plan & Contingency Plan of Dandewala- GPC, Pipelines & Drilling Rig of Oil India Limited was updated during the current year. QRA & ERDMP for DND-GPC as per ERDMP regulations 2010 by PNGRB is under preparation.

During the current year the mutual aid scheme agreement for firefighting aid between M/s. Oil India Limited, Jodhpur & M/s. ONGCL, Jodhpur was renewed for a period of five years.

8.4.2 ENVIRONMENT

Through regular monitoring and proper co-ordination, the Safety & Environment section could successfully abate the pollution problems arising out of the Company’s various operational activities during the year 2016-2017. Periodical jobs like obtaining Consents from statutory authorities and all time bound information were furnished to the State Pollution Control Board regularly.

During the year, Oil India Limited, Rajasthan Project has been accorded Environmental Clearance (EC) from Ministry of Environment and Forest, for drilling 20 Developmental wells at Baghewalla PML , District Jaisalmer . Consent to Establish (CTE) was granted for Drilling Locations RJBH, RJBI, RJBJ, RJBG, RJBF, WDW, RBAS, RBAU & RBAT by Rajasthan State Pollution control Board.

No public pollution complaints were received during the current financial year.

“World Environment Day” on 5th June was organized at Rajasthan Project in a befitting manner to pass the message of Environmental Protection amongst employees and the public as well.

Page 36: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

35

8.4.3 FIRE SERVICE

During financial year 2016-17, following are the details of the major activities of fire service at Rajasthan Project:

a) No. of personnel attending First-aid fire fighting training = 281

b) No. of Fire Mock Drill Conducted =15

c) Fire Extinguisher Inspection = 392

d) Fire Call Reported = Nil

e) Fire Service Stand by = 42

Fire Service Week was observed at Rajasthan Project from 14th to 20th of April, 2016. New fire extinguishers of Dry Chemical Powder of 25 kg, 50 kg & 75 Kg capacity have been procured for Rajasthan project.

8.4.3 SAKSHAM - 2017

Pursuant to the directive of Ministry of Petroleum and Natural Gas, Govt. of India, Oil India Limited, Rajasthan Project observed Oil and Gas Conservation, mass awareness campaign ‘SAKSHAM-2017’ from 16th January 2017 – 15th February 2017 with various plans and programs.

The campaign was to sensitize the masses about the conservation and efficient use of

petroleum products towards achieving twin objectives of better health & environment and securing availability of oil & gas for future generations.

The inaugural function of this campaign was held at OIL House, DND-GPC & Loc RBAS, Baghewala on 16th January 2017 with taking of the “Oil & Gas Conservation Pledge” and formation of Human chain as well as Save oil & gas march. An Auto Emission (PUC) Check up camp for vehicles was organised on 25.01.2017. A publicity van was sent to nearby villages on 03.02.2017 for distribution of leaflets, booklets & posters carrying the message of oil and gas conservation. Renewable appliances such as solar heater & solar panel were also exhibited in front of OIL House on 07.02.2017. Drawing & essay competitions for school children wére conducted at RSM International School on 08.02.2017 to spread awareness among school children on oil & gas conservation. Concluding function comprising of Open Quiz Competition was held on 15.02.2017 at OIL House Auditorium.

.

8.5.0 COST & ENERGY SAVING MEASURES, ENVIRONMENT PROTECTION AND NEW TECHNOLOGY ADOPTION:

8.5.1 Cost Saving Measures:

Combined contracts for construction of multiple Drilling Locations were prepared with the help of Contracts Section which saved tangible tendering fees as well as intangible time and man-days of the company.

Page 37: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

36

Surveys were conducted with the help of GPS coordinates and real-time Google map images requiring minimal manpower and time.

8.5.2 Energy Conservation Measures:

Autoclaved Aerated Concrete (AAC) Blocks are used in TVC Extension building at Tanot. AAC Blocks are highly insulating material which would substantially save electricity in running ACs during summer scorching heat of Tanot.

High efficiency, low power consumption ACS of 5 Star ratings were installed at Guest House to lower power consumption.

8.5.3 Environment Protection and Pollution Control Measures:

Replacement of non-accoustic DG sets with eco-friendly (noise and emission) DG sets at Guest House and Hamira Stores.

ACs with eco-friendly gas were installed at Guest House, Hamira Stores and OIL House.

AAC Blocks used in TVC Extension building are eco-friendly building material recommended by IGBC (Indian Green Building Council) / GRIHA (Green Rating for Integrated Habitat Assessment). This material makes use of fly ash which is an industrial waste. Moreover, it has lesser Embodied Energy, which means it requires less energy in process of its manufacturing in comparison to conventional bricks.

8.6.0 New Technologies:

CAD (Computer Aided Design) software including AutoCAD and Sketchup are extensively used for designing, planning and executions.

Surveys are conducted based on GPS coordinates and real-time Google map images.

**********************************************************************************

Page 38: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

37

9.0 DRILLING DEPARTMENT: 9.1 Target and Achievement (Drilling & Work-over Activities):

Type of

Well Target

(m) Achievement

(m) Percentage (%)

Exploratory 1250 1278 100.24 Development 8000 8054 100.67

Overall 9250 9332 100.88

Development wells drilled in the financial year 2016-2017 are Loc: RJBI (DND#26), Loc: WDW#1, Loc: RJBG (DND#27) and Loc: RJBF (DND#28) in Jaisalmer PML area of Jaisalmer basin. The development well RJBF was drilled down to 2865 m with conventional coring in (2555 m – 2575 m ); (2680 m-2698 m);( 2698 m- 2717 m) & (2738 m – 2750 m) in stages, Also Side Wall Coring was taken in this well from 2780.5 m – 2512 m.

