I-75 Update Northern Kentucky to Montgomery County Traffic Engineering Workshop

June 5, 2013

Corridor Improvement Projects

• KY 338 and KY 536 DCD Interchanges

• Brent Spence Bridge

• Mill Creek Expressway

• Thru the Valley

• Hamilton/Butler I-75 Widening

• Butler/Warren I-75 Widening

• Warren I-75 Widening

KY 338 (Richwood Road) DCD Interchange Project

KY 338 (Richwood Road) DCD Interchange Project

KY 338 (Richwood Road) DCD Interchange Project

KY 536 (Mt. Zion Road) DCD Interchange Project

North South Transportation Initiative (NSTI)

• Major Investment Study conducted by Ohio-Kentucky-Indiana Regional Council of Governments (OKI) and the Miami Valley Regional Planning Commission (MVRPC)

• Began in 2000 and completed in 2004

• OKI Board of Trustees accepted the report recommendation of Four continuous lanes on Interstate 75 throughout the OKI region, including auxiliary lanes as warranted.

• The NSTI also recommended a series of Access Modification Alternatives to be balanced with the overall Corridor Capacity improvements

I-75 Corridor Major Projects

The purpose of the project is to: • Improve safety

• Improve traffic flow and level of service

• Correct geometric deficiencies

• Maintain connections to key regional and national

transportation corridors

PURPOSE

STUDY AREA

• Project length: 7.8

miles

• $2.7 billion in

construction costs

• Safety concerns

• Functionally obsolete

• 172,000 vehicles per

day

• $417 billion in freight

• Connecting 10 states

• Steps One – Four

• 25 conceptual alternatives were studied

• Five alternatives and several sub-alternatives were

recommended for further study

• Steps Five – Six

• Eight conceptual alternatives were studied in detail

• Steps Six – Seven: completed in August 2012

• Alternatives E and I were recommended for further study

ALTERNATIVE I

• Design features provide

better level of service on the

freeway system

• Minimizes environmental

impacts

• Lower costs

• New bridge west of existing

Brent Spence Bridge

PREFERRED ALTERNATIVE

CONFIGURATION- KENTUCKY

CONNECT TO EXISTING

LANE CONFIGURATION,

3 LANES NORTHBOUND,

4 LANES SOUTHBOUND

6 LANES EACH

DIRECTION IN

CUT-IN-HILL SECTION

NEW BRIDGE OVER

OHIO RIVER, WEST

OF EXISTING BRIDGE

COVINGTON CONFIGURATIONS

ALTERNATIVE I

BRIDGE CONFIGURATIONS

ALTERNATIVE I

•Existing Brent Spence Bridge will remain •Top Deck: Interstate-71 NB: two lanes with two full-width shoulders

•Lower Deck: Collector Distributor NB: three lanes with one full-width shoulder

•New Double Deck Bridge •Top Deck: Interstate-71 SB: two lanes with two full-width shoulders; and

Interstate-75 SB: three lanes with two full-width shoulders

•Lower Deck: Interstate-75 NB: three lanes with two full-width shoulders; and

Collector Distributor SB: three lanes with two full-width shoulders

Interstate-71 Interstate-75 Local

BRIDGE CONFIGURATIONS

ALTERNATIVE I

BRIDGE TYPE SELECTION

ALTERNATIVE 1

BRIDGE TYPE SELECTION

ALTERNATIVE 3

PREFERRED ALTERNATIVE

CONFIGURATION- OHIO

NEW BRIDGE OVER

OHIO RIVER, WEST

OF EXISTING BRIDGE

NEW INTERCHANGE

AT WESTERN HILLS

VIADUCT

CINCINNATI CONFIGURATIONS

ALTERNATIVE I

PROJECT SUMMARY

• 7.8 mile corridor

• $2.7 billion in construction costs

• Safety concern

• Functionally obsolete

• 172,000 vehicles per day

• 17% trucks, over 30,000 per day

• $417 billion in freight

• Connecting to 10 states

DELIVERING

THE PROJECT

• Traditional funding

method =

construction in 2040

or later

Value for Money

Study (VfM) –

Opt ions Ana lys i s

• Reviews current and future costs of project along with evaluation of current design (Value Engineering)

• Explores project delivery

options for construction of a new corridor

• Study should show which

delivery option is most cost-effective

Mill Creek Expressway

MCE Project Summary • Phase 1: HAM-75-5.58, PID 82278; Award Date – May 2011; Completion Date – Sept. 2014

• Reconstruct I-75 on new horizontal and vertical alignments to allow for four continuous lanes in each direction.

