analysis methodologies to replacemrent steam generators · * consulting nuclear project manager,...

46
Application of CPSES Accident Analysis Methodologies to Replacemrent Steam Generators Power October 18, 2005

Upload: others

Post on 17-Apr-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Application of CPSES AccidentAnalysis Methodologies to

Replacemrent Steam Generators

Power

October 18, 2005

Page 2: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

TXU Power Participants *b TX UPower

Dr. Whee Choe

* Safety Analysis Manager

James Boatwright

* Consulting Nuclear Project Manager, Safety Analysis- Steam Generator Replacement Project NSSS Engineering and

Licensing Support Lead

Dr. Hugo da Silva

u Consulting Thermal-Hydraulics Engineer, Safety Analysis

Ben Mays

u Steam Generator Replacement Project Manager

Denny Buschbaum

u Licensing Basis Manager, Regulatory Affairs

2

Page 3: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Agenda t TX Uw40 Power

Purpose of today's discussions

Overview of the Replacement SG Project

a Replacement SG design description

• Operating strategy changes

• Schedules

Background on TXU's analysis capabilities and methods

Application of TXU's non-LOCA transient analysis methods to the RSG

Application of TXU's LOCA analysis methods to the RSG

Concluding discussions

3

Page 4: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Purpose *d TXU"2Power

Familiarize NRC reviewers with TXU Power's LOCA and non-LOCA accidentanalysis methodology topical report supplements supporting TXU's SteamGenerator Replacement Project

Answer questions to facilitate the review process as much as possible

4

Page 5: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Comanche Peak Steam Electric Station (CPSES) ,TXUUnit 1 Power

4-loop Westinghouse NSSS with large dry containment

Part of two-unit site with shared control buildings

Originally rated at 3411 MWth, now at 3458 MWth with MUR uprate

Current SG: Westinghouse D4 with integral preheater

* Alloy 600 SG tubes• Approximately 3% tube plugging level

Replacement SG: Westinghouse L\76 with feed ringa Alloy 690 SG tubes

During same outage (1 RF12 in Spring, 2007), replace reactor vessel upperhead and support structures (missile shield, CRDM cooling ductwork, etc.)

5

Page 6: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Replacement SG Design Features Aft TX U

Westinghouse A76 feed ring design

Similar to A75 design in use at Shearon Harris and V.C. Summer

Relative to D4 SG, the A76 SG has:

* 76,000 ft2 heat transfer area (vs. 48,000 ft2)

* 5532 U-tubes (vs. 4578)

* 3/4" tube OD (same)

* 1.03" triangular pitch (vs. 1.0625" square pitch)

* Top of tube bundle 8 ft higher

* Separate Main feedwater and auxiliary feedwater piping nozzles- Eliminates delay time for purging AFW lines of hotter MFW fluid

6

Page 7: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Replacement SG Design Features TX UPower

Relative to D4 SG, the A76 SG has:

* Essentially the same exterior envelope

* 5330 ft3 Shell-side volume (vs. 5954 ft3)

* Increased Tube Side Volume- Approximately 825 ft3 additional RCS volume- ~8% increase

* Circulation Ratio of - 4 (vs. .2.4)* Slightly larger secondary fluid mass

* 251" narrow range water level span (vs. 233")

7

Page 8: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Replacement SG Design Features A*d TXU'"I Power

D4 SG

A76 SG -Walef Plenum

Hot Leg Cold Leg

8

Page 9: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Replacement SG Design Features

Elevated feedring with top discharge nozzles

Nozzle holes sized to trap loose parts* Hole diameter less than tube to tube clearance

ll XI S*TOP DISCHARGESPRAY NOZZLE

12 TXUPower

I .

A)--- . .P

I . . I.

A.;-,fl ;S...

9

Page 10: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Replacement SG Feedwater Distribution Ring *"' Power

(II=nnonno nn 0nnno n

10

Page 11: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Operating Strategy Changes Power

Generically, design for a Tavg range of 589.20F to 574.20F

Limit Steam Pressure to 1000 psia

* Initially, set full power Tavg - 5850F @ 3458 MWth

* Raise Tavg toward 589.20F as SG heat transfer capability decreases (dueto fouling or tube plugging)

Design to a much tighter Tavg range (e.g., ±1 OF) on cycle-specific basis

Lower values of Tavg are intended for future use in Tavg coastdown

11

Page 12: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Schedules

March 2007

Supporting Milestones:

