LST Mechanical Design Review. Mechanical Installation Preparation H. James Krebs October 21, 2003. Mechanical Installation Preparation. IR-12 will be the location of most mechanical preparation work during 2004 & 2005 Why IR-12? IR-12 Hall is very similar to IR-2 Hall Same floor plan - PowerPoint PPT Presentation

TRANSCRIPT

October 22, 2003 H.J. Krebs 1

LST Mechanical Design Review

Mechanical Installation Preparation

H. James KrebsOctober 21, 2003

October 22, 2003 H.J. Krebs 2

Mechanical Installation Preparation• IR-12 will be the location of most mechanical

preparation work during 2004 & 2005• Why IR-12?

– IR-12 Hall is very similar to IR-2 Hall• Same floor plan• Identical 50/10 ton crane combination

– We need space• IR-12 is empty• IR-2 is presently occupied with BaBar related items

– Present status• 3 technical support staff now housed at IR-12• Engineering offices are under construction

– Estimated completion November 1– Jim Krebs & Zohrab Vassilian move to IR-12 immediately after

completion of this review

October 22, 2003 H.J. Krebs 3

IR-2

October 22, 2003 H.J. Krebs 4

IR-12

October 22, 2003 H.J. Krebs 5

IR-12 Activities• Pre-installation preparation of brass plates

– Radius corners– Drill & tap threaded holes for slide screws and swivel

shackles– Adjust camber if necessary– Stage plates for assembly

• BaBar model– Build a fairly crude but full scale mock-up of the

forward end of BaBar including:• Barrel assembly simulating corner blocks removed• FWD end doors• FWD PEP pier• FWD PEP beam line

October 22, 2003 H.J. Krebs 6

October 22, 2003 H.J. Krebs 7

October 22, 2003 H.J. Krebs 8

12” Thick (Z) Sextant Prototype

October 22, 2003 H.J. Krebs 9

Sextant Iron Cable Channel

October 22, 2003 H.J. Krebs 10

October 22, 2003 H.J. Krebs 11

October 22, 2003 H.J. Krebs 12

October 22, 2003 H.J. Krebs 13

IR-12 Activities• Purpose of Model

– Construct elevator platform• Test function• Check for interferences with end doors, beamline and PEP

pier• Load test• Modify as necessary for corrections or improvements

– Brass installation preparation• Test installation hardware• Load test• Practice brass plate installation• Brass push/pull test (see talk by Allen Constable)

– LST detector installation preparation• Test installation hardware• Practice LST detector installation

– A full Z length (3750mm) gap model exists for this

October 22, 2003 H.J. Krebs 14

Full Z Length (Layer 17) Gap Model

October 22, 2003 H.J. Krebs 15

Full Z Length (3750mm) Gap Model

October 22, 2003 H.J. Krebs 16

IR-12 Activities• Steel handling fixtures

– Train technical support staff– Check centers of gravity– Determine appropriate rigging– Load test– Function test, if possible– Modify as needed

October 22, 2003 H.J. Krebs 17

Test of End Plug Fixture

October 22, 2003 H.J. Krebs 18

Test of End Plug Fixture (Cont’d)

October 22, 2003 H.J. Krebs 19

Test of End Plug Fixture (Cont’d)

October 22, 2003 H.J. Krebs 20

Conclusions and Comments• The full scale model will be a valuable tool for

installation preparation– Earthquake bracing must be designed for this model– EQ committee approval approximately mid November– Construction of model shall commence end of

November• All support personnel will be trained using actual

hardware• Hardware will be tested to assure fit function and

safe operation• Brass absorber will be prepared and staged for

installation