• Reconstruct the Mitchell Avenue interchange to a Tight Urban Diamond Interchange to relieve congestion and improve safety.

• Widen Mitchell Avenue to accommodate the new interchange design.

• Phase 2: HAM-75-3.68, PID 82282; Award Date – Feb. 2010; Completion Date – Sept. 2011

• Replacement of the Monmouth Street overpass. • Reconstruction of Monmouth Street and its conversion to a local through street between Central

Parkway and Colerain Avenue. • Removal of the Bates Avenue Bridge to clear an overhead obstruction to future mainline

construction. • Removal of the pedestrian bridge between Colerain Avenue and Central Parkway to clear an

overhead obstruction to future mainline construction.

• Phase 3: HAM-74-18.00, PID 82284; Award Date – Nov. 2011 ; Completion Date – Sept. 2014 • Reconstruct the Colerain Avenue and Beekman Street intersection. • Upgrade the current ramps at the interchange by providing new pavement or pavement

rehabilitation. • Converting the facility to curb and gutter design, and adding pedestrian access between Colerain

Avenue and Elmore Street along the Beekman Street corridor. • Adding a westbound I-74 Access from Colerain Avenue. • Removing the ramp from I-74 WB to Elmore Street. • Removing the ramp from Spring Grove Avenue to I-74 EB.

MCE Project Summary • Phase 4: HAM-75-2.30, PID 76257; Award Date – Nov. 2012; Completion Date – July 2017

• Reconstruct I-75 on new horizontal and vertical alignments to allow for four continuous lanes in each direction. Provide auxiliary lanes between interchanges.

• Reconstruct the Hopple Street interchange and improve traffic operations on Hopple Street and Martin Luther King Drive.

• Construct noise walls along the I-75 corridor • Eliminate a left hand exit off of I-75 NB. • Provide full directional movement to I-75 from the Hopple Street interchange, eliminating the need for

local access at the I-74/75 interchange. • Construct new connector road for Hopple Street to Central Parkway

• Phase 5: HAM-75-3.85, PID 83723; Award Date – Oct. 2020; Completion Date – Aug. 2024

• Reconstruct I-75 on new horizontal and vertical alignments to allow for the addition of one continuous lane in each direction.

• Reconstruct I-74 between the I-74/75 interchange and the Beekman Street interchange to reduce congestion and improve safety.

• Reconstruct the I-74/75 interchange to relieve congestion and improve safety. • Construct noise walls along the I-74 corridor. • Eliminate local access ramps within the I-74/75 system interchange.

• Phase 6: HAM-75-7.72, PID 82283; Award Date – May 2013; Completion Date – Sept. 2015

• Replace existing RR Bridge over I-75 with a new bridge on new alignment. New bridge will accommodate future mainline I-75 design.

• New bridge will be designed to accommodate two tracks

MCE Project Summary • Phase 7: HAM-75-6.78, PID 82286; Award Date – Oct. 2020; Completion Date – Oct. 2023

• Reconstruct I-75 on new horizontal and vertical alignments to allow for four continuous lanes in each direction. Provide auxiliary lanes between interchanges as required.

• Construct noise walls along the I-75 corridor

• Phase 8: HAM-75-7.85, PID 77889; Award Date – Oct. 2017*; Completion Date – Oct. 2020

• Reconstruct I-75 on new horizontal and vertical alignments to allow for four continuous lanes in each direction. Provide auxiliary lanes between interchanges as required.

• Construct noise walls along the I-75 corridor.

• Reconstruct the I-75 interchange with SR-562 to improve safety and relieve congestion.

• Removal of the partial interchange with Towne Street.

• Phase 8A: HAM-4/561-2.66/7.01, PID 89835; Award Date – Apr. 2016*;

Completion Date – Oct. 2016

• Replace Bridge carrying Seymour Ave. over I-75.

• Reconstruct portions of Bridge Number HAM-4-0266.

* Earliest possible Award Dates. Phases 8 and 8A do not have committed construction funding

Thru the Valley

TTV Project Summary • Phase 1: HAM-75-12.60, PID 82288; Award Date – Oct. 2015; Completion Date – Oct. 2018

• The scope of Phase 1 reconstruction limits are from south of Shepherd Lane to north of Glendale Milford Road. The following work is to be undertaken:

• Reconstruct IR 75 to allow for four continuous lanes in each direction • Reconstruct the Shepherd Lane interchange by moving the southbound ramps at Mangham Drive to

Shepherd Lane • Reconstruct the Glendale Milford interchange to accommodate capacity improvements Add auxiliary

lanes between Shepherd Lane and Glendale Milford Road

• Phase 2: HAM-GE Parkway, PID 88135; Award Date – Oct. 2015*; Completion Date – Oct. 2018 • The scope of Phase 2 reconstruction limits are from Shepherd Lane to Glendale Milford Road. The following

work is to be undertaken:

• Construct a local road between Shepherd Lane and Glendale Milford Road east and adjacent to IR 75 • Construct a ramp from southbound IR 75 at Glendale Milford road to tie in to the new local road.

