welcome lindsay whalin, ms, pg leona heights sulfur mine & creek cleanup darin ranelletti

Post on 19-Jan-2016

219 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

WELCOME

Lindsay Whalin, MS, PG

Leona Heights Sulfur Mine & Creek Cleanup

Darin Ranelletti

PROJECT PURPOSE & DESIGN

Lindsay Whalin, MS, PGSan Francisco Bay Water Board

Leona Heights Sulfur Mine & Creek Cleanup

1. Lindsay1. Lindsay

Purpose of Cleanup

Project Goals

Current

Design

Presentation Outline3

2. Phil2. Phil

Construction Management Project

Duration Construction

days/hours Road use/

Traffic Noise control Dust control Access route Staging areas

3. Darin3. Darin

City PermitsEnvironment

al Review

Timeline

Next Steps

Location

Mining Waste

Piles

McDonell

Ave. Leona

St.

4

N

The Problem

5

Leona Heights Sulfur Mine & Creek Cleanup

The Problem: Mining Waste6

The Problem: Acid Mine Drainage7

The Problem

Leona Creek:Not just ugly…

MercuryCadmiumCopperLead

Arsenic

8

10 to 10,000 x levels toxic to wildlife

(no pathway to humans)

: It’s Toxic to Wildlife

Agencies InvolvedAgencies InvolvedProject GoalsProject Goals

Cleanup mine site, eliminate acid mine drainage

Cleanup Leona Creek

Minimize impacts Disturbance of neighbors

(dust, noise, traffic) Tree removal Wildlife

Water Board Required and oversees

cleanup, design, stream habitat protection

City of Oakland Permits & environmental

review (CEQA)

US Army Corps Engineers Stream protection

Ca Dept. Fish &Wildlife Endangered species &

stream protection

The Goals, Actions, & Actors9

The Solution

10

Leona Heights Sulfur Mine & Creek Cleanup

Current Condition

Natural Hillside

11

Mining W

aste

Natural Hillside

12

The Solution: Isolate Mining Waste

Mining W

aste

PresentPresent FutureFuture

The Results13

: Green, Stable Hillsides

Images courtesy of LSA Associates and Andrew McNichol

Run-on Prevention

Channel

PresentPresent FutureFuture

The Results: : Expanded Cul-de-sac on McDonell

14

Images courtesy of LSA Associates and Andrew McNichol

Run-on Prevention Channels

PresentPresent FutureFuture

The Results: Green, Stable Hillsides15

Images courtesy of LSA Associates and Andrew McNichol

PresentPresent FutureFuture

Skelly and Loy Inc.

16

The Results:Clean, Stable Creek

CONSTRUCTION MANAGEMENT

17

Leona Heights Sulfur Mine & Creek Cleanup

Phil Goalwin, PGE2C Remediation

Construction Management

Staging Areas

Access Route

Logistics of Using McDonell Ave

Dust Control

Noise Control

Construction Days/Hours

Project Duration

18

Staging Areas

Primary Staging Area McDonell Cul-De-Sac and Site Entrance

Materials Staging Area Leona Lodge Overflow Parking Lot

19

Haul Route And Staging Areas20

Access Route

McDonell Ave. vs. Fire Road Why not Fire Road?

Segments with Steep grades (up to 15%) 180 degree Switchbacks Appr0ximately 3.0 miles roundtrip Shuts down trail for 5 months Larger air emissions Habitat for Alameda whip snake Biological mitigation/Vernal Pools Only emergency access Need improvements to use Still need to cross and use McDonell Ave

21

Fire Road22

Access Route

McDonell Ave. vs. Fire Road Why McDonell Ave?

Right at the primary staging area

Appr0ximately 0.6 miles from materials staging area

Paved road with gentle slope

Less air emissions

No biological mitigation

Do not need improvements to use

Reduced environmental impacts

23

McDonell Use Logistics

5 Materials Staging Events

Each Event lasts 5 days (Monday~Friday)

Flagmen with radios to implement traffic control

Small Haul Trucks (with payload <10 tons)

Truck speeds to be kept under 10 mph

Residents will be given priority to truck traffic

24

Dust Control

Limited water spray to soils graded, excavated,

truck loaded., etc.

Amount to control dust, but not cause runoff

Cover soil stockpiles with weighted plastic

sheeting

Vehicles <5mph

Minimize material drop heights during unloading

25

Noise Control

Smaller Equipment

Noise Reduction Blankets on Perimeter

Fence

Noise Reduction Blankets on Temporary

Fence

No Construction Work at night, on weekends

or holidays

26

Construction Days/Hours

Weekdays only (Monday-Friday)

Working Hours - In Accordance With

City Of Oakland Conditions Of Approval

No Holidays

27

Project Duration

Construction Start

Early to Mid May 2014

Construction Completion

September 30, 2014

28

PERMITTING

29

Leona Heights Sulfur Mine & Creek Cleanup

Darin Ranelletti, PlannerCity of Oakland

City of Oakland Permits30

Creek Permit For clean-up work in creek

Tree Removal Permit To remove and replace trees impacted by project

Grading Permit To ensure stable slopes

Street Permit For work in McDonall Avenue cul-de-sac

Environmental Review (CEQA)31

AestheticsAir QualityBiologicalCultural

Environmental analysis to include topics such as:

GeologyHydrologyNoiseTraffic

CEQA document = Mitigate Negative DeclarationAll impacts reduced to less-than-significant levels

Timeline32

Nov 2013: Permit applications submitted to City

Feb 2014: Community meeting

Mar 2014: Public notices sent out Starts official 30-day public review period

May 2014: Permits issued

May 2014: Project starts

Sept 2014: Project complete

Next Steps33

Public notices sent out (March)

Environmental document available on City’s website and in City offices

30-day public review period

Permits issued

Thank you34

Questions or comments?

top related