Broadwind Wind Tower Shipments 2014

Pete Lynch/Dawn Johnston representing WisDOTFeb 26, 2014 –Northcentral Technical College

Project Description Routes Load Dimensions Known construction/Mitigations Communication Protocol Questions

Overview

2

256 loads - 64 four piece towers Projected Start - June 9 2014 Projected Duration - 8 to 10 weeks*

* Depends on final loading plans/equipment rotation

Project Overview

3

Monthly operations calls to build and clear routes

30 days prior to first move switch to weekly check in calls

LCS entries need to be timely and accurate Monitored for incidents by central office Monitored by region for program/project

changes Construction, Maintenance, Bridge Postings, etc

Routes

4

Map

Routes (cont.)

5

All 15’6” H or less and 14’9” W or less TOP – 220K wtg 180 L Upper Mid – 245K wtg 185 L Lower Mid – 258 wtg 180 L Base – 258 wtg 150 L

Load Dimensions

6

Construction STH 29 June/July Structures

B37-02-01 B37-02-02

Single Lane Closures 14’ restriction 1 foot shy

STH 29 July-Sept Structures

B37-01-14 Single Lane Closures 14’ restriction 1 foot shy

7

Sign Sleeve

Mitigation

8

Sign Sleeve

Mitigation

9

Dan Mulder Section Chief Freight and Roadside Facilities daniel.mulder@dot.wi.gov (608) 266-3471

Region OSOW staff can contact BHM Staff as well

Communication Protocol

10

Questions

11