Project Progress–8th

Sep,2014

MY HOME VIHANGA BLOCK-“01” AS ON 8th Sep, 2014

Basement –II, Basement-I, Ground, 1st to 11th Floor Slabs Completed

MY HOME VIHANGA BLOCK - “02” AS ON 8th Sep, 2014

Basement –II, Basement-I, Ground, 1st to 9th Floor Slabs Completed

MY HOME VIHANGA BLOCK- “03” AS ON 8th Sep, 2014

Basement II & I Slabs Completed

MY HOME VIHANGA BLOCK- “04” AS ON 8th Sep, 2014

Basement II & I Slabs Completed

MY HOME VIHANGA BLOCK- “05” AS ON 8th Sep, 2014

Basement-II Slab Completed, Basement-I Columns Work In Progress

MY HOME VIHANGA BLOCK- “06” AS ON 8th Sep, 2014

Basement II & I Slabs Completed

MY HOME VIHANGA BLOCK-“07” AS ON 8th Sep, 2014

PCC & Footing work In Progress

MY HOME VIHANGA BLOCK-“08” AS ON 8th Sep, 2014

PCC Work In Progress

MY HOME VIHANGA BLOCK- “09” AS ON 8th Sep, 2014

PCC & Footings Work In Progress

MY HOME VIHANGA BLOCK- “10” AS ON 8th Sep, 2014

PCC & Footings Work In Progress

MY HOME VIHANGA Block-“11 & 12” AS ON 8th Sep,2014

Earth Work Completed

MY HOME VIHANGA BLOCK-“13” AS ON 8th Sep, 2014

Grade Slab Sand Filling work In Progress

MY HOME VIHANGA BLOCK-“14” AS ON 8th Sep, 2014

Footings Work In Progress

MY HOME VIHANGA BLOCK-“15” AS ON 8th Sep, 2014

Basement-II & I Slabs Completed

MY HOME VIHANGA BLOCK-“16” AS ON 8th Sep, 2014

Basement II Slab Completed, Basement-I Slab Shuttering Work In Progress

MY HOME VIHANGA BLOCK-“17” AS ON 8th Sep, 2014

Grade Slab Completed, Basement-II Slab Shuttering Work In Progress

MY HOME VIHANGA BLOCK-“18” AS ON 8th Sep, 2014

Grade Slab Completed

MY HOME VIHANGA BLOCK-“19”AS ON 8th Sep, 2014

Basement –II Slab Completed, Basement-I Slab Shuttering Work In Progress

MY HOME VIHANGA BLOCK-“20” AS ON 8th Sep, 2014

Basement II Slab Completed, Basement-I Slab Columns Work Progress