MTC / ABAG Plan Bay Area (2040)
Regional Sustainability
2Note: For five BART served counties: Alameda, Contra Costa, San Francisco, San Mateo, and Santa Clara
Job Growth• ~ 1,000,000• > 25% of growth near BART
Household Growth• ~ 625,000
• San Francisco 100,000• Alameda 160,000• Contra Costa
90,000 • San Mateo
60,000• Santa Clara 215,000
• > 25% of growth near BART
Oakland Airport ConnectorAutomated People Mover System (APM)
Replace AirBART Bus with:
Automated People Mover (APM)
Driverless
Electrically driven
Exclusive 3.1 mile guideway
Extremely consistent & reliable
Seamless ticketing
Comfortably carry 3.2 Million Annual Passengers (MAP)
Expandable to 4.9 MAP
Trains every 4.5 minutes
Ride time 8 minutes – door to door 14 min
4
OAC Alignment
Doppelmayr Cable Car • DCC’s Development of Pinched Loop Technology
Page # 14
OAK BART
OAC Look Ahead
Activity Start Estimated Finish
Station(s) Construction September 2011 November 2013
Guideway Construction June 2011
Maintenance & Storage Facility July 2011
Vehicle Fabrication December 2012
Train Control System Fabrication January 2013 June 2013
System Testing
Start of OAC Service
September 2013
August 2013
August 2013
September 2014
Fall 2014
December 2013