monthly stakeholder presentation june 24, 2020

Post on 17-Feb-2022

1 Views

Category:

Documents

0 Downloads

Preview:

Click to see full reader

TRANSCRIPT

Monthly Stakeholder Presentation

June 24, 2020

2

This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity

other than FDOT staff is not official. Any questions can be sent to FDOT-D6PIO@dot.state.fl.us.

This presentation may not be altered.

* This schedule does not reflect days added to the contract for

holidays, weather days or special events

3

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

• Ongoing nighttime closure on

I-95 from NW 8 Street to NW

29 Street for concrete

replacement activities

• Concrete replacement

ongoing on the northbound

lanes

• Saw cutting of existing

pavement ongoing in the

southbound lanes

* This schedule does not reflect days added to the contract for

holidays, weather days or special events

4

ONGOING LANECLOSURES

THREE MONTH LOOK AHEAD

ANTICIPATED LANE CLOSURES ON THE I-95 CORRIDOR:

• Nighttime lane/ramp closure along I-95 between NW 8 Street and NW

29 Street

• Closure hours have been adjusted based on current traffic

conditions from 6:30 p.m. until 5:30 a.m.

5

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

Bridge widening on SR 836 near NW 17 Avenue and NW 10 Avenue

6

• Demolition of median area on SR

836 is ongoing and continues

moving to the west

• Auger Cast Pile operations are

scheduled to begin in July for the

foundations that will support the new

double decked section of SR 836

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

7

ANTICIPATED LANE CLOSURES ON SR 836 CORRIDOR:

• Single and double lane/ramp closures along eastbound and westbound SR

836

• Arterial roads under SR 836

• Closure hours have been adjusted based on current traffic conditions from

8 p.m. until 5:30 a.m.

• Single daytime lane closures on westbound SR 836 from 6 a.m. – 2 p.m.

ONGOING LANECLOSURES

THREE MONTH LOOK AHEAD

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

8

• Ongoing sheet pile installation for

signature bridge arch # 4

foundation

• Construction of the signature

bridge center pier ACP foundations

(Ongoing)

• ACP foundations for Arch # 2

expected to begin in early July

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

9

Column construction ongoing north

of I-395

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

10

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

Installing falsework for segment

erection

Bridge segments for I-395 weigh between

50 and 93 tons each

11

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

Bridge segments for I-395 weigh between 50 and 93 tons each

12

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for

holidays, weather days or special events

13

Ongoing Auger Cast Pile Foundation

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

* This schedule does not reflect days added to the contract for

holidays, weather days or special events

14

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES

Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. There will

be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street)

and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur

Causeway).

Close Bayshore loop ramp to EB MacArthur Causeway (August 2020)

1

1

2

2

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

15

ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:

• Lane closures along eastbound and westbound I-395

• Lane closures along Biscayne Boulevard and other arterial roadways

adjacent to I-395

• I-395 to I-95 ramp closures

• Closure hours have been adjusted based on current traffic

conditions from 8 p.m. until 5:30 a.m.

ONGOING LANECLOSURES

THREE MONTH LOOK AHEAD

16

COMMUNITY OUTREACH

PROJECT WEBSITE

• www.i-395miami.com

• Sign-up for project alerts/updates

Lane closure information

Upcoming construction activities

Presentations

• Calendar of events

OUTREACH OFFICE IN THE OVERTOWN COMMUNITY

• 1035 NW 3 Avenue, Miami, Florida 33136 (CLOSED AT

THIS TIME)

STAKEHOLDER MEETINGS

• Stakeholder meetings will be held virtually until further

notice. Next meeting date: TBD.

786-280-0983

OGonzalez@mrgmiami.com

Contact:Oscar Gonzalez

www.i-395miami.com

THANK YOU!

17

top related