analysis of the ventilation system - universiteit...
TRANSCRIPT
Analysis of the ventilation system
Internship report External supervisor: R.F.J. Leurink
Jasper Zuurveld (s1479660) Engineering department
University of Twente UT supervisor: S. Hoekstra
Grolsch brewery, Enschede
1 March – 31 May 2018
Analysis of the ventilation system – Jasper Zuurveld II
Preface I would like to thank Grolsch for the possibility to execute my internship at the brewery. It was a great
experience to be able to walk through the different areas of the brewery in order to get to all air
treatment units. Also the possibility to join the “bier ambassadeurs programma” is really appreciated.
Furthermore I would like to thank the Engineering team at Grolsch for the good time during my
internship. The team was very open to each other and there was always time for some questions. As an
engineering team can be imagined, there was a lot of coffee and a good amount of sarcasm involved,
providing a pleasant atmosphere. Thereby I would like to thank Rob Leurink for his time, effort and
expertise while supervising me during the internship. He gave me a great insight in the way he is
working and how it is to be working in a technical environment.
The last person I would like to thank is Eric. Eric has been my eyes and ears, in and around the
ventilation units. He is the one who is responsible for the maintenance concerning the ventilation
system of the brewery, resulting in a lot of knowledge of the system. Therefor he was a great help when
I had questions about the ventilation units.
Analysis of the ventilation system – Jasper Zuurveld III
Summary This report contains the main findings of the 3 month internship of Jasper Zuurveld, which started 1
March 2018. The assignment for this internship was to investigate the state of the ventilation system at
the brewery. The ventilation system was installed around 2003, during the build of the brewery. The
goal of the internship is to investigate the current state of the ventilation system. This investigation is
divided into the following parts:
• Update the documentation of the ventilation system
• Determine the criticalities and risks of the system
• Investigate the maintenance performed and improve the maintenance plan if needed
• Analyze the controls of the system and provide recommendations to improve those controls.
The documentation of the ventilation system is updated and supplemented, with maps and tables to
provide more insight in the different ventilation units. These files can be accessed digitally, ensuring that
everyone can access them easily.
In order to find the risks and criticalities of the ventilation system a QFMECA is performed. Out of the
QFMECA came that Grolsch has the most risks on a shortage of refreshment of the air and on controlling
the relative humidity.
The first one is important because the government has made certain rules that there should always be
enough refreshment. In offices there is the possibility to open the windows and at packaging the roof
hatches can be opened, meaning that fresh air still could enter the building. For the main lab and the
visitors are this is not the case, so these ventilation units have more priority.
The second risk taken is on the relative humidity which is present in multiple areas and has on average
the highest risk priority numbers. The main reason for this is that the relative humidity is not controlled
in most areas. Also there are almost no opportunities to influence the relative humidity, because the
weather outside has the most influence on it. The result is that during the winter, when the outside air is
relative dry, the relative humidity in the brewery is also way too low. To lower the risks taken on
humidity, the humidity should be monitored at the offices and visitors area.
At the moment there is not a really strong maintenance strategy for the maintenance of the ventilation
system. One worker of the technical service is responsible for maintaining the air treatment units. He
has on average 3 days a week in which he should maintain the ventilation system. This includes also the
heat piping towards the ventilation unit, electrical and mechanical matters and problem solving. An
improved maintenance plan is generated in collaboration with the mechanic who is responsible for the
system. In this way, the system will be maintained properly and the chance of breakdowns will decrease.
At the Grolsch brewery, the ventilation system is controlled based on the outside temperature. Based on
the outside temperature the temperature of the ingoing air will be calculated. At packaging the system
is also controlled on the inside relative humidity. For the controls multiple recommendations are
provided to improve the working of the system.
Overall a lot of recommendations are provided in a recommendations report. These recommendations
are prioritized and provided with an indication of the amount of time and/or cost is takes to implement
the improvement. All the files generated for the analysis are provided to Grolsch digitally.
Analysis of the ventilation system – Jasper Zuurveld IV
Table of content
Preface .......................................................................................................................................................... II
Summary ...................................................................................................................................................... III
Table of content ........................................................................................................................................... IV
Table of figures ............................................................................................................................................. V
1 About Grolsch ....................................................................................................................................... 6
2 Introduction .......................................................................................................................................... 7
2.1 Why should there be ventilation? ................................................................................................ 7
2.2 Possibilities of ventilation ............................................................................................................. 7
3 Problem definition .............................................................................................................................. 10
4 Situation at Grolsch ............................................................................................................................. 11
4.1 Layout of Grolsch ........................................................................................................................ 11
4.2 Overview of the air treatment units ........................................................................................... 12
4.3 Locations of the air treatment units ........................................................................................... 13
5 Risk analysis ........................................................................................................................................ 15
5.1 QFMECA ...................................................................................................................................... 15
5.1.1 Results of QFMECA ............................................................................................................. 16
5.1.2 Risks at Grolsch ................................................................................................................... 17
6 Maintenance ....................................................................................................................................... 18
6.1 Current maintenance at Grolsch ................................................................................................. 18
6.2 Deferred maintenance ................................................................................................................ 18
6.3 Improvements on maintenance .................................................................................................. 19
7 Controls of the ventilation system ...................................................................................................... 19
7.1 Expected pattern during the year ............................................................................................... 20
7.2 Working principle at Grolsch ...................................................................................................... 20
7.3 Improvements on controlling the system ................................................................................... 22
8 External parties ................................................................................................................................... 24
9 Conclusions ......................................................................................................................................... 25
10 Recommendations .......................................................................................................................... 26
11 References ...................................................................................................................................... 28
12 Appendix ......................................................................................................................................... 29
12.1 Appendix 1: Milestone planning ................................................................................................. 29
12.2 Appendix 2: Overview of the components in the air treatment units ........................................ 30
Analysis of the ventilation system – Jasper Zuurveld V
12.3 Appendix 3: Inside of a ventilation unit ...................................................................................... 31
12.4 Appendix 4: Overview of the components in the air dryers ....................................................... 34
12.5 Appendix 5: QFMECA .................................................................................................................. 35
12.6 Appendix 6: Photo report (In Dutch) .......................................................................................... 36
12.7 Appendix 7: Overview with recommendations (In Dutch) ......................................................... 46
12.8 Appendix 8: Self-reflection on the internship at Grolsch ........................................................... 48
Table of figures
Figure 1: Types of ventilation systems .......................................................................................................... 8
Figure 2: Project chart ................................................................................................................................. 10
Figure 3: Map with the different areas at the Grolsch brewery ................................................................. 11
Figure 4: Cover of ring binder with information about the air treatment units ......................................... 12
Figure 5: Location of the air treatment units .............................................................................................. 13
Figure 6: Floor plan with the locations and some information of the air treatment units ........................ 14
Figure 7: Location of the air dryers ............................................................................................................. 14
Figure 8: Heating and cooling principle ...................................................................................................... 20
Figure 9: Set points blow-in temperature based on outside temperature ................................................ 21
Figure 10:Control parameters ventilation packaging ................................................................................. 21
Figure 11: Weathered outside thermometer ............................................................................................. 22
Figure 12: Roof hoods in front of inlet ........................................................................................................ 22
Analysis of the ventilation system – Jasper Zuurveld 6
1 About Grolsch History of Grolsch In 1615 Willem Neerfeldt founded a brewery in the village of Grolle, which has now become Groenlo, in the Dutch province of Gelderland. His daughter married Peter Cuijper, who was appointed Guild Master of the brewers' guild of Grolle in 1676. In 1895, this successful brewery, known as 'De Klok', was taken over by their descendants who sold it to Theo de Groen, offspring of another true family of brewers. Meanwhile, in that same year, a number of textile manufacturers, merchants and bankers decided to set up another beer brewery, 'De Enschedesche Bierbrouwerij'. During the First World War ingredients were in short supply, causing the quality of the beer to drop, accompanied by a sharp fall in sales. The management of De Enschedesche Bierbrouwerij therefor decided to sell the business to Theo de Groen. In 1922, De Klok in Groenlo merged with De Enschedesche Bierbrouwerij to become 'De Klok', later renamed 'De Grolsche Bierbrouwerij'. Grolsch's new state-of-the-art brewing facility, located on the border between Enschede and Boekelo, became operational in 2004, replacing the old breweries in Enschede and Groenlo. Grolsch is part of Asahi Europe Ltd. since October 2016. [1] Brewing process Brewing beer is a 100% natural process. What the basic recipe is, of course, remains secret, but Grolsch works with two kinds of hops that gives Grolsch its own taste. Of course, the ingredients are of the highest quality and the brewing process is perfectly checked. Hop Hop provides the aroma and the bitter taste of our beer. It is a climber of which only the flowers of the female hop plant are used for brewing beer. In the past, hop was added to beer as a preservative, but today it is added for taste. Water Beer consists of more than 90% water. Good water is essential for a good quality of beer. During the construction of the new Grolsch brewery in 2004, a seven kilometer long water pipeline was built for the original water sources in the Northern part of Enschede. This is done to use the same water for our beer. Barley Barley is a grain and belongs to the grass family. Germinating barley grains (barley malt) are the main raw material for beer. Not all barley can be used for beer. Brew barley contains many starches and few proteins. You can also use other cereals for brewing beer. For example, wheat is an important ingredient of Weizen beers. Yeast Yeast causes the sugars to be converted into alcohol during the brewing process. Grolsch uses her own yeast because every yeast strain has its own character and greatly influences the taste of the beer. There are two types of yeast in the base: above fermentation and low fermentation. [2] Beers In the brewery in Enschede, in addition to the trusted Grolsch Premium Pilsner, various delicious beers are brewed according to their own recognizable recipe. There are various Grolsch special beers (including Weizen, Cannon, Autumnbok, Springbok), Grolsch 0.0% and the various variants of Grolsch Radler, but also Kornuit, De Klok and several other brands such as Peroni Nastro Azzurro. For these brands, Grolsch provides all distribution, marketing and sales activities for the Dutch market. [3]
Analysis of the ventilation system – Jasper Zuurveld 7
2 Introduction This report starts with an introduction on why there should be ventilation and how this could be
accomplished. Then the problem definition will be given, with the motivation for this project. An
overview of the ventilation system at Grolsch is provided next. This includes an overview of the
locations and components of the ventilation units located at Grolsch. The existing data is checked
and the information is updated. While having all the documentation of the system, a failure mode,
effects, and criticality analysis (FMECA) is performed, giving an insight in which ventilation units have
the highest risk priority number (RPN) and should get the most care. In section 6 the maintenance of
the ventilation system is analyzed. This is done in combination with the mechanical worker and with
the previous gained knowledge of the FMECA. Analyzing the controls of the system is done in section
7. This chapter will conclude with recommendation to improve the controls of the ventilation system.
In section 9 and 10, all the chapters will be concluded and the recommendations will be given in the
form of a recommendations report. These recommendations are sorted on priority and on the
investment.
2.1 Why should there be ventilation? Refreshment of the air is needed in all types of buildings, for example houses, commercial buildings
and factories. This refreshment is needed to ensure the air quality in the building. Good quality air
has a relative humidity of 40-60% and contains less than 1100 PPM CO2. The quality of the air will
decrease when there is no ventilation due to for example copiers, paperwork and people. This poor
quality air should be taken out of the building. In order to ensure that there is enough ventilation,
the government have set up some rules concerning ventilation. These rules can be found in article
3.6 of the building decree [4]. This provides a minimum amount of ventilation per person or per
square meter. In this way a minimum amount of fresh air is provided every hour. On the other hand,
the air flow not must not exceed 0.2m/s while entering the area, because this could be irritating for
the people working in the area.
In addition to the rules of the government, some regulations are stated in the Working Conditions
Decree. Article 6.2 provide some rules concerning ventilation. In order to let people work in the
company, the following 4 points must be matched:[5]
1. Sufficient non-polluted air should be present in the workplace.
2. Ventilation installations should always be ready for operation.
3. Ventilation installations should function such that employees are not subjected to
inconvenient draughts.
4. Ventilation installations should be supplied with a control system which detects faults in the
installation insofar as this is necessary for the health of the employees.
According to the points stated above it is a task for Grolsch to make sure that the ventilation system
is working at the moments it should be. Therefor the most common ways of ventilation will now be
discussed.
2.2 Possibilities of ventilation Due to the improvements of the isolation of buildings, the ventilation due to leakage of the building
will decrease. Therefor other possibilities should be used to ensure the air quality inside the building.
