us highway 17 (center street) sidewalk feasibility study town of pierson, florida
Post on 17-Dec-2015
215 Views
Preview:
TRANSCRIPT
Hagstrom Road to Fourth Avenue
Rural section of road ROW approximately 180’ and
can accommodate sidewalks Pedestrian crossing at
Hagstrom not recommended due to limited visibility at curve in road, uncontrolled intersection and speeds exceeding 40 miles per hour (MPH)
Wide width commercial dirt driveway openings exist along corridor
No obstructions observed within proposed path of the sidewalk, however, potential conflicts may arise that can be resolved by field relocation of obstacle or the pathway.
No curb and gutter on west side of road, 7-1/2 foot paved shoulder
Curb and gutter south of Fourth Avenue on the east side of road ends at private drive (photos 4 & 6)
Steep slopes to adjacent open drainage ditches exist in some areas
Fourth Avenue to Second Avenue
ROW narrows to approximately 60 feet north of Fourth Avenue
Pedestrian crossings not recommended due to speeds exceeding 40 miles per hour (MPH) and uncontrolled intersections
Unmarked 5.5 foot bike lanes exist No obstructions observed within
proposed path of the sidewalk however, potential conflicts may arise that can be resolved by field relocation of obstacle or the pathway
Wide width concrete and dirt driveway openings exist along corridor
No curb and gutter on west side of ROW to just south of Third Avenue
One open drain crossing without railing, both sides of ROW between Fourth Avenue and Third Avenue
Sidewalk ramps and detectable warning surface exists at all four corners of Second Avenue
Yellow flashing light at intersection of Second Avenue
Existing sidewalk begins north of Second Avenue on both sides of the ROW
Washington Avenue to First Avenue
Existing detectable warning surface at end of sidewalk curb ramps at all intersections
No curb and gutter along this segment of the corridor
Approximately 10 feet of ROW on the east side from edge of pavement
Large and numerous driveway openings on east side; o approximately 52 foot first
opening, o approximately 61 foot
second opening, o and approximately 153 foot
opening closest to First Avenue
A lighted pedestrian crossing and crosswalks exist at corner of Washington and US HWY 17
Construct sidewalk at grade such that it is ADA compliant.
Provide high-visibility crosswalk markings at all side street roadway crossings. All crosswalks should be six-feet wide at a minimum.
Avoid mid-block crosswalks at uncontrolled intersections.
Install pedestrian signage to existing flashing traffic signal over the crosswalk proposed to cross US HWY 17 at Second Avenue.
Provide ADA compliant sidewalk ramps at all new crosswalk locations.
Include detectable warning surface on curb cuts at all crosswalk locations.
Install longitudinal barriers for the one open drain crossing located on both sides of ROW between Fourth Avenue and Third Avenue
Relocate existing utilities within the proposed path of the sidewalk to a location within the existing right of way.
Avoid trees within the proposed path of the sidewalk.
Provide concrete driveway aprons between US HWY 17 and the back of the proposed sidewalk at all asphalt and gravel driveways.
Increase concrete thickness of the
sidewalk to six inches at driveway crossings and areas subject to vehicular crossing to discourage breakage caused by the excessive weight of vehicles.
Construct curb and gutter along the west side of US HWY 17 south of Third Avenue to extent of existing curb on east side of ROW in order to be consistent with existing construction.
Construct curb and gutter along the east side of US HWY 17 between First Avenue and Washington Avenue in order to be consistent with existing construction.
Add marking and signage as part of the existing bike lanes from Fourth Avenue to Washington Avenue.
Improve pedestrian safety by closing driveway openings and increasing access management. Alternatively, provide high-visibility sidewalk markings at all driveway openings.
Add signage to increase awareness of the slow speeds required along this corridor.
Install stop bars and pedestrian crosswalks at all roadway crossings.
Design Changes May Occur!!
CONCEPTUAL DESIGN RECOMMENDATIONS
FINANCIAL FEASIBILITY
• Table 1 provides an Engineer’s Opinion of Probable Cost to construct the proposed corridor based on FDOT 2011 Basis of Estimates Handbook.
• This estimate is based primarily upon the FDOT 12 Month Moving Average Item Unit Cost Report for Area 6, with costs through 11/30/2012.
• Cost projections have been shown for sequential years up to 2015 based on a unit cost annual increase based on an inflation factor of five percent.
• The total estimated cost for design and construction of the sidewalks along US HWY 17 corridor as discussed in this report for the year 2012 is $789,520.00 ranging up to $913,968.00 in 2015.
US Highway 17 (Center Street)Sidewalk Feasibility StudyTown of Pierson, Florida
SUMMARY
• Safety is of paramount concern for the consideration of this project.
• Properly planned and constructed sidewalks can address pedestrian safety by separating
pedestrians from vehicle traffic, providing a safe and functional space for all users of the
corridor.
• Adequate ROW exists along the corridor on both sides of the pavement to construct the desired
facilities without the need for encroachment out side the right-of-way boundaries.
• The concept plan and typical cross sections included within this report were formulated based
on the results of compiling data regarding existing conditions and applicable FDOT design
guidelines.
• Based on the data gathered, a 5 foot concrete sidewalk is proposed to be located 5 feet from the
back of curb and 6 feet from edge of pavement.
• Potential conflicts may arise along this proposed path that can be resolved by field relocation of
obstacle or the pathway.
• A public involvement program will be provided by the Town of Pierson as part of the design
schedule for the project.
• The total estimated cost for design and construction of the sidewalks along US HWY 17
corridor as discussed in this report for the year 2012 is $789,520.00 ranging up to $913,968.00
in 2015.
• The results of the study identified the recommended width of the sidewalk and its location was
feasible in order to design a cost-effective path that fits within the existing right-of-way.
top related