an innovative and automated solution for prc...
TRANSCRIPT
AN INNOVATIVE AND AUTOMATED SOLUTION FOR PRC-027-1 COMPLIANCE
Joe Perez, P.E.Founder - Protection Engineer
SynchroGrid
Luke HankinsDesign Engineer
SynchroGrid
Presented at the 71st AnnualTexas A&M Conference for Protective Engineers
Casey ThomasProtection Engineer
EKPC
Presentation Outline• Introduction
• PRC-027-1 Requirement R1 Relay Setting Development Process
R1 Manual Process R1 Simplified Automated Process
• PRC-027-1 Requirement R2 Relay Coordination Process
R2 Existing Process R2 Simplified Automated Process
• Conclusions
2
IntroductionPRC-027-1
• Purpose: “To maintain the coordination of protection systems installed to detect and isolate faults on BES elements, such that those protections systems operate in the intended sequence during faults.”
R1: Establish a process for developing new and revised settings. Process shall include: Review of short circuit modelReview of protection settings
R2: Perform a protection system coordination study:Not to exceed six yearsFault base current exceeds 15%
3
Introduction• Complying with PRC-027-1 is a daunting task that will
require extensive resources.
• Existing solutions and processes:
Time consuming Prone to error Broken and not continuous
4
Introduction• An Innovative solution could achieve…
Well Defined and Simplified process for Relay Setting Development and Coordination
Faster
Easier
Less error-prone
Above all – process must be continuous
• Let’s take a look at where we are now for R1 and R2 and see where we could be if we used an Innovative Process for relay setting development and coordination
5
Presentation Outline• Introduction
• PRC-027-1 Requirement R1 Relay Setting Development Process
R1 Manual Process R1 Simplified Automated Process
• PRC-027-1 Requirement R2 Relay Coordination Process
R2 Manual Process R2 Simplified Automated Process
• Conclusions
6
Relay Setting Development Manual Process
7
For each Terminal• Sanitize Aspen Model• Use standard spreadsheets to
develop settings• Enter settings into RDBs• Peer reviewer repeats process
Verify Model
Utilize Standard Settings
Template
Enter Settings Into .RDB File
Repeat Process Through Peer
Review
R1.1
R1.2
R1
Substation A 138kV
Relay
Substation B 138kV
Relay Setting Development Manual Process
8
Model Verification• Terminal Application
Line impedance Relay Groups
CT, PT ratios
Relay settings
Zone/Overcurrent Elements
Fault Detectors
• Manageable for simple projects• Not manageable for Wide Area
Studies
Verify Model
Utilize Standard Settings
Template
Enter Settings Into .RDB File
Repeat Process Through Peer
Review
R1.1
R1.2
R1
Substation A 138kV
Relay
Substation B 138kV
Relay Setting Development Manual Process
9
Settings Templates and Export to RDB• Spreadsheets or Mathcad:
Perform faults manually Normal Conditions
N-1
Copy and paste data Aspen – Spreadsheets
Spreadsheets - RDB
Verify Model
Utilize Standard Settings
Template
Enter Settings Into .RDB File
Repeat Process Through Peer
Review
R1.1
R1.2
R1
Substation A 138kV
Relay
Substation B 138kV
Relay Setting Development Manual Process
10
Settings Templates and Export to RDB• Spreadsheets or Mathcad: Different philosophy per engineer Very error-prone
Copy and paste
At least a day of work
Verify Model
Utilize Standard Settings
Template
Enter Settings Into .RDB File
Repeat Process Through Peer
Review
R1.1
R1.2
R1
Substation A 138kV
Relay
Substation B 138kV
Relay Setting Development Manual Process
11
Settings Templates and Export to RDB
Verify Model
Utilize Standard Settings
Template
Enter Settings Into .RDB File
Repeat Process Through Peer
Review
R1.1
R1.2
R1
Substation A 138kV
Relay
Substation B 138kV
Relay Setting Development Manual Process
12
Peer Review Process• Repeat steps• Separate engineer• Perform all calculations again• Limit input from original setter
Verify Model
Utilize Standard Settings
Template
Enter Settings Into .RDB File
Repeat Process Through Peer
Review
R1.1
R1.2
R1
Substation A 138kV
Relay
Substation B 138kV
Relay Setting Development Manual Process
13
Overall Manual Process• Error Prone - copy and paste and manual use
of short circuit program.
• Time Consuming - spend much time identifying and understanding issues, instead of focusing on resolving them.
• Frustrating – Can lead to burnout and turnover.
• Ad Hoc – Spreadsheets often obfuscate the intent of the philosophy. Barrier to institutionalization of knowledge and best practices.
Verify Model
Utilize Standard Settings
Template
Enter Settings Into .RDB File
Repeat Process Through Peer
Review
R1.1
R1.2
R1
Substation A 138kV
Relay
Substation B 138kV
Presentation Outline• Introduction
• PRC-027-1 Requirement R1 Relay Setting Development Process
R1 Manual Process R1 Simplified Automated Process
• PRC-027-1 Requirement R2 Relay Coordination Process
R2 Manual Process R2 Simplified Automated Process
• Conclusions
14
Relay Setting Development Simplified Process - Automation
15
Simplified Process• “ A Novel Approach to Relay
Setting Development”
Verify Model
Utilize Standard Settings
Template
Enter Settings Into .RDB File
Repeat Process Through Peer
Review
R1.1
R1.2
R1
Relay Setting Development Simplified Process - Automation
16
Relay Setting Development Simplified Process - Automation
17
Relay Setting Development Simplified Process - Automation
18
Simplified Relay Setting Process• Eliminates Copy and Paste errors• Reduces human error • Minimizes time spent in calculating settings• Creates time to scrutinize how every change
affects the protection of the grid• A standardized process that is uniformly applied,
provides compliance with PRC-027-1 (R1)
Verify Model
Utilize Standard Settings
Template
Enter Settings Into .RDB File
Repeat Process Through Peer
Review
R1.1
R1.2
R1
Substation A 138kV
Relay
Substation B 138kV
Presentation Outline• Introduction
• PRC-027-1 Requirement R1 Relay Setting Development Process
R1 Manual Process R1 Simplified Automated Process
• PRC-027-1 Requirement R2 Relay Coordination Process
R2 Manual Process R2 Simplified Automated Process
• Conclusions
19
Relay Coordination StudiesRequirement and Options
20
R2: Option 1• Perform Relay Coordination not to
exceed six years for each BES element 21 Distance Elements 50 Instantaneous Overcurrent 51 Time Overcurrent
Option 1
R2
Substation A 138kV
Relay
Substation B 138kV
Time BaseSix Years
Option 2
Option 3
Fault Base
Combination Options 1 or 2
Relay Coordination StudiesRequirement and Options
21
R2: Option 2• Perform Relay Coordination at fault
current baseline Establish a fault current baseline Bus fault
Compare current fault values to fault current baseline >15% - perform coordination
Not to exceed six years Baseline must be established prior to
effective date
Option 1
R2
Substation A 138kV
Relay
Substation B 138kV
Fault Base
Time BaseSix Years
Combination Options 1 or 2
Option 2
Option 3
Relay Coordination StudiesRequirement and Options
22
R2: Option 3• Use a combination of options 1 and 2
Perform coordination for facilities above 345kV every 6 years
Perform fault base coordination for facilities below 345kV
Option 1
R2
Substation A 138kV
Relay
Substation B 138kV
Fault Base
Time BaseSix Years
Combination Options 1 or 2
Option 2
Option 3
Relay Coordination StudiesManual Process
23
EKPC: Chose Option 1• Review and calculate relay settings on a 5 year rotation as part of a Wide
Area Coordination All lines 100kV and above Moving towards 69kV system Large part will be reviewed faster due to relay upgrade projects Ensures relays settings and coordination are updated every 5 years
Option 1
Substation A 138kV
Relay
Substation B 138kV
Time BaseSix Years
Relay Coordination StudiesMajor Challenges Complying with R2
24
Short circuit programs• Wide-Area Coordination
• Must use complicated macros Offer little to no customizability.
• Limited means to sanitize model
• Outputs mass amounts of dataUnreadable.
• Engineer must organize, classify and resolve
Option 1
R2Fault Base
Time BaseSix Years
Combination Options 1 or 2
Option 2
Option 3
Relay Coordination StudiesMajor Challenges Complying with R2
25
Spreadsheets
• Provide some mechanism to organize data
• Complex template must be developed
• Fault information from short circuit program to spreadsheets must be exportedRequires programing knowledge
• Spreadsheet must be maintained by original developerKnowledge lost when engineer moves on
Option 1
R2Fault Base
Time BaseSix Years
Combination Options 1 or 2
Option 2
Option 3
Presentation Outline• Introduction
• PRC-027-1 Requirement R1 Relay Setting Development Process
R1 Manual Process R1 Simplified Automated Process
• PRC-027-1 Requirement R2 Relay Coordination Process
R2 Manual Process R2 Simplified Automated Process
• Conclusions
26
R2 Requires a Unified ProcessToday’s Process Unified Process
• Templates allow process customization.
• Automatic model sanitation already finds certain classes of errors (more coming).
• Data is categorized by test type and priority, visual presented in a manageable manner.
• Bidirectional communications merges initial coordination and resolutions into same GUI.
• Direct export of resolutions into rdbs.
27
• Flexibility limited to macros or coding.
• Model verification is primarily a manual, tedious activity.
• Vast amounts of data must be examined to identify and resolve conflicts.
• Data intake is one time. Proposed fixes must be manually checked in short circuit program.
• Does not address data transfer to configuration file. Additional copy/pasteto export fixes to RDBs.
Process Framework for R2
28
Collect Data
Short Circuit Program
Relay Setting File
Data • Primary Line• Source, Remote, and Tap
Lines• Auto & Distribution XFMRs
Fault Simulation• Strongest
Source Removed
• Contingencies
Automated Coordination R2Template Creation Verify Model
Export Feature
Bi-Directional
Template ApplicationReceived Violations Resolve Violations
Unified Process for R2• The key to a successful wide-area coordination study is a
clearly defined process.
29
Verify Model Data
Run Coordination
Study
Develop Coordination
Template Criteria
Dynamically Resolve
Violations
Generate Final Report
Receive Coordination
Violations
Unified Process for R2• The key to a successful wide-area coordination study is a
clearly defined process.
30
Verify Model Data
Run Coordination
Study
Develop Coordination
Template Criteria
Dynamically Resolve
Violations
Generate Final Report
Receive Coordination
Violations
Unified Process for R2
31
Verify Model Data
Run Coordination
Study
Develop Coordination
Template Criteria
Dynamically Resolve
Violations
Generate Final Report
Receive Coordination
Violations
Develop Coordination
Template Criteria
• Step 1: Define Coordination Template• Several different coordination test options
• Zone reach checks• CTI study• Sensitivity studies
• Define specific criteria for each type of test • System conditions• Fault types/locations• Acceptable ranges
Unified Process for R2
S32
Unified Process for R2
S33
Unified Process for R2
34
Verify Model Data
Run Coordination
Study
Develop Coordination
Template Criteria
Dynamically Resolve
Violations
Generate Final Report
Receive Coordination
Violations
Develop Coordination
Template Criteria
Verify Model Data
• Step 2: Verify Model Data• PRC-027 R1 requires an accurate short circuit model.
• Software can aid in finding errors:• Missing line impedances• Missing relays• Incorrect voltages, CTRs, & PTRs
Unified Process for R2
35
Verify Model Data
Run Coordination
Study
Develop Coordination
Template Criteria
Dynamically Resolve
Violations
Generate Final Report
Receive Coordination
Violations
• Step 3: Run Coordination Study• Apply template to sanitized short circuit model• Select area of study
• Tier• Area• Specific kV• Select list of buses• Buses with 15% fault current change
Verify Model Data
Run Coordination
Study
Unified Process for R2
36
Verify Model Data
Run Coordination
Study
Develop Coordination
Template Criteria
Dynamically Resolve
Violations
Generate Final Report
Receive Coordination
Violations
• Step 4: Receive Coordination Violations• All issues organized and elegantly displayed on system dashboard
• Organized by levels of severity (Minor, Moderate, Major)
• Utilization of database and big data visualization techniques to provide an overall representation of grid conditions
Run Coordination
Study
Receive Coordination
Violations
Unified Process for R2
S37
Unified Process for R2
S38
Unified Process for R2
39
Verify Model Data
Run Coordination
Study
Develop Coordination
Template Criteria
Dynamically Resolve
Violations
Generate Final Report
Receive Coordination
Violations
• Step 5: Dynamically Resolve Violations• Begin resolving issues by substation
• Make changes to problem relays via automated solution while coordination results are dynamically updated
• Allows engineer to instantly see how their changes have affected the scope of the grid.
Receive Coordination
Violations
Dynamically Resolve
Violations
Unified Process for R2
S40
Unified Process for R2
41
Verify Model Data
Run Coordination
Study
Develop Coordination
Template Criteria
Dynamically Resolve
Violations
Generate Final Report
Receive Coordination
Violations
• Step 6: Generate Final Report• After all changes have been made/approved:
• Export updated settings into short-circuit program model
• Export updated settings to .rdb
• Export final report
Dynamically Resolve
Violations
Generate Final Report
Presentation Outline• Introduction
• PRC-027-1 Requirement R1 Relay Setting Development Process
R1 Manual Process R1 Simplified Automated Process
• PRC-027-1 Requirement R2 Relay Coordination Process
R2 Manual Process R2 Simplified Automated Process
• Conclusions
42
Conclusion• PRC-027 compliance process can be simplified and improved
by advances in software.
• Our streamlined framework builds upon our previous work to provide a customizable process for relay settings development, meeting the requirement for R1.
• We’ve extended the framework to address R2, providing a process that aids in model verification, enables flexibility in coordination study specification and productivity in violation resolution.
• Continued emphasis on copy/paste removal. Mission critical data should not be manually transmitted.
43
Thank You