The following possibilities are the most common ones that are used to ventilate buildings.
Analysis of the ventilation system – Jasper Zuurveld 8
Natural ventilation
This principle uses natural ways to ventilate the building. Natural ventilation can be ensued by
opening a window or a door and by ventilation strips located in windows. This type of ventilation is
very common in residential buildings. This kind of ventilation is called ventilation type A.
Mechanical ventilations
Mechanical ventilation is used when natural ventilation, ventilation type A, is not sufficient or when
the ventilation should be better controlled. Mechanical ventilation uses a ventilator to actively
transport air in and/or out of the building. In this way, the location where the fresh air will move in
and/or the Polluted air will move out can be selected. There are still some options to select when
using mechanical ventilation.
1. Ventilation type B: Only mechanical supply of
fresh air. In this way the pressure in the building
will be increased, resulting in air that moves out
through windows, ventilation strips, doors and
cracks.
2. Ventilation type C: Only mechanical extraction of
polluted air. In this way the fresh air will enter
the building through windows, ventilation strips,
doors and cracks.
3. Ventilation type D: Mechanical supply and
extraction of air. With this option the inside
climate can be controlled the best, because the
ingoing and extracted air can be controlled. By
using an energy retrieval unit the heat of the
outgoing flow is reused to preheat the incoming
flow. In this way a lot of energy can be reused,
meaning less heating costs.
The four different kinds of ventilations systems are visualized in Figure 1. The ventilation at Grolsch is
mostly a type D and sometimes a type B system. This is done to make sure that the air is filtered
before entering the building. When applying system type A or C the polluted outside air will not be
filtered before it enters the building. This will not ensure clean air inside, which should be prevented
when producing consumer beverages.
Possibilities to reuse energy
In general there are three kinds of heat recovery systems namely, a heat recovery wheel, a plate heat
exchanger and a twin coil system. For the first two systems the ingoing and outgoing air should be at
the same location, where the twin coil can transport the heat through another medium from one
location to another. A heat recovery wheel is a turning wheel that is located half in the ingoing and
half in the outgoing air. In the warm flow the wheel will be heated. Because the wheel is turning, the
heated part of the wheel will go into the cold ingoing flow. There the heat will be extracted from the
wheel, preheating the ingoing air. A plate heat exchanger is a simple concept. The ingoing and
outgoing air will transfer the heat to each other while separated by some metal sheets. Unlike with
the heat recovery wheel, there is no mixing possible of ingoing and outgoing air. The last system is
the twin coil system. This system has an air to liquid heat exchanger in the ingoing as well as in the
outgoing air flow. By pumping the liquid, most of the times a combination of water and glycol, the
Figure 1: Types of ventilation systems
Analysis of the ventilation system – Jasper Zuurveld 9
heat can be transferred between the two air flows. All of these system will make sure that less
energy will be used to heat the building during the winter.
Analysis of the ventilation system – Jasper Zuurveld 10
3 Problem definition Brewing beer is the main goal of the Grolsch brewery. All the processes which have direct impact on
the production of beer have the main focus of the engineering team. But, there are also a lot of
processes that are less connected to the main process of brewing beer, like the ventilation system.
Therefor this system is way less maintained and optimized than the core processes. Most of the time
the ventilation works just fine, but when something is wrong, people notice it directly. Therefor it is a
very interesting subject to investigate and to give recommendations to improve the ventilation
system.
In the first weeks of the internship a project charter and a project planning were generated. Grolsch
has a structured template which is used for all projects. This template produces a one page overview
of the description, goal, results, scope, people involved, risks and benefits of the project. All this
information about the internship project can be found in this overview, displayed in Figure 2. The
combination of this project description and the milestone planning can be found in Appendix 1
Figure 2: Project chart
Risks
Insight in the functioning, risks and maintenance of the ventilation will
be generated. This knowlage will keep the risks, costs, safety and
working climate better in control.
There is a lack of knowledge at Grolsch over the system, which could
lead to wrong information, resulting in wrong conclusions.
Time shortage due to the fact that companies will be consulted and my
contract will end in 3 months.
A - Opdrachtgever
R - Projectleider
I - Inform
S - Support
- Mechanisch Engineer
S - Support
S - Support
C - Consult
I - Inform
- Martin Bosscher
- Freddie Groeneveld
- John Kalma
- Consultant Ext
- Susan Ladrak
- Jasper Zuurveld
- Rob Leurink
Project Description
Goal Result(s) Scope
BenefitsTeam Members Role
An overview of the air treatment system at
Grolsch.
A completed version of a FMECA for the air
treatment system.
A preferred maintenance plan and the
comparison with the existing plan.
The comparison between the system with those
manufactured nowadays.
Overview of possibilities to improve the controls
of the air treatment system.
The total ventilation system of the brewery
will be in the scope of the project.
For packaging the layout of the ventilation
system in the hall will be taken into account.
Depending on the FMECA the focus will
move to the critical parts of the system.
The ventilation system is in use since the construction of the Grolsch brewery in 2002. Since then, maintenance cost is kept to a minimum, not knowing
the effects of that decision. It is not known if the systems produced nowadays significant have improved in comparison to those out of 2002. Controlling
the system is done automatically, but it is not known if these settings are optimized. Also the risks of a system failure is not known.
Investigate the ventilation system to provide
an insight in:
The risks and criticalities.
The required level of maintenance and if it is
currently met.
The difference between the system at
Grolsch and the machines manufactured
nowadays.
Possibilities to improve the control of the
ventilation system.
Analysis of the ventilation system – Jasper Zuurveld 11
4 Situation at Grolsch In this chapter the details of the ventilation system at Grolsch will be presented. This includes the
locations and specifications of the 29 air treatment units and the 8 air dryers.
4.1 Layout of Grolsch To be able to distribute the beer to the customers, more than only a beer brewing line is needed. The
brewed beer should be stored in tanks in a refrigerated area and bottled at a packaging facility. Daily
Thousands of tests are done on the beer at the main lab to guarantee the premium quality. Also
manpower is needed in the office like people of HR, sales and engineering. All these different areas
have different requirements on the ventilation system. Therefor the brewery is divided into the
following areas, have all different requirements concerning the ventilation system:
Figure 3: Map with the different areas at the Grolsch brewery
• Brewers home (yellow)
• Packaging (red)
• Offices (orange)
• Visitors areas (green)
• Refrigerated area (blue)
• Main lab (purple)
• Storage (brown)
• Areas without mechanical ventilation (white)
Analysis of the ventilation system – Jasper Zuurveld 12
4.2 Overview of the air treatment units In the brewery, 29 air treatment units are installed. In addition to that, there are 8 air dryers that
prevent condensation on the cold beer tanks. The air treatment units can have the following
functions:
• Refreshing of a certain amount of air per hour (m^3/h)
• Heating the air
• Cooling the air
• Humidifying the air
• Drying the air
• Filtering the air
• Reusing the thermal energy that leaves the building
The air treatment units in the different areas have different functions to fulfill. Therefor some
components will be located in one unit, but not in another. In all the air treatment units there is the
possibility to heat and filter the ingoing air. At the offices the air
can be cooled using a top cooling, the same holds for the
refrigerated areas and the main lab. All other areas have no
possibility to cool the air inside the building. Humidifying is
only possible in one warehouse and drying is only done in
the refrigerated areas. The heat or cool energy of the
outgoing flow is reused to pre-heat or cool the ingoing air,
with exception of the air treatment units with a low volume
capacity. A global overview of the air treatment units in the
different areas is given in Table 1. An overview of all the
different components of the 29 different units is provided
in Appendix 2 and a photo report of the different
components of the ventilation units can be found in
Appendix 3. In addition to this overview, there is a ring
binder available that contains additional information of the
29 air treatment units. Including information on
dimensions, powers, efficiencies and materials.
There are also 8 air dryers located in the brewery. The
producer of these dryers is Munters. In the same format
as for the air treatment units, an overview is
constructed with general information of the 8 units. This overview can also be found in Appendix 4.
For the air dryers also, a ring binder is available with some extra information.
Table 1: Global overview of the different components of the air treatment units in the different areas
Figure 4: Cover of ring binder with information about the air treatment units
Analysis of the ventilation system – Jasper Zuurveld 13
4.3 Locations of the air treatment units In addition to the overview of the components of the air treatment units, a map is created to indicate
the locations of the units. This map is made interactive. When the pdf file is opened, some
information of the unit will be displayed when moving the mouse towards it. This menu displays the
following information:
• The area that the unit ventilates
• The capacity of the unit in m^3/h
• The type of heat recovery system
• The location Where the unit can be found
This information is displayed in Dutch because some users may not understand English. A screenshot
of this overview can be found in Figure 5. In Figure 6 the same map with the information of one air
treatment unit is shown. In addition to the air treatment units the location of the air dryers are
shown in Figure 7. In this way, the different units can be located rather easily. In combination with
the components overview, the main information of a unit can be gathered rather quickly.
The files mentioned above can be found on the server of Grolsch under the name of: “Gebouw
overzicht met luchtdrogers.pdf” and “Gebouw overzicht met LBK.pdf”.
Figure 5: Location of the air treatment units
Analysis of the ventilation system – Jasper Zuurveld 14
Figure 6: Floor plan with the locations and some information of the air treatment units
Figure 7: Location of the air dryers
Analysis of the ventilation system – Jasper Zuurveld 15
5 Risk analysis In this chapter the general risk of ventilation will be discussed. In order to get a good view on the
risks taken at Grolsch, a QFMECA is executed together with some colleagues, involving a
maintenance engineer, a brewer and a process engineer. The method and the results of this analysis
will be provided.
5.1 QFMECA To get an overview of the risks and criticalities of the ventilation system, a QFMECA is executed. In
this QFMECA, 5 different areas with ventilation are taken into account. In these different areas
different processes are happening, resulting in other risks. The following 6 areas are taken into
account: the brew house, packaging, offices, visitors areas, cool beer storage and the main lab. For
each area, the effect of the possible failures of the main functions of the system were examined. The
functions are: Cool down or heat up the building, having a certain refreshment of the air in the
building, keeping the humidity in limit and avoiding a certain pollution within the room. For each of
these functions the severity, occurrence and detectability of the failure modes were indexed in a
ranking between 1 and 6. The meaning of this index number is given in the table below. Table 2: Ranking QFMECA
By multiplying these numbers with each other, the risk priority number (RPN) is calculated. When
this number is higher, more risk is involved when this function of the system will fail. Therefor this
function should be secured to prevent a failure from happening. In this case a grading between the
number 1 to 6 is given, therefor the highest RPN possible is 6*6*6=216. Of course this is very unlikely
to happen, because this is an enormous risk. Multiple times a day a failure results in injuries or dead,
without the possibility to detect the failure. Therefor a logic RPN should be chosen to function as
threshold. A threshold is chosen with a medium risk of 3 for all indexes, which will result in a
threshold 3*3*3 = 27. All the RPN numbers were examined if they are above 27. When some
function had an index value of 6, it will always be taken into account.
Functions of the ventilation system The risk of the failure of the ventilation system will be examined during the QFMECA. As discussed in chapter 4.2 the ventilation system has multiple functions to fulfil. The risk of a system that will not work as it should be, could have different consequences in different area. So, the previous mentioned 6 different areas were taken into account. For the QFMECA the components of the ventilation system are converted into the following functions:
• Provide a certain amount of refreshment
• Controlling the temperature
Analysis of the ventilation system – Jasper Zuurveld 16
• Controlling the humidity
• Keep pollution out of the inside air
5.1.1 Results of QFMECA In this section, the key findings of this QFMECA will be provided. In table 3 the main risks, when some
ventilation unit or components of it will fail, are given. For example, when the ventilation in the brew
house will fail, the temperature will rise. This will have effect on the people that are in the area, as on
the machines. Therefor more attention should be given to the risk that the ventilation system could
not provide the right temperature. Another interesting one is the relative humidity at packaging,
both a too high as a too low humidity is a risk. The reasoning behind all the generated RPN numbers
can be found in appendix 5.
Table 3: Results of QFMECA
Temperature Refreshment Relative humidity Pollution
Brew house Too high (RPN: 27)
Packaging Too low (RPN: 32) Too high (RPN: 45) Too low (RPN: 40)
Offices Too low (RPN:40) Too low (RPN:64)
Visitors area Too low (RPN:40) Too low (RPN:36)
Refrigerated area Too high (RPN:48)
Main Lab Too high (RPN:45) Too low (RPN:40)
Pollution is in none of the areas a considerable risk. This is due to the fact that Grolsch filters the air
before blown into the building. When applying a ventilation system D the inflow and outflow of air
will be done mechanical, thereby the pollution outside will not move unfiltered into the building.