Exploratory well RBAS (Bikampur #1) drilled in the financial year 2016-2017 in Baghewala PML area of Bikaner Nagur basin. The well (Loc: RBAS) was spudded on 26.12.2016 and at the end on the F.Y. the well was drilled down to 1278 m. Total mud loss occurred at 559 mtrs in 12.1/4” section in upper carbonate formation. The loss could not be arrested even after placing 22 no. LCM pills and 11 no. of cement plugs. Subsequently lowered 9.5/8” casing at 559 mtrs and cemented. The well was subsequently drilled to 1278 mtrs with no return to partial return. The innovative way of putting two bentonitic cement plugs and eight numbers of high concentration unswelled bentonite LCM pills before each pulling out bit trip helped to achieve the mud return. 5.1/2” casing was landed at 1269 mtrs and cemented with partial return (80- 85) % of mud. Subsequent log showed moderate to good cementation against Bilara and Jodhpur (pay zone) formations The Drilling Rig (John#12) De- hired on 16.03.2017 at 7.00AM.

Work-over achievement in terms of number of jobs completed was 14 (fourteen) as against annual target of 13 jobs. Work-over jobs were carried out in the following locations DND#14,DND#19,DND#11,DND#9,DND#8,DND#25,DND#24,DND#22,DND#26,DND#04,BGT#01 & DND#06(live perforation) ,BGW#5 . At the end of the extended contract period , the Work over Rig GTC-100-03 was de-hired on 05-02-2017.

In the financial year 2016 - 2017, Rajasthan project have achieved drilling meterage of 9332 m as against 9250 m of annual target and completed a total of 14 number work-over jobs as against annual target of 13 jobs with one Drilling Rig and one Work-over Rig operation in Rajasthan Project . For the last two consecutive years, our achievement in drilling and work-over front in RP was more than 100% of annual target . This commendable performance could be achieved because of sincere & dedicated efforts put forward by all of us involved directly or indirectly in field operations.

9.2 Reasons for shortfall from Target –

Page 39: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

38

Drilling & work-over targets in RP were achieved by 100.88 %.

9.3 Tendering and Contractual Progress -

LOA of Contract (No. 6208205) for hiring the services of one 1000 HP Mobile Drilling Rig Package (John#29) against Baghewala PML area of Bikaner Nagur basin has been issued. The tendering process for hiring Cementing and BHP services; Coring services; Horizontal drilling and Liner Hanger services are on progress . Procurement process of L80 casing for two horizontal and two vertical drilling wells is on progress. The above services are required towards drilling of well with thermal completion in Baghewala PML area of Bikaner Nagur Basin in Rajasthan.

9.4 Cost Saving Measures -

Completed five numbers of drilling wells including one Water Disposal Well within the stipulated time period.

Faster ILM in case of both drilling & work-over wells than the stipulated time-frame as per Contract thereby increasing Rig utilization time resulting in overall improvement of performance.

Optimum utilization of bit life in order to reduce quantity of drill bit consumption vis-à-vis number of bit trips in a well.

Use of integrated small cementing set-up attached to Work-over Rig for cement plug/squeeze jobs in almost all the work-over wells.

9.5 Energy Conservation Measures -

1. Use of Rig & Mud Pump Engines on load requirement basis only. 2. Maintaining the Power Packs/Engines in switch-off mode during well-logging &

production testing operations. 3. Use of Portable Gen-Set for lighting purpose at night. 4. Strict adherence to periodic servicing & pro-active maintenance of Engines resulted

in fuel efficiency thereby saving HSD & lubricants. 9.6 Environment Protection & Pollution Control Measures -

1. Effluent disposal was restricted to the pit lined with HDPE sheet to prevent flow of

effluent to surrounding areas and percolation of the same to the soil underneath. 2. Use of environmental friendly water base mud system in drilling well minimized

pollution control hazards. 3. Erection of brick-wall bunds around diesel storage tank, power-packs minimized

pollution risk caused by accidental spillage of HSD. 4. Use of acoustic Gen-Set at well-sites & camps helped reducing noise pollution to a

great extent. 5. Use of ear & nose muffs to minimizing noise & health pollution. 6. Collection of burnt lube oil in drums during servicing of power-packs/engines in

drilling & work-over wells and safe disposal thereafter.

Page 40: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

39

************************************************************

Page 41: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

40

10. FINANCE & ACCOUNTS SECTION:

10.1.0 Organization: .

10.1.1 Management: The department is headed by Chief Manager (F&A) who is assisted by three Level -1 executives one level -2 executive (Chief Manager-1, Managers-2 & Deputy Managers-1) to carry out all departmental activities.

10.1.2 Manpower Strength: Manpower strength in the department was -

2015-16 2016-17 Executives (nos) 5 5 Workmen (nos) 8 8

10.1.3 Transfers: Shri G.P. Saha (MFA) has been transferred from the project during the last part of the current year.

10.1.4 Retirements : Nil 10.1.5 Training: Following executives attended training & seminar programme:-

(i) Shri Om Prakash – GST at Jaipur & New Delhi

10.1.6 Infrastructure: Infrastructure(major items only) facilities available in Finance & Accounts department are :-

SN Description Numbers 1.6.1 PC 12 1.6.2 Printers 11 1.6.3 Cash Vault 2 1.6.4 SAP based phones 1 1.6.5 DoT Phones 2 1.6.6 Intercom 12

10.2.0 Transaction Processing: 10.2.1 Cash and Bank Documents-

(Documents in Nos.) Desctiption 2015-16 2016-17 Cash 228 569 Bank 2942 3982

10.3.0 Revenue: (Amount in ` Lakhs)

SN Description 2015-16 2016-17

3.1.1 Natural Gas Sales 9355.15 6934.88

Page 42: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

41

3.1.2 MGO 618.13 - 3.1.3 Condensate Sale 39.58 56.62 3.1.4 Heavy Oil - - 3.1.5 Interest on Short Term Deposits 16.26 19.92 3.1.6 Renewable Energy Revenue 5115.63 6241.00

