Next planned test steps on two beam prototype modules. With input from Michail Anastasopoulos, Nicolas Chritin, Sylvain Griffet, Juha Kemppinen, Raphaël Leuxe, Mateusz Sosin. Special thanks to Serge Lebet and Philippe De Souza. 07-02-11. Short term program & expected results by end of 2012. - PowerPoint PPT Presentation

TRANSCRIPT

Next planned test steps on two beam prototype modules

07-02-11 H. MAINAUD DURAND

With input from Michail Anastasopoulos, Nicolas Chritin, Sylvain Griffet, Juha Kemppinen, Raphaël Leuxe, Mateusz Sosin

Special thanks to Serge Lebet and Philippe De Souza

2

Two beam prototype modules

Validation of the following strategies [Q1 - Q3 2011]

o Pre-alignment of the components on their support within 10 microns, inter-comparison between methods (AT 401, micro-triangulation,…)

o Articulation point : the adjacent extremities of girders follow within a few microns

o Micrometric adjustment using linear actuators

Alignment systems providing a determination of the position with micrometric accuracy and precision [Q2 - Q4 2011]

o Inter-comparison between oWPS and cWPS

o Inter-comparison between RASNIK and WPS [Q3 - Q4 2011]

Active pre-alignment: tests of the algorithms [Q2 2011]

Feedback concerning schedule, cost, general strategy of installation, and two beam modules in CLEX

Compatibility with other systems (vacuum, waveguides,…), stability [Q3 2011 – Q3 2012]

Short term program & expected results by end of 2012

Zoom on the next 6 months…

Installation & validation of alignment systems

Qualification of linear actuators (1DOF tests)

Alignment of Micro-contrôle girders w.r.t station unit

TestsWith external constraints

Once girders are re-installed in 169

Mid March

[2 months]Tests

Without external constraints (vacuum, waveguides)

Fidu

cial

isati

on a

nd d

imen

sion

al c

ontr

ol

4

Zoom …

Install & adjust plates

Install & adjust stretching devices

Install cWPS sensors + tiltmeters

Installation & validation of alignment systems

On concrete blocks On girders + cradles Around modules

Install cWPS

install tilt meter

Install cables + acquisition system

Prepare software

Install stretched wires

Validation of alignment systems

(radial & vertical displacements of wires in order to check proportional responses of sensors)

(Michail) (Michail)

5

Zoom …

1 DOF test bench (Mateusz)

Qualification of linear actuators (1DOF tests)

1DOF test bench : design ok, assembly ok, software ready end of this week

Qualification of Boostec linear actuators one per one [week 07 & 08]

Qualification of Micro contrôle linear actuators one per one [week 09 & 10]

Tests foreseen (over the whole range):

Linearity

Repeatability

Resolution

Determination of backlash

6

Zoom … Tests

Qualification of concept of articulation point (Micro-contrôle versus Boostec/CERN:

• Metrological evaluation

• Behavior of the articulation point w.r.t micrometric displacements, w.r.t larger displacements (+/- 1mm)

• Impact at beam level

• Impact of displacements on adjacent articulation points

• Validation of algorithm of repositioning

• Implementation of active pre-alignment

(Mateusz Sosin)

Zoom … Fiducialisation and dimensional control

Inter-comparison between methods:

• Romer Arm: order, reception tests & « prise en main »

• Laser Tracker AT 401: order, reception tests & « prise en main »

• Micro-triangulation: development of software, qualification tests, order of material

Preparation, follow-up of all dimensional controls & fiducialisation on components. (see table)

Zoom … Fiducialisation and dimensional control

(Sylvain)

9

Validation of sub-micrometric active alignment using WPS sensors and cam movers [Q1-Q2 2011]

Compatibility with stabilization requirements (first Eigen frequency > 50 Hz) [Q2 2011]

Feedback for design of the MB quad mock-up type 1 and 4, foreseen for the two beam

prototype modules in lab and CLEX [Q3 2011 - Q1 2012]

MB quad mock-up

Short term program & expected results by end of 2012

Mock-up ready [end of February 2011]

Validation of the algorithm of repositioning [Q1-Q2 2011]

(Michail, Raphaël)