I-75 Update Northern Kentucky to Montgomery County Traffic Engineering Workshop June 5, 2013

Upload: vuongdat

Post on 21-Aug-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

I-75 Update Northern Kentucky to Montgomery County Traffic Engineering Workshop

June 5, 2013

Page 2: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

Corridor Improvement Projects

• KY 338 and KY 536 DCD Interchanges

• Brent Spence Bridge

• Mill Creek Expressway

• Thru the Valley

• Hamilton/Butler I-75 Widening

• Butler/Warren I-75 Widening

• Warren I-75 Widening

Page 3: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

KY 338 (Richwood Road) DCD Interchange Project

Page 4: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

KY 338 (Richwood Road) DCD Interchange Project

Page 5: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

KY 338 (Richwood Road) DCD Interchange Project

Page 6: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

KY 536 (Mt. Zion Road) DCD Interchange Project

Page 7: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

North South Transportation Initiative (NSTI)

• Major Investment Study conducted by Ohio-Kentucky-Indiana Regional Council of Governments (OKI) and the Miami Valley Regional Planning Commission (MVRPC)

• Began in 2000 and completed in 2004

• OKI Board of Trustees accepted the report recommendation of Four continuous lanes on Interstate 75 throughout the OKI region, including auxiliary lanes as warranted.

• The NSTI also recommended a series of Access Modification Alternatives to be balanced with the overall Corridor Capacity improvements

Page 8: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

I-75 Corridor Major Projects

Page 9: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

The purpose of the project is to: • Improve safety

• Improve traffic flow and level of service

• Correct geometric deficiencies

• Maintain connections to key regional and national

transportation corridors

PURPOSE

Page 10: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

STUDY AREA

• Project length: 7.8

miles

• $2.7 billion in

construction costs

• Safety concerns

• Functionally obsolete

• 172,000 vehicles per

day

• $417 billion in freight

• Connecting 10 states

Page 11: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

• Steps One – Four

• 25 conceptual alternatives were studied

• Five alternatives and several sub-alternatives were

recommended for further study

• Steps Five – Six

• Eight conceptual alternatives were studied in detail

• Steps Six – Seven: completed in August 2012

• Alternatives E and I were recommended for further study

Page 12: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

ALTERNATIVE I

• Design features provide

better level of service on the

freeway system

• Minimizes environmental

impacts

• Lower costs

• New bridge west of existing

Brent Spence Bridge

Page 13: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

PREFERRED ALTERNATIVE

CONFIGURATION- KENTUCKY

CONNECT TO EXISTING

LANE CONFIGURATION,

3 LANES NORTHBOUND,

4 LANES SOUTHBOUND

6 LANES EACH

DIRECTION IN

CUT-IN-HILL SECTION

NEW BRIDGE OVER

OHIO RIVER, WEST

OF EXISTING BRIDGE

Page 14: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

COVINGTON CONFIGURATIONS

ALTERNATIVE I

Page 15: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

BRIDGE CONFIGURATIONS

ALTERNATIVE I

Page 16: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

•Existing Brent Spence Bridge will remain •Top Deck: Interstate-71 NB: two lanes with two full-width shoulders

•Lower Deck: Collector Distributor NB: three lanes with one full-width shoulder

•New Double Deck Bridge •Top Deck: Interstate-71 SB: two lanes with two full-width shoulders; and

Interstate-75 SB: three lanes with two full-width shoulders

•Lower Deck: Interstate-75 NB: three lanes with two full-width shoulders; and

Collector Distributor SB: three lanes with two full-width shoulders

Interstate-71 Interstate-75 Local

BRIDGE CONFIGURATIONS

ALTERNATIVE I

Page 17: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

BRIDGE TYPE SELECTION

ALTERNATIVE 1

Page 18: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

BRIDGE TYPE SELECTION

ALTERNATIVE 3

Page 19: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

PREFERRED ALTERNATIVE

CONFIGURATION- OHIO

NEW BRIDGE OVER

OHIO RIVER, WEST

OF EXISTING BRIDGE

NEW INTERCHANGE

AT WESTERN HILLS

VIADUCT

Page 20: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

CINCINNATI CONFIGURATIONS

ALTERNATIVE I

Page 21: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

PROJECT SUMMARY

• 7.8 mile corridor

• $2.7 billion in construction costs

• Safety concern

• Functionally obsolete

• 172,000 vehicles per day

• 17% trucks, over 30,000 per day

• $417 billion in freight

• Connecting to 10 states

Page 22: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

DELIVERING

THE PROJECT

• Traditional funding

method =

construction in 2040

or later

Page 23: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

Value for Money

Study (VfM) –

Opt ions Ana lys i s

• Reviews current and future costs of project along with evaluation of current design (Value Engineering)

• Explores project delivery

options for construction of a new corridor

• Study should show which

delivery option is most cost-effective

Page 24: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

Mill Creek Expressway

Page 25: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

MCE Project Summary • Phase 1: HAM-75-5.58, PID 82278; Award Date – May 2011; Completion Date – Sept. 2014

• Reconstruct I-75 on new horizontal and vertical alignments to allow for four continuous lanes in each direction.

• Reconstruct the Mitchell Avenue interchange to a Tight Urban Diamond Interchange to relieve congestion and improve safety.

• Widen Mitchell Avenue to accommodate the new interchange design.

• Phase 2: HAM-75-3.68, PID 82282; Award Date – Feb. 2010; Completion Date – Sept. 2011

• Replacement of the Monmouth Street overpass. • Reconstruction of Monmouth Street and its conversion to a local through street between Central

Parkway and Colerain Avenue. • Removal of the Bates Avenue Bridge to clear an overhead obstruction to future mainline

construction. • Removal of the pedestrian bridge between Colerain Avenue and Central Parkway to clear an

overhead obstruction to future mainline construction.

• Phase 3: HAM-74-18.00, PID 82284; Award Date – Nov. 2011 ; Completion Date – Sept. 2014 • Reconstruct the Colerain Avenue and Beekman Street intersection. • Upgrade the current ramps at the interchange by providing new pavement or pavement

rehabilitation. • Converting the facility to curb and gutter design, and adding pedestrian access between Colerain

Avenue and Elmore Street along the Beekman Street corridor. • Adding a westbound I-74 Access from Colerain Avenue. • Removing the ramp from I-74 WB to Elmore Street. • Removing the ramp from Spring Grove Avenue to I-74 EB.

Page 26: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

MCE Project Summary • Phase 4: HAM-75-2.30, PID 76257; Award Date – Nov. 2012; Completion Date – July 2017

• Reconstruct I-75 on new horizontal and vertical alignments to allow for four continuous lanes in each direction. Provide auxiliary lanes between interchanges.

• Reconstruct the Hopple Street interchange and improve traffic operations on Hopple Street and Martin Luther King Drive.

• Construct noise walls along the I-75 corridor • Eliminate a left hand exit off of I-75 NB. • Provide full directional movement to I-75 from the Hopple Street interchange, eliminating the need for

local access at the I-74/75 interchange. • Construct new connector road for Hopple Street to Central Parkway

• Phase 5: HAM-75-3.85, PID 83723; Award Date – Oct. 2020; Completion Date – Aug. 2024

• Reconstruct I-75 on new horizontal and vertical alignments to allow for the addition of one continuous lane in each direction.

• Reconstruct I-74 between the I-74/75 interchange and the Beekman Street interchange to reduce congestion and improve safety.

• Reconstruct the I-74/75 interchange to relieve congestion and improve safety. • Construct noise walls along the I-74 corridor. • Eliminate local access ramps within the I-74/75 system interchange.

• Phase 6: HAM-75-7.72, PID 82283; Award Date – May 2013; Completion Date – Sept. 2015

• Replace existing RR Bridge over I-75 with a new bridge on new alignment. New bridge will accommodate future mainline I-75 design.

• New bridge will be designed to accommodate two tracks

Page 27: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

MCE Project Summary • Phase 7: HAM-75-6.78, PID 82286; Award Date – Oct. 2020; Completion Date – Oct. 2023

• Reconstruct I-75 on new horizontal and vertical alignments to allow for four continuous lanes in each direction. Provide auxiliary lanes between interchanges as required.

• Construct noise walls along the I-75 corridor

• Phase 8: HAM-75-7.85, PID 77889; Award Date – Oct. 2017*; Completion Date – Oct. 2020

• Reconstruct I-75 on new horizontal and vertical alignments to allow for four continuous lanes in each direction. Provide auxiliary lanes between interchanges as required.

• Construct noise walls along the I-75 corridor.

• Reconstruct the I-75 interchange with SR-562 to improve safety and relieve congestion.

• Removal of the partial interchange with Towne Street.

• Phase 8A: HAM-4/561-2.66/7.01, PID 89835; Award Date – Apr. 2016*;

Completion Date – Oct. 2016

• Replace Bridge carrying Seymour Ave. over I-75.

• Reconstruct portions of Bridge Number HAM-4-0266.

* Earliest possible Award Dates. Phases 8 and 8A do not have committed construction funding

Page 28: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

Thru the Valley

Page 29: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

TTV Project Summary • Phase 1: HAM-75-12.60, PID 82288; Award Date – Oct. 2015; Completion Date – Oct. 2018

• The scope of Phase 1 reconstruction limits are from south of Shepherd Lane to north of Glendale Milford Road. The following work is to be undertaken:

• Reconstruct IR 75 to allow for four continuous lanes in each direction • Reconstruct the Shepherd Lane interchange by moving the southbound ramps at Mangham Drive to

Shepherd Lane • Reconstruct the Glendale Milford interchange to accommodate capacity improvements Add auxiliary

lanes between Shepherd Lane and Glendale Milford Road

• Phase 2: HAM-GE Parkway, PID 88135; Award Date – Oct. 2015*; Completion Date – Oct. 2018 • The scope of Phase 2 reconstruction limits are from Shepherd Lane to Glendale Milford Road. The following

work is to be undertaken:

• Construct a local road between Shepherd Lane and Glendale Milford Road east and adjacent to IR 75 • Construct a ramp from southbound IR 75 at Glendale Milford road to tie in to the new local road.

• Phase 3: HAM-75-10.10, PID 88124; Award Date – April 2016* ; Completion Date – Oct. 2018 • The scope of Phase 3 reconstruction limits are from Paddock Road to Galbraith Road. The following work is

to be undertaken:

• Reconstruct IR 75 to allow for four continuous lanes in each direction • Reconstruct the left hand exit from northbound IR 75 to Galbraith Road as a right hand exit • Improve ramps for eastbound SR 126 to southbound IR 75, Galbraith Road to southbound IR 75 and

northbound IR 75 to eastbound and westbound SR 126 • Add auxiliary lanes between Paddock Road and SR 126

* Earliest possible Award Dates. Phases 2 and 3 do not have committed construction funding

Page 30: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

TTV Project Summary • Phase 4: HAM-75-11.09, PID 88129; Award Date – Oct. 2015*; Completion Date –July 2017

• The scope of Phase 4 is to replace the railroad bridge over southbound IR 75. The following work is to be undertaken:

• Replace the Norfolk Southern railroad bridge over southbound IR 75 and the Millcreek

• Phase 5: HAM-75-11.02, PID 88132; Award Date – April 2016*; Completion Date–Oct. 2017 • The scope of Phase 5 reconstruction limits are Galbraith Road to south of Shepherd Lane on southbound IR

75. The following work is to be undertaken:

• Reconstruct southbound IR 75 to allow for four continuous lanes

• Construct an exit to Galbraith Road and Anthony Wayne Avenue with a C-D type ramp

• Add auxiliary lane between Galbraith Road and Shepherd Lane

• Phase 6: HAM-75-11.05, PID 88133; Award Date – Jan. 2018* ; Completion Date–Oct. 2019

• The scope of Phase 6 reconstruction limits are Galbraith Road to south of Shepherd Lane on northbound IR 75. The following work is to be undertaken:

• Reconstruct northbound IR 75 to allow for four continuous lanes

• Add auxiliary lane between Galbraith Road and Shepherd Lane

* Earliest possible Award Dates. Phases 4, 5 and 6 do not have committed construction funding

Page 31: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

TTV Project Summary • Phase 7: HAM-75-10.52, PID 88134; Award Date – Jan. 2017; Completion Date – Oct. 2018

• The scope of Phase 7 is to add two ramps to the IR 75 and SR 126 interchange. The following work is to be undertaken:

• Construct a ramp for westbound SR 126 to northbound IR 75

• Construct a ramp for southbound IR 75 to westbound SR 126

• Remove existing ramp for Galbraith Road to westbound SR 126

• Phase 8: HAM-75-10.10, PID 76256; Award Date – Jan. 2017; Completion Date – Oct. 2018 • The scope of Phase 8 reconstruction limits are Glendale Milford to Kemper Road. The following work is to be

undertaken:

• Reconstruct IR 75 to allow for four continuous lