IBIS2007 1
Chaptre 2. Facility Layout1. Introduction2. Product layout3. Process layout4. Fixed position layout5. Facility layout supplement
IBIS2007 2
IntroductionIntroduction
Facility layout design is necessary when building a new facility or Facility layout design is necessary when building a new facility or renovating an existing one in order to improve process flow and renovating an existing one in order to improve process flow and minimize waste space.minimize waste space.
Facility layout largely depends on the shape and size of the Facility layout largely depends on the shape and size of the building.building.
IBIS2007 3
Facility layout is importantFacility layout is important
The overall layout of a facility will last for long time and only minor The overall layout of a facility will last for long time and only minor changes are possible after the building or renovation.changes are possible after the building or renovation.
Layout has enormous effect on daily operations.Layout has enormous effect on daily operations.
Layout dictate the distance a patient or staff member travelsLayout dictate the distance a patient or staff member travels
Layout influences the interations and communications of the staff Layout influences the interations and communications of the staff members.members.
IBIS2007 4
Goals of Facility layoutGoals of Facility layout
Functionality:Functionality:
• Placing heavily interated departments togetherPlacing heavily interated departments together
• Placing apart departments that should not be closePlacing apart departments that should not be close
• Ensuring space and form requirementsEnsuring space and form requirements
• Facilitating communicationFacilitating communication
Cost savings:Cost savings:
• Reduction of travel timesReduction of travel times
• Reduce overall space requirementReduce overall space requirement
• Enabling for reduced staffing by placing similar job functions Enabling for reduced staffing by placing similar job functions togethertogether
IBIS2007 5
Three basic types of Facility layoutThree basic types of Facility layout
Product LayoutProduct Layout
Process LayoutProcess Layout
Fixed position layoutFixed position layout
Can be used to either a single department or an entire facility.Can be used to either a single department or an entire facility.
But also:But also:
Retail store layoutRetail store layout
Warehousing and storage layout (relation of unloading and Warehousing and storage layout (relation of unloading and loading areas)loading areas)
IBIS2007 6
Types of manufacturing systemsTypes of manufacturing systems
• Job-Shop productionJob-Shop production
• Process layout, functionally similar machines are groupedProcess layout, functionally similar machines are grouped
• Flow-shop productionFlow-shop production
•Product layout, machines are arranged along the Product layout, machines are arranged along the manufacturing processes of a productmanufacturing processes of a product
•Celluaire manufacturing systemsCelluaire manufacturing systems
•Hybrid layout, similar parts and corresponding machines are Hybrid layout, similar parts and corresponding machines are groupedgrouped
• Project shopProject shop
•Product is fixed, personnel and equipment brought to itProduct is fixed, personnel and equipment brought to it
• Continuous-flow processContinuous-flow process
•Chemical plants and flood industryChemical plants and flood industry
IBIS2007 7
Organisation dans les hôpitauxOrganisation dans les hôpitaux
• Principalement une organisation fonctionnelle en unités Principalement une organisation fonctionnelle en unités de soins, plateaux techniques auxquels on associés de soins, plateaux techniques auxquels on associés tous les ressources humaines/matérielles de chaque tous les ressources humaines/matérielles de chaque fonctionfonction
• un patient passe d’une unité à l’autre en fonction des un patient passe d’une unité à l’autre en fonction des soins nécessairessoins nécessaires
• mais aussi des ressources humaines/matérielles mais aussi des ressources humaines/matérielles mutualisées, et des ressources humaines détachées à mutualisées, et des ressources humaines détachées à d’autres unités, ...d’autres unités, ...
IBIS2007 8
Layout of an emergency departmentLayout of an emergency department
SurgerySurgery
RadiologyRadiology
E.R. triage roomE.R. triage room Emergency room admissionsEmergency room admissions
LaboratoriesLaboratories
E.R. bedsE.R. beds PharmacyPharmacy Billing/exitBilling/exit
Patient APatient A
Patient BPatient B
Patient A (broken leg) proceeds to ER triage, radiology, surgery, bed, Patient A (broken leg) proceeds to ER triage, radiology, surgery, bed, pharmacy, billing. Patient B (pacemaker rpoblem): ER triage, surgery, pharmacy, billing. Patient B (pacemaker rpoblem): ER triage, surgery, pharmacy, lab, bed, billing.pharmacy, lab, bed, billing.