Also the pollution will not affect the process because the total brewing and bottling process is an
closed process, where the product will not interact with the environmental air.
The one with the highest RPN is the low relative humidity in the offices with a RPN of 64. Therefor
this one will be examined closely. Like stated before, the RPN is a multiplication of the numbers for
the severity, occurrence and detection. The indexes of the relative humidity in the offices were
established by the group on:
• Severity: 4, failure is disadvantageous for the production process.
o A low relative humidity will result in a irritations of the staff. Dry eyes, dry skin and
they will be more thirsty. All of this will result in a lower productivity and more
absenteeism.
o During wintertime the relative dry air will result in a low feeling temperature,
resulting in higher heating costs.
• Occurrence: 4, multiple times a month.
o At the moment there are no inspections, so the group was thinking that this was the
case during the winter months and sometimes in the summer period, resulting in
multiple times a month.
• Detection: 4, will only be noticed during inspection.
o In the offices only the temperature is measured and the relative humidity isn’t. There
is no system to check the relative humidity, so only when there is an inspection, the
low relative humidity will be detected.
With this kind of reasoning the entire QFMECA is filled. In appendix 5 the results of the QFMECA is
given. In this appendix only the ones with a RPN higher than 27 are displayed, because only these are
Analysis of the ventilation system – Jasper Zuurveld 17
the interesting ones. The intermediate result of the QFMECA can be found in a separately supplied
Excel file called “QFMECA_ventilation_system.xlsx”.
5.1.2 Risks at Grolsch Out of the QFMECA came that Grolsch have the most risks on a shortage of refreshment of the air
and the on controlling the relative humidity. The first one is important because the government has
made certain rules that there should always be enough refreshment. In case of a failure of the
ventilation system, there is the possibility to open the windows in offices and at packaging the roof
hatches can be opened, meaning that fresh air still could enter the building. For the main lab and the
visitors this is not the case, so these ventilation units have a higher priority.
The risk taken on the relative humidity is in multiple areas present and has on average the highest
risk priority numbers. The main reason for this is that the relative humidity is not controlled in most
areas. Also there are almost no opportunities to influence the relative humidity, because the weather
outside has the most influence on it. The result is that during the winter, when the outside air is
relative dry, the relative humidity in the brewery is also way too low. To lower the risks taken on
humidity, the humidity should be monitored at the offices and visitors area. Also it should be
investigated if the humidity can be controlled by introducing the possibility to control the humidity
in the offices, visitors area and at packaging. This can be done by installing new equipment or by
adjusting the controls. So, when the system fails, controlling the humidity at packaging is the hardest.
During the year, controlling the humidity in the offices and visitors area is the most difficult.
It is important to keep in mind that the control of the system should be examined if this is done
correctly. When illogical actions take place, a lot of energy can be wasted. Also the air quality inside
the building cannot be guaranty. Therefor the logic behind the controls of the ventilation system
should be examined closely. This is done for the ventilation system at Grolsch and the results can be
found in chapter 7.
Also, when the system is controlled as it should be, people can manipulate the system by hand. This
could also result in unwanted effects. A part of the air treatment units are located behind locked
doors, but most units can be accessed by everyone in the brewery. For example some valves for the
heating element were manually opened, resulting in high energy consumption and reduction of
working climate. For the working of the ventilation system, it is best that only the mechanics could
change the settings of the systems at Grolsch.
Analysis of the ventilation system – Jasper Zuurveld 18
6 Maintenance This chapter will discuss the maintenance aspects of the ventilation system. First the situation
nowadays at Grolsch will be discussed. Then an maintenance plan will be provided. This plan is
constructed based on visual inspections, maintenance done earlier, advise of producers and the
results of the QFMECA.
6.1 Current maintenance at Grolsch At the moment there is not a really strong maintenance strategy for the maintenance of the
ventilation system. One worker of the technical service is responsible for maintaining the air
treatment units. He has on average 3 days a week in which he should maintain the ventilation
system. This includes the heat piping towards the ventilation unit, electrical and mechanical matters
and problem solving. Because this worker is already working on the ventilation system since the
construction of the brewery, he knows a lot about the system and what the common failures are.
Just after the brewery was build, there was a maintenance plan for the ventilation system. For a
couple of years a checklist was filled to make sure the ventilation system was performing optimally.
The documentation of these years is still available. After a few years, the brewery was taken over by
the SABMiller group and a reorganization happened. There wasn’t time for the ventilation anymore,
because it was not the main process. During this time more failures started to arrive, so the
mechanic got some time back to maintain the ventilation system. Since then the mechanic started to
do the maintenance tasks, but did not fill the checklists anymore. This maintenance consists of
problem solving, cleaning, inspections and small maintenance tasks. Most of the failures will give an
error on the screen in the brewers home. From the point that the mechanic notices this waring, he
will move to the ventilation unit to repair the failure. This can be for example a worn belt, a broken
motor or an air valve that is broken. Because not all failures will give a notification on the screen it is
important that the mechanic occasionally will visually inspect the ventilation units to detect failures.
In addition he will carry out some maintenance tasks like lubricating the bearings.
In addition to the maintenance done internally, some other companies execute maintenance on the
ventilation system. Yearly, the air filters will be delivered and partly replaced by Camfil. During one
week, 2 engineers of Camfil will replace the old filters with new ones and clean the inside of the
ventilation units. The filters are delivered some time ahead, so the engineer at Grolsch can make sure
that the new filters will be at the ventilation units already. He also finishes the replacement of the
filters, because not all of the filters can be replaced during the week Camfil is present. If there is
some budget at the end of the year, another company will be contacted to clean and overhaul one or
two ventilation units. In 2013 the company Blygold was contracted to optimize 2 ventilation units at
packaging.
So, to conclude, at the moment the maintenance that is done consists of: Inspection, problem
solving, conducting of small maintenance tasks, yearly changing the filters and if there is budget
some optimizations.
6.2 Deferred maintenance Because there is not really a maintenance plan the technical service worker executes the
maintenance mostly on his own insight. Resulting in the fact that some maintenance points will not
be executed as many times as they should be. With that reason is for this study there is an inspection
done on the system to see where the maintenance could be improved. To get an insight in this
deferred maintenance, pictures were taken of all the things that are deviating from standard. These
Analysis of the ventilation system – Jasper Zuurveld 19
pictures are placed in a photo report. This report contains maintenance actions for the technical
service worker, but also major maintenance actions that should be executed by an external
company. Therefor this photo report will help the team of the engineering department to determine
if there are investment needed to keep the risks low and the system running the coming years. The
photo report can be found in Appendix 6.
Together with the mechanic the bearings of an air treatment unit are inspected. This is done to
investigate the condition and the type of bearing. In the documentation there was no information
about the types of bearings used in the ventilator. Bearings, produced by SKF that are typically used
for this kind of situations, have a lifespan of around 20.000 to 40.000 running hours. Because the
brewery is built in 2003 the expectation was that the bearings would be worn out, but this was not
the case at the unit that was inspected. It turned out during the inspection that standard types of
bearings were used. This was good news, because when a bearing will fail, the bearing can be
replaced rather quick by a new one, namely in 2 hours. Therefor there failure can be resolved rather
quickly. Also this will prevent lots of different spare parts, because the standard bearing are already
on hand.
6.3 Improvements on maintenance For the mechanic at Grolsch an overview is made of all the components that should be inspected
with a specific interval. During the development of this overview, multiple discussions with the
mechanic took place, resulting in a reliable and complete overview. This overview can be used in case
that the current mechanic will stop working at Grolsch for some reason, and must be inputted in the
maintenance management system SAP-PM.
During one of the first weeks of the internship the air filters were changed. This was just before the
beginning of the anther dust season. In this season the air is polluted, this can be seen by for
example the dust on cars. The conclusion, out of a conversation with a specialist on ventilation, was
that it was better change the filters just after this season.
For the ventilation system, time-based maintenance is applied. Once a year the filters will be
changed and the bearings will be lubricated, regardless of the condition. To change based on
calendar time was a conscious choice for changing the filters, because Grolsch is producing
beverages for customers. Another point why changing the filters is not done based on the condition
is due to the fact that there is no digital measurement on the pressure drop over the filters, there are
only analog measurements. The pressure drop over the filter is an indication on the state of the filter,
but does also depends on the volume flow over the filter which is not always the same. This makes it
harder to determine the condition of the filters without digital measurements.
For the other components of the ventilation unit, it is also very difficult to determine the working
hours. This is because the ventilation system is not logged. For some components, like pumps and
ventilators, the working hours can be found in the software, but this number has a maximum of
10.000. After the 10.000 is reached the counter is lowered a little bit, without sending a warning.
Multiple counters have reached this point, so the working hours of these components cannot be
estimated correctly. It is recommended to find a way to save the working hours properly. This can be
done by yearly noting down the values and resetting the counter of the LBK. Another way is to
increase the limit of the counter.
7 Controls of the ventilation system Each ventilation unit at the Grolsch brewery is controlled by a control panels. These panels are
controlling the system based on live measurements. The status of the system and the real time
Analysis of the ventilation system – Jasper Zuurveld 20
measurements can be consulted at a computer in the brewers home. The system works autonomous,
but units or components of the units can be switched on or off manually.
7.1 Expected pattern during the year The ventilation system is controlled mainly on the outside temperature. This means that, based on
the outside temperature, the system should heat or cool the air. When it is very cold outside, the
heating element and the heat recovery should be working. When the outside temperature increases,
most of the heating needed can be supplied by the energy recovery, so the heating element will
switch off. The heat recovery will stop when the air supplied should be cooler than the outside
temperature, then the cooling will start. From the point that the extracted air is cooler than the
outside temperature, the heat recovery will turn on. In this way the thermal energy that is already in
the building is optimal used. The logic explained above is graphically displayed in Figure 8 .
Figure 8: Heating and cooling principle
During the internship at Grolsch, a lot all sorts of weather has passed. There were days where it was
freezing outside and days with 28 degrees Celsius. This was very handy with checking if the system
was working like expected, because there was no possibility to look back in time what the system
had done. The conclusion of the evaluation is that the system is doing what was expected, based on
its measurements. The problem however was that not all measurements provided the correct values.
The effect of this will be discussed in the following chapter after the working principle at Grolsch is
explained.
7.2 Working principle at Grolsch At the Grolsch brewery, the ventilation system is controlled based on the outside temperature.
Based on the outside temperature the temperature of the ingoing air will be calculated. For each
ventilation unit the set points for the ingoing air temperature can be adjusted, this can be seen in
Figure 9. The outside temperature is measured on three different places, each one controlling a part
of the ventilation units. During the time that it is cold outside, the ingoing air should be warmed. This
firstly will be done by the heat recovery system. When this is not sufficient, the heating element will
provide the extra heat that is needed. Also, during winter time the air circulation in the offices is
0
1
-10 -8 -6 -4 -2 0 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34
Swit
ched
off
(0
) to
tu
rned
on
(1)
Outside temperature (ᵒC)
Heating and cooling
Heating Cooling Energy recovery
Analysis of the ventilation system – Jasper Zuurveld 21
lower than during the rest of the year, this must be done manually. In this way the amount of heat
needed is reduced to a minimum. During the hot summer days, when the temperature of the
outgoing air is less that the outside air, the system will use its heat recovery system as a cool
recovery system. The ingoing air will be cooled by the air that is leaving the building, before the
cooling element cools the air to the required temperature. In this way the amount of cooling energy
is reduced. The air circulation during the summer days is not reduced, due to the fact that the system
has a “top-cooling” and otherwise the cooling is not sufficient and the temperature in the building
would increase.
The program controlling the system is called Desigo Insight. This program visualizes the ventilation
system in a graphical environment. This makes it insightful which processes occur in each ventilation
system. The screenshots of Figure 9 and 10 are also from the same program, which is showing that it
is simple to adjust the set points. When for some reason the program closes and the computer will
shut down the ventilation will keep on running.