January 2005

October 2005

November 2005

March 2006

May 2006

February 2007

Power

Steam Generator Replacement Outage Begins

Submit Topical Report Supplements

Significant "N-1" SGRO prep work during I RF1 I

Submit required changes to the Tech Specs

NRC approval of Topical Report Supplements

Submit any License Amendments identified through1 OCFR50.59 Evaluations

NRC Approval of RSG-related licensing actions

12

Page 13: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Background on TXU's Analysis Capabilities PoweU

TXU developed in-house core design and safety analyses methodologies

* CASMO/SIMULATE core design methods

* RETRAN/VIPRE non-LOCA transient analysis methods

* LOCA analysis methods derived from Siemens Power Corp. methods

Topical Reports reviewed and approved by NRC

* First topical report approved in 1988

* All were approved by 1993

Used to support 15 reload core configurations for Comanche Peak SteamElectric Station

Expertise and models applied to a wide variety of plant support issuesincluding IPE/PRA success criteria, startup testing, simulator qualification,design modification evaluations, resolution of emergent issues, etc.

13

Page 14: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Background on TXU's non-LOCA Analysis TxUMethodsCurrent Non-LOCA methods:

R)(E-89-002-A, "VIPRE-01 Core Thermal-Hydraulic Analysis Methods forComanche Peak Steam Electric Station Licensing Applications"

RXE-91-001-A, "Transient Analysis Methods for Comanche Peak SteamElectric Station Licensing Applications"

RXE-91-002-A, "Reactivity Anomaly Events Methodology"

TXX-88306, "Steam Generator Tube Rupture Analysis"

RXE-91-005-A, "Methodology for Reactor Core Response to SteamlineBreak Events"

RXE-94-001-A, "Safety Analysis of Postulated Inadvertent Boron DilutionEvent in Modes 3, 4, and 5"

14

Page 15: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Background on TXU's non-LOCA Analysis Po TxUMethodsEach topical report was individually reviewed and approved; however,...

Through the RAI process, the scope of RXE-91-001-A came to include thegeneralized non-LOCA accident analysis methodology

Now consider RXE-91-001-A to be the "umbrella" non-LOCA topical report

To address generic activities such as the replacement SG, consider asupplement to RXE-91-001-A to be appropriate

15

Page 16: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Background on TXU's non-LOCA Analysis TPowxeMethodsCurrently licensed approach to SG models:

* Single-node model used in SGTR and SLB analyses

• Three-node model used in other non-LOCA analyses- Internal recirculation loop is not modeled

* Detailed, multi-node model used to determine mass equivalency forsimulating SG water level trip functions

Coarsely-noded model justified through comparisons of integrated systemresponses to CPSES transient data

16

Page 17: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Background on TXU's non-LOCA AnalysisMethods

Any Questions or Comments?

M TXwUByPower

17

Page 18: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Application of TXU's non-LOCA transient Por TXUanalysis methods to the RSG Power

During initial RSG project planning, all topical reports reviewed to assesseffects of RSG on approved analysis and model methods

X Analysis and modeling methods remain applicable

• For those analyses which are relatively insensitive to the SG model, stillrequired to update SG model with replacement SG geometrical attributes

* For those analyses which show some sensitivity to the SG model, requirea different SG model (preheater vs. feed ring)- Conforming modifications to SG water level trip functions

Also assessed the effects of the replacement SG on the course of transientsand accidents

Only feedwater line break has any relevant differences- Due to elevated feed ring, early transient response similar to steam line

break

18

Page 19: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Application of TXU's non-LOCA transientanalysis methods to the RSG

Pwer TXU

Due to extensive discussions ofdecision made to submit topicalapproved TXU methods to feed

preheat SG design in RXE-91-001-A,report supplement to describe application ofring SG design

Current methods will continue to be used to support Unit 2

1.9

Page 20: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Topical Report Supplement PowXeU

ERX-04-005, "Application of TXU Power's Non-LOCA Transient AnalysisMethodologies to a Feed Ring Steam Generator Design"

ERX-04-005 supplements the approved TXU non-LOCA transient analysismethodology topical reports (via RXE-91-001-A)

Included in the supplement:

* Assessments of effects of the replacement SG on the transient-specificmethodology

* Identification of new models required for specific analyses

• Assessment of transients with different phenomena or sequence of events

* Demonstration analysis of the feedwater line break accident

20

Page 21: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Assessments of effects of the replacement SGon the non-LOCA analysis methodologyGeneral analysis methodology remains applicable

Po TXUv44l-"r Power

For each transient or accident:

a Ensure important phenomena are modeled

a Identify conservative initial conditions and equipment performancecharacteristics for each relevant event acceptance criterion

* Consider loss of offsite power where required

a Identify limiting single active failure

21

Page 22: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Identification of different required models Ad TXUPower