IBIS2007 9
Chaptre 2. Facility Layout1. Introduction2. Product layout3. Process layout4. Fixed position layout
IBIS2007 10
Product LayoutProduct Layout
The product layout arranges equipment (departments) in the The product layout arranges equipment (departments) in the order of production process flow.order of production process flow.
Generally used in mass production such as automobile assembly Generally used in mass production such as automobile assembly where the processes are standardized and there is little variation.where the processes are standardized and there is little variation.
Product layout is generally less flexible and requires higher initial Product layout is generally less flexible and requires higher initial equipment costs.equipment costs.
But it minimizes the process cycle time and increases equipment But it minimizes the process cycle time and increases equipment utilisation.utilisation.
Examples: hospital cafeteria, standardized biological tests.Examples: hospital cafeteria, standardized biological tests.
IBIS2007 11
Product LayoutProduct Layout
Product layout, known as assembly line balancing problem, is Product layout, known as assembly line balancing problem, is generally determined by the product or service itself.generally determined by the product or service itself.
Most decisions concern Most decisions concern
• assignment of basic operations to different workstations assignment of basic operations to different workstations
• in order to balance the workloads in order to balance the workloads
• such that each station has approximately the same cycle time, such that each station has approximately the same cycle time, i.e. the time for one item to pass through that workstation i.e. the time for one item to pass through that workstation (Why)(Why)
Two types of problems:Two types of problems:
• Using a minimum number of workstations to achieve a given Using a minimum number of workstations to achieve a given cycle timecycle time
• Minimizing the cycle time given the nb of workstationsMinimizing the cycle time given the nb of workstations
IBIS2007 12
Product LayoutProduct Layout
An example of 3 stations and cycle time 70.An example of 3 stations and cycle time 70.
Waste time = ?, workstation cycle time = ?Waste time = ?, workstation cycle time = ?
IBIS2007 13
Product layoutProduct layout
• Since variability is inherent in health care, the product layout is Since variability is inherent in health care, the product layout is rarely used in health care other than for supporting activitiesrarely used in health care other than for supporting activities
• Although the health care process is similar for a patient group Although the health care process is similar for a patient group with similar diagnosis, the amount of time that patients spend in with similar diagnosis, the amount of time that patients spend in each process varies greatly. Line balancing is impossible.each process varies greatly. Line balancing is impossible.
IBIS2007 14
Chaptre 2. Facility Layout1. Introduction2. Product layout3. Process layout4. Fixed position layout
IBIS2007 15
Process layoutProcess layout
The process layout, known as layout by functionality, groups The process layout, known as layout by functionality, groups different types of process (departments, equipments) together to different types of process (departments, equipments) together to provide the maximum flexibility.provide the maximum flexibility.
Hospital groups together functions such as intensive care, Hospital groups together functions such as intensive care, surgery, emergency medecine, and radiology as separate surgery, emergency medecine, and radiology as separate departmentsdepartments
The flexibility allows accomodate the variability of patient flows The flexibility allows accomodate the variability of patient flows and times while preserving high utilisation of resourcesand times while preserving high utilisation of resources
The downside of a process layout is the large travel time, and The downside of a process layout is the large travel time, and high material handling costs. A good layout will reduce this high material handling costs. A good layout will reduce this negative impact.negative impact.
IBIS2007 16
Closeness-based methodCloseness-based method
Identify the desireness and undesireness of closeness by Identify the desireness and undesireness of closeness by closeness rating chartcloseness rating chart..
Codes for desired closeness:Codes for desired closeness:
A – absolute necessaryA – absolute necessary
E – very importantE – very important
I – importantI – important
O – ordinary importantO – ordinary important
U – unimportantU – unimportant
X – undesirable.X – undesirable.
