KCI New Terminal Project Update
Transportation, Infrastructure & Operations CommitteeDecember 16, 2020
12/16/2020
-
Agenda
Executive Status Report
Topping Out & Steel Beam Signing Project Progress MWBE/Workforce
Terminal Workforce Enhancement Programs (TWEP)
Upcoming Milestones
12/16/2020
-
Executive Status ReportNovember 2020
12/16/2020
-
12/16/2020
-
12/16/2020
-
12/16/2020
-
12/16/2020
-
12/16/2020
-
12/16/2020
-
12/16/2020
-
12/16/2020
-
1% for Public Art Program
First Call for Entry (CaFE) RFQ for Artists Opened October 13, 2020
Virtual Outreach Events Held October 28th & 31st, 2020 288 Registered
Deadline for First CaFE RFQ December 6, 2020
Proposals Received 1,068 total entries Breakdown:
282 Check In Hall 288 Baggage Claim 262 Node A Fountain 236 Node B
Estimated Selection Committee Recommendation of Finalists to
Municipal Arts Commission April 2021
Second CaFE RFQ for Artists December 2020
Virtual Outreach Events Planned January 6th & 9th, 2021
Concourses CaFE RFQ Spring 2021
12/9/2020
-
View Towards Departures
Site Aerial View
Parking Garage ConstructionDepartures Level Elevated Roadway/Parking Structure
12/16/2020
-
Topping Out & Steel Beam Signing
12/16/2020
-
Topping Out & Steel Beam Signing Commemorates the
completion of steel assembly operations and “topping out” of the final steel structure
Honors the accomplishments of the craftworkers who are bringing the facility to life
KCI New Terminal Project on track to top out in 30 days –on schedule.
12/16/2020
-
Sign the Beam Campaign Community members were invited to add their name to one
of the last steel beams to be placed in the New Terminal at KCI, as a thank you for your donation to the fund.
All donations will go toward the United Way’s COVID-19 Recovery Fund, to provide: Healthcare
Food Insecurity (Groceries & Meal Distribution)
Permanent Housing & Support
Education & Child Care
Other Critical Human Services
12/16/2020
-
12/1/2020
-
Supporting the Community
12/16/2020
-
Project Progress
12/16/2020
-
12/1/2020
10/16/2020
-
12/1/2020
10/16/2020
-
ELEVATED ROADWAY
CONCOURSE A
CONCOURSE CONNECTORCONCOURSE B
HEADHOUSE
PARKING GARAGE
-
Structural Steel
-
Elevated Roadway
https://www.facebook.com/BuildKCI/photos/pcb.786879535225606/786878688559024/?__cft__%5b0%5d=AZWH7Xz2skOedJJa8wJGGtK16-w_l9h9z9rTKhDxGZ_jo0w6XBevWceCwpiowaNM17uljlDk0j-tnXJQXK8aRLvQRYgWY4aJpfHnqJeQgIEh42kcoLrJ9MHKtAF-h7XSsp3a335Wz-F4nHGKH5p3_b-C&__tn__=*bH-R
-
Curtain Wall Installation
-
Parking Garage – Deep Foundation Work
12/1/2020
-
Parking Garage – Precast Erection
-
M/WBE & Workforce Participation
12/16/2020
-
M/WBE Participation Verified Payments
SERVICE TYPE FIRM TYPEFAIRNESS IN
CONSTRUCTION/HRD GOALS
EDGEMOOR DEVELOPER’S
PLEDGE
PAID TO DATEAS OF
DEC. 11, 2020
Professional Services
MBE 17.0% 20.0% 20% $11.2 M
WBE 12.0% 15.0% 13% $7.1 M
Construction Services
MBE 15.0% 20.0% 16% $39.1 M
WBE 9.0% 15.0% 8% $18.7 M
Source: B2G Now
12/16/2020
-
Workforce Participation
CONSTRUCTION EMPLOYMENT
WORKFORCE PARTICIPATION GOALS
WORKFORCE TOTALS AS OF DEC. 11, 2020
Minority Workforce* 20.00% 20%
Women Workforce* 2.75% 7%
KCMO Workforce* N/A 15%
KC Metro Workforce** N/A 81%
12/16/2020
Source: *B2G Now, **E-comply
-
Terminal Workforce Enhancement Programs (TWEP)
12/16/2020
-
12/16/2020
-
TWEP: Workforce Training Program
Congrats to Class 4 - graduated November 6, 2020
Recruitment for future classes to resume January 2021,pending Covid-19 status
12/16/2020
-
TWEP: Workforce Training Program
19 trainees & 13 project partnersponsors
8 Trades represented: Carpenter, cement mason, electrical
worker, ironworker, laborer, roofer,plumber, pipefitter
Demographics: Race:
48% (9) African American, 26% (5)Caucasian, 21% (4),Hispanic/Latino, 5% (1) other
Gender: 85% male (16), 16% female (3)
African American 48%
Caucasian26%
Hispanic/Latino21%
Other5%
