WCCUSD Bond Program Project Status Report

Citizen Bond Oversight CommitteeMeasure M, D, J, D-2010 & E-2012

Coronado Elementary School:Replacement Campus

Coronado Elementary School: Replacement Campus

Construction Contract Value:

$26,974,910

Percent Complete:

15%

Change Orders: $0 (0%)

Notice to Proceed:

1/6/14

Completion Date:

5/31/15

El Cerrito High School: Stadium

El Cerrito High School: Stadium

Construction Contract Value:

$13,438,000

Percent Complete:

14%

Change Orders: $0 (0%)

Notice to Proceed:

1/27/14

Completion Date:

9/27/15

Gompers / LPS: Replacement Campus

Gompers / LPS: Replacement Campus

Construction Contract Value:

$53,887,350

Percent Complete:

55%

Change Orders:

$673,2971.23%

Notice to Proceed: 8/20/12

Completion Date:

8/15/15

Helms Middle School: Sports Field

Helms Middle School: Sports Field

Construction Contract Value:

$5,951,048

Percent Complete:

99%

Change Orders:

$212,694 (3.45%)

Notice to Proceed:1/7/13

Completion Date:

4/21/14

Kennedy High School: Science Wing Renovation

Kennedy High School: Science Wing Renovation

Construction Contract Value:

$4,136,303

Percent Complete:

83%

Change Orders: $81,893 (1.94%)

Notice to Proceed: 9/16/13

Completion Date:

9/16/14

Kennedy High School: Richmond Swim Center

Kennedy High School: Richmond Swim Center

Construction Contract Value:

7,642,921

Percent Complete:

5%

Change Orders: $0 (0%)

Notice to Proceed: 4/28/14

Completion Date:

4/28/15

Montalvin Elementary School: New Classroom Building

Montalvin Elementary School: New Classroom Building

Construction Contract Value:

$2,843,000

Percent Complete:

15%

Change Orders: $0 (0%)

Notice to Proceed: 2/3/14

Completion Date:

10/31/14

Ohlone Elementary School: West Campus Replacement

Ohlone Elementary School: West Campus Replacement

Construction Contract Value:

$16,961,000

Percent Complete:

90%

Change Orders:

$1,645,876 (8.85%)

Notice to Proceed: 8/1/11

Completion Date:

9/25/14

Pinole Valley High School: Detention Basin, Utilities, & Paving

Pinole Valley High School: Detention Basin, Utilities, & Paving

Construction Contract Value:

$2,126,744

Percent Complete:

90%

Change Orders: $0 (0%)

Notice to Proceed: 11/12/13

Completion Date:

3/22/14

Pinole Valley High School: Interim Housing Campus

Pinole Valley High School: Interim Housing

Construction Contract Value:

$5,530,000

Percent Complete:

10%

Change Orders: $0 (0%)

Notice to Proceed: 4/7/14

Completion Date:

8/15/14

Portola Middle School: Campus Replacement

Portola Middle School: Campus Replacement

Construction Contract Value:

$42,762,406

Percent Complete:

34%

Change Orders:

$88,792 (.20%)

Notice to Proceed:5/13/13

Completion Date:

12/29/15