IBIS2007 17
Closeness-based methodCloseness-based method
Closeness rating chartingCloseness rating charting
A
E
AO
U
IE
X
I
E
U
I
U
X
X
1. Nurses’ station1. Nurses’ station
2. Ambulance entrance2. Ambulance entrance
3. Patient Room Area3. Patient Room Area
4. Laundry4. Laundry
5. Main entrance5. Main entrance
6. Dietary Department6. Dietary Department
40*8040*80
40*4040*40
remainingremaining
40*8040*80
80*8080*80
40*8040*80
area in marea in m DepartmentDepartment
IBIS2007 18
Closeness-based methodCloseness-based method
Using a heuristic rule to design layout.Using a heuristic rule to design layout.
Step 1. Assign departments to available spaces according Step 1. Assign departments to available spaces according desired closeness relationships identified as absolutely necessary desired closeness relationships identified as absolutely necessary or undesirable, i.e. A and X, by starting with the most frequent or undesirable, i.e. A and X, by starting with the most frequent department in either relationship.department in either relationship.
A graph representation of A and X closeness can be built.A graph representation of A and X closeness can be built.
Step 2. Consider other departments with relationships E, I, O, U.Step 2. Consider other departments with relationships E, I, O, U.
IBIS2007 19
Closeness-based methodCloseness-based method
Ambulance Ambulance entranceentrance
Nurses’Nurses’StationStation
PatientPatientroom arearoom area
Main entranceMain entrance
LaundryLaundry
DietaryDietaryDepartmentDepartment
AA AA
XX
XX
XX
A and X closeness representationA and X closeness representation
IBIS2007 20
Closeness-based methodCloseness-based method
2 Ambulance 2 Ambulance entranceentrance
1 Nurses’1 Nurses’StationStation
3 Patient3 Patientroom arearoom area
5 Main entrance5 Main entrance
4 Laundry4 Laundry
6 Dietary6 DietaryDepartmentDepartment
AA AA
XX
XX
XX
A and X closeness representationA and X closeness representation
IBIS2007 21
Closeness-based methodCloseness-based method
Final layoutFinal layout
5. main5. mainentranceentrance
Amb.Amb.entranceentrance
4. L
aun
dry
4. L
aun
dry
6. D
ieta
ry6
. Die
tary
De
pt.
De
pt.
1 nurses’1 nurses’stationstation
3. Patient Room area3. Patient Room area
400 m400 m
200 m200 m
IBIS2007 22
Distance and cost-based methodDistance and cost-based method
This method tries to minimize the costs or repetitive distances This method tries to minimize the costs or repetitive distances traveled by patients and staff.traveled by patients and staff.
Data representing such traffic are represented in a Data representing such traffic are represented in a from-to chartfrom-to chart which represents the nb of trips or flows between departments.which represents the nb of trips or flows between departments.
Once the traffic information is identified, departments with most Once the traffic information is identified, departments with most frequent traffics are assigned to adjacent locations.frequent traffics are assigned to adjacent locations.
Informations such as department space requirement, fixed Informations such as department space requirement, fixed locations, ... can be taken into account.locations, ... can be taken into account.
The problem is highly combinatorial when the nb of department is The problem is highly combinatorial when the nb of department is large and software tools such as CRAFT are necessary.large and software tools such as CRAFT are necessary.
IBIS2007 23
Distance and cost-based methodDistance and cost-based method
Formall, the objective is to Formall, the objective is to
Minimize total cost TC = Minimize total cost TC = ijij D Dijij W Wijij C Cijij
wherewhere
W =[WW =[Wijij] is the From-To traffic matrix] is the From-To traffic matrix
D =[DD =[Dijij] is the distance matrix (Manhattan distance or Euclidean ] is the distance matrix (Manhattan distance or Euclidean
distance, why)distance, why)
C =[CC =[Cijij] is the unit traffic cost] is the unit traffic cost
IBIS2007 24
Distance and cost-based method Distance and cost-based method
Example:Example:
Consider a small hospital of 3 departments A, B, C. Three Consider a small hospital of 3 departments A, B, C. Three locations 1, 2, 3 of identical size are available.locations 1, 2, 3 of identical size are available.
Assume that a nurse can walk 100 feet in 30 seconds and earn Assume that a nurse can walk 100 feet in 30 seconds and earn $48 per hour.$48 per hour.
