LA PROGRESS Pre-Qualification stage completed for all 3 projects Contract awarded for Hydrodynamic Surveys –EMU Limited Contracts have been awarded for Topographic Surveys Work briefs have been sent out for Bathymetric Surveys

TRANSCRIPT

SOUTH WEST STRATEGIC REGIONAL COASTAL

MONITORING PROGRAMMEUPDATE

ROB WEBBONOFFICE MANAGER

PROGRAMME UPDATE

Local Authorities

• Hydrodynamic Surveys

• Control Network

• Topographic Surveys

• Bathymetric Surveys

Environment Agency

• Aerial Photography

• LiDAR Surveys

• Ecological Surveys

LA PROGRESS

• Pre-Qualification stage completed for all 3 projects

• Contract awarded for Hydrodynamic Surveys – EMU Limited

• Contracts have been awarded for Topographic Surveys

• Work briefs have been sent out for Bathymetric Surveys

Hydrodynamic Data• 6 Directional Wave Buoys:

– Moored to the seabed– Radio link to a land station– Broadband link to the CCO– Real time data every 30

minutes– Freely available as of April

2007– Already installed at

Minehead, Perranporth, West Bay and Chesil

Hydrodynamic Data

• 2 Tide Gauges:– Downward looking WaveRex

tide gauges– Installed on fixed structure– Broadband connection back

to CCO– Real time data– One at Teignmouth, one at

West Bay

Control Network

• 115 points• 3 Hour occupation• Surveyed and Processed• Tied into OS and EA

networks• Data to be placed on

website

Topographic surveys

• 5 work packages awarded to 4 contractors

• Cartographical surveys won TSW1

• Contract meetings 25th and 30th January

• Surveys will begin in February• 1 baseline survey• 2 interim profiles per year• 1 post storm

Bathymetric surveys

• 8 work packages• Bathy work brief sent

out 08/01/2007• Surveys to begin in

Summer• Single beam survey• 1 km offshore to

MHWN

© Titan Environmental Surveys Ltd

Aerial Photography

• Simmons Aerofilm• 20% Flown• To be completed Summer 2007

Aerial Photography

LiDAR

• Awarded in-house (Twerton)• 10% Flown• Currently being used to ortho-rectify aerial

photos• To be completed by May 2007

LiDAR

Image courtesy of Environment Agency

Office Update

• All Software and Hardware up and running• 2 new employees• Strong links with University of Plymouth

• All data collected, processed and analysed at Plymouth before transfer to CCO website

Working Together

• Special requirements from the programme?

• We aim to provide:– A regional approach– High quality data– Freely available to any interested parties– Website live from April 2007

• Historical Data

Any Questions?