Add photo of pipeline install

MPWSP Governance Committee MeetingJuly 18, 2018

1

MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

2017 2018 2019 2020 2021

AUTHORIZATIONS

PWM

MONTEREY PL & PS

DESAL

EIR/EISCPCN

IN-SERVICE

MPWSP ANTICIPATED SCHEDULE

CDP

IN-SERVICE

IN-SERVICE

START CONSTRUCTI

ON

Status UpdatePipeline and Pump Station

3

8

Pipeline Bridge Crew

~6.5 miles of 36” pipe installed

Pump Station Crew

MONTEREY PIPELINE CONSTRUCTION

ASR 5 & 6 RFPs

5

ASR Wells 5 & 6 RFPs

• ASR Well Drilling• Design – Bid - Build (DBB)

• ASR Well Above Ground Facilities• Design - Build (DB)

InterconnectsRR-B & HH-TG

6

ASR Wells 5 & 6 Anticipated Schedule

7

Estimated Schedule

Start Construction Q2 - Q3 2019

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Specs

Note: Aniticpated schedule is dependent on permit approvals and could shift by up to six months.

Start-upSite Prep

Well Construction/TestingBidding

2017 2019 2020

PDR

PDR

2018

Facility ConstructionBidding Design

ASR-5 and ASR-6 Wells

Fitch Park ASR Facility

GC Review of RFPs

8

ASR Wells 5 & 6 RFP Evaluation Criteria

9

Additional future RFPs

• Castroville Pipeline

• Satellite system interconnect pipelines

• Slant Wells Civil & Electrical Work

InterconnectsRR-B & HH-TG

10

Q & A

11