Unit traffic cost Cij = 0.004$ / foot walkUnit traffic cost Cij = 0.004$ / foot walk
locationlocation11
locationlocation22
locationlocation33
100 feet 100 feet100 feet 100 feet
IBIS2007 25
Distance and cost-based methodDistance and cost-based method
Distance matrix (in feet)Distance matrix (in feet)
LocationLocation
From/ToFrom/To 11 22 33
11 -- 100100 200200
22 100100 -- 100100
33 200200 100100 --
Condensed traffic matrixCondensed traffic matrix
DepartmentDepartment
From/ToFrom/To AA BB CC
AA -- 33003300 14001400
BB -- 200200
CC --
Traffic matrix (in trips)Traffic matrix (in trips)
DepartmentDepartment
From/ToFrom/To AA BB CC
AA -- 10001000 300300
BB 23002300 -- 100100
CC 11001100 100100 --
IBIS2007 26
Distance and cost-based methodDistance and cost-based method
locationconfiguration 1 2 3 TC
1 A B C 2520$2 A C B 3280$3 B A C 2040$4 B C A 3280$5 C A B 2040$6 C B A 2520$
Dept.Dept.BB
Dept.Dept.AA
Dept.Dept.CC
IBIS2007 27
Distance and cost-based method : example 2Distance and cost-based method : example 2
The Walters Company’s management wants to arrange the 6 The Walters Company’s management wants to arrange the 6 departments of its hospital in a way that will minimise departments of its hospital in a way that will minimise interdepartmental material handling costs. They make an initial interdepartmental material handling costs. They make an initial assumption (to simplify the problem) that each department is 20x20 assumption (to simplify the problem) that each department is 20x20 feet and that the building is 60 feet long and 40 feet wide. The feet and that the building is 60 feet long and 40 feet wide. The process layout procedure that they follow involves 6 steps.process layout procedure that they follow involves 6 steps.
IBIS2007 28
Distance and cost-based method : example 2Distance and cost-based method : example 2
Step 1. Construct a « from-to-matrix » showing the flow of patients Step 1. Construct a « from-to-matrix » showing the flow of patients or personnals from department to department.or personnals from department to department.
50 100 0 0 20
30 50 10 0
20 0 100
50 0
0
IBIS2007 29
Distance and cost-based method : example 2Distance and cost-based method : example 2
Step 2. Determine the space requirements of each department.Step 2. Determine the space requirements of each department.
DepartmentDepartment
11
DepartmentDepartment
22
DepartmentDepartment
33
DepartmentDepartment
44
DepartmentDepartment
55
DepartmentDepartment
66
room1room1 room2room2 room3room3
room4room4 room5room5 room6room6
Building dimensions and a possible department layoutBuilding dimensions and a possible department layout
IBIS2007 30
Distance and cost-based method : example 2Distance and cost-based method : example 2
Step 3. Develop an intial schematic diagram showing the sequence Step 3. Develop an intial schematic diagram showing the sequence of departments through which patients will have to move. Try to of departments through which patients will have to move. Try to place departments of heavy flow next to one antoher.place departments of heavy flow next to one antoher.
11 22 33
4455
66
5050 3030
100100
2020
5050
1010 2020100100
5050
IBIS2007 31
Distance and cost-based method : example 2Distance and cost-based method : example 2
Step 4. Determine the cost of this layout with traffic cost of 1€ Step 4. Determine the cost of this layout with traffic cost of 1€ between adjacent departments and 2€ between non adjacent between adjacent departments and 2€ between non adjacent departments.departments.
Cost = 570 €.Cost = 570 €.
11 22 33
4455
66
5050 3030
100100
2020
5050
1010 2020100100
5050
IBIS2007 32
Distance and cost-based method : example 2Distance and cost-based method : example 2
Step 5. Try to improve this layout by trial and error to establish a Step 5. Try to improve this layout by trial and error to establish a reasonable good arrangement.reasonable good arrangement.
Switch departments 1-2 as there is a heavy traffic between dept. 1-Switch departments 1-2 as there is a heavy traffic between dept. 1-3. Cost = 480 €.3. Cost = 480 €.
