monterey peninsula water supply project ... - … · add photo of pipeline install mpwsp governance...

11
Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

Upload: others

Post on 23-Sep-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

Add photo of pipeline install

MPWSP Governance Committee MeetingJuly 18, 2018

1

MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

Page 2: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

2017 2018 2019 2020 2021

AUTHORIZATIONS

PWM

MONTEREY PL & PS

DESAL

EIR/EISCPCN

IN-SERVICE

MPWSP ANTICIPATED SCHEDULE

CDP

IN-SERVICE

IN-SERVICE

START CONSTRUCTI

ON

Page 3: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

Status UpdatePipeline and Pump Station

3

Page 4: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

8

Pipeline Bridge Crew

~6.5 miles of 36” pipe installed

Pump Station Crew

MONTEREY PIPELINE CONSTRUCTION

Page 5: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

ASR 5 & 6 RFPs

5

Page 6: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

ASR Wells 5 & 6 RFPs

• ASR Well Drilling• Design – Bid - Build (DBB)

• ASR Well Above Ground Facilities• Design - Build (DB)

InterconnectsRR-B & HH-TG

6

Page 7: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

ASR Wells 5 & 6 Anticipated Schedule

7

Estimated Schedule

Start Construction Q2 - Q3 2019

J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D

Specs

Note: Aniticpated schedule is dependent on permit approvals and could shift by up to six months.

Start-upSite Prep

Well Construction/TestingBidding

2017 2019 2020

PDR

PDR

2018

Facility ConstructionBidding Design

ASR-5 and ASR-6 Wells

Fitch Park ASR Facility

Page 8: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

GC Review of RFPs

8

Page 9: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

ASR Wells 5 & 6 RFP Evaluation Criteria

9

Page 10: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

Additional future RFPs

• Castroville Pipeline

• Satellite system interconnect pipelines

• Slant Wells Civil & Electrical Work

InterconnectsRR-B & HH-TG

10

Page 11: MONTEREY PENINSULA WATER SUPPLY PROJECT ... - … · Add photo of pipeline install MPWSP Governance Committee Meeting July 18, 2018 1 MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE

Q & A

11