Generically:a Modify coarse-node SG to remove preheater (if previously modeled)

* Update model to reflect replacement SG geometry

Feedwater line break (FLB) - specific

* Replacement SG blowdown is predominantly steam (vs. liquid for D4 SG)

* Necessitates a different SG model

22

Page 23: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Assessment of transients with different il TXUphenomena or sequence of eventsOnly feedwater line break identified as different

FLB with a preheat SG:

• Initially, saturated liquid blowdown through preheater box with integralflow restrictors in the feedwater nozzle

* Essentially, the SG inventory is being drained

* Relatively little heat removal due to low-quality fluid discharge

FLB with a feed ring SG:

* Short duration of saturated fluid relief through flow distribution nozzles andinto the feed ring, exiting the SG through a nozzle with no flow restrictors

* Once flow distribution nozzles uncover (very quickly in accident),saturated steam blow down (similar to steam line break)

* After inventory is exhausted, heatup is similar to preheat SG, but greaterRCS cooldown has previously occurred

23

Page 24: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

SG model changes tP-4 TXUPower

For FLB analyses, chose to adopt feed ring SG model developed byWestinghouse* Relatively detailed model including the internal recirculation loop• Based on RETRAN-02

* Benchmarked against plant data* Model methodology reviewed and approved by NRC

- WCAP-14882-P-A

• Widely used by Westinghouse• Demonstrated to be robust through internal testing

Noding diagram is contained in WCAP-14882-P-A (Westinghouseproprietary)

For configuration control convenience, chose to use this model for all non-LOCA transients and accidents except for SGTR and SLB

24

Page 25: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

SG water level model changes TX UPower

For the LOAC and LOFW analyses, detailed vendor design information usedto assess the mass equivalency for the SG water level -low-low trip functions

w Essentially the same as current practice for determining mass equivalency

For the FLB analysis, SG water level indication based on AP betweeninstrument tap locations

Corrected for limitations of the model- Lower tap is near bottom of a homogenous volume, which results in an

artificially high mass between tap elevations

Approach is essentially the same as that currently used with TXU'sdetailed SG model when determining the mass equivalency for thecoarsely-noded SG model

25

Page 26: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

RSG Feedwater line break T) TXUPower

Due to early uncovery of elevated feed ring, early transient response similarto steam line break

The RSG feedwater line break event results in:* Initial cooldown as faulted SG depressurizes* Subsequent Reactor Coolant System heatup due to degradation of heat

sink* Ultimate mitigation when auxiliary feedwater flow is sufficient to remove

decay heat

Limiting single failure remains in the Auxiliary Feedwater System where:* One motor-driven auxiliary feedwater pump is assumed to feed only the

faulted SG, with no credit for heat removal* The second motor-driven auxiliary feedwater pump (feeding two intact

SGs) is the assumed single failure* The turbine-driven auxiliary feedwater pump requires a steam generator

water level -low-low signal in two or more SGs to start

26

Page 27: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

RSG Feedwater line break PoeTXU

For larger break sizes, the rapid steam pressure decrease leads to earlysteam line isolation and safety injection actuation

u Significant delay in obtaining 2nd steam generator water level - low-lowsignals from intact, isolated steam generators

For smaller break sizes, the low steam pressure setpoint may not be reachedfor several minutes, but MFW can still be delivered to intact steam generators

a Loss of heat sink effects bounded by maximum break size

27

Page 28: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Feedwater line break - Comparisons to D4analyses Power

7000

6000

I 5000-J

tu

' 4000

o 3000LA.

20000:

100

100 1000

TIME (SEC)10000

1.0

0.8

O 0.6

0-JLAI 0.4

0.2

0.0

10 100 1000

TIME (SEC)10000

28

Page 29: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Feedwater line break - Comparisons to D4analyses

a TXUw412 Power

120000

100000

-J

cn 80000En

C) 60000U)aw6, 40000ALLL

< 20000

0 100 200 300 400

TIME (SEC)600 600 700

2600

to 2400

" 2200UJw

0:W 2000N

U)t3 1800

a1

160010 100 1000

TIME (SEC)

10000

29

Page 30: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Feedwater line break - Comparisons to D4analyses

, TXwU

Z 1400V-(, 1200wcc

3 1000n

U)LU

W 800

0I-600

(9Z 400

F 200

en 0

10 100 1000

TIME (SEC)10000

30

Page 31: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Summary of non-LOCA Topical Report < TXUSupplement Power

Descriptions of original and replacement SG designs and characteristics

Assessments of the effects of the replacement SG on the approved non-LOCA accident analysis methodologies