10.4.0 Contribution to Exchequer:

(A) State Government

(Amount in ` Lakhs) SN Description 2015-16 2016-17

4.1 Royalty 4.1.1 Natural Gas 850.47 630.44 4.1.2 Condensate 17.39 9.89 4.1.3 Heavy Oil - - 4.2 Sales Tax (VAT/CST) 4.2.1 Natural Gas 371.95 391.33 4.2.2 Condensate 1.06 1.14 4.2.3 Heavy Oil - 4.3 Entry Tax 6.26 32.52

(B) Central Government

(Amount in ` Lakhs) SN Description 2015-16 2016-17

4.3 Cess 4.3.1 Condensate 6.198 10.39 4.4 TDS Deposited 4.2.1 Employees 627.44 590.611 4.2.2 Contractors 88.32 237.97

10.5.0 Income Tax Demand Notices:

DCIT (TDS), Income Tax Department, Jodhpur after surveying our accounts and records

for the FY 2007-08 and 2008-09 issued two demand notices for `.223 Lakh alleging short

Page 43: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

42

recovery of TDS from the contractors/sub-contractors. The demand notices of DCIT (TDS) were challenged before the CIT (Appeals), Jodhpur and our appeal was pending adjudication before CIT (Appeals), Jodhpur as on 31.03.2011. Subsequently, CIT (A), Bikaner has passed the appellate order on 31.10.2011. In the order of CIT (A), commissioner has decided that rate of TDS will be 10% as per section 194 J & 194 I . However, since all the contractors have filed their return of total income and therefore, TDS short deducted in previous years i.e. 10% minus 2%, can not be recovered from OIL but interest on such short deduction shall be leviable & recoverable from the company. Matter was discussed with taxation cell/ consultant & accordingly, we have filed the appeal before ITAT which is pending. Subsequently, Case was heard on various dates in ITAT, Jodhpur. After hearing the case at ITAT, Jodhpur thereafter on various dates, the verdict was given in our favour on 31.07.2013. Later on, we have got a refund of INR 1.70 crores from the Income Tax department. However , Income tax department has filed an appeal against the ITAT order in Rajasthan High court .

Meanwhile, we have received another notice for similar type of case for the Financial

year 2009-10 & 2010-11 and an appeal is being filed for the same with the help of our local tax consultant . We also received notice for the F.Y. 2011-12, 2012-13 & 2013-14 for the similar type of issue from the department which is dealt with by engaging a consultant. All the cases from FY 2009-10 to 2013-14 have been settled in favour of OIL by CIT (A) in the month of March 2016.

10.6.0 Service Tax & Excise Cases:

a)Service Tax : OIL had availed services of cementing from a foreign contractor & made a payment of ` 2.60 crores approx. However, applicable service tax was not deposited due to lack of clarity on the rulings. Later on, OIL deposited the service tax along with interest amounting to ` 28,83,637 & ` 10,79,457 respectively .However, vide order dtd 30.03.2012 , department imposed penalty of `28,83,637. We have filed an appeal against the order on 25th June,2012 with Commissioner (Appeals-II) & stay application is pending before the appellate authority.

b) Excise Cases: Show cause notice from the office of Commissioner of Central Excise, Jaipur (C.No.V(27)Adj.11/JPR-II/43/2014/1484 dated 28.02.2014) was received alleging OIL of evading payment of Rs.14,32,03,934/- on clearance of Natural Gas during the period February 2009 to December 2013 .

After filing of reply , an amount of Rs.4,45,47,248 deleted for the period from Feb 2009 to March 2011 and AO maintained a demand of Rs.9,86,56,676/- and in addition to that a penalty of Rs.4,93,28,338/- and Rs.20,00,000/-imposed (Total Rs.14,99,85,014)for the period from April 2011 to December 2013. OIL have filed an appeal to CESTAT ,New Delhi on 22.12.2014 against the order of AO. And Appeal was accepted by CESTAT ,New Delhi on19/02/2015 .

Page 44: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

43

Further show cause notice was issued by Commissioner of Central Excise, Jaipur for the period from Jan 2014 to Oct 2014 . After our reply to notice AO maintained the demand for Rs. Rs.3,12,65,906/- along with interest Rs.25,00,000/- and penalty Rs. 1000000/- (Total Rs.3,47,65,906 /-). OIL have filed an appeal to CESTAT,New Delhi on 02/04/2015 against the order of AO. And Appeal was accepted by CESTAT,New Delhi.

Further show cause notice was issued by Asst .Commissioner of Central Excise, Jodhpur for the period March 2014,April 2014 and December 2014 for Rs.1,48,470 dated 23.03.2015 . Oil filed reply to notice AO on 27.07.2016 . However AO maintained the demand . OIL have filed an appeal before Honourable Commissioner (Appeals) on 08/10/2016 against the order of AO.

Further show cause notice was issued by Commissioner of Central Excise, Jaipur for the period from Nov 2014 to March 2015 for Rs.2,09,86,361 dated 30.11.2015 . Oil filed reply to AO on 09.01.2016 . The case is decided in favour of Oil India Limited on 21/12/2016 .

10.7.0 Outstanding amount with GAlL: An amount Rs.1.78 crores was receivable from M/S Gail (India) Limited on account of MGO and interest thereon . After Intervention of Director (F) and Director (E&D) and a subsequent discussion between OIL and M/S Gail(India) Limited officials at Jodhpur. M/s GAIL(I) Ltd paid an amount of Rs 0.63 lacs to OIL on account of two MGOs and for another MGO of Rs.1.04 cr, M/s GAIL requested to consider the period as force Majeure . Accordingly , a proposal was put up and competent authority agreed to their request that there was no fault of either side in maintaining Gas supply . For interest on MGO, competent authority agreed to the request made by GAIL for waiver of interest on MGO .

