Presented by:Aldo MazzaferroDirector of Project DevelopmentECG Engineering, P.C.
PhaseIResults•After implementation is complete, Measurement & Verification (M&V) phase begins to prove success of the project
•In Phase I, Johnson Controls (JCI) guaranteed $1,913,955 in annual savings for the District
•If those savings were not achieved, JCI would write the District a check to make up for the shortfall
•Findings of M&V Report• Ph I savings exceeded guarantee by ~20% ($201,041)• PSE&G Rebate achieved $1.0M vs the expected $869,000
An Energy Conservation Plan
Commack School DistrictSeptember 19, 2016
Agenda
4
Phase 2 Project Overview Energy Efficiency Measures Cost and Savings Summary Johnson Controls Qualifications Next Steps Questions and Answers
Phase 2: Project Overview
Project Overview
District Annual Energy Savings: $752,510 - 32%
Project Cost: $14,575,507
Facility Improvement Measures (FIM) :
10
Payback Period: 17.9 years
Savings Guarantee: 100%
6
Energy Performance Contracting is:Energy Performance Contracting is:
An agreement that allows school districts to take budgeted utility and operational costs and reallocate them into energy saving capital
Improvements without the need for Increased Taxes.
Energy Efficiency Measures
8
Energy Conservation Measures – Lighting Upgrades with Ceiling Replacement
Total Districtwide LED Upgrades: Over 17,000
New Ceilings at the High School Art Gallery –Approx. 2,800 Square Feet
Commack Middle School Auditorium Lighting upgrade
Retrofit Exterior Lighting Fixtures with LED
Total Exterior Fixtures to be retrofitted : 353
Annual Savings: $172,630
Art Gallery Ceilings
9
Energy Conservation Measures –Energy Management System
Air Handling Unit DDC Refit Districtwide : 53 Units Pneumatic Repair & Refurbishments Districtwide
Unit Ventilators: 392 Radiators/Convectors: 587 Day/Night Zones: 71
Optimal Start & Front-End User Interface Upgrades at Burr and Sawmill DDC Control of Relief Dampers at Commack High School: 11 Units DDC Controls of Exhaust Fans: 83 Units Districtwide
Annual Savings: $63,046
10
Energy Conservation Measures – Boiler Replacement
New Dual Fuel Condensing Boilers at North Ridge Primary & Rolling Hills Primary
Annual Savings: $6,332
North Ridge
Rolling Hills
Building Proposed Units Proposed Qty.
North Ridge Fulton VTG 3000 2
Rollling Hills Fulton VTG 2000 2
11
Energy Conservation Measures – Roof Replacements
New Roofs at Commack High School, Indian Hollow Primary School, and Rolling Hills Primary School
Annual Savings: $18,381
HS: Approx. 152,000 Sq. ft. Indian Hollow: Approx. 47,100 Sq. ft.
Rolling Hills: Approx. 46,700 Sq. ft.
12
Energy Conservation Measures –Photovoltaic Electric Generation
Total 1,786.84 kW Roof Mounted Photovoltaic Districtwide
Annual Savings: $364,420
Site Name PV Size (kW)Commack High School 975 . 260 North Ridge Primary 341 . 000 Indian Hollow Primary 272 . 800 Rolling Hills Primary 197 . 780
Totals 1,786 . 840
13
Energy Conservation Measures –Photovoltaic Electric Generation
Commack High School Indian Hollow Primary
School
14
Energy Conservation Measures –Photovoltaic Electric Generation
Rolling Hills Primary School
North Ridge Primary School
15
Energy Conservation Measures – Cogeneration
Total Cogen Size District-wide: 200 kW
Tecogen InVerde 100 Units with Backup Power
Replaces existing diesel fired emergency generators
Annual Savings: $62,842
Building Cogen Size
Burr Intermediate School 100 kW
Sawmill Intermediate School 100 kW
Total 200 kW
16
Energy Conservation Measures – Plug Load Controllers