Figure 9: Set points blow-in temperature based on outside temperature
At packaging, the system is actively controlling the amount of air circulation, based on the relative
humidity in the building. The process at packaging uses a lot of heat and water and thereby
producing a lot of humidity. Therefor the system is controlled such that with a high relative humidity
there will be more refreshment of the air. The problem is that the system doesn’t reviews the
humidity of the outside temperature. So it can be the case that the outside air contains more
humidity than the inside air and that the ventilation only increases the relative humidity in the
building. The set points for the amount of refreshment can be adjusted in the system, like shown in
Figure 10.
Figure 10:Control parameters ventilation packaging
Analysis of the ventilation system – Jasper Zuurveld 22
7.3 Improvements on controlling the system In this section some improvements on controlling the system will be discussed. These improvements
are suggested to get the best out of the ventilation system.
Outside thermometers
During the sunny mornings, the thermometers are located in
the sun. These thermometer have a protection against the
radiation of the sun, but this is weathered like can be seen in
Figure 11. The effect of this is that the measurement of the
outside temperature is much too high. As said before, when
the outside temperature is higher that the temperature of the
air that leaves the building, the heat recovery will start. Due to
the fact that in the morning the measurements shows 6 degree
to high, the colder outside air will be heated up before it will
be cooled. This costs a lot of energy, which could simply be
avoided. Because the system is controlled on the outside
temperature, these temperature meters should be replaced.
Roof hoods at packaging
The ventilation at packaging is done by the
ventilation units and by roof hoods. An
overpressure is created in order to let the air
leave the building through these roof hoods. The
air leaving through these hoods will not pass any
heat recovery system, so the heat is lost. For
some reason a part of the hoods is manually
opened by default when the ventilation is shut
down, also during wintertime. This results in a lot
of heat losses during the winter, so make sure
that these roof hoods are closed by default. This
will also make sure that unfiltered outside air will
not enter the building when the system is off and
there is no overpressure.
Another point is that some of the roof hoods are located just before the inlet of the fresh outside air,
this situation can be seen in Figure 12. This is the case at ventilation units 1.1, 1.2, 1.4, 1.5 and 1.7.
The wet and warm air that leaves through these hoods will enter the building again. The advice is to
close these roof hoods permanently, probably this could be done by some hardware changes.
Minimal running hours
Some Ventilation units are turned off by default. This is due to the fact that the areas are not used
anymore or that other ways of ventilation are applied. For different components of the ventilation
units it is the best when the ventilation unit is turned on regularly. This is for example the case for
Figure 12: Roof hoods in front of inlet
Figure 11: Weathered outside thermometer
Analysis of the ventilation system – Jasper Zuurveld 23
components with lubrication. There are 2 ventilation units switched off by default, namely unit
number 4 located at BV2 and unit number 19 located at RB1. It has already happened that a units
broke down when turned on after a long time being turned off, which emphasizes the importance of
regularly switching on the units. For example, an improvement would be to switch on the units on for
half an hour once a week.
Anticipate on weather forecast
When it is a hot summer day, the ventilation system consumes a lot of energy to cool the building
during the day. In the morning the outside temperature is relatively low, providing the possibility to
move the heat out of the building without using the active cooling. At the moment, the temperature
of the ingoing air is determined based on the outside temperature, meaning that the heat will stay in
the building resulting in more cooling cost in the evening. When a weather forecast can be
implemented in the system, the system can cool the building in the morning hours with the outside
temperature when it will be a hot day. Of course the parameters should be defined. An educated
guess for the values is done, when applying more investigation is needed. An example of the
parameters will be:
• Weather forecast of the temperature should be higher than 25 degree Celsius.
• The inside temperature may not come below 21 degree Celsius.
• Ingoing air may not be colder than the minimum provided. Most cases 16 degree Celsius.
• The outside temperature is higher than the calculated temperature of the ingoing air.
Only when all the points above are met the “summer morning program” will be started. When one of
the points is not met the normal program will be followed again.
Relative humidity at the offices
The relative humidity is most of the year too low in the offices, especially during the winter. In the
winter the outside air is already relatively dry and Grolsch has no possibilities to humidify the air. An
additional problem is that at the moment, the relative humidity is not measured in the offices. This
combination makes that the relative humidity cannot be controlled at all. It is important to keep the
relative humidity during the year at 40-60%. The effects of a low relative humidity are not directly
visible, but can be from dry skin and itchy eyes to illness. There are multiple ways to increase the
humidity of the air inside the offices, like for example by placing more plants, place locally some
humidifiers or place a humidifier in the ventilation unit. The best solution depends on the size of the
problem. One colleague has already started an investigation, measuring the humidity in the offices,
so this is an ongoing investigation.
Analysis of the ventilation system – Jasper Zuurveld 24
8 External parties During the internship there has been contact between the intern and 2 external companies. These
companies gave a lot of insight in the working principles, do’s and don’ts of ventilation. Blygold in
combination with Agema Advies en techniek and Camfil are the companies that were contacted by
the intern. A short company description and goal if their visit will be given below.
Blygold
“It began in the early 1970’s when Rijk Bleijenberg discovered a new chemical cleaning method for
cooling devices whilst on a working trip in the USA. Later in 1976 he founded his own company under
the name of BlyChem (Bleijenberg Chemicals) and introduced these new innovative methods for the
first time in the Netherlands
In the years to follow, the rising demand for corrosion protection on heat exchangers of HVAC
equipment significantly increased. As a solution a unique new product was ingeniously invented. This
product BlyGold Plus, aptly named because of it’s golden colour, was the launch of the now
acclaimed brand Blygold.
Today Blygold is partnered with more than 75 companies in over 55 countries and is a well-known
and reputable name in the HVAC industry. This is mainly thanks to the dedicated and enthusiastic
partners that have chosen to work with Blygold. Together they benefit from this successful formula.”
[6]
Last year a case study is done to improve the air conditions at packaging during the year. This study
was focused on finding ways to get the temperature and relative humidity at packaging in control.
The solution was a package of which the costs were too high and the rate of return was too low, so
this is not implemented yet. Blygold accepted the invitation to come by and a very informative
conservation followed with their ventilation specialist. This conservation was at the beginning of the
internship, which gave a lot of insight in ventilation and helped a lot executing the internship.
Camfil
“Camfil is a global leader in the air filtration industry with more than half a century of experience in
developing and manufacturing sustainable clean air solutions that protect people, processes and the
environment against harmful airborne particles, gases and emissions. These solutions are used
globally to benefit human health, increase performance and reduce energy consumption in a wide
range of air filtration applications. Our 26 manufacturing plants, six R&D sites, local sales offices and
3,800 employees provide service and support to our customers around the world. Camfil is
headquartered in Stockholm, Sweden. Group sales total more than SEK 6 billion per year.” [7]
Camfil is contracted to replace the air filters once a year, this was done during the internship. On
advice of the engineers of Camfil who were replacing the filters, a study is executed to improve the
performance of the system. Therefor the account manager of Camfil was invited to execute an
optimization for multiple air treatment units. On some locations at the brewery there could be
placed other filters to decrease the costs of purchase and energy cost during the year. On some
locations the best filters were already used. This advice is forwarded to the head of the technical
service, which will order this more efficient filters next year during the filter change.
Analysis of the ventilation system – Jasper Zuurveld 25
9 Conclusions The internship assignment was meant to investigate the ventilation system at the Grolsch brewery.
The goal of this assignment was to investigate the ventilation system to provide an insight in:
• The risks and criticalities.
• The required level of maintenance and if it is currently met.
• Possibilities to improve the control of the ventilation system.
In addition to these goals the documentation of the ventilation system should be updated to get
more insight in the system installed. This last one is done by creating maps with the locations of all
the different ventilation units and with the locations of the air dryers. In total the system installed at
Grolsch consists out of 29 ventilation units and 8 air dryers. Information about the components
inside of the ventilation units is collected in one table to provide a quick overview.
Next the risks and criticalities were determined by executing a QFMECA. The conclusion of the
analysis was that each area in the brewery has different requirements on the ventilation, resulting in
different criticalities and failure modes. At the moment the system or components of the system
fails, most trouble will be to keep enough refreshment and to keep the relative humidity on the
correct level. Keeping the relative humidity on the right level is, also when the system doesn’t fails, a
problem because the relative humidity is not measured and controlled in most parts of the brewery.
The maintenance of the ventilation system is done by one mechanic who is involved in the system
since the start of the brewery at this location. Therefor he knows a lot about the system, but this
made him easygoing on some parts that are not that important in his eyes. To make sure all the
points of the ventilation system will be checked and maintained, a maintenance plan is created in
cooperation with the mechanic. The results of the QFMECA were used while creating this
maintenance plan. In addition to this plan a photo report is created, which consist of all the
remarkable points of the ventilation system which should be maintained by the mechanic or by a
project of the engineering department.
The last part in this report goes about the controls of the ventilation system. The most outstanding
conclusion is that the system is controlled on the outside temperature, not on the temperature
measures inside the building. This will not give too many problems in general cases when the
setpoints are properly programmed and the building consist of one open area. But when there are
multiple rooms, like in the offices, the ventilation system cannot perform optimally. Also some
improvements on the controls are provided of which some are applied already. These improvements
will decrease the energy usage or increase the inside air conditions.
During the investigation a lot of points of attention passed. This means that there were a lot of things
that could be improved or optimized. These recommendations are collected and summarized in a
recommendation report. This report is divided into 3 priorities to give an insight which should be
undertaken first, also a time and cost indication is given.
Analysis of the ventilation system – Jasper Zuurveld 26
10 Recommendations As can be imagined, no system is perfect. Of course there should be searched for the best
performance under the restricting budgets. After reviewing the system during the internship, ideas
to maintain and improve the system came into consideration. Some of these ideas are already
implemented, others take some more time to investigate or implement. Some will improve the air
quality in the buildings, some others will reduce the energy usage. An overview of the
recommendations for improving the system is generated. This overview contains a periodization and
an indication on the amount of time and/or cost it takes to implement the improvement. This
overview is generated in Dutch and can be found in Appendix 7. Because the amount of
recommendations, the ones with the highest priority will be discussed below.
High priority Time needed/ costs involved.
At the brewery, the ventilation units at BV1-BV3 have the most signs of wear. The reason for this is that these units have to process a lot of humid air. It is important for the working of the system that this corrosion should be removed. Small parts can be coated by an engineer. The condition of unit 1.7 and 1.1 is so bad that these should be revived. The ventilation units at the offices however are still looking good.
Much
The exhaust pipe of the pasteur, which has the goal to remove the moisture to prevent that this will go into the building, is just in front of the inlet of fresh air. In this way the moisture will still access the building. The more alarming is the effect of this moisture in the ventilation unit, these are subjected to lots of rust and corrosion. Find a way to move the outlet of the Pasteur of line 7.
Considerable
At the brewery all kinds of measurements are saved in order to analyze it. This is not the case of the ventilation system. Safe this information in order to be able to investigate if the system is working as it should be. The data that should be saved is for example the energy consumption of the heating, cooling and electricity. Thereby the setpoints of the different components are interesting.
Considerable
There are 3 outside temperature measurements on which the system is controlled. All these measuring instruments are weathered, causing unreliable measurements in the morning when the sun is shining. This leads to unnecessary consumption of energy during the summer days. The measuring instruments should be replaced
Little
At some locations at the brewery the air treatment units are permanently switched off. Being permanently switched off is bad for the state of the ventilation units and could give failures when suddenly turned on. Make sure each unit is switched on at least once a week.
Little
The HTHW network at packaging is broken at multiple points. The leakages already have already caused damage at the ceiling and dripped down beside the some control panels of the packaging lines. Make sure that these leakages will be repaired as soon as plausible.
Little
Heating is a considerable cost during the wintertime and consumes a lot of energy at packaging. Nevertheless the rook caps in BV1 and BV2 are standard opened for one third during the year. Also when the ventilation is switched off. Heating energy can be saved by closing these roof caps permanently when the ventilation is switched off. This will also prevent the entering of pollution in the building. By moving the air out of the building through the ventilation unit, more thermal energy out of the building can be reused.
Little
Analysis of the ventilation system – Jasper Zuurveld 27
Some of the roof caps are located just in front of the suction grill for fresh outside air. This is the case for units 1, 2, 4, 5 and 7. Investigate the possibility to close these rook caps permanent. This will probably be a mechanical adjustment.