• Phase 3: HAM-75-10.10, PID 88124; Award Date – April 2016* ; Completion Date – Oct. 2018 • The scope of Phase 3 reconstruction limits are from Paddock Road to Galbraith Road. The following work is

to be undertaken:

• Reconstruct IR 75 to allow for four continuous lanes in each direction • Reconstruct the left hand exit from northbound IR 75 to Galbraith Road as a right hand exit • Improve ramps for eastbound SR 126 to southbound IR 75, Galbraith Road to southbound IR 75 and

northbound IR 75 to eastbound and westbound SR 126 • Add auxiliary lanes between Paddock Road and SR 126

* Earliest possible Award Dates. Phases 2 and 3 do not have committed construction funding

TTV Project Summary • Phase 4: HAM-75-11.09, PID 88129; Award Date – Oct. 2015*; Completion Date –July 2017

• The scope of Phase 4 is to replace the railroad bridge over southbound IR 75. The following work is to be undertaken:

• Replace the Norfolk Southern railroad bridge over southbound IR 75 and the Millcreek

• Phase 5: HAM-75-11.02, PID 88132; Award Date – April 2016*; Completion Date–Oct. 2017 • The scope of Phase 5 reconstruction limits are Galbraith Road to south of Shepherd Lane on southbound IR

75. The following work is to be undertaken:

• Reconstruct southbound IR 75 to allow for four continuous lanes

• Construct an exit to Galbraith Road and Anthony Wayne Avenue with a C-D type ramp

• Add auxiliary lane between Galbraith Road and Shepherd Lane

• Phase 6: HAM-75-11.05, PID 88133; Award Date – Jan. 2018* ; Completion Date–Oct. 2019

• The scope of Phase 6 reconstruction limits are Galbraith Road to south of Shepherd Lane on northbound IR 75. The following work is to be undertaken:

• Reconstruct northbound IR 75 to allow for four continuous lanes

• Add auxiliary lane between Galbraith Road and Shepherd Lane

* Earliest possible Award Dates. Phases 4, 5 and 6 do not have committed construction funding

TTV Project Summary • Phase 7: HAM-75-10.52, PID 88134; Award Date – Jan. 2017; Completion Date – Oct. 2018

• The scope of Phase 7 is to add two ramps to the IR 75 and SR 126 interchange. The following work is to be undertaken:

• Construct a ramp for westbound SR 126 to northbound IR 75

• Construct a ramp for southbound IR 75 to westbound SR 126

• Remove existing ramp for Galbraith Road to westbound SR 126

• Phase 8: HAM-75-10.10, PID 76256; Award Date – Jan. 2017; Completion Date – Oct. 2018 • The scope of Phase 8 reconstruction limits are Glendale Milford to Kemper Road. The following work is to be

undertaken:

• Reconstruct IR 75 to allow for four continuous lanes in each direction

• Improve ramp capacity at the Sharon Road interchange

• Add auxiliary lanes between Glendale Milford Road and Sharon Road and between Sharon Road and IR 275

• HAM- Demo Stearns / Foster, PID 95567; Award Date – May 2014; Completion Date – Jan. 2015 • The scope is to demolish the remaining Stearns and Foster structure.

* Earliest possible Award Dates. Phases 7 and 8 do not have committed construction funding

Northern Corridor Projects

• Hamilton/Butler I-75 Widening; Award Date – 2002; Completion Date – 2005

• Rehabilitation of I-75 and overpasses between I-275 and Tylersville Road.

• Addition of 1 through lane in each direction of I-75

• Butler/Warren I-75 Widening; Award Date – 2007; Completion Date – 2011

• Rehabilitation of I-75 and overpasses between Tylersville Road. and SR 122

• Addition of 1 through lane in each direction of I-75

• Reconstruction of SR 63 interchange into a SPUI

• Warren I-75 Widening; Award Date – 2009; Completion Date – 2012

• Rehabilitation of I-75 and overpasses between SR 122 and Montgomery County Line

• Addition of 1 through lane in each direction of I-75

• Reconstruction of SR 122 interchange

• Reconstruction of the SR 73 interchange

• Widening of SR 122

THANK YOU