Original Scope
District ContingencyProject Contingency
Original Contract Amount
Amendment to Scope
Amendment to District Contingency
Amendment to Project Contingency
Amendments to DateRevised Contract Amount
District Contingency $145,825
Executed CO 1 $740 1%
Remaining Contingency $145,085 99%
Project Contingency $0
Executed CO 0 $0
Remaining Contingency $0
Pending PCOs (District) 3 $22,474
Pending PCOs (Project) 0 $0
Rejected PCOs (District) 0 $0
Rejected PCOs (Project) 0 $0
Completed & Stored $ Billed to Date 57%Stop Notices
Completed Work:
146 130%
Upcoming Work:
Project Issues:
Sche
dule
Original Project Duration 112
Revised Completion Date 12/31/2020
NTP
Calendar Days Lapsed
Final Completion
Approved Time Extensions
Revised Project Duration
Proj
ect T
eam
Owner WCCUSD
Inspector
DBEHA Architects
Lathrop Construction
Construction Manager Swinerton
$344,906$0
Proj
ect S
tatu
s
Fire alarm, data cabling, public address system installed.
Quality Control Punchlist inspection with Architect completed.
Portable vendor will complete punch list corrective work.
New transformer scheduled to be delivered and installed for power.
Intrusion alarm system to be bid as a separate package for the portables.
ADA pathway work and parking lot striping work to start.
ADA path of travel through the Staff Parking Lot will require some asphalt demolition and re-paving in order to provide a code compliant level pathway.
9/11/2020
Structure Groups
112
12/31/2020
0
01-11906504-119532
$0
$0
Proj
ect S
cope
Provide sitework to prepare for two new custom designed portable buildings to serve as the new Health Center at Richmond High School, utilizing the old Building A site. Provide site work to demolish old paving, perform new grading and paving, extend utility services including electrical power, data, sewer, water and storm drain work, provide ADA path of travel, parking lot striping, fire alarm, low voltage and intrusion alarm systems. The new portable buildings will be provided and installed by Class Leasing LLC. Site work provided by Lathrop Construciton Associates.
$600,000
Project Status Report: 2/3/2021
Cont
ract
Sum
mar
y
$454,175
$145,825
$600,000
$0
$0
Project No: DSA No:
Richmond High SchoolHealth Center Project
1180 23rd StreetRichmond CA 94804
Project Status Reports- RHS Health Center 2.3.2021