Little
Analysis of the ventilation system – Jasper Zuurveld 28
11 References
[1] http://www.royalgrolsch.com/content/our-brewery
[2] http://www.royalgrolsch.com/content/our-beers-0
[3] http://www.royalgrolsch.com/content/history
[4] https://rijksoverheid.bouwbesluit.com/Inhoud/docs/wet/bb2012/hfd3/afd3-6
[5] https://puc.overheid.nl/doc/PUC_1174_14/1/#112487
[6] https://www.blygold.com/about-us/
[7] http://www.camfil.co.uk/About-Camfil-/
Analysis of the ventilation system – Jasper Zuurveld 29
12 Appendix
12.1 Appendix 1: Milestone planning
Project milestones 'Project Ventilation System'Activity Resp. RAG 10 11 12 13 14 15 16 17 18 19 20 21 22
RL P 1 1 1
A
RL MB P 1 1 1
A
JK P 1 1 1
A
RL P 1 1 1
A
FG P 1 1 1
A
P 1 1 1 0
A
P 1
A
P 1 1
A
P
A
P
AIssue that w ill impact total project on time, cost or scope. Needs to be escalated by the project team
Issue that does not jeopardize total project on time, cost or scope. Can be resolved by project team
Performing to plan
Red
Amber
Green
1
2
3
4
6
7
8
5
Get an insight of the systems installed and provide an overviewJZ
Carry out a FMECA to discover the risks and criticalitiesJZ
Investigate if the maintenance performed is sufficient JZ
Analyze and optimize the controls of the ventilation system
JZ
JZ
Write report, make and present (end)presentation
Support
Present the intermediate results and conclusions at the monthly
meeting JZ
Finalize report based on feedback from end presentationJZ
Compare the system at Grolsch to those manufactured nowadaysJZ
Analysis of the ventilation system – Jasper Zuurveld 30
12.2 Appendix 2: Overview of the components in the air treatment units Added file on server Grolsch: Samenvatting_inhoud_ventilatiekasten_en_luchtdrogers_Grolsch.xlsx
Naam Nummer op LBK Locatie Verdieping Aanvoercapaciteit (m^3/h) Aanvoercapaciteit (l/s) Afvoercapaciteit(m^3/h) Delta capaciteit (m^3/h) Aanvoer ventilator Afvoer ventilator Ventilator aansturing
Vernieuwde
controllers Locale afzuigventilator Dakkappen
Registers
buitenkanalen
Recirculatie
registers
Filter
Aanvoer
Filter
Afvoer
Bottelarij 1.1RK1 BV1 1 BV1 2 110.000 30.556 55.000 55.000 Ja Ja Meerdere setpoints Nee Nee Ja Ja Ja Ja Ja
Bottelarij 1.2RK1 BV1 2 BV1 2 110.000 30.556 55.000 55.000 Ja Ja Meerdere setpoints Nee Nee Ja Ja Ja Ja Ja
Bottelarij 1.3RK1 BV1 3 BV1 2 110.000 30.556 55.000 55.000 Ja Ja Meerdere setpoints Nee Nee Ja Ja Ja Ja Ja
Bottelarij 1.4RK1 BV2 4 BV2 2 110.000 30.556 55.000 55.000 Ja Ja Meerdere setpoints Nee Nee Ja Ja Ja Ja Ja
Bottelarij 1.5RK1 BV2 5 BV2 2 110.000 30.556 55.000 55.000 Ja Ja Meerdere setpoints Nee Nee Ja Ja Ja Ja Ja
Bottelarij 1.6RK1 BV2 6 BV2 2 110.000 30.556 55.000 55.000 Ja Ja Meerdere setpoints Nee Nee Ja Ja Ja Ja Ja
Bottelarij 1.7RK1 BV3 7 BV3 2 110.000 30.556 55.000 55.000 Ja Ja 0 tot 100% Ja Nee Ja Ja Ja Ja Ja
Bottelarij 1.8RK1 BV3 8 BV3 2 110.000 30.556 55.000 55.000 Ja Ja 0 tot 100% Ja Nee Ja Ja Ja Ja Ja
30LBK30 HK6 2e verdieping 9 BV1 2 13.500 3.750 13.500 0 Ja Ja Aan uit Nee Nee Nee Ja Ja Ja Ja
31BK31 HK6 main lab 10 BV1 2 9.000 2.500 9.000 0 Ja Ja Aan uit Nee Nee Nee Ja Ja Ja Ja
Pasteur 5RK1 DT1 11 DT1 1 5.500 1.528 5.500 0 Ja Ja Laag en hoog toerental Nee Nee Nee Ja Nee Ja Nee
Kantoren / was -kleedruimten blok L DT1 12 DT1 1 7.600 2.111 6.775 825 Ja Ja Aan uit Nee Nee Nee Ja Nee Ja Ja
Kantoren / was -kleedruimten CM2 13 CM2 1 7.600 2.111 6.775 825 Ja Ja Aan uit Nee Nee Nee Ja Nee Ja Ja
Centrale magazijn 4RK1 CM2 14 CM2 1 20.000 5.556 0 20.000 Ja Nee Aan uit Nee Nee Nee Ja Ja Ja Nee
28LBK28 HK6 1e verdieping ( noord ) 15 HK6 1 10.000 2.778 10.000 0 Ja Ja Aan uit Nee Nee Nee Ja Ja Ja Ja
Kantoren/Kantine VG1 16 VG1 1 4.000 1.111 4.000 0 Ja Ja Aan uit Nee Nee Nee Ja Ja Ja Nee
Reclame 2RK1 RM1 17 RM1 1 1.200 333 0 1.200 Ja Nee Aan uit Nee Ja Nee Ja Nee Ja Nee
6LBK6 Repaking 6RK1 OP1 18 OP1 1 2.500 694 0 2.500 Ja Nee Aan uit Nee Ja Nee Ja Nee Ja Nee
7LB7 Rest.beer 6RK1 RB1 19 RB1 1 7.500 2.083 7.500 0 Ja Ja Laag en hoog toerental Nee Nee Nee Ja Ja Ja Nee
Control Room 20 BH2 2 7.000 1.944 7.000 0 Ja Ja 0 tot 100% Nee Nee Nee Ja Nee Ja Ja
Brouwhuis verdieping 21 BH2 2 86.500 24.028 86.500 0 Ja Ja 0 tot 100% Nee Nee Nee Ja Ja Ja Nee
Brouwhuis B.G. 22 BH2 3 63.500 17.639 63.500 0 Ja Ja 0 tot 100% Nee Nee Nee Ja Ja Ja Nee
26LBK26 HK2 23 BH2 3 18.750 5.208 18.750 0 Ja Ja 0 tot 100% Ja Nee Nee Ja Ja Ja Ja
33LBK33 HK4 1e verdieping 24 HK4 0 16.500 4.583 8.750 7.750 Ja Ja 0 tot 100% Nee Nee Nee Ja Ja Ja Ja
32LBK32 HK4 beganegrond 25 HK4 0 23.500 6.528 23.500 0 Ja Ja 0 tot 100% Nee Nee Nee Ja Nee Ja Ja
27LBK27 HK5 26 HK5 2 11.200 3.111 11.200 0 Ja Ja Aan uit Nee Nee Nee Ja Ja Ja Ja
34LBK34 HK4 2e verdieping 27 HK4 2 9.500 2.639 9.500 0 Ja Ja Aan uit Nee Nee Nee Ja Ja Ja Ja
25LBK25 HK1 28 HK1 2 11.200 3.111 11.200 0 Ja Ja Aan uit Nee Nee Nee Ja Ja Ja Ja
29LBK29 HK6 1e verdieping ( zuid ) 29 HK6 1 11.000 3.056 11.000 0 Ja Ja Aan uit Nee Nee Nee Ja Ja Ja Ja
Naam Verwarmingselement Koelelement Bevochtiger Ontvochtiger Druppelvanger Twin Coil Warmte Wiel Plaatwarmte-wisselaar WTW systeem Verlichting
Aantal
compontenten Locatie beschrijving Kolom1 Kolom2 Kolom3 Kolom4
Bottelarij 1.1RK1 BV1 Ja Nee Nee Nee Ja Ja Nee Nee Ja Ja 10 In de open ruimte boven BV1 aan de kant van het magazijn.
Bottelarij 1.2RK1 BV1 Ja Nee Nee Nee Ja Ja Nee Nee Ja Ja 10 In de open ruimte boven BV1 aan de kant van het magazijn.
Bottelarij 1.3RK1 BV1 Ja Nee Nee Nee Ja Ja Nee Nee Ja Ja 10 In de open ruimte boven BV1 aan de kant van het magazijn.
Bottelarij 1.4RK1 BV2 Ja Nee Nee Nee Ja Ja Nee Nee Ja Ja 10 In de open ruimte boven BV2 aan de kant van het magazijn.
Bottelarij 1.5RK1 BV2 Ja Nee Nee Nee Ja Ja Nee Nee Ja Ja 10 In de open ruimte boven BV2 aan de kant van het magazijn.
Bottelarij 1.6RK1 BV2 Ja Nee Nee Nee Ja Ja Nee Nee Ja Ja 10 In de open ruimte boven BV2 aan de kant van het magazijn.
Bottelarij 1.7RK1 BV3 Ja Nee Nee Nee Ja Ja Nee Nee Ja Ja 11 In de open ruimte boven BV3 aan de kant van het magazijn.
Bottelarij 1.8RK1 BV3 Ja Nee Nee Nee Ja Ja Nee Nee Ja Ja 11 In de open ruimte boven BV3 aan de kant van het magazijn.
30LBK30 HK6 2e verdieping Ja Ja Nee Nee Ja Nee Ja Nee Ja Ja 10 In de open ruimte boven BV1 tegen de muur van HK6 aan de kant van het magazijn.
31BK31 HK6 main lab Ja Ja Nee Nee Ja Nee Ja Nee Ja Ja 10 In de open ruimte boven BV1 tegen de muur van HK6 aan de kant van BV1.
Pasteur 5RK1 DT1 Ja Nee Nee Nee Nee Nee Nee Nee Nee Ja 4 In technische ruimte die toegankelijk is vanaf BV2.
Kantoren / was -kleedruimten blok L DT1 Ja Ja Nee Nee Ja Nee Nee Ja Ja Ja 9 In technische ruimte die toegankelijk is vanaf BV2.
Kantoren / was -kleedruimten CM2 Ja Nee Nee Nee Ja Nee Nee Ja Ja Ja 8 In technische ruimte dat zich in de mannen kleedruimte bevind in CM2.
Centrale magazijn 4RK1 CM2 Ja Ja Ja Nee Ja Nee Nee Nee Nee Ja 7 Op hoogte in het magazijn, tegen de buitenmuur aan de kant van CM1. Bereikbaar via ladder.
28LBK28 HK6 1e verdieping ( noord ) Ja Ja Nee Nee Ja Nee Ja Nee Ja Ja 10 In ruimte naast de watertank van de sprinkler installatie, bereikbaar via wenteltrap naast de watertank.
Kantoren/Kantine VG1 Ja Nee Nee Nee Nee Nee Nee Nee Nee Ja 5 Op hoogte naast het kantoor aan de kant van VL2, bereikbaar via ladder.
Reclame 2RK1 RM1 Ja Nee Nee Nee Nee Nee Nee Nee Nee Ja 4 Op het dak van het kantoor, geheel in de hoek.
6LBK6 Repaking 6RK1 OP1 Ja Nee Nee Nee Nee Nee Nee Nee Nee Ja 4 Op hoogthe in de hoek met VG1 en RM1. Toegankelijk via trap ruimte zelf of via deur vanuit VG1.
7LB7 Rest.beer 6RK1 RB1 Ja Nee Nee Nee Nee Nee Nee Nee Nee Ja 5 Op hoogthe in de hoek met VG1 en OP1. Toegankelijk via ladder.
Control Room Ja 2 maal Nee Nee 2 keer Nee Nee Ja Ja Ja 9 In BH2 op de tweede verdieping tegen de buitenmuur en FK1 aan.
Brouwhuis verdieping Ja Nee Nee Nee Nee Nee Nee Nee Nee Ja 5 In BH2 op de tweede verdieping tegen de buitenmuur en BH3 aan.
Brouwhuis B.G. Ja Nee Nee Nee Nee Met LBK26 Nee Nee Ja Ja 7 In BH2 met trap naar de derde verdieping, in het midden van de ruimte tegen FK1.
26LBK26 HK2 Ja Ja Nee Nee Ja Met Brouwhuis Ja Nee Ja Ja 12 In BH2 met trap naar de derde verdieping, tegen uur van HK2.
