an over view of the high rise buildings
TRANSCRIPT
AN OVER VIEW OF THE HIGH RISE
BUILDINGS
BY
N.KRISHNAM RAJUADVISOR TO APHB
Introduction
In Metropolitan Cities , where the pressure on land is rapidly Increasing due to rapid growth of industry and trend towards Urbanization, vertical expansion is the only answer.
Multi storeyed buildings lead to greater co
ordination Between various departments and their
efficient functioning. General principles of planning and design of multi
storeyed have been discussed.
Generally Building Construction is Classified as :
1. Load Bearing
2. RCC Framed
3. Composite Structure
What is a Project ?In simple term project is one temporary activity with a clear start and a end
The main elements are
1. Time2. Cost3. Resources4. Clear roles and responsibility5. Delivery
Detailed Design :1. Develop detailed design from approved scheme
design.
2. Detailed design will confirm type of construction, quality of materials and standard of workmanship.
Specifications :
Prepare detailed information including
Drawing Schedules
Specification of Materials
Workmanship
Design :
1. Evaluation of design requirements2. Review of compatibility of the design with the plan and
budget.3. Identification of design objectives, design stages, activities
and elements.4. Regular Monitoring of the design development.5. Identification of proposed design changes and their
resolution.6. Assessment of design progress related to the design
schedule.7. Evaluation of as to the completeness of construction
information.8. Review of sample materials and mock ups for compliance
with specifications.9. Identification and arrangement of the final standard of
acceptance of the construction..
Civil Engineering Comprises of
Planning
Design
Construction
Quality Control.
The Main components of Buildings are :1. Earth Work :
1. Excavation of Foundation. 2. Filling in Foundation3. Filling in Basement.4. Open and Pile Foundation
2. Section : Concrete3. Section : Brick masonry / Stone masonry 4. Section : Flooring5. Section : Roofing and Ceiling 6. Section : Plastering, Painting.7. Section : Wood Work8. Section : Structural Steel Work.9. Plumbing Services.10.Miscellanies.
PLANNING
RCC Frame Structures :
1. Generally buildings are constructed in two categories.
2. Framed Structure usually built with column and beam and in filled brick walls.
3. Load bearing structure is usually built with 1 ½ brick thick both for external and internal walls.
The Design of a structure presents two told problems :
1. If has to be so constructed that it serves the need efficiently for which it was intended (Functional design)
2. It has to be strong enough to resist the loads and forces to which it is subjected during its service (Structure design)
The important aspects in the structural design are
1. To determine the loads / forces which the frame work will be required to support.
2. Selection of a suitable structural arrangement and materials of construction.
3. Analyzing the internal stresses in the frame work.
4. Proportioning the members of the frame work.
General Design Consideration :
1. Aim Design :
To provide a safe and economic structure complying to the users requirement.
2.Method of Design :
Structure and structural elements shall normally be designed by limit state method.
Mix design with suitable materials, quality control, adequate detailing and good super vision are equally important.
3. Durability, Workmanship and Materials :
1. Quality of concrete, steel, other materials, workmanship, should be adequate for safety, serviceability and durability.
Type of Construction
1. Load bearing (up to 1 or 2 floor)
2. Reinforced frame (RCC)
3. Composite construction For High rise structures
4. Steel framed construction
5. Concrete walls (shear walls) structures.
4. Choice of mix
Based on the No. of floors and flexural stresses for Beam, slabs and footing and predominant stress in compression for column members.
5. Preliminary design of RCC frame :
For fixing up of tentaive sizes of members of the frame.
6. Detailed design of RCC Frame :
By adopting loads & stresses including seismic forces, giving sectional properties and material properties,. Analysis and design of entire framed structure can be evaluated
FOUNDATIONS
Sub Soil Exploration and Sampling
Adequate knowledge of the sub soil characteristics for safe and efficient design of foundation.
The basic aim of a sub soil exploration is to obtain the strata grapy and physical properties of the soils underlying the site.
Location of ground water level.
Methods of Tests :
1. Open Test : Suitable for shallow depth.
2. Boring : Suitable for deep exploration (like tube, Augur borings) 3. Sub surface sounding.
Geophysical Methods.
1. The samples collected should represent the nature of subsoil.
2. S.B.C. of soils shall be arrived based on shear parameters as per the relevant IS Code – 6403 – 1981.
3. Also necessary to conduct standard penetration test (or) plate bearing test to assess the safe pressure with regard to settlement.
4. The settlement aspect is to be examined carefully in the case of clayey soils.
Foundations :
Depth of foundation is to be decided based on the soil strata from the trial pits / explorations conducted.
Foundation are normally placed below the ground surface.
The purpose of providing a foundation is to distribute the load over a layer area at a uniform rate so that the pressure does not exceed the allowable bearing capacity of soil below :
Objects of Foundations :
Foundations are provided for the following purposes.
1. To distribute the total load coming on the structure on a large area so as to bring down the intensity of load at its base below the safe bearing capacity of the sub – soil.
