New Ringgold Middle School

Project SlideshowJanuary 6, 2017

Building Areas

Pour Concrete Floor – Kitchen – Area A

Pour Concrete Floor – Kitchen – Area A

Prep for Concrete Floor – Cafeteria – Area A

Prep for Concrete Floor – Mech. Room – Area A

Pour Concrete Floor – Mech. Room – Area A

Concrete Slab on Grade Progress

Brick Installation – Area A

Brick Installation – Area A

Brick Installation – Area A

Masonry Installation – Area A

Masonry Installation – Area A

Masonry Installation – Area A

Stud Wall Framing – Area A

Work Progress – 1st Floor - Area A

Masonry Installation - 2nd Floor – Area A

Masonry Installation - 2nd Floor – Area A

Work Progress – 2nd Floor – Area A

Masonry Installation – 2nd Floor- Area B

Masonry Installation – 2nd Floor- Area B

Masonry Installation – 2nd Floor- Area B

Decking Installation – Area B

Work Progress – 2nd Floor - Area B

Brick Installation – Area C

Work Progress – 1st Floor - Area C

Bar Joist Detailing – Area C

Decking Installation – Area C

Work Progress – 2nd Floor - Area C

Steel Detailing – Area D

Masonry Installation – Area D

Masonry Installation – Area D

Work Progress – Area D

Steel – Area A

Bar Joist Installation – Cafeteria – Area A

Bar Joist Installation – Cafeteria – Area A

Bar Joists at Loading Dock Area – Area A

Roof Decking – Mech. Room – Area A

Roof Progress

Continue Setting Door Frames

Masonry Installation – Fitness Center

Masonry Installation – Fitness Center

Door Cut – Fitness Center

Underground Electric – Cafeteria – Area A

Transformer Pad Set

Plumbing Through Wall Penetrations

• Continue Masonry Installation – Areas A, B, C & D• Complete Brick Installation - Courtyard• Continue Plumbing & Electrical Wall Rough In• Concrete Slabs on Grade – Cafeteria - Area A• Concrete Slab on Deck – Area B & C• Continue Roof Decking – Area A• Continue Steel Erection – Area D• Roofing – Area A• Continue Stud Wall Installation• Installation of Switchgear• Set Transformer• HVAC Piping Installation – Area A• Steel Erection at Fitness Center• Installation of Anti Seep Collar at Retention Tank #2

Scheduled Work for Next Few Weeks

The End