Broadwind Wind Tower Shipments 2014
Pete Lynch/Dawn Johnston representing WisDOTFeb 26, 2014 –Northcentral Technical College
Project Description Routes Load Dimensions Known construction/Mitigations Communication Protocol Questions
Overview
2
256 loads - 64 four piece towers Projected Start - June 9 2014 Projected Duration - 8 to 10 weeks*
* Depends on final loading plans/equipment rotation
Project Overview
3
Monthly operations calls to build and clear routes
30 days prior to first move switch to weekly check in calls
LCS entries need to be timely and accurate Monitored for incidents by central office Monitored by region for program/project
changes Construction, Maintenance, Bridge Postings, etc
Routes
4
Map
Routes (cont.)
5
All 15’6” H or less and 14’9” W or less TOP – 220K wtg 180 L Upper Mid – 245K wtg 185 L Lower Mid – 258 wtg 180 L Base – 258 wtg 150 L
Load Dimensions
6
Construction STH 29 June/July Structures
B37-02-01 B37-02-02
Single Lane Closures 14’ restriction 1 foot shy
STH 29 July-Sept Structures
B37-01-14 Single Lane Closures 14’ restriction 1 foot shy
7
Sign Sleeve
Mitigation
8
Sign Sleeve
Mitigation
9
Dan Mulder Section Chief Freight and Roadside Facilities [email protected] (608) 266-3471
Region OSOW staff can contact BHM Staff as well
Communication Protocol