33LBK33 HK4 1e verdieping Ja Ja Nee Nee Ja Nee Ja Nee Ja Ja 10 In de kelder van HK4, Met de lift naar de BG, links de trap naar beneden nemen. Achter kast 24, verdeeld over 2 kasten.
32LBK32 HK4 beganegrond Ja Ja Nee Nee Ja Ja Nee Nee Ja Ja 9 In de kelder van HK4, Met de lift naar de BG, links de trap naar beneden nemen.
27LBK27 HK5 Ja Ja Nee Nee Ja Nee Ja Nee Ja Ja 10 In technische ruimte bovenaan trap op tweede verdiepping.
34LBK34 HK4 2e verdieping Ja Ja Nee Nee Ja Nee Ja Nee Ja Ja 10 Op de tweede verdieping, midden op de verdieping in technische ruimte.
25LBK25 HK1 Ja Ja Nee Nee Ja Nee Ja Nee Ja Ja 10 In technische ruimte bovenaan trap op tweede verdiepping.
29LBK29 HK6 1e verdieping ( zuid ) Ja Ja Nee Nee Ja Nee Ja Nee Ja Ja 10 In technische ruimte in de gang van HK6 tegen BV1.
Betekenis kolommen schema
Nummer op LBK Elke kast heeft op de buitenkant in een groen blokje zijn eigen nummer staan.
Locatie Dit is de locatie waar de LBK staat. Dit hoeft niet hetzelfde gebouw te zijn als deze ventileert.
Verdieping Geeft aan op welke verdieping de LBK is gepositioneerd.
Aanvoercapaciteit (m^3/h) De hoeveelheid lucht die de aanvoerzijde van LBK per uur kan verwerken.
Aanvoercapaciteit (l/s) De hoeveelheid lucht die de aanvoerzijde van LBK per seconden kan verwerken.
Afvoercapaciteit(m^3/h) De hoeveelheid lucht die de afvoerzijde van LBK per uur kan verwerken.
Delta capaciteit (m^3/h) Het verschil tussen de luchtaanvoer en luchtafvoer.
Aanvoer ventilator Is er een ventilator in de LBK aanwezig om lucht aan te voeren
afvoer ventilator Is er een ventilator in de LBK aanwezig om de lucht af te voeren
Ventilator aansturing Op welke manier worden de ventilatoren aangestuurd? Vaste setpoint(s) of een 0-100% sturing.
Vernieuwde controllers Zijn er vernieuwde controllers geplaatst in de kast omdat de voorgaande verouderd en defect waren?
Afzuigventilator Sommige locaties hebben alleen inblaas via een LBK en een afvoer via
Dakkappen Op sommige locaties zijn er dakkappen aanwezig waardoor de lucht het gebouw kan verlaten.
Registers buitenkanalen Geeft aan of de aan- en afvoer kanalen van de LBK ge
Recirculatie registers Geeft aan of de LBK uitgevoerd is met een recirculatieklep om afgezogen lucht deels terug te het gebouw in te blazen.
Filter Aanvoer Word de buitenlucht gefilterd?
Filter Afvoer Word de afgezogen lucht gefilterd?
Verwarmingselement Is de LBK uitgevoerd met een verwarmingselement?
Koelelement Is de LBK uitgevoerd met een koelelement?
Bevochtiger Is de LBK uitgevoerd met een bevochtiger?
Ontvochtiger Is de LBK uitgevoerd met een ontvochtiger?
Druppelvanger Is de LBK uitgevoerd met een druppelvanger?
Twin Coil Is de LBK uitgevoerd met een twin coil?
Warmte Wiel Is de LBK uitgevoerd met een warmte wiel?
Platenwisselaar Is de LBK uitgevoerd met een platenwisselaar om energie terug te winnen?
WTW systeem Is de LBK uitgevoerd met een warmte terugwin systeem?
Verlichting Is de LBK uitgevoerd met een verlichting?
Aantal compontenten Is de LBK uitgevoerd met een aantal compontenten?
Locatie beschrijving Korte beschrijving waar de LBK gevonden kan worden.
Analysis of the ventilation system – Jasper Zuurveld 31
12.3 Appendix 3: Inside of a ventilation unit
1 Registers
• Dicht
• Open
2 Filters
• Zakken
• Voorkant
• Binnenkant
Analysis of the ventilation system – Jasper Zuurveld 32
3 Ventilator
• Aanzuigkant met elektromotor
• Uitblaaskant
4 Warmte terugwinningswiel
• Inblaas
• Afzuig
• Aansturing met riem
4b
Andere warmte terugwinning mogelijkheden
• Plaatwarmte-wisselaar
• Twin Coil
5 Verwarming
• Element
• Leidingwerk met regelklep
Analysis of the ventilation system – Jasper Zuurveld 33
6 Koeling
• Element
• Leidingwerk met regelklep
7 Druppelvanger
8 Verlichting
Analysis of the ventilation system – Jasper Zuurveld 34
12.4 Appendix 4: Overview of the components in the air dryers
Analysis of the ventilation system – Jasper Zuurveld 35
12.5 Appendix 5: QFMECA (This file can be found on the server of Grolsch under the name: QFMECA_ventilation_system.xlsx)
0
Process Name: Luchtventilatiesysteem Brouwerij Prepared by: Jasper Zuurveld
Responsible: Jasper Zuurveld FMECA Date: 22-03-2018
Controls
Prevention
O
C
C
Controls
Detection
BrouwhuisLuchtverversing/temp
eratuurbeheersing
binnentemperatuur 29
gradenTe hoog
Mensen rondleiding
klagen, slechte
werkomgeving,
Instrumentatie
verslechterd
3 Geen 3
Geen automatische
melding, op eigen
inzicht of bij klachten.
3 27
Klep verwarming staat
handmatig open
Grote
toename
Geen
effect
Geen
effect
Verslechte
ring3 Geen 3
Geen automatische
melding, op eigen
inzicht of bij klachten.
3 27
Voorkomen dat kleppen
opengezet kunnen worden.
Met regelmaat controleren of
ze dicht staan
Packaging Luchtverversing1-4 keer per uur
tijdens productieTe weinig
Ophoping CO2 en
vocht zal niet worden
afgevoerd
4 2 4 32Batchgerichte
aansturing
Alle luchtregisters
naar buiten zitten
dicht
ToenameGeen
effect
Geen
effect
Verslechte
ring4
Softwarematig
ingesteld dat dit niet
zou moeten
voorkomen
2Geen terugkoppeling
binnen het systeem4 32
Met regelmaat visueel
inspecteren of alles nog naar
behoren werkt.
Luchtvochtigheid op
pijl houden40-60% Te hoog
Verhoogde kans op
bacteriegroei, vocht
kan neerslaan
5 3 3 45Dakkappen open bij te
hoge luchtvochtigheid
machines produceren
te veel vochtToename
Geen
effect
Verslechte
rd
Verslechte
ring3
Beter dichten en
isoleren wassers6
Het is visueel
zichtbaar dat er damp
opstijgt.
2 36
Vochtafgifte van machines
proberen in te perken, anders
lokaal actief afzuigen.
lucht wordt niet
genoeg ontvochtigd
Geen
effect
Geen
effect
Verslechte
rd
Verslechte
ring4 Meer lucht verversen 6
Ventilatiesysteem
pakt dit zelf aan. 2 48
Mogelijkheid onderzoeken of
ontvochtigen mogelijk is.
Aansturen op absolute i.p.v.
relatieve luchtvochtigheid
Meer lucht verversen,
betekend niet dat dit
drogere lucht is
Luchtvochtigheid op
pijl houden40-60% Te laag
Karton en papier
worden statisch4 2 5 40
Effect op karton, niet
op te merken op
product zoals bij te
vochtig
Te veel droge lucht
wordt er van buiten
naar binnen geblazen.
ToenameDaling van
kwaliteit
Verslechte
rd
Geen
effect 3
Minder
luchtverversing als
luchtvochtigheid laag
is.
3
Waardes aflezen op
computer, is geen
standaard handeling
5 45
Aansturen op absolute
luchtvochtigheid, momenteel
minder verversen.
Kantoren Luchtverversing
2-5 keer verversen
per uur tijdens
kantooruren
Te weinig
Ophoping van CO2,
productiviteit gaat
omlaag
5 2 4 40
Alle luchtregisters
staan dichtToename
Daling van
kwaliteit
Verslechte
rd
Grote
verslechter
ing
5
Softwarematig
ingesteld dat dit niet
zou moeten
voorkomen
2
Geen meldingen van
gebroken onderdelen,
klachten nemen toe
4 40
Met regelmaat visueel
inspecteren of alles nog naar
behoren werkt.
Luchtvochtigheid op
pijl houden40-60% Te laag
Meer ziekteverzuim,
lagere
gevoelstemperatuur
4 4 4 64
Droge lucht van buiten
word naar binnen
gezogen (koude
dagen)
Geen
effect
Daling van
kwaliteit
Verslechte
rd
Verslechte
ring4 Geen 3
In kantoren zijn geen
meters aanwezig. 4 48
Onderzoeken hoe groot dit
probleem is. Meters
ophangen. -> is al een
onderzoek naar gestart
Vooral met koud weer
Afzuigen vochtige
lucht
Geen
effect
Daling van
kwaliteit
Geen
effect
Verslechte
ring3
Geen, word zelfs niet
gemeten3
In bezoekersruimten
zijn geen RV meters
aanwezig.
4 36 Aansturen op luchtvochtigheidEffect versterkt door
centrale verwarming
Bezoekersruimte Luchtverversing
2-5 keer verversen
per uur tijdens
kantoor en
bezoekersuren
Te weinig Ophoping CO2 4 2 5 40
Alle luchtkleppen naar
buiten zitten dichtToename
Daling van
kwaliteit
Verslechte
rd
Verslechte
ring4
Softwarematig
ingesteld dat dit niet
zou moeten
voorkomen
2 Inspectie bij de kast 4 32
Software doorlichten om
erachter te komen
waarom/hoe dit zou kunnen
gebeuren
CO2 melder voor
aansturing geeft foute
waarde
AfnameGeen
effect
Geen
effect
Verslechte
ring3
Begrenzen welke
waardes aanvaardbaar
zijn
2 Metingen controleren 5 30
Er voor zorgen dat het
minimale afzuigniveau
voldoende is.
Luchtvochtigheid op
pijl houden
40-60%
Te laagNadelige gevolgen op
welzijn bezoekers3 3 4 36
Afzuigen vochtige
lucht
Geen
effect
Daling van
kwaliteit
Geen
effect
Verslechte
ring3
Geen, word zelfs niet
gemeten3
In bezoekersruimten
zijn geen RV meters
aanwezig.
4 36 Aansturen op luchtvochtigheidEffect versterkt door
centrale verwarming
Teveel droge lucht
naar binnen blazen
Geen
effect
Daling van
kwaliteit
Geen
effect
Verslechte
ring3
Geen, word zelfs niet
gemeten3
In bezoekersruimten
zijn geen RV meters
aanwezig.
4 36 Aansturen op luchtvochtigheid Vooral met koud weer
Koele opslagLuchtvochtigheid op
pijl houden
<40%
te hoogIjsvorming of condens
op tanks6 2 4 48
Droogfunctie van
luchtdroger is
uitgevallen
ToenameGeen
effect
Verslechte
rd
Geen
effect 6
onderhoud aan de
luchtdrogers 2
Melding op een
scherm3 36 Met regelmaat inspecteren
Main labVerwarmen van de
ruimte18-21˚C Te hoog
Nadelige gevolgen
voor micro5 3 3 45
Klep verwarming staat
handmatig open
Grote
toename
Daling van
kwaliteit
Verslechte
rd
Geen
effect 5 Geen 2 Geen 4 40
Regelmatig alle kleppen
langslopen en dichtdraaien.
Onderzoeken of dit
voorkomen kan worden.
Klep verwarming zit
vast
Grote
toename
Daling van
kwaliteit
Verslechte
rd
Geen
effect 5 Geen 2 Geen 3 30
Onlogische temperaturen
nalopen
Buitenlucht klep zit
vastAfname
Daling van
kwaliteit
Verslechte
rd
Verslechte
ring5
Uitlijnen en smeren
van de lagers 2
Melding op het
scherm3 30
Met regelmaat visueel
inspecteren of alles nog naar
behoren werkt.