Race DemographicsClass 4 Breakdown
12/16/2020
-
Upcoming Milestones in Next 90 Days
Terminal Structure Completion
Temp. Watertight & Heated Spaces
HVAC & Electrical Equipment Deliveries
Permanent Power Activation
Baggage Handling System Sub Starts Onsite
Vehicle Access to Elevated Roadway
12/16/2020
-
New Terminal Construction Status Concrete Slab-on-Grade
Bldgs. 1 – 9, 10A, 11A, 12A, 13 & 14 – Complete Bldg.10B – Start in December. Finish in January 2021
Structural Steel Bldgs. 1, 2, 3, 5, 6, 7, 8, 9, 10A & B, 13 & 14 – Complete Bldg. 11A – Finish in December Bldg. 11B – Finish in January Bldg. 12A - Started Y-Columns & Box Beams – 4 remaining
Elevated Deck & Concrete Slabs on Metal Deck Elevated Decks - Complete Bldgs. 1 – 5, 7, 9, 10A, 11A, 12A, 13 & 14 – SOMD Complete Finish SOMD Bldg. 6 - December Place SOMD Bldg. 8 – December Place SOMD Bldg. 10B – Finish in December Start SOMD Bldg. 11B - December
Precast Exterior Panels Sequence 1 (Bldgs. 10B, 11B & 12B east side) – Complete Sequence 2 (Bldgs. 1, 2 & 3) – Complete Sequence 3 (Bldgs. 9 & 10B (west side)) – Complete Sequence 4 (Bldgs. 12A, 13 & 14) – started 11/25 - Complete in December Sequence 5 (Bldgs. 5 & 6) – start & complete in December
Roofing Bldg. 1 & 14 - Complete Bldgs. 2, 3, 5 & 10A – Ongoing Bldg. 9 – Finish in December Bldg. 6 & 13 – Start in December
12/16/202037
-
New Terminal Construction Status Glass Curtain Wall
Bldg. 1, 2, 3 & 9 – Complete Bldg. 1 & 9 Clearstory – Started Bldg. 5 – Start in December Bldg. 10 - Started
Masonry Bldgs. 1, 2, 3, 7, 9 & 14 – Complete Bldgs. 5, 8, 10B & 13 – Complete in December Bldg. 11A – Start in December Bldg. 12A - Ongoing
Framing (Lower Level) Lower Level
Bldgs. 1, 2, 3, 9, 10A, 13 & 14 – Ongoing Upper Level
Bldgs. 1, 2, 3, & 9 – Ongoing
O/H Mechanical, Electrical & Plumbing (MEP) Rough-In Lower Level
Bldgs. 1, 2, 3, 9, 10A, 13 & 14 – Ongoing Upper Level
Bldgs. 1, 2, 3 & 9 - Ongoing
38 12/16/2020
-
Landside & Airside Civil Projects Elevated Roadway
Complete
Landside Roadways MSE Wall No. 1 (Departure Level Roadway) – Complete Exit Bridge
Double Tee’s Placed Place Roadway Slab - December
MSE Wall No. 2 – (Approach Level Roadway) H-Piling Placed Excavation for MSE Wallpanels - Started
GSE Fueling Pad Piping Installation - Started Completion & Turnover – December/January
Surface Parking Lot Paving North & West Lot - Complete
Airside Civil NE Ramp Demolition/Fill - Started Stormwater Box Culvert – Started Sanitary Sewer - Started MSE Retaining Wall scheduled start – December Taxiway B – Closed Twy. L to Twy. A6
3912/16/2020
-
Landside & Airside Civil Projects Parking Garage
Auger Cast Piling – 1323 out of 1952 Precast Erection (Area 1) – Started & Ongoing
Evergy Terminal Power Distribution – Ongoing Redundant Power – Ongoing
Aviation Fueling Work Area 1 - 10” & 12” Fuel Lines under Connector – Started Work Area 2 – Manifold – December start
40 12/16/2020
-
Stay Tuned
kci-edgemoor.com
cwcjv.comBusiness & Employment Opportunities
buildkci.com
KCI-Edgemoor
KCIAirport
BuildKCI
@kciedgemoor
@kciairport
@BuildKCI
12/16/2020
KCI New Terminal Project UpdateAgendaExecutive Status Report� November 2020Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 111% for Public Art ProgramSlide Number 13Topping Out & Steel Beam SigningTopping Out & Steel Beam SigningSign the Beam CampaignSlide Number 17Supporting the CommunityProject ProgressSlide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27M/WBE & Workforce ParticipationSlide Number 29Workforce ParticipationTerminal Workforce Enhancement Programs (TWEP)Slide Number 32Slide Number 33TWEP: Workforce Training Program TWEP: Workforce Training ProgramUpcoming Milestones in Next 90 DaysNew Terminal Construction StatusNew Terminal Construction StatusLandside & Airside Civil ProjectsLandside & Airside Civil ProjectsSlide Number 41