analysis of wave power production system · analysis of wave power production system technical...
TRANSCRIPT
Analysis of wave power production systemTECHNICAL REPORT no. 2548 and extended analyses, 20.05.2015
Objectives
Fedem Technology AS (Fedem) has been invited by Murtech AS (Client) to
perform hydrodynamic and structural analyses of a floating wave power
generator concept.
The aim of the analysis is to investigate the concept by means of a dynamic
simulation model that will aim to determine the power production potential.
Scope of work
• WP1: Establish a design basis based on input from the client
• WP2: Data collection and initial analyses (normal operation)
• WP3: System model (normal operation)
• WP4: Structural integrity (storm condition)
• WP5: Reporting
Case Operating condition Wave height, Hmax [m]
1 Normal (WP2/3) 1
2 Normal (WP2/3) 2
3 Normal (WP2/3) 4
4 Normal (WP2/3) 6
5 Storm (WP4) 15
WP1: Design basis
WP1: Design basis
Pontoon properties Value Unit
Mass 7500 kg
Draft 0.65 m
Outer diameter 8.0 m
Diameter waterline 6.6 m
0.71m
0.65m
3.3m
4.0m 0.35m
mean sea level
WP2: Computational fluid dynamics (CFD)
Main conditions for the CFD simulations:
• Performed in Star-CCM+ provided by CD-adapco.
• Three-dimensional and time-dependent.
• Reynolds-averaged Navier-Stokes (RANS) turbulence model.
• Regular incoming waves with wave height according to scope of work. Wave
length calculated to avoid breaking.
• One single pontoon able to move in the vertical direction only (no friction or
generator resistance).
WP2: CFD results, pontoon movements
Vertical pontoon
translations [m]
Vertical pontoon
velocities [m/s]
WP2/3/4: Structural model
Main conditions for the structural simulations:
• Performed in FEDEM simulation software.
• Simulations predict the dynamic response of elastic mechanisms experiencing
non-linear effects such as large rigid-body rotations.
• Hydrodynamic loads from the Morison equation valid for slender beams only.
• Pontoons able to move along beam elements (no friction or generator
resistance).
WP2: Tuning of structural model
System parameters in
FEDEM must be tuned
for a realistic behavior of
the pontoons, according
to CFD results.
WP3: Complete structural model, remarks
Differences from design basis:
• As a result of preliminary studies
which showed instability issues
by using one central mooring line
only, mooring lines were
connected to the system in three
points of the structure, leading to
a connection point 20m below
the buoyancy tank.
• The truss structure of the system
was for simplicity modelled by
beams with circular outer cross
section. The transparent
properties of L-profiles, as
intended for the truss structure
by the client, were adapted by
tuned hydrodynamic properties
of the beam elements.
WP3: Structural results, pontoon movements
Vertical pontoon
translations [m]
Vertical pontoon
velocities [m/s]
WP3: Structural results, potential power production
CaseWave height
[m]
Wave period
[s]
Wave length
[m]
Average power
output [kW]
Case 1 1 2.7 12 380
Case 2 2 3.0 16 690
Case 3 4 4.5 36 805
Case 4 6 5.4 52 951
Case 5 (storm) 15 8.7 119 NA
Note:
Due to the simplified wave load calculations
based on the Morison equation, pontoon
movements were somehow overestimated in
FEDEM for cases with waves shorter about 3x
the outer diameter of the pontoon. These
movements could not be damped sufficiently in
FEDEM to match CFD results for Case 1 and 2.
In addition, the wave energy processing through
the system is not reduced in FEDEM due to
power extraction of the pontoons, e.g., the total
power estimated for the complete structural
model is somewhat overestimated in the present
analyses.
WP3: Structural results, overall system behavior
Case 3
system inclination
WP4: Structural results, storm conditions
A capacity check of the beams in the slider/truss structure has been conducted.
It is found that:
• the L-profiles meet the requirement against buckling.
• yield of the cross section will occur before buckling.
• the max. stress utilization factor for the brace is 0.02 (1 is max. allowed).