2. To support the structure.
3. To give enough lateral stability to the structures against wind, rain, earthquake, etc.
4. To prepare a level and hard surface for concreting and masonry work.
5. To transmit the superimposed loads through side friction and end bearing in case of deep foundation
6. To distribute the non-uniform load of the superstructure evenly to the sub-soil.
7. To provide structural safety against undermining or scouring due to animals, flood water etc.,
8. To prevent or minimize cracks due to movement of moisture in case of weak or poor soils.
Foundation :
1. Engineers need to know the character and magnitude of forces in order to design and contact structures.
2. One has to study the system of soil below the earth surface at various levels under ground depending upon the past experience.
3. Repairs to foundations are expensive. Structures should be founded an stable soils.
4. Certain soil deposits wherein wetting of the soil beyond a stress level causes steep reduction in stiffness resulting from disruption of soil structure.
5. Subject to rate of loading, disruption in soil structure takes place at a faster pace than the development of new structural bonds which Leeds to vertical deformation at locations of high stress due to disturbance of soil structures.
6. Problems associated with foundation in clay soils are well known.
7. Swelling clays create large uplift forces on the peripheral walls during rainy season. A reverse situation may arise at region of moderate rainfall when the central region of a building founded on clay soil is prone to swelling during dry spells.
A. Differential settlement due to unconsolidated fill.
B. Differential settlement due to uplift of shrinkage soil, shrink and expand with changes in moisture content.
C. Vertical and diagonal cracker are noticed on external walls.
8. The problem of dampness in buildings requires a systematic
approach to determine the causes of leakage, the source
from which the moisture is derived and measured which are
likely to prove effect ion.
TYPES OF FOUNDATIONS
DETAILING OF FOOTINGS
PILE CAP
PLAN
STARTER BARS
TOP BARS
HORIZONTAL BARS
PILE
CLEAR OVERHANG
100 TO 150
STIRRUPS
SECTION 1-1
BOTTOM BARS
CONCRETEGrades : The Concrete shall be designated as follows :
Group Grade (1) (2)Ordinary M 10Concrete M 15M 20Standard Concrete M25, M 55High Strength M60, M 65Concrete M 70, M 75, M 80
NoteIn the Designation of Concrete M refer to mix and the number to specify compressive strength of 150 MM size cube at 28 days expressed as N/mm2
Workability Of Concrete :The concrete shall be of adequate workability for the placing condition of concrete and can be properly compacted.
How to Achieve Durable Structures :1. The structure should also be designed for
environment loads and detailing done.2. Selection of construction materials.3. Concrete should be impermeable.4. Good construction practices should be followed.5. Planned maintenance.6. Proper specifications.
Durability of Concrete :
1. The materials and mix proportion specified and used should be such as to maintain in integrity to protect embedded steel from corrosion.
2 One of the main characteristics Influencing the durability of concrete is the permeability to the ingress of Water, Oxygen, Carbon Dioxide and Other Deleterious Substances.
3 Impermeability is governed by the constituents and workability used in making the concrete
Factors Influencing Durability :
(a) Environment
(b) Cover to embedded steel
(c) Type and quality of material used
(d) Cement content / W.C.R. of concrete
(e) Workmanship to obtain full compaction and
efficient curing
(f) Shape and size of the member
Exposure Condition :
(1) Mild
(2) Moderate
(3) Severe
(4) Very Severe
(5) Extreme
Production of Concrete :
1. Quality assurance measures are both technical and organizational. The job of quality control and quality assurance would involve quality audit of both inputs as well as outputs.
Inputs OutputsMaterial for Concrete – Concrete in
PlaceWorkmanship in allStages of Batching, Mixing,Transportation, Placing, Compaction, Curing etc.,
Batching :
In Batching Concrete, quantity of both cement and aggregates shall be determined by mass.
R.M.C. :
As per IS 4926Volume batching may be allowed only where weigh batching is not practical.
Form Work :
1. The form work shall be designed and constructed so as to remain sufficiently rigid during placing and compaction of Concrete and to prevent loss of slurry from the concrete.
2. For details regarding design, detailing etc., reference may be as per IS 14687
3. Cleaning and treatment of form workThe face of form work in contact with concrete shall be cleaned and treated with form release agent.
4. Stripping timeForm shall not be released until the concrete has achieved a strength of at least twice the stress to which the concrete may be subjected at the time of removal form work. Details may be as per IS 456 – 2000.
Assembly of Reinforcement :
1 Reinforcement shall be bent and fixed in
accordance with procedure (specified in IS
2502)
2 Bar bending schedule shall be prepared for
all reinforcement work.
3 Reinforcement shall be placed and
maintained in the position shown in the
drawings by providing proper cover blocks,
spaces, supporting bars etc.,
Welded Joints : In reinforcement may be used in accordance with IS 2751 and IS 9417.
Placing Compaction :
1. The concrete shall be placed and compacted before initial setting of concrete commences and shall not be subsequently disturbed.
2. Concrete shall be compacted using mechanical vibration complying with IS 2505, IS 2506, IS 2514 and IS 4656.
3. Over vibration and under vibration of concrete are harmful and should be avoided.
Expansion Joints :
To allow variations in
temperature, expansion joints
in Frames are essential,
normally @ 45meters length be
provided.