Discussion of the replacement SG model

Description of the revised feedwater line break analysis methodology

* Including comparisons of sample analysis results to results with originalSG

31

Page 32: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

RSG Supplement to TXU'sLOCA Methodologies

Power

Hugo C. da Silva

October 18, 2005

Page 33: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Purpose: T X U

Familiarize NRC Reviewers with TXU's LOCA Topical ERX-04-004 entitled:

"Replacement Steam Generator Supplement to TXU Power's Large andSmall Break Loss-of-Coolant Accident Methodologies"

TXU already has NRC-approved ECCS Evaluation Models for Large andSmall Break LOCA- TXU is requesting that this topical be considered as a supplement to

be applied only to Unit 1 with the Replacement A-76 SG's* The methodology changes proposed are simply due to the new RSG

design- The existing NRC-approved methodologies will continue to be applied

unchanged to Unit 2 with the current D-5 SG's

33

Page 34: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Approach: TXUPower

* A differential approach was adopted for the Topical Report.- Only the methodology changes are presented. The unchanged parts

of the methodology are not repeated. The changes are those requiredby the new RSG design.

- This approach was intended to streamline the topical and its review.- This approach also avoids the need to make portions of this topical

proprietary by referencing proprietary figures and statements inpreviously NRC-approved topical reports.

* Still, this Topical Report includes a complete set of demonstrationanalyses for both Large Break and Small Break LOCA.- The demonstration analyses have the same scope, i.e., include all the

same relevant sensitivities, as the analyses submitted to the NRC withthe original methodologies.

34

Page 35: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Affected Elements: g& TXUPower

i Small Break LOCA- Only the system thermal-hydraulic response was potentially affected.

Therefore, the ANF-RELAP input was the only thing changed.

* Large Break LOCA- Only the system thermal-hydraulic response was potentially affected.

Thus, only RELAP4 and REFLEX inputs were affected.

35

Page 36: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

LBLOCA (RELAP4 & REFLEX) Model Changes: aft TXUv44sW Power

a Replaced existing steam generator geometry with A-76 geometry- The existing nodalization structure was preserved.

* The Large Break remains the LIMITING LOCA

36

Page 37: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

LBLOCA Demonstration Analyses: AM TXUv',ZV Power

• Break spectrum (required by Appendix K)- 3 Split breaks cases were run (A = 2.0, 1.6 & 1.0 x Cold Leg Area).- 3 DEG breaks cases were run (CD = 1.0, 0.8 and 0.6).

* CD = 1.0 was limiting and became the "Base Case"

* Single failure- Loss of I ECCS train vs. Loss of 1 train of LPI (RHR)

* Loss of 1 train of RHR was limiting

* Convergence criterion (Optional)- Varied RELAP4 convergence criterion, ESPW = 0.5 -> 0.25

* Little difference between cases, shows robustness.

37

Page 38: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

LBLOCA RSG A-76 vs. D-4 Results: * TXUPower

* Effect of SG type on LBLOCA response is predictable and small

- PCT occurs slightly earlier in the A-76 than in the D-4* This is due to the larger RCS volume inventory in the A-76, which retains

more water at the end of blowdown and therefore quenches sooner.- As a result, the PCT is lower in the A-76 than in the D-4.

- Sensitivities lead to the same conclusions in the A-76 and the D-4* Break Spectrum: DEG break with CD = 1.0 remains limiting* Single Failure: Loss of 1 train of RHR remains limiting

• LBLOCA remains limiting with respect to SBLOCA

38

Page 39: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

SBLOCA (ANF-RELAP) Model Changes: Ai, TXU" Power

a Replaced existing steam generator geometry with A-76 geometry- The existing nodalization structure was preserved.- No MFW "purge" flow in the RSG. Might impact loop seal clearing.

* Minor change in the upper downcomer (Fig. 2.3 of RXE-95-001-P-A)- Combined previously-split volumes to improve robustness

39

Page 40: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

SBLOCA Demonstration Analyses: *o> TXUv4~FPower

* Break spectrum (required by Appendix K)- 3 inch, 4 inch and 5 inch breaks were run.

* 4 inch was limiting and became the "Base Case"

* Cross-flow sensitivity study (required by Methodology)- Same as in previous topical report (RXE-95-001-P-A).

* Study was performed for the "Base Case" .* Little difference from varying the X-flow K. Nominal "K" was limiting.

* Time step sensitivity study (optional)- Only required by the methodology if certain criteria are met. They were

not. However, this study was performed anyway.* Study was performed for all break sizes.* Little difference between cases, shows robustness.* Selected time step was limiting.