Luchtverversing2-5 keer verversen
per uurTe weinig Ophoping CO2 5 2 4 40
Alle luchtregisters
naar buiten zitten
dicht
ToenameDaling van
kwaliteit
Verslechte
rd
Verslechte
ring5
Softwarematig
ingesteld dat dit niet
zou moeten
voorkomen
2
Komt er een melding
van, dat een actuator
niet werkt?
4 40
Met regelmaat visueel
inspecteren of alles nog naar
behoren werkt.
0
D
E
T
R
P
N
Actions Recommended RemarksEffect on
product
Effect on
process
Effect on
well-being
S
E
V
Current ProcessEffect on
energy
consumpti
on
Main potential causesBuilding section Function RequirementsPotential Failure
Mode
Potential Effects of
Failure
Analysis of the ventilation system – Jasper Zuurveld 36
12.6 Appendix 6: Photo report (In Dutch) De foto’s zijn geordend in: Binnenkant LBK, luchtbuizen en rooster, leidingwerk HTHW en koeling, aansturing
en overig
Foto Locatie Wat te zien Probleem Oplossing
BV1, LBK1 Aanslag aan de binnenkant van de LBK
Roestvorming door versleten coating en vocht in de kast
Monteur: Nieuwe coating aanbrengen Engineering: Kast laten reviseren door externe partij
BV1, LBK1 Aanslag aan de binnenkant van de LBK
Roestvorming door versleten coating en vocht in de kast
Monteur: Nieuwe coating aanbrengen Engineering: Kast laten reviseren door externe partij
BV1, LBK1 Aanslag aan de binnenkant van de LBK
Roestvorming door versleten coating en vocht in de kast
Monteur: Nieuwe coating aanbrengen Engineering: Kast laten reviseren door externe partij
BV2, LBK6 Aanslag aan de binnenkant van de LBK
Roestvorming door versleten coating en vocht in de kast
Monteur: Nieuwe coating aanbrengen Engineering: Kast laten reviseren door externe partij
BV3, LBK7 Aanslag aan de binnenkant van de LBK
Roestvorming door versleten coating en vocht in de kast
Monteur: Nieuwe coating aanbrengen Engineering: Kast laten reviseren door externe partij
Analysis of the ventilation system – Jasper Zuurveld 37
Foto Locatie Wat te zien Probleem Oplossing
BV3, LBK8 Aanslag aan de binnenkant van de LBK
Roestvorming door versleten coating en vocht in de kast
Monteur: Nieuwe coating aanbrengen Engineering: Kast laten reviseren door externe partij
BV3, LBK8 Aanslag aan de binnenkant van de LBK
Roestvorming door versleten coating en vocht in de kast
Monteur: Nieuwe coating aanbrengen Engineering: Kast laten reviseren door externe partij
BV3, LBK8 Luchtregisters staan maar deels open
De verse lucht moet door een veel kleinere opening. Dit geeft een groter verbruik.
Monteur: Registers afstellen en repareren.
BV1, LBK1 Schimmelvorming in de kast op de druppelvanger die na de twin coil geplaatst is aan de afzuigkant van de LBK
Door de vochtige en warme lucht uit de hal begint er schimmelvorming op te treden
Monteur: Reinigen van de druppelvanger
Analysis of the ventilation system – Jasper Zuurveld 38
Foto Locatie Wat te zien Probleem Oplossing
BV3, LBK7 Wegens lekkages aan het HTHW systeem is de condenswaterafvoer van de LBK losgekoppeld om het water van de lekkage af te voeren
Condenswater blijft in de LBK aanwezig. Ook wordt er nu valse lucht aangezogen via de losgehaalde afvoer.
Monteur: Lekkages HTHW systeem verhelpen waarna de afvoer weer in oude staat herstellen.
BV1, LBK1 Condenswater vormt zich in de LBK. In de winter stroomt de warme vochtige afgevoerde lucht langs een wand met registers waarachter de koude buitenlucht stroomt. Dit geeft condens op de wand en er is geen afvoer aanwezig.
Extreem veel vocht in de LBK. Dit bevordert de groei van schimmels.
Afvoer mogelijkheid toevoegen.
BV1, LBK1 Watervorming door condensvorming in de LBK
Vocht op plekken waar dit niet gewenst is. Corrosie vormt aan de onderkant van de LBK.
Engineering: Onderzoeken of er een afvoer geplaatst kan worden in samenwerking met een externe partij.
Bij meerdere kantoren
De afvoer van condenswater is afgesloten, omdat er rioollucht aangezogen werd. Dit gaf een rioolgeur in de kantoren.
Het condenswater dat zicht vormt in de LBK kan niet afgevoerd worden.
Monteur: Installeren van een nieuwe afvoer waar geen lucht door aangevoerd wordt.
Analysis of the ventilation system – Jasper Zuurveld 39
Foto Locatie Wat te zien Probleem Oplossing
BV1-BV3 Vuile inblaaspatronen van het ventilatiesysteem.
De vieze patronen boven het vullen ziet er niet hygiënisch uit. Zijn klachten van binnengekomen van de bezoekers van de brouwerij tour.
Technische dienst: Reinigen van de inblaaspatronen wanneer er te veel vervuiling op de patronen zit.
BH3 Stofophoping en vervuiling op het aanzuigrooster van de ventilatie van het brouwhuis begane grond en HK2.
Door de stofophoping kan de buitenlucht minder goed naar binnen komen. Vervuiling zal in filters komen.
Technische dienst: Reinigen van de roosters.
BH3 Inzuig van verse lucht brouwhuis en HK2 (rooster links onder) zit dicht bij uitblaas rooster van het brouwhuis (rooster op het dak)
Met een bepaalde wind wordt de lucht en geur van het brouwhuis bij HK2 weer naar binnen gezogen
-
BV3, dak boven afvullijn 7
De afvoer van het vocht van de pasteur voor het aanzuigrooster van de luchtbehandeling.
Er word veel vocht naar binnen gezogen, geeft roestvorming in de kast en hogere luchtvochtigheid in de hal.
Engineering: Zoeken naar een manier om de uitblaas van de pasteur te verplaatsen.
Analysis of the ventilation system – Jasper Zuurveld 40
Foto Locatie Wat te zien Probleem Oplossing
BV3, LBK8, afvullijn 7
Sporen van roest dat met condenswater uit de kast gelopen is.
Door het bovenstaande komt er overmatig veel vocht in de LBK. Hierdoor vorm er roest, wat vervolgens uit de LBK stroomt
Engineering: Zoeken naar een manier om de uitblaas van de pasteur te verplaatsen.
BV1, LBK1 Uitblaasroosters bij packaging zijn vies en zitten vol met schimmelgroei.
Schimmelgroei wil je niet hebben binnen de luchtbehandeling bij packaging.
Monteur: Reinigen van de uitblaasroosters bij packaging
BV2, LBK 5 afzuigkanaal
Vervuiling in de kanalen die de lucht afzuigen bij packaging.
Bij te veel vervuiling moeten de kanalen gereinigd worden. Momenteel is valt de vervuiling nog mee, dus is er nu nog geen probleem.
Monteur: Vervuiling in de buizen blijven controleren.
Aanzuig, alle LBK
Coating die uit de buizen komt aan de kant waar de buitenlucht wordt aangezogen.
De coating die bij het bouwen gebruikt is, was niet geschikt voor het materiaal waar de buizen van gemaakt zijn. Nu laat het los en kan er roestvorming ontstaan.
Engineering: Onderzoeken wat de gevolgen exact zijn en onderzoeken hoe dit probleem opgelost kan worden.
HK5, 1e verdieping
Schone aanvoerbuis van verse lucht. De filters doen hun werk goed.
- -
Analysis of the ventilation system – Jasper Zuurveld 41
Foto Locatie Wat te zien Probleem Oplossing
BV2, LBK5 Schone aanvoerbuis van verse lucht bij packaging. Ook hier doen de filters hun werk goed.
- -
BV2, LBK5 aanzuig buitenrooster
Vervuiling op de aanvoerroosters bij packaging.
De groei van vervuiling kan een kiem zijn voor bacteriën en bij loslaten zal het de filters vervuilen.
Monteur: Reinigen van vervuilde roosters bij packaging.
BV1, LBK1 Emmers zijn opgehangen aan het HTHW systeem om het water van de lekkages op te vangen.
Er zijn lekkages in het HTHW systeem.
Monteur: Het verhelpen van de lekkages.
BV1, LBK1 Er is een emmer geplaatst om het water van de lekkage van het HTHW systeem op te vangen.
Er zijn lekkages in het HTHW systeem.
Monteur: Het verhelpen van de lekkages.
BV1,LBK1 De bovengenoemde maatregelen werken niet voldoende, emmer zit vol en lekkages vinden plaats. Water stroomt over de vloer.
Er zijn lekkages in het HTHW systeem. De maatregelen getroffen zijn niet voldoende.
Monteur: Het verhelpen van de lekkages.
Analysis of the ventilation system – Jasper Zuurveld 42
Foto Locatie Wat te zien Probleem Oplossing
BV1, LBK1 Water stroomt vanaf de lekkages naar scheuren in de vloer waar het vocht in kan trekken. Het vocht trekt in het beton en lekt er door heen naar de verdieping eronder.
Er zijn lekkages in het HTHW systeem. Vocht trekt in de betonnen vloer en lekt er door heen.
Monteur: Het verhelpen van de lekkages.
Regelkasten kolonne 3
Het bovengenoemde water druppelt neer rondom de regelkasten van kolonne 3.
Water en regelkasten gaan niet goed samen. Groot risico tot kortsluiting resulteren in stilstand kolonne 3!
Monteur: Het verhelpen van de lekkages. Voorkomen dat water bij regelkasten kan komen.
Plafond BV1 Door de lekkages zijn de plafondplaten aangetast. Ziet er allemaal niet fris meer uit voor bezoekers brouwerij tour.
Plafondplaten zijn verkleurd door lekkages.
Monteur/installatie bedrijf: Vervangen platen met waterschade.
BV1-BV3 Lekkages bij een afsluiter van het HTHW systeem.
Kleppen worden jaarlijks een aantal keer geopend en gesloten. Door de hoge temperatuur van het water drogen deze kleppen uit en gaan lekken als er aan gedraaid wordt.
Engineering: Bepalen of deze lekkages er zijn. Indien dit het geval is de kleppen vervangen door kleppen die tegen de hoge temperatuur kunnen.
BV1-BV3 Nadat er aan de afsluitkleppen gedraaid is beginnen deze te lekken. Aan sporen op de grond te zien gebeurd dit al jaren.
De afsluitkleppen gaan lekker wanneer hieraan gedraaid wordt.
-
Analysis of the ventilation system – Jasper Zuurveld 43
Foto Locatie Wat te zien Probleem Oplossing
BV1-BV3 Wederom sporen van lekkages door sluiten kleppen. Ook een afgebroken handvat van een afsluitklep.
De afsluitkleppen gaan lekker wanneer hieraan gedraaid wordt. De handvatten breken af.
Engineering/ technische dienst: Nieuwe handvatten/ kleppen installeren.
Alle afsluiters HTHW netwerk
Handvat is afgebroken afsluiters HTHW systeem packaging
Na verloop van jaren op hoge temperatuur beginnen de handvatten af te breken.
Engineering/ technische dienst: Nieuwe handvatten of nieuwe kleppen plaatsen.
Verkleuring isolatie HTHW systeem
De isolatie is verkleurd door de hoge temperatuur van het HTHW systeem.
-
BV1, LBK Main Lab
Tape rondom een nieuw geplaatste pomp van het leidingwerk van de koeling. Bak om lekkages op te vangen.
En is geen nieuwe isolatie geplaatst/ beschikbaar. Lekkages zijn ontstaan door het plaatsen van de nieuwe pomp.
Monteur: Nieuwe isolatie plaatsen. Lekkage verhelpen.
Analysis of the ventilation system – Jasper Zuurveld 44
Foto Locatie Wat te zien Probleem Oplossing
BV1, LBK Main Lab
Isolatie van de leidingen van het koelnetwerk is extreem aangetast.
Isolatie van de leidingen van het koelnetwerk is extreem aangetast.
Monteur: Lekkages verhelpen en nieuwe isolatie plaatsen.
BV1, naast uitblaas LBK 1
Zwart verkleurde thermometer voor de buitenlucht en temperatuur.
Door de verkleuring wordt in de ochtend wanneer de zon erop staat, de temperatuur te hoog aangegeven. De meter geeft een buitentemperatuur aan, maar niet de temperatuur die aangezogen wordt.