10.8.0 Receipt of outstanding amount from RUVNL: In wind power plants payment is always delayed , beyond credit period allowed as per PPA . RUVNL offered for releasing the payment upto Dec,2016 subject to waiver of LPS by 50% . Competent authority of M/s OIL accepted the offer of RUVNL and received an amount of Rs.42.00 cr on 31.03.2017 towards the pending bills up to Dec 2016 and Reduced LPS.

10.9.0. Accounting:

Page 45: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

44

Quarterly Accounts pertaining to Rajasthan Business Area have been completed well within the target date set by General Manager (F&A) FHQ. The quality of books of accounts has been maintained at the desired level. So far, there is no adverse comment from the auditors on the Accounts of RP up to the 3rd Quarter FY 2016-17. Fourth Quarter Accounts for FY 2016-17 are under audit.

10.10.0 E-Payment:

E-payment is considered to be the most transparent method of effecting remittance to various vendors. During the year 2016-17, payment to the vendors through E-Payment mode, were successfully made. Almost all kinds of payments have been brought under E-Payment mode and the quantum of payment through E-Payment mode has been increasing day by day. Presently, E-Payment has been achieved to the extent of 90-98 % against the target of 90% in terms of value of the total payment.

10.11.0 Austerity & cost control Measures

In terms of the directives of Director (Finance) vide letter dated 11th November 2016 , efforts are on to control the expenditure on various items indicated in these circulars. We shall try to implement austerity measures in totality in compliance to the circular. Some of the items of expenditure strictly controlled are as under:-

1-Maintenance of building, office equipments, travel, transport, communication, stationary, furniture etc.

2-Organizing conferences/seminars/workshop etc.

3-Civil & electrical works.

4- Judicious use of stationary especially paper, shall be made. E-mail communication shall be encouraged.

5- Judicious use of Office car/Pool cars & avoidance of the wasteful expenditure.

6- overtime

7.Advertisement

Out of the austerity measures mentioned above, we have already taken action on few points to ensure the reduction in the expenditure. However, this will be further taken forward to ensure further visible reduction in the expenses.

Page 46: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

45

10.12.0 Joint Venture Accounting :

The following Joint Ventures under NELP are handled by the project during F.Y. 2016-17 :

Joint Venture Partners Participating Interest (%)

OPERATOR

STATUS

RJ-ONN-2005/2

OIL

HOEC

HMEL

60%

20%

20%

OIL

Two Wells completed in Block in Ist Exploration Phase. Block stands relinquished w.e.f. 25.12.2015.

RJ-ONN-2004/3

OIL

GGR

HPCL

60%

25%

15%

OIL Relinquished in January 2012

RJ-ONN-2004/2

OIL

GGR

75%

25% OIL

Highly viscous heavy oil found in exploratory well drilled in Phase-I of the block. MWP of drilling 1 well in Phase-II completed. Phase-II expired on 20.07.2015. Government’s decision on OIL’s application for grant of additional time period for carrying out appraisal Work Programme and retention of 10.24 SQKM area under Mining Lease is awaited.

RJ-ONN-2002/1

OIL

ONGC

60%

40% OIL Relinquished

RJ-ONN-2001/1

OIL

ONGC

70%

30% OIL Relinquished

RJ-ONN-2000/1

OIL 100% OIL Relinquished

GK-OSJ-3

RELIANCE

OIL

ONGC

60%

15%

25%

RELIANACE

Relinquished

Page 47: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

46

In respect of operated block RJ-ONN- 2004/2, under NELP VI and RJ-ONN- 2005/2 under NELP VII, the total expenditure during FY 2015-16 was `12.51 crores & `37.36 respectively and during FY 2016-17, the expenditure (provisional) in these blocks have been to the tune of `0.50 crore & `1.24 crores respectively.

In addition to the above expenditure, during FY 2014-15, OIL has paid LD amounting to `1.08 crore for block RJ-ONN-2004/2 for seeking 6 Month’s Extension in Phase-II of the block. During FY 2015-16, OIL has paid LD amounting to `1.87 crore for seeking 2nd Extension of 6 Months in Phase-I of block RJ-ONN-2005/2 and has paid LD amounting to `27.82 crore towards LD for Unfinished Minimum Work Programme of Phase-I for the block . Block RJ-ONN-2005/2 is relinquished w.e.f. 25.12.2015 after completion of Phase-I exploration period.

10.13.0 Bill Tracking System:

Bill Tracking system implemented in the department is running smoothly and all the SES based bills etc are recorded in system while receiving and while sending them back. However, this system needs to be strengthened further for optimum results.

10.14.0 Online Tax Payment:

Payment of Direct Taxes (TDS/TCS) is being done through ONLINE payment Gateway of SBI Bank using OLTAS (Online Tax Accounting System).

Payment of Indirect Taxes (Service Tax, Royalty, Entry Tax, CST, VAT etc.) is being done through ONLINE Payment Gateway of State Bank of India.

**********************************************************************************

Page 48: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

47

11.0 MATERIALS & CONTRACT DEPT.: 11.1.0 Material management is an approach for planning, organizing, and controlling all those activities principally concerned with the flow of materials and hiring of services required for an organisation. It is a business function for planning, purchasing, moving, storing material in an optimum way which help organisation to minimize the various costs like inventory, purchasing, material handling and distribution costs. The fundamental objectives of the Materials Management function, often called the famous 5 Rs of Materials Management, are acquisition of materials and services:

a. of the right quality b. at the right time c. at the right price d. in the right quantity e. from the right source

11.1.1 The basic objective of Materials & Contract Department at Rajasthan Project is: To buy at the lowest price, consistent with desired quality and service. To maintain a high inventory turnover, by reducing excess storage, carrying costs and inventory

losses occurring due to deteriorations, obsolescence and pilferage. To maintain continuity of supply, preventing interruption of flow of materials and services to

users. To maintain the specified material quality level and a consistency of quality which permits

efficient and effective operation. To develop reliable alternate sources of supply to promote a competitive atmosphere in

performance and pricing. To minimize the overall cost of acquisition by improving the efficiency of operations and

procedures. To develop and maintain good supplier relationships in order to create a supplier attitude and

desire to furnish the organisation with new ideas, products, and better prices and service. To achieve a high degree of cooperation and coordination with user departments. To maintain good records and controls that provides an audit trail and ensures efficiency and

honesty. To participate in Make or Buy decisions.