DepartmentDepartment
22
DepartmentDepartment
11
DepartmentDepartment
33
DepartmentDepartment
44
DepartmentDepartment
55
DepartmentDepartment
66
room1room1 room2room2 room3room3
room4room4 room5room5 room6room6
IBIS2007 33
Distance and cost-based method : example 2Distance and cost-based method : example 2
Step 6. Prepare a detailed place considering space or size Step 6. Prepare a detailed place considering space or size requirements of each department; that is, arrange the departments requirements of each department; that is, arrange the departments to fit the shape of the building and obstables.to fit the shape of the building and obstables.
IBIS2007 34
Mathematical model for identical dept. Mathematical model for identical dept.
Problem: Locate N department on N locations in order to minimize Problem: Locate N department on N locations in order to minimize total traffic cost.total traffic cost.
Decision variable : Xij = 1 if dept. i is located at location jDecision variable : Xij = 1 if dept. i is located at location j
Minimize TC = Minimize TC = ijij i’j’i’j’ D Djj’jj’ W Wii’ii’ C Cij ij XXij ij XXi’j’i’j’
wherewhere
jj X Xij ij = = ii X Xij ij =1=1
W : traffic matrix, D : distance matrixW : traffic matrix, D : distance matrix
C : unit traffic costC : unit traffic cost
Linear Programming model can be developped for the case of Linear Programming model can be developped for the case of rectangular departments of different sizes.rectangular departments of different sizes.
IBIS2007 35
Mathematical model for identical dept. Mathematical model for identical dept.
Problem: Locate N department on N locations in order to minimize Problem: Locate N department on N locations in order to minimize total traffic cost.total traffic cost.
Decision variable : Xij = 1 if dept. i is located at location jDecision variable : Xij = 1 if dept. i is located at location j
Minimize TC = Minimize TC = ijij i’j’i’j’ D Djj’jj’ W Wii’ii’ C Cij ij XXij ij XXi’j’i’j’
wherewhere
jj X Xij ij = = ii X Xij ij =1=1
W : traffic matrix, D : distance matrixW : traffic matrix, D : distance matrix
C : unit traffic costC : unit traffic cost
Linear Programming model can be developped for the case of Linear Programming model can be developped for the case of rectangular departments of different sizes.rectangular departments of different sizes.
IBIS2007 36
Chaptre 2. Facility Layout1. Introduction2. Product layout3. Process layout4. Fixed position layout
IBIS2007 37
Fixed position layout Fixed position layout
The fixed-position layout consists of the fixed service positions The fixed-position layout consists of the fixed service positions where personnel and materials come together to perform the where personnel and materials come together to perform the service.service.
Generally used in industry when the product is either too large or Generally used in industry when the product is either too large or too delicate to more such as airplane assembly.too delicate to more such as airplane assembly.
In inpatient hospital rooms (especially in an intensive care unit), the In inpatient hospital rooms (especially in an intensive care unit), the service position is the patien bed.service position is the patien bed.
The operating table in an operating room is another example.The operating table in an operating room is another example.
IBIS2007 38
Fixed position layout Fixed position layout
Designing a fixed position layout entails positiioning several service Designing a fixed position layout entails positiioning several service positions withing a given area, each of which may require an positions withing a given area, each of which may require an adjacent but separate support area.adjacent but separate support area.
Conflicts about space constraints and timing have to be resolved Conflicts about space constraints and timing have to be resolved (suspended x-ray machine and overhead lighting)(suspended x-ray machine and overhead lighting)
IBIS2007 39
Chaptre 2. Facility Layout1. Introduction2. Product layout3. Process layout4. Fixed position layout5. Facility layout supplement
IBIS2007 40
Fixed position layout Fixed position layout
Designing a fixed position layout entails positiioning several service Designing a fixed position layout entails positiioning several service positions withing a given area, each of which may require an positions withing a given area, each of which may require an adjacent but separate support area.adjacent but separate support area.
Conflicts about space constraints and timing have to be resolved Conflicts about space constraints and timing have to be resolved (suspended x-ray machine and overhead lighting)(suspended x-ray machine and overhead lighting)