MPWSP Governance Committee MeetingJuly 18, 2018
1
MONTEREY PENINSULA WATER SUPPLY PROJECT UPDATE
2017 2018 2019 2020 2021
AUTHORIZATIONS
PWM
MONTEREY PL & PS
DESAL
EIR/EISCPCN
IN-SERVICE
MPWSP ANTICIPATED SCHEDULE
CDP
IN-SERVICE
IN-SERVICE
START CONSTRUCTI
ON
Status UpdatePipeline and Pump Station
3
8
Pipeline Bridge Crew
~6.5 miles of 36” pipe installed
Pump Station Crew
MONTEREY PIPELINE CONSTRUCTION
ASR 5 & 6 RFPs
5
ASR Wells 5 & 6 RFPs
• ASR Well Drilling• Design – Bid - Build (DBB)
• ASR Well Above Ground Facilities• Design - Build (DB)
InterconnectsRR-B & HH-TG
6
ASR Wells 5 & 6 Anticipated Schedule
7
Estimated Schedule
Start Construction Q2 - Q3 2019
J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D
Specs
Note: Aniticpated schedule is dependent on permit approvals and could shift by up to six months.
Start-upSite Prep
Well Construction/TestingBidding
2017 2019 2020
PDR
PDR
2018
Facility ConstructionBidding Design
ASR-5 and ASR-6 Wells
Fitch Park ASR Facility
GC Review of RFPs
8
ASR Wells 5 & 6 RFP Evaluation Criteria
9
Additional future RFPs
• Castroville Pipeline
• Satellite system interconnect pipelines
• Slant Wells Civil & Electrical Work
InterconnectsRR-B & HH-TG
10