TYPICAL EXPANSION JOINT
(REINFORCEMENT DISCONTINUOUS
AT JOINT)25mm WIDE EXPANSION JOINT
FOOTING
Contd…
TYPICAL EXPANSION JOINT
FILLED WITH SEALENT
25mm WIDE EXPANSION JOINT
(REINFORCEMENT DISCONTINUOUS
AT JOINT)
Construction Joints :
1. To comply with IS 11817 to be provided at accessible location to permit cleaning.
Curing :
1 Curing is the process of preventing the loss of moisture from concrete.
2 The prevention of moisture loss from concrete is particularly important if the water cement ratio is low.
CONSTRUCTION JOINT IN FOOTING
- INDICATES DIRECTION OF CONCRETING
PROVISION OF KICKER IS OPTIONAL
CONSTRUCTION JOINT IN COLUMN
- INDICATES DIRECTION OF CONCRETING
Contd……
CONSTRUCTION JOINT IN COLUMN
- INDICATES DIRECTION OF CONCRETING
Contd…
CONSTRUCTION JOINT IN SLAB
- INDICATES DIRECTION OF CONCRETING
CONSTRUCTION JOINT AT BEAM - COLUMN
JUNCTION
- PERMITTED ONLY WHEN
CONCRETING OF
TAKEN UP IMMEDIATELY
AFTER CONCRETING
- INDICATES DIRECTION
OF CONCRETING
A
B
CONSTRUCTION JOINT AT BEAM - COLUMN
JUNCTION
- INDICATES DIRECTION OF CONCRETING
PERMITTED ONLY WHEN
1. SHEAR RESISTANCE OF CONCRETE IS NEGLECTED.
2. INTERFACE TREATED AS HIGH IN THE DESIGNS AND
3. ADEQUATE DEVELOPMENT LENGTH OF PROTRUDING REINFORCING BARS ENSURED.
- INDICATES DIRECTION OF CONCRETING
CONSTRUCTION JOINT AT BEAM - COLUMN
JUNCTION
TYPICAL CONSTRUCTION JOINT IN ONE-WAY SLAB
PLAN
Contd……
CROSS SECTION - TYPICAL
Contd…
TYPICAL CONSTRUCTION JOINT IN ONE-WAY SLAB
1. Moist Curing :
Exposed surfaces of concrete shall be kept
continuously in a damp or wet condition by
ponding or by covering with a layer of sacking,
Canvas etc., for at least 7 days from the date of
placing of concrete in case OPC and 10 days where
mineral admixture / blended cement are used shall
not be less than 10 days for concrete exposed to dry
and hot weather condition
2. Membrane Curing :
Approved curing compound may be used in lieu of
moist curing. Impermeable membrane such as poly
ethylene sheet covering closely the concrete surface
may be used to provide effective barrier against
evaporation.
3. Supervision :
Constant and strict supervision of all the items of
construction is necessary during progress of work.
WALLS :External Walls :
In framed construction, the function of external filler wall is to provide adequate weather protection.
Internal Partition Walls :The Function of Internal Walls is to divide Floor space.
External Finishing1. Generally framed construction with brick filler
walls the external plastering is likely. to crack at Junction of RCC and masonry work.
2. Better to provide chicken mesh at Junction for producing effective bond.
I. Water Supply in Multi Storage Building
Water Supply for :
1. Drinking purpose .
2. Water Closets, Wash Basin.
3. Kitchen, Canteen
4. Fire Fighting
5. Air Conditioning
6.Horticulture Purpose.
II. Sanitary Installation
A Common shaft should be provided for taking all water supply drainage, soil and vent pipes from all water closet room.Sanitary installation should be provided as per IS1172.
III. Drainage Problems :
In Multi Storeyed Building
A. Drainage of the roofB. Drainage of Basement C. Water Proofing of roofs D. Planning for materials E. Norms for room
IV. Air Conditioning of High Rise Buildings
Two Main Types of Air Conditioning Plant.
1. Evaporation Type :
Work on principle of evaporative cooling.
2. Refrigeration Type :
Producing rigid Controlled condition of temperature, humidity.
V. Electrical Lift
Number and location of lifts have to be fixed according to functional requirement of building.
Medium Speed : For 6 to 10 Stages.High Speed : For taller Building.
Details of lift, dimension of lift wall, Lift pit, Machine room have to be essential.
VI. Fire Safety in Multi Storyed Office Buildings :
a. Fire hazard is a a major problem.
b. Niches should be provided on all floors to house the fire fighting equipment.
c. Automatic fire extinguisher devises to be installed; including in door hydrant on each floor.
d. Hydrant should be centrally located.
e. Automatic fire alarm systems are necessary for safe evacuation of the population.
VI. Fire Escapes (IS 1644) :
To assist in quick evacuation of the population of building when on fire.
Types of Constructions :
a. Fire Escapeb. Spiral stairsC. Ladders
C. Ladders
1. All types should be mounted on the outside of building and have direct connection with ground.
2. Materials used to conform IS 1642.
3. Entrances to external escapes should be quite separate.
4. Route to External Escape should be free from any obstruction.
RESIDENTIAL
COMPLEXES