40

Page 41: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

SBLOCA RSG A-76 vs. D-4 Results: A-MV. owTXU

• Break Spectrum (Required by Appendix K)- 4 inch limiting for A-76 whereas 3 inch limiting for D-4.

* This is due to differences in transient liquid distributions, consistent with theA-76's larger RCS volume & taller tube bundle

* Cross-flow sensitivity study- Similar conclusions to previous (D-4) topical report:

* Nominal K remains more limiting than 1 OxK and K/1 0* Differences between results varying K were not significant

* Time step sensitivity study- Similar conclusions to previous (D-4) topical report:

* Differences between results varying time step were not significant.* Selected time step remains limiting

41

Page 42: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

SBLOCA RSG Break Spectrum Results:v46-) TPower

CPSES-1 SBLOCA D76 RSG - 4-Inch Break14.0

- 12.0

> 10.00

la 8.00tn, 6.0

° 4.0

2.0

0.0

-k. __ __I__W"-% L

-F

+

2000.0

C1800.09.-E 1600.0

E 1400.00.E 1200.0

la 1000.0coO 800.0

x 600.0

400.0

CPSES-1 SBLOCA D76 RSG - 4-lnch Break

I TEPW-ll I --

_ttTIEUP 129tat$2Gt 1

HllEUP 129tt0t30St {\

- IX k__g- I e-

0 500 1000

Time (sec)

0 5001500 2000 1000

Time (sec)

1500 2000

14.0

12.0

t 10.00-j.O 8.00

,l- 6.0

C 4.0

2.0

0.0

CPSES-1 SBLOCA D76 RSG - 3-Inch Break

- 1 _ I_I

. k /I

2000.0

- 1800.0UI.

. 1600.0

P 1400.0

E 1200.0

'a 1000.0

t 800.0

600.0

400.0

IF -IItMUP 129101108

-KHrMMP 129101208

HTIEmP 129101308

. HTIEMP 12910140

CPSES-1 SBLOCA D76 RSG - 3-Inch Break

-II , _ . -

KI__I~ IiL L

0 500 1000

Time (sec)

1500 2000 0 500 1000

Time (sec)

1500 2000

42

Page 43: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

SBLOCA RSG X-Flow & Time Step Sensitivities:

CPSES-1 SBLOCA D.76 RSG - 4-Inch Break - XfMow Study

* TXUv'40%y Power

2000.0

1800.0

1600.0

c1400.0C

e 1200.0

E 1000.0a)

E 800.0C)F 600.0

400.0

200.0

0.0

0 200 400 600 800 1000

Time (sec)1200

CPSES-1 SBLOCA D-76 RSG - 4-inch Break - Time Step Study2000.0

1800.0

1600.0

C-1400.00I

- 1200.0

E 1000.0as

E 800.0cQ

F 600.0

400.0

200.0

0.0

I I I I ,.

__._ I

+

0 200 400 600Time (sac)

800 1000 1200

43

Page 44: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

LOCA Overall Conclusions ,TXpoTXUPower

For BOTH the Large and Small Break LOCA:- Only system thermal-hydraulic response was potentially affected

* RELAP4 and REFLEX SG input change for LBLOCA* ANF-RELAP SG input change for SBLOCA (downcomer node change)

- A complete set of demonstration analyses was performed* LBLOCA PCT occurs sooner and is lower in the A-76 vs the D-4

- Larger RCS volume -÷ higher post-blowdown lower plenum inventory* SBLOCA limiting break 4 inch in the A-76 vs 3 inch in the D-4

- A-76's larger RCS volume & taller tube bundle -* differences in RCStransient liquid distributions

* All Other SBLOCA and LBLOCA analyses show similar trends andconclusions in the A-76 as in the D-4

- The proposed methodologies are essentially the same as thosepreviously approved and extensively used for both CPSES units withModel D SGs

44

Page 45: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

General Discussions ovE TXUPower

Any Comments or Questions?

45

Page 46: Analysis Methodologies to Replacemrent Steam Generators · * Consulting Nuclear Project Manager, Safety Analysis - Steam Generator Replacement Project NSSS Engineering and Licensing

Summary 6<& TXUPower

TXU Power's non-LOCA and LOCA analysis methods have been reviewedand approved by the NRC

Analysis methods have been applied to support 15 reload core configurationsfor CPSES since 1993

Similar methods and models have been used extensively for a variety ofplant-support applications

TXU engineers are well-versed in the use of these tools, which provide goodrepresentation of the design and operation of CPSES

Extending the application of these methods to feed ring SG design

Assessed the continued applicability of the methods

Updated models where appropriate

Continue to apply same proven methods and modeling approaches to RSG

46