Nieuw kapje plaatsen zodat de meting in de zon ook betrouwbaar is. De meter aan de aanzuigkant plaatsen zodat deze informatie geeft over de lucht die aangezogen word.
BV1, op de hoek van jet dak aan de aanzuigkant
Totaal vergaan weerstation. Temperatuurmeter hangt op de kop en de windrichting meter hangt scheef.
De metingen zijn niet meer betrouwbaar, maar de aansturing wordt hier wel op gedaan.
Monteur: Plaatsen van nieuwe meetapparatuur.
HK6.10.06 Thermometer in kantoor Suzan geeft 29.3 graden Celsius aan op een zonnige dag. De meter van het systeem eronder geeft aan dat het 35.6 graden is. Buiten was het rond de 25 graden.
De meter geeft een te hoge waarde aan. De temperatuur loopt binnen te veel op, blijkbaar heeft het kantoor niet voldoende koel capaciteit via de ventilatie.
Monteur: Meter vervangen/ kalibreren. Engineering: Een bedrijf inschakelen die de luchtstroom in HK6 zuid kan controleren en aanpassen.
Analysis of the ventilation system – Jasper Zuurveld 45
Foto Locatie Wat te zien Probleem Oplossing
Bedrijfsuren op computer scherm
De bedrijfsuren van verschillende onderdelen van de LBK bij packaging.
De meters kunnen niet verder dan 10.000 bedrijfsuren. Wanneer dit gehaald wordt, gaat de stand een beetje terug. Daarom is het aflezen van de bedrijfsuren onbetrouwbaar en kan er geen onderhoud op bedrijfsuren worden uitgevoerd.
Engineering: Ervoor zorgen dat de meters de daadwerkelijke bedrijfsuren aan geven. Dit geeft veel inzicht in het gebruik van de LBK.
LBK control room. Meter zit op alle kasten.
Een analoge meter die het drukverschil over de filtersectie meet.
Wanneer deze meters digitaal zouden zijn zouden de filters vervangen kunnen worden p[ het moment dat het drukverschil te groot zou worden. Nu worden de filters klakkeloos ieder jaar vervangen
Engineering: Plaatsen van digitale meters voor het drukverschil. Onderzoeken of aan de hand van het drukverschil de filters vervangen kunnen worden. Voor een test hiermee kan er eerst 1 LBK gedaan worden.
HK6, kantoortuin
Lichtbak voor natuurlijk licht in de kantoren.
De lichtbak is groot en laat daardoor veel warmte door. Hierdoor is het in de zomer niet koel te krijgen met de ventilatie.
Engineering: Onderzoeken of er een mogelijkheid is om het licht door te laten, maar de warmte buiten te laten.
HK6 noord, gang 2e verdieping
Lichtbak die is dichtgemaakt door plafondplaten
Mogelijke oplossing voor bovenstaande. Echter val het natuurlijke licht wel weg.
Engineering: Onderzoeken of dit een oplossing is tegen de warmte in de kantoortuin.
Analysis of the ventilation system – Jasper Zuurveld 46
12.7 Appendix 7: Overview with recommendations (In Dutch) Geordend in prioriteit inclusief tijds- en/of kostenindicatie.
Hoge prioriteit Tijd/Kosten
De kasten in BV1-BV3 hebben de meeste vertoningen van slijtage. Dit komt door de grote hoeveelheid vochtige lucht die door de kasten gaan. Aanbevolen wordt om deze kasten als eerste een grote onderhoudsbeurt te geven, te beginnen bij kast 1.8 en 1.1. De luchtbehandelingskasten van de kantoren zien er allemaal nog goed uit.
Veel
De meters die de condities buiten meten, waarop het hele systeem geregeld wordt, zijn alle 3 verweerd. Het gaat hier 1 maal om een weerstation en 2 keer alleen een temperatuur en relatieve luchtvochtigheidsmeter. Deze geven daardoor gedurende zonnige morgens te hoge temperaturen aan. Deze meters dienen vervangen/opgeknapt te worden.
Redelijk
De uitlaat van de pasteur van lijn 7 zit recht voor in aanzuig van LBK1.8. Dit geeft extreem veel vocht en corrosie binnen de kast. Probeer de uitlaat te verplaatsen.
Redelijk
Start met het opslaan van de gegevens over het ventilatiesysteem. Momenteel kan er niet worden teruggekeken naar wat het systeem gedaan heeft, dit zou wel gewenst zijn om het gedrag te analyseren.
Redelijk
Zorg ervoor dat de alle luchtbehandelingskasten minimaal 1 uur in de week draaien. Momenteel staan er nog een aantal kasten in de brouwerij structureel uit, dit is uitermate slecht voor de kasten.
Weinig
Op meerdere locaties van het HTHW bij packaging systeem zijn lekkages gevonden. Deze lekkages hebben er tot 2 maal toe gezorgd dat er water rondom de regelkasten van de colonnes eronder stond. Zorg ervoor dat deze zo spoedig mogelijk gemaakt worden.
Weinig
In de winter kost het verwarmen bij packaging veel energie. Echter staan het hele jaar door de dakkappen voor 1/3 open, ook als de ventilatie uit staat. Hierdoor gaat er veel energie verloren door het dak. Een betere optie zou zijn om alle lucht door de LBK te laten gaan, zodat er meer energie teruggewonnen kan worden.
Weinig
Bij packaging zijn er een aantal dakkappen die de warme vochtige lucht afvoeren recht voor de aanzuig van verse buitenlucht. Het gaat hier om de kasten met nummer 1, 2, 4, 5 en 7. Onderzoek de mogelijkheid om die vijf dakkappen permanent te sluiten. Dit zal waarschijnlijk een mechanische aanpassing zijn.
Weinig
Matige prioriteit Tijd/Kosten
Vooral bij packaging komt het voor dat de kleppen, die de warmtetoevoer van het verwarmingselement regelen, warm water doorlaten. Dit zorgt voor extra warmtegebruik en te warme temperaturen in de hal. Het advies is om de HTHW leiding automatisch volledig te sluiten als de kasten geen warmte nodig hebben. Deze zullen ook automatisch openen wanneer er vraag is naar warmte.
Veel
Tijdens warm weer krijgt de ventilatie de temperatuur niet laag bij engineering, dit komt door de instraling van warmte van de lichtbak. Om het tijdens de warme dagen (25 graden of meer) relatief koel te krijgen zou er gekeken moeten worden om de instraling van warmte door de lichtbak te verminderen.
Veel
De relatieve luchtvochtigheid binnen de kantoren is structureel te laag. Dit heeft negatieve gevolgen op de gezondheid van de werknemers. Ook geeft dit een lagere gevoelstemperatuur gedurende de winter, waardoor er extra stookkosten zijn.
Veel
Analysis of the ventilation system – Jasper Zuurveld 47
De luchtdrogers staan 24 uur per dag te draaien en gebruiken daarmee veel energie. Er bestaan mogelijkheden om de energie her te gebruiken binnen de luchtdroger. Op de website van Munters is daar meer informatie over te vinden.
Redelijk
De coating aan de binnenzijde van de luchttoevoer van alle luchtbehandeling laat los, dit zal in combinatie met de buitenlucht zorgen voor corrosievorming. Onderzoek de effecten hiervan en onderzoek hoe dit opgelost moet worden.
Redelijk
Een aantal van de dakkappen staat recht voor de aanzuig van verse lucht voor packaging. Onderzoek hoeveel effect dit heeft en of de mogelijkheid er is om deze dakkappen permanent te sluiten.
Weinig
De afvoer van het condenswater van de LBK van een aantal kantoren zijn doorgezaagd en afgesloten omdat er rioollucht aangezogen werd. Deze afvoer zit er echter niet voor niks, dus deze moeten wel weer gerepareerd worden.
Weinig
Lage prioriteit Tijd/Kosten
In LBK1.1 van packaging een keer een vacuüm ontstaan, waardoor de tussenwand met registerkleppen krom is getrokken. Deze wand is weer recht getrokken, maar sindsdien geven de registerkleppen regelmatig storing. Ze zijn al een keer gedemonteerd, zonder effect, dus onderzoek hoeveel het kost om een nieuwe registers te kopen.
Redelijk
Op de 2e verdieping van HK4 zit geen vast personeel. Af en toe worden er vergaderingen gehouden. Het ventilatiesysteem is daarom standaard uitgeschakeld en indien nodig handmatig ingeschakeld. Bij het plaatsten van een bewegingsmelder kan het systeem starten wanneer er langere tijd personen bevinden in HK4.
Redelijk
Met warme dagen is het in de ochtend vaak nog lekker koel buiten. Aangezien het systeem alleen op de buitentemperatuur regelt zal het warme kantoor in de morgen niet echt afgekoeld worden en in de middag juist meer moeten koelen. Onderzoek of de mogelijkheid er is om een temperatuur verwachting in het systeem te importeren en daarop het systeem te laten anticiperen.
Redelijk
De filters vervangen na het stuifmeelseizoen. Na dit seizoen zit er minder stuifmeel in de lucht, dus zullen de filters langer schoon blijven en dus minder energie opnemen.
Redelijk
Wanneer een pomp van het HTHW netwerk defect is komt dit vaak door de waaier die gebroken is. Momenteel word de pomp nu in zijn geheel vervangen, omdat de monteur niet in staat is om alleen een waaier te regelen. Naar verwachting zijn de waaiers wel los te verkrijgen, onderzoek of dit mogelijk is, kan ook hoop bestelkosten van nieuwe pompen schelen.
Weinig
De luchtbehandeling van het brouwhuis stond op maandagmorgen uit, juist wanneer de warmte uit het brouwhuis nuttig gebruikt kon worden voor het aanwarmen van HK2. Deze tijden zijn nu op elkaar afgestemd.
Geen
Analysis of the ventilation system – Jasper Zuurveld 48
12.8 Appendix 8: Self-reflection on the internship at Grolsch Here I want to discuss my personal experience of the internship at Grolsch. While looking back on the
internship I can say that I have learned a lot during my time at Grolsch. It was a great experience,
working in a company with an actual production process. During the internship I was a member of the
engineering team, consisting of around 12 coworkers. Each of the coworkers has his own specific tasks,
making it clear who could give information over specific subjects. I had to consult with multiple people
of different departments and with different education levels. This made my internship very diverse,
being a connection between the mechanic and the engineers at the office.
After the first month of the internship I presented the intermediate results, in order to make sure that
the executed project would met the expectations of my supervisors. In addition to that I had on average
every week a meeting with Rob Leurink to discuss the progress. This was for me a convenient way to
hand over the information as soon as possible. I really appreciated the time Rob had for me. Small
question could be asked directly, cause Rob was located next to me in the so called “office garden”.
These gardens were a sign of the way of working at Grolsch, everyone was very open to each other.
The open garden was for me a good way of connecting to my colleagues. During the internship I started
to have discussions about what I have seen more openly with these colleagues. Also when it was not
about my assignment, but to help them with theirs.
Things I learned:
• Making contact with other companies, in name of Grolsch, and set up meetings with them. In
these meetings I had to be the chairman leading the conversation. This was something I never
experienced on the UT.
• The way of working in a company that is focused on producing and celling beverages. This
includes the focus on the main process and working with capex to improve and maintain the
process.
• Getting the reasonability for a subject and making sure that I deliver work on which Grolsch
could move on and make sure the ventilation will be properly working for the next years to
come.
Improvement points:
• I can be working on my own a lot, which is fine, but for the assignment it could be better to be
more open and discuss about the way I should deliver the work.
• I had a very broad assignment, on which I could spent a lot more time. The result of this is that I
sometimes spend time on things that at the end never will be used. Therefor keeping more
focus on the assignment during the internship will be a learning goal the next time.
• During the internship I was a bit reservedly in discussions with others, this holds also during
presentations. Therefor I should “man up” and get some more personality to improve the way I
made my points.
The next time I have to do an assignment at a company I would like to have an assignment that consist
of optimizing a process. During the time at Grolsch I liked the jobs of Rob and Martin a lot, they were
both optimizing the processes. One the processes at packaging, the other the processes at the utility
building. For future careers I would like to gain an opportunity in this kind of work area.
At the end, it was a great opportunity for me to learn and grow in my experience of working in an
engineering environment. It gave me insight in the way of working I could experience after graduating
for my master mechanical engineering at the University of Twente.