11.2.0 The major achievement of the department in the current financial year are: i Saved INR 23.44 Lakhs in advertisement cost of tender.

ii The advertisement cost per tender is reduced from INR 3.35 Lakhs to INR 1.96 Lakhs

iii Reduced the inventory by INR 798.72 Lakhs in the current financial year i.e. a reduction by 35.93 %.

11.2.1 The statistical data related to procurement of goods, services and inventory management during the period 2014-15, 2015-16 and 2016-17 is furnished below:

A. Purchase Requisition (PR) Processed Year->

2014-15 2015-16 2016-17 Nos. / Value of PR Processed Nos. Value (L) Nos. Value (L) Nos. Value (L) Stock 17 142 20 481 33 1397 Direct Charge & Capital 108 5404 102 11318 73 7041 Service PR 49 6124 92 24154 65 16924 Spot Purchase 211 9 250 21 202 21 Development NIL 1 6.24 NIL

Total 385 11679 465 35980 373 25383

Page 49: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

48

% Increase 20.78 208.08 -19.78 -29.45

B. Tender Floated (i) Material Procurement (Goods)

Year->

2014-15 2015-16 2016-17 Nos. /Value of Tender floated Nos. Value (L) Nos. Value (L) Nos. Value (L) Limited Tender (Manual) 33 75 20 76 22 78 Limited Tender (e-Tender) 1 206 0 0 0 0 Press Tender (Manual) 0 0 0 0 0 0 Press Tender (e-Tender) 5 11250 12 6967 21 4096

Total 39 11531 32 7043 43 4174 % Increase -17.95 -38.92 34.38 -40.74

(ii) Service / Works Contract Year->

2014-15 2015-16 2016-17 Nos. / Value of Tender floated Nos. Value (L) Nos. Value (L) Nos. Value (L) Limited Tender (Manual) 5 428 3 20 5 37 Limited Tender (e-Tender) 1 400 1 4863 0 0 Press Tender (Manual) 7 65 2 15 0 0 Press Tender (e-Tender) 23 15987 18 7021 19 8083

Total 36 16880 24 11919 24 8120 % Increase -33.33 -29.39 0.00 -31.87

C. Purchase Order (PO) Placed Year->

2014-15 2015-16 2016-17 Nos. /Value of PO placed Nos. Value (L) Nos. Value (L) Nos. Value (L) Stock 18 435.08 12 212.52 17 297.62 Direct Charge & Capital 59 223.26 43 10902.31 40 359.58 Spot Purchase 182 8.00 191 19.77 145 15.57 Development 0 0 1 6.24 0 0

Total 259 666.3 247 11140.8 202 672.8 % Increase -4.63 1571.95 -18.22 -93.96

D. Service / Works Contract Awarded Year->

2014-15 2015-16 2016-17 Nos. /Value of Service Contract placed during period

Nos. Value (L) Nos. Value (L) Nos. Value (L)

Total 39 8888 71 21756 48 10841 % Increase 82.05 144.78 -32.39 -50.17

Page 50: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

49

E. Lead Time for Procurement of Goods & Services (i) Lead Time for Procurement of Goods: Year->

2014-15(days) 2015-16(days)

2016-17(days)

Stock-Indigenous 118 - 119 Stock-Foreign 268 232 232 DC-Indigenous 89 77 156 DC-Foreign - 291 300

(ii) Lead Time for Procurement of Services: Year->

2014-15 2015-16 2016-17 Indigenous 155 78 127 Foreign 202 - 271

F. Warehousing at Hamira

With proper manag

ement and controlling of placement of Purchase Orders (inflow of goods) including issue of goods (outflow) we could reduce the inventory by INR 798.72 Lakhs in the current financial year i.e. a reduction by 35.93 % . Due to continuous drilling and work-over operation throughout the year there is 192.63% increase in the number of materials issue documents.

G. Major PO & Service Contract Placed During 2016-17

SL Purchase Order

Brief Description of Goods/Services Value (in Lakhs)

1 7118415 Casing N-80, 13.3/8”-400M & 9.5/8”-3400 M 144.16 2 7951031 PUMP-WELL SERVICING 140.97 3 7118662 Cement API Class G, 50 Kg Bag-18000 MT 79.20 4 7600831 SS X-Mass tree assy. 65.08 mm bore – 6 Nos. 46.03 5 7907942 GENERATING SET – 2 Nos. 33.15 6 7907943 AIR CONDITIONERS 33.12 7 7908299 TANK-RECTANGULAR – 4 Nos. 25.16 8 7117915 Barytes Powder-300 MT 23.08 SL Service

Contract Brief Description of Goods/Services Value (in

Lakhs)

1 6207762 Hiring of Drilling Rig-1400+ HP for KGB 5176.29

Year->

2014-15 2015-16 % Increase 2016-17 % Increase

Inventory in Lakhs 3283.52 2222.83 (-)32.30 1424.11 -35.93 Consignment Received 63 92 46.03 121 31.52 Good Receipt Documents 46 78 69.56 62 -20.51 Goods Issue Documents 74 190 156.76 556 192.63 Road Permit Issued 62 91 46.77 121 32.97 Stock Items Physically Verified 920 979 6.41 1088 11.13

Page 51: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

50

2 6208205 HIRING OF 1 NO. MOBILE DRILLING RIG 2346.63 3 6207621 Hiring of MUD ENGINEERING & DWM for KGB 1100.87 4 6109841 Consultancy Services for Exploitation of Heavy Oil 558.61 5 6109961 Hiring of Skilled/Unskilled Manpower 160.45 6 6207666 Hiring of Tractor Trailer unit 112.50 7 6208237 Providing day to day miscellaneous civil works 85.68 8 6110645 Hiring of 20 KL Bowser 79.56 9 6110297 Construction of Drill. Loc at BGW 78.73 10 6110081 TVC Extension 72.12 11 6110298 Construction of Approach Roads 70.26 12 6110612 CHARTER HIRE OF SRP SURFACE UNITS 70.17 13 6109850 O&M of DND-GPC, Tanot GGS & TVC 69.85 14 6109917 Hiring of Mud Logging Services 65.47 15 6110651 3 Years AMC of SCADA System 63.74 16 6110429 AMC for Kingdom Software 63.17 17 6208290 Hiring of Materials handling at Hamira 50.34 18 6207667 Hiring of 10 T capacity Crane on call-out 47.36 19 6208204 HIRING OF BHP DATA ACQUISTION SERVICES 41.30 20 6110675 HIRING OF MOBILE PUMPING UNIT SERVICES 23.20 21 6110669 CAMC for HVAC at OIL HOUSE 19.68 22 6110112 Hiring of 20'Long 7.5 MT Truck 17.61 23 6110619 Housekeeping Services for OIL House 12.84 24 6110246 Construction of toilet block, gate etc. 12.40 25 6109967 TRANSPORT SERVICE WITH 1 NO. AC4WD CAR 11.90 26 6110105 Housekeeping services for OIL House 11.70

H. Press Advertisement Cost

Year-> 2014-15 2015-16 2016-17

Press Tender Nos. & Cost Nos. Value (L) Nos. Value (L) Nos. Value (L)

37 281.90 34 113.77 46 90.33 Advertisement Cost Per Tender 7.62 3.35 1.96

% Increase -8.11 -56.04 35.29 -41.49

With proper monitoring, control and clubbing of open tenders we could save INR 23.44 Lakhs in the current financial year. The advertisement cost per tender is reduced from last year’s cost of INR 3.35 Lakhs to INR 1.96 Lakhs in the current financial year.

I. Manpower Executive L-4 L-3 L-2 L-1 Total Short

Sanctioned - 1 1 4 6 Existing 1 - 2 2 5 1

Workman 7

Note:

Page 52: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

51

(i) One L-1 executive from Production Department is working part time with us for dealing with service PR for civil, transport and miscellaneous jobs.

(ii) One L-1 executive looking after Hamira Godown retired on 30.06.2015 and has been engaged on contract basis up to 21.04.2017

J. Training

Program Title Grade Name Program Category

Institute Venue

DISHA A NEW JOURNEY POST RETIREMENT

H VK SAHU IN HOUSE 6TH SENSE RESOURCES PVT. LTD., BANGALORE

DULIAJAN

INTERPERSONAL RELATIONS FOR TEAM BUILDING

H VK SAHU IN HOUSE DR. SOURABH SETHI JODHPUR

KEEP IN TOUCH H VK SAHU IN HOUSE OIL INDIA LTD JODHPUR

INTERPERSONAL RELATIONS FOR TEAM BUILDING

F PRAKASH MAZUMDAR

IN HOUSE DR. SOURABH SETHI JODHPUR

KEEP IN TOUCH F PRAKASH MAZUMDAR

IN HOUSE OIL INDIA LTD JODHPUR

KEEP IN TOUCH F ANITA DAM IN HOUSE OIL INDIA LTD JODHPUR

11.2.2 Vendor Meet: It has always been an endeavour of M&C department to encourage more and more participation of vendors against its tenders and to achieve the same, understanding of Company’s Procurement Procedures is very essential on the part of the vendors. It was, therefore, felt very essential to organise a “Vendor Awareness Program” at Jodhpur to bring in awareness among the vendors of Rajasthan Project and accordingly, Vendor Awareness Program was arranged on 11th November 2016 at Hotel Taj, Hari Mahal, Jodhpur to share the procurement procedure and e-tendering process of OIL. The event was conducted very successfully wherein around 36 members from vendor representing 22 vendors attended the program. An interactive session was conducted between the participating vendors and Panel of senior executives from OIL towards the end of the program, wherein the vendors/representatives were asked to put forward their issues, if any, as well as suggestions to OIL. The interactive session went-off very well with very positive feedback from the participating vendors. The presence of Independent External Monitor (IEM) added value to the sessions. There was also representation from OIL’s other spheres and vigilance department as well as representation from other PSU like ONGC, Jodhpur. **********************************************************************************

Page 53: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

52

12.0 ADMINISTRATION DEPARTMENT 12.1.0 Introduction Oil India Limited established its Project Office at Jodhpur in the year 1983 for exploration of hydrocarbon in the THAR DESERT of Western Rajasthan. From the date of inception of Rajasthan Project, Administration department is playing a key role in managing various Administration and ER functions of the project as well as liaison with State & Central Govt. authorities for obtaining speedy approvals for execution of the related jobs. During the year under review, Administration Department has carried out all the responsibilities effectively and with great enthusiasm towards maintaining industrial harmony and cordial relations between Management and Union members providing the required administrative services and support . Following are detailed activities under Administration department during the year 2016-2017. 12.2.0 Administrative Matters.

1. Executive Strength as on 31.3.2017 : 48 2. Board Sanctioned : 51

Break-up of executives department-wise: Sl. No. Department Strength

01 ED (RP) Section 02 02 Administration 04 03 Finance & Accounts 04 04 Chemical 03 05 Drilling 05 06 Geoscience 09 07 Materials 07 08 Technical Service 06 09 Vigilance 01 10 Production 07 12.2.1 Executives on short term contractual appointment as on 31.03.2017 : 02 12.2.2 Work persons strength as on: 31.03.2017 : 93

Sanctioned strength :80+(16sportsperson supernumeraries)

12.2.3 New Recruitment for the year 2016-2017 : NIL Department-wise beak-up of work person: Sl. No. Department Strength 01 ED (RP)’s Section 02 02 Administration 25 (including 9 sports person)

Page 54: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

53

03 Accounts 07 (including 1 sports person) 04 Drilling 04 (including 1 sports person) 05 Chemical 05 (including 1 sports person) 06 Materials & Contract 08 (including 1 sports person) 07 Geo science 11 (including 1 sports person) 08 TS/Civil 17 09 Production 13 (including 1 sportsperson) 10 Vigilance 01 (Sports person) TOTAL (As on 31.3.2017): 93 NOTE: Two workpersons Superannuated on 30.06.2016 & 28.02.2017 12.2.4 Reserved categories

1. S.C. : 14 2. S.T : 01 3. Physical Handicapped : 02 4. OBC : 20 (as per Govt. Of India notified list) 5. General : 56

12.2.5 Employment generated during the year 2016-2017 : NIL 12.2.6 Industrial Relations Industrial relations with employees remain cordial, harmonious and peaceful during the year under review. 12.2.7 Training and Development For development of executives and work persons , OIL (RP) has been regularly organizing training programmes . During the year, following executives/ workperson were nominated for residential training/in-house programmes . Executives Sr.No. Name of Executive Course Title Period Venue 01 Sh. Om Prakash, Sr.M.

(F&A) 37th Regional Conference of CIRC

26-27 Aug., 2016

Jaipur

02 Sh. D. Bhuyan, Sr. Chemist

General Management cum Leadership Programme.

11-24 Sept., 2016

Hyderabad

3 Sh. Abjhit Dam, DGM (TS) & Sh. H.K. Barua, CC (RP)

Leadership from Inside Out.

13-14 June, 2016

NOIDA

4 Sh. P.K. Chetia, SG

Petrophysics for Professionals

17-19 Oct. 2016

New Delhi

5 Sh. Om Prakash Seminar on GST devising Implementation Strategies & Redefining

27.10.2016 New Delhi

Page 55: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

54

Process 6 Sh. R. Tumung, Dy.CE

(Pdn) & HK Choudhary, Dy.CE (Drilling)

Transformational Leadership under Project Udaan.

08.11.2016 NOIDA

7 Sh. H.K. Barman, Sr. M (OL)

Implementation of Official Language

21-23 Oct. 2016

Darjeeling

8 Sh.D.K. Das, CE (Electricals) Sh. Abhijit Dam, DGM (TS)

Renewable Energy Generation, Integration, Forecasting Issues and Role of Smart Grid.

08-09 Dec . 2016

Guwahati

In-house Training Programme attended by Executives Executives Sr.No. Name of Executive Course Title Period Venue 01 17 executives Effective

Interpersonal Relations for Team Building.

11-12 July, 2016

Hotel Park Plaza

Workperson NIL 12.2.9 Important Programmes: a) World Environment Day was celebrated on 5th June, 2016 in a befitting manner. It included pledge taking and tree sapling plantation in OILHOUSE, Jodhpur premise. b) Yoga Day Celebrated: 2nd International Yoga Day was celebrated at OIL House, Jodhpur on 21st June, 2016. On this day, noted yoga trainer, Shri Vinod Acharya imparted yoga training to about 100 nos. of participants including executives and employees of Rajasthan Project, Jodhpur and their family members. c) Workshop on RTI: One day workshop on “Best Practices On RTI” was held on 28.02.2017 at Jodhpur Office. The workshop is aimed at providing the information about the best practices prevalent in the industry with respect to RTI Act.

12.2.10 Social Welfare activities (a) OIL’s provided financial assistance of Rs. 0.20 Lakhs to JIET, Jodhpur for organizing two days National Workshop on Advanced Solar Photovoltaic. (b ) OIL SUPER 30 at Jodhpur for providing coaching to under privileged students for preparation for admission to IIT/NIT and other reputed Engineering institutes. Total cost of the project is Rs. 54.45 Lakhs. (c) Financial Assistance of Rs. 0.30 Lakhs to JIET for organizing National Conference on Recent Advances in Environment Science and Engineering Technology.

Page 56: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

55

(d) Financial assistance of Rs. 12.04 Lakhs (2nd instalment) for repairs of conference hall in collectorate office complex Jaisalmer. 12.2.11 Executives Transferred from RP Sl. No Name Designation Date of Release 1 Sh. M. Konwar Dy.Mgr. (Materials) 14.04.2016 2 Shri D. Sen Sr. AO 07.05.2016 3 Shri Bishnu Medhi Suptg. Chemist 07.05.2016 4 Shri S. Deb Dy. CED 14.05.2016 5 Sh. Pradeep Singh Dy. SG 25.06.2016 6 Sh. N. Vashisht GM (A&ER) 25.06.2016 7 Sh. AK Agarwal CE (FS) 05.08.2016 8 Sh. KK Deka Dy. CE (P) 01.10.2016 9 Sh. S.K. Sinha S.E. (IT) 01.12.2016 10 Sh. G.P. Saha Manager (F&A) 18.02.2017 12. 2.12 Executives Transferred to R.P

Sl. No Name Designation Date of Joining 1 Sh. A.K. Meena Admin. Officer 01.04.2016 2 Sh. T.N. Singh SE (Wlg.) 12.04.2016 3 Sh. Mobia Gambo Sr. CE 16.04.2016 4 Sh. G. Goel Dy. CE (FS) 18.04.2016 5 Sh. Madhurjya Barua CM (A&ER) 20.04.2016 6 Sh. H.K. Choudhary Dy. CE (D) 25.04.2016 7 Sh. D. Bhuyan Sr. Chemist 02.05.2016 8 Sh. MM Pegu Sr. Engr (IT) 15.11.2016 9 Sh.B. Baskota Electrical Engr 28.12.2016 10 Sh. P. Dutta ASO/PO 28.01.2017 11 Sh. M. Dutta Engr. (Instt.) 20.02.2017 12 Sh. D. Shankar Manager (Mat.) 07.03.2017

12.2.13 Retirement : Shri N.Kalla (Manager-Admin) & Sh. GP Sharma (Sr. Store Officer) superannuated on 30.06.16 and 31.01.2017 respectively 12.2.14 Resignation : Nil 12.2.15 Implementation of Official Language Official Language is implemented at RP as per the directive of Ministry of Home Affairs and Department of Official Language . As per the roster being maintained the executives & employees were trained in Hindi Shikshan. Hindi Fortnight was celebrated from 01-15 September 2016 . Rajyabasha Samaroh was celebrated on 15.09.2016 . 4 nos. of Hindi

Page 57: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

56

Workshop was organized during the year with maximum participation of executives and employees . 12.2.16 Medical For providing best possible medical services to its employees and their eligible dependents OIL has recognized 7 hospitals in Jodhpur. We are also managing a dispensary with AMA on retainership basis. Deserving cases are referred for specialized treatment on AMA’s recommendation and with approval of the authority as per company’s rule. Medical facility available at Tanot Village Complex was also providing primary medical facility not only to our employees but to the villagers too. In the absence of any medical facility at Tanot and nearby villages, the setup proves to be a blessing for all the villagers. 12.2.17 Sports We have two teams (Basket ball and volley ball) who represents OIL at various State/National level tournaments in addition to PSPB. The following are the details of various tournaments in which OIL’s team participated during the period. a. Volley Ball Sl. No. Tournament Level Venue Position 1 XXXVII PSPB PSPB Debradun

from 01-04 December, 2016

Third

b. Basketball Sl. No. Tournament Level Venue Position 1 NA NA NA 12.2.18 Austerity Measures As directed by the competent authority, Administration Department has taken all possible steps towards reducing the avoidable expenditures during the current financial year. The jobs have been planned in such a way that OT incurred is zero. We have reduced the hiring of callout vehicles by using car pool method for serving in the Fields at Jaisalmer/Bikaner. The unutilized capital budgets were surrendered. 12.2.19 Golden Memories of 2016-17

OIL, Rajasthan Project, Jodhpur has shown remarkable progress in the use of Official Language Hindi for which OIL, RP, was awarded with Rajbasha Mukutmoni Shied by the Bharatiya Bhasha avong Sanskriti Kendra, New Delhi on 23.10.2016.

Oil India Ltd., Rajasthan Project, Jodhpur has shown remarkable progress in the use

of Official Language Hindi for which OIL, RP, Jodhpur has been awarded with 1st

Page 58: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

57

Position in Rajyabasha Shield by the Town Official Language Implementation Committee, Jodhpur on 20th December, 2016.

******************************************************************************

Page 59: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

58

13.0 Information Technology 13.1 PREAMBLE The goal of the IT department is to meet the information requirements of all activities at different levels within the organization by leveraging the latest technology in the best possible and most cost effective manner to achieve higher productivity. 13.2 The major regular activities of the Department are listed below: 13.2.1 IT Security

Ensuring perimeter security through Firewalls User Authentication through Microsoft Active Directory Antivirus Server and Client management IT Security audit & implementation of audit recommendations

13.2.2 User support

Support to Email users Providing and supporting Internet connectivity to users Anti-virus, AD front-end support SAP ERP front-end support. Other applications user support. ERP related support

13.2.3 Network management

Maintenance and administration of LAN Maintenance and administration of WAN - VSAT, MPLS Maintenance and administration SCADA network between Tanot to Jodhpur Maintenance and support of Satellite Phone Maintenance and support of Voice communication between Tanot, GGS & Dandewala

13.2.4 Hardware management

IT Infrastructure Planning, procurement, maintenance of Desktops, Laptops, Servers, Printers, Scanners etc.

IT Asset management Preventive maintenance of generic IT assets Maintenance and support of EPABX telephone exchange

13.2.5 Planning & Administration

Payments of all the IT related contract and Purchase Orders Preparing departmental reports, annual reports etc. Co-ordinating matters related to the Rajasthan Project:

Annual report of the project Annual Capital and Revenue budget of the project Monitoring and utilization of capital and revenue budget of the project Closing of not used / unutilised budget of the project

Page 60: ANNUAL REPORT 2016 17 - Oil India · 4.1 Budget Performance Capital budget target for 2016-2017 was about ₹ 32,26,30,397.00 and procurement/ commitment have been made against ₹

59

13.3 ACHIEVEMENTS Implementation of Access Control System : It is an electronic smart card based

access control system to ensure that only authorised persons are allowed to enter a physical room, building or any gated infrastructure. The system is also integrated into the Fire Detection and Alarm System (FDAS) placed in OIL House ensuring safety to the working personnel.

Implementation of Biometric Attendance System : It is a biometric based attendance recording and monitoring system which can generate multiple reports related to attendance in workplace with flexible parameters.

Implementation of CCTV system : To enhance the perimeter security of OIL House, CCTV system with 21 cameras has been installed. It allows for live view, playback and storage of CCTV footage, giving a complete video surveillance solution.

Implementation of Visitor Management System: In order to keep track and give controlled access of OIL House to visitors, a visitor management system has been implemented in OIL House. The information of the visitors is kept in a database and report can be generated accordingly. It is integrated to Access Control System to give controlled access to visitors. 15.0 ACKNOWLEDGMENT We acknowledge with sincere gratitude the assistance, co-operation and guidance extended to Rajasthan Project by Chairman and Managing Director, Director (Exploration & Development) and Director (Finance) for its sustainability, encouraging the activities in Heavy Oil project and NELP blocks in a progressive manner. This has ushered the Project into a period of opportunity.

We also offer our thanks to Director (HR&BD) as well as Director(Operations), the officers and staff in corporate office, field headquarters, all Projects and spheres for their kind help and co-operation in carrying out the activities in the Project successfully. The unstinted support and co-operation received from all the executives and staffs of Rajasthan Project are thankfully acknowledged .

***************************************