Over 1,300 Plug Load Controllers
System uses existing Wi-Fi network communicates to an energy management user interface
Annual Savings: $57,220
17
Other Measures
Air Conditioning Compressor Controllers (61 Districtwide) – Savings $6,351
Energy Efficient RTU Replacements (3 at HS, 1 at MS) – Savings $1,288
Cost and SavingsSummary
19
Cost and Savings Summary
Positive cash flow: $6,369,828A A1 A2 A=A1-S2 B C D=A+B+C E D+G
YrNYSED Building
Aid
NYSED Building Aid less non-aidable measures at 90%
Annual Energy Cost With Out
Savings
Annual Energy Cost with
ImprovementsAnnual Energy
SavingsAnnual O&M
savings
National Grid Rebate
Program Total Annual Savings Annual Lease Payment Annual Cash FlowCumulative Cash Flow
1 ($623,316) ($560,985) $2,293,242 $1,540,732 $752,510 $56,064 $48,000 $1,417,559 $1,293,759 $123,800 $123,800
2 ($623,316) ($560,985) $2,339,107 $1,571,546 $767,561 $57,185 $0 $1,385,730 $1,293,759 $91,971 $215,771
3 ($623,316) ($560,985) $2,385,889 $1,602,977 $782,912 $58,329 $0 $1,402,225 $1,293,759 $108,466 $324,237
4 ($623,316) ($560,985) $2,433,607 $1,635,037 $798,570 $59,496 $0 $1,419,050 $1,293,759 $125,291 $449,528
5 ($623,316) ($560,985) $2,482,279 $1,667,737 $814,541 $60,685 $0 $1,436,212 $1,293,759 $142,452 $591,980
6 ($623,316) ($560,985) $2,531,924 $1,701,092 $830,832 $61,899 $0 $1,453,716 $1,293,759 $159,957 $751,937
7 ($623,316) ($560,985) $2,582,563 $1,735,114 $847,449 $63,137 $0 $1,471,571 $1,293,759 $177,811 $929,749
8 ($623,316) ($560,985) $2,634,214 $1,769,816 $864,398 $64,400 $0 $1,489,782 $1,293,759 $196,023 $1,125,772
9 ($623,316) ($560,985) $2,686,898 $1,805,213 $881,686 $65,688 $0 $1,508,358 $1,293,759 $214,599 $1,340,371
10 ($623,316) ($560,985) $2,740,636 $1,841,317 $899,320 $67,002 $0 $1,527,306 $1,293,759 $233,547 $1,573,918
11 ($623,316) ($560,985) $2,795,449 $1,878,143 $917,306 $68,342 $0 $1,546,632 $1,293,759 $252,873 $1,826,791
12 ($623,316) ($560,985) $2,851,358 $1,915,706 $935,652 $69,709 $0 $1,566,345 $1,293,759 $272,586 $2,099,377
13 ($623,316) ($560,985) $2,908,385 $1,954,020 $954,365 $71,103 $0 $1,586,452 $1,293,759 $292,693 $2,392,070
14 ($623,316) ($560,985) $2,966,553 $1,993,101 $973,452 $72,525 $0 $1,606,962 $1,293,759 $313,203 $2,705,272
15 ($623,316) ($560,985) $3,025,884 $2,032,963 $992,921 $73,975 $0 $1,627,881 $1,293,759 $334,122 $3,039,394
16 $0 $0 $3,086,402 $2,073,622 $1,012,780 $75,455 $0 $1,088,235 $0 $1,088,235 $4,127,629
17 $0 $0 $3,148,130 $2,115,094 $1,033,036 $76,964 $0 $1,109,999 $0 $1,109,999 $5,237,628
18 $0 $0 $3,211,092 $2,157,396 $1,053,696 $78,503 $0 $1,132,199 $0 $1,132,199 $6,369,828
Total ($9,349,743) ($8,414,769) $49,103,614 $32,990,626 $16,112,988 $1,200,460 $48,000 $25,776,216 $19,406,388 $6,369,828 $6,369,828
How does the Cash Flow work?
Tax exempt lease payment $(1,293,759)
Energy savings $752,510
NYSSED aid $560,985
Annual O&M Savings $56,064
Rebates Program $48,000
Annual M&V Service Cost $(0)
Net cash flow to District $123,800
Year 1
Project Timeline
21
BOE to Authorize EPC: Nov 2016BOE to Authorize EPC: Nov 2016
JCI to provide design criteria to ECG: Jan 2017JCI to provide design criteria to ECG: Jan 2017
ECG to prepare submission to SED: Feb 2017 – Apr 2017ECG to prepare submission to SED: Feb 2017 – Apr 2017
SED Approval & Financing: Nov 2017SED Approval & Financing: Nov 2017
Construction commences: Dec 2017Construction commences: Dec 2017
Construction substantial completion: Nov 2018Construction substantial completion: Nov 2018
Final Completion: Dec 2018Final Completion: Dec 2018
QuestionsQuestions?