What isSelf-organization ?

CENTRALSOFT CO.Ltd,Eiichi Hayashi

the 3rd workshop of “SUKU-SUKU SCRUM club” in japan

2010年1月23日土曜日

SUKU-SUKU?• “SUKUSUKU” is from Japanese word “すくすく” .

• That meaning is growth quickly and healthily.

• It is words used in hope of the growth of the child.

google group: http://groups.google.co.jp/group/sukusuku-scrum?hl=ja

The total person in charge is ebaky

2010年1月23日土曜日

Eiichi HayashiMay 27th 2008

Certified Scrum Trainer President, Board of Directors

Scrum Alliance, Inc.

The profile of the lecturer

Chief of CENTRALS0FT Co., Ltd. in japan My hobby is play piano, djembe, composition. With PM or an architect or planning of education system, administration. It is developed the musical instrument in the former work in a musical instrument maker. I like an object and I make a thing and like it. Member of DRUM CIRCLE FACILITATOR ASSOCIATION Certified SCRUM master. Certified NLP practitioner

2010年1月23日土曜日

EM ZERO VOL2The article that I wrote

2008/11

“The secret of the practice application to learn from a scrum introduction example.”

2010年1月23日土曜日

“I think that try new technique and inspect it that the posture to apply is very important, but it is not a good thing that think with "a silver bullet" solving it by a blow.

I think that it is what you do with the team member who is in the very front now anytime to be the most important.”

EM ZERO VOL2The article that I wrote

2010年1月23日土曜日

I do not think that a one

specific way goes well in any kind of case at all.

2010年1月23日土曜日

Let's think with your own head!

2010年1月23日土曜日

To that end, it is importance

to make "understanding"

why seems to be it.2010年1月23日土曜日

That’s why

2010年1月23日土曜日

SUKUSUKU

2010年1月23日土曜日

What will self-organization

be?

2010年1月23日土曜日

The self-organization is one of the value of the scrum

2010年1月23日土曜日

Self-organizing = Teamwork

2010年1月23日土曜日

Teamwork•cooperate with each other. •get rid of nobody. •Sports team.

•A supervisor does not order it one by one.

•With the pass of the soccer team.

•get a score by teamwork.2010年1月23日土曜日

What is important by teamwork? An attitude?  A method ?

Or?2010年1月23日土曜日

We will regard self-organization as instructions type

organization by WBS and

comparison of task Kamban

2010年1月23日土曜日

WBS ?

•Work Breakdown Structure

•A figure of constitution that divided the whole project into careful work.

• It is called the "work division constitution" "work exploded views".

2010年1月23日土曜日

A Gantt chart

2010年1月23日土曜日

point of the WBS management

• Decided charge, personal work. • A delay of the tasks is responsibility of the individuals.

• Personal responsibility is clear. • The risk that his task is late when he supports other member work.

• 1+1+1=3. • It is made of Excel, and it is stored a server.

2010年1月23日土曜日

Responsibility by the WBS

management

2010年1月23日土曜日

The delay of the task

• The person played truant.

• The concentration of the person was not enough.

• The ability of the person was not enough.  

• The person is got angry at.  

• The person feels responsibility and goes to his office on a holiday.

2010年1月23日土曜日

The delay of the task. In fact?

•The estimate was too small.

•Unexpected difficulty appeared.

2010年1月23日土曜日

A task is completed early

•The person did his/her best. •As for the person, ability improved.

•The person devised it. •The person concentrated on it.

2010年1月23日土曜日

A task is completed earlyIn fact?

•A plan was able to afford. • It was easier than an assumption.

• If a veteran cooperates; quickly. • I was able to do it by copy and paste unexpectedly.

2010年1月23日土曜日

The completion of the task was the same as a plan

•An accurate work estimate.

•The project goes well.

2010年1月23日土曜日

The completion of the task was the same as a plan.In fact?

• A work man-hour matched an estimate by chance.

• I did it leisurely to the limit and all ended it in last one hour.  (A student syndrome)

• Though I ended it to bloom, I reported completion since I worked on rearranging and studied and buried time, and it was it in a fixed date. (The progress does not come)

2010年1月23日土曜日

A weak point of the WBS management

• Overtime work of the person whom I am cooperative, and have a strong sense of a sense of responsibility is easy to increase.

• A burden is easy to center on one.

• There are a person and a period without the concentration .

• If management becomes careful, the → motivation falls down. The person is easy to become strong in the sense that is not voluntary. .

2010年1月23日土曜日

• There are many the people who are late than it ends up being early in a task.  • Because when he can end up being early, he

elaborate it for a over quality and tend it to be buried by study work.

• If with many numbers of people, one leader instructions type fails. • The possibility that misunderstanding of specifications

produces because a worker is easy to become nearsighted is comparatively high.

A weak point of the WBS management

2010年1月23日土曜日

An advantage of the WBS management

•Because it is clear, a plan is easy to steam.

•A customer is easy to understand.

• It is hard to play truant from the way. (?)

• It is used well.2010年1月23日土曜日

TASK KAMBAN

2010年1月23日土曜日

Production control Kamban of the Toyota origin

2010年1月23日土曜日

The member chooses the task by a

morning gathering every morning from here.

2010年1月23日土曜日

The member chooses the task by a

morning gathering every morning from here.

2010年1月23日土曜日

The person signs it and puts it on here if I

choose a card.

2010年1月23日土曜日

The person signs it and puts it on here if I

choose a card.

ハヤシ

2010年1月23日土曜日

If his task is over, his card move to here.

ハヤシ

2010年1月23日土曜日

If his task is over, his card move to here.

ハヤシ

2010年1月23日土曜日

When all are over, it is so

2010年1月23日土曜日

What is task Kamban?• The charge is not decided beforehand. A task is

responsibility of the teams.

• The member pushes forward work while cooperating by a team.

• The member can choose the task by oneself while adjusting it in a team.

• Even if perform cooperation to the other member; because one's task is late, need not to be had square.

• There is overwhelmingly much quantity of communication.

2010年1月23日土曜日

Confirmation in a thing of the point that the progress was left.

2010年1月23日土曜日

A burn down chart

2010年1月23日土曜日

Responsibility with task Kamban

2010年1月23日土曜日

The delay of the task

2010年1月23日土曜日

The delay of the task

I do not understand it well!

2010年1月23日土曜日

A task is completed early

2010年1月23日土曜日

A task is completed early

I do not understand it well!

2010年1月23日土曜日

Task completion matches a plan

2010年1月23日土曜日

Task completion matches a plan

I do not understand it well!

2010年1月23日土曜日

I do not watch the progress by the task unit.

I judge it from a total points. The person who can do it is fast, and a

slow person is slow. That's it.The estimate is a scale not a period.

2010年1月23日土曜日

A burn down chart

2010年1月23日土曜日

A good point of task Kamban

2010年1月23日土曜日

•1+1+1=4 or 5. •I do not say 6 (double). •The know-how of the person who can do it is easy to open early. •A new device is easy to be given by communication. •Management, a person based on trust are easy to grow up. •Because there is consciousness in the whole of specifications, it is hard to misunderstand the

2010年1月23日土曜日

A fault of task Kamban

• It takes a communication cost. (A morning gathering, a meeting in the team)

• It takes time till productivity is finished.  

• When management is too slow; a risk to fall morals.

• (Teamwork in the breakwater of the moral hazard.)

• Personal productivity is incomprehensible. (What would you do to performance rating?)

2010年1月23日土曜日

Q&A2010年1月23日土曜日