• the max. stress utilization factor for the column is 0.11 (1 is max. allowed).
It is, however, recommended to conduct a more detailed structural assessment when
more details of the truss structure is available.
WP5: Animations
Animations showing CFD and FEDEM simulations are attached according to the
following references:
CaseWave height,
Hmax [m]
Wave period,
T [s]
Wave length,
L [m]File name
1 1 2.7 12CFD_Case1.avi
Fedem_Case1.avi
2 2 3.0 16CFD_Case2.avi
Fedem_Case2.avi
3 4 4.5 36CFD_Case3.avi
Fedem_Case3.avi
4 6 5.4 52CFD_Case4.avi
Fedem_Case4.avi
5 15 8.7 119Fedem_Case5.avi
(FEDEM only)
WP5: Concluding remarks
Pontoon geometry:
• From the CFD analyses it is concluded that the pontoons follow the wave propagation
closely, especially for wave lengths greater than two times the pontoon diameter.
However, as the wave height increases, the waves tends to partly break on top of the
pontoons, limiting the vertical displacement of the pontoons and hence power
production.
Potential power production:
• The total power production estimated from the pontoon weight and velocities has
been presented and it is seen that a theoretical peak production of 1200kW is
achieved for Case 4 (instantaneous), while the average power output was 951 kW.
Structural integrity under storm conditions:
• The capacity check showed that the truss construction meets the design
requirements when subjected to the global forces and moments occurring in storm
condition (Case 5). Hence, it is assumed that sufficient capacity is also achieved
during normal operating conditions.
WP5: Recommendations and further work
Pontoon geometry:
• The geometry of the pontoons may be revised as waves tends to partly break on top
of the pontoons. In addition, a detailed CFD analysis of the complete system may be
performed in order to account for such effects as shielding from the upstream
pontoons etc.
Potential power production:
• Fedem Technology recommends an investigation of the wave power system
subjected to irregular sea to be performed. This should be conducted together with
applying realistic power generator resistance, as well as frictional contact mechanics
between pontoon and truss structure, as this will affect the pontoon response.
Mooring arrangement:
• It is advised to further revise the mooring arrangement as the center of gravity and
center of buoyancy are closely located, which will lead to instability.
• It is also believed that by improving the mooring arrangement, the lean-over effect of
the system will be reduced.
Extended analyses - models
Model Buoyancy tank BallastTotal weight
tank + ballast
0 Steel
thickness 20mm, diameter
10,3m, height 4m
weight 46,2 tons
Concrete
in bottom of tank
thickness 150 og 500 mm
weight 44,3 tons
90,5 tons
1
Steel
thickness 20mm
diameter 16,3m
height 4m
weight 97,3 tons
(relevant for models
1, 2 og 3)
Concrete
in bottom of tank
thickness 200mm
weight 95,5 tons
192,8 tons
2 Concrete
below tank
Ø 3m x 3m
weight 48,8 tons
146,1 tons
3 Concrete
below tank
Ø 3m x 5m
weight 81,3 tons
178,6 tons
Extended analyses - results
ModelSystem rotation
(max. angle)Comments
0 Case 1: 4,3
Case 2: 13,4
Case 3: 12,1
Case 4: 14,2
Model and results from first phase of project (three
mooring lines).
1 Case 1: 3,4
Case 2: 10,5
Case 3: 11,5
Case 4: 14,3
General:
The results show that it is possible to utilize only one
mooring line by increasing the diameter of the
buoyancy tank to 16,3 m. All models show maximum
angles of rotation within the upper requirement of 15
deg and Case 2 – 3 also meet the lower
requirement of 10 deg for all sea states.
Models:
Model 1 gives the biggest system rotation due to the
locations of buoyancy and mass centers being
close. The rotation is reduced for Model 2 og 3
when the center of mass was lowered together with
a reduction in the total ballast weight.
2 Case 1: 1,3
Case 2: 3,5
Case 3: 4,4
Case 4: 5,7
3 Case 1: 1,1
Case 2: 2,9
Case 3: 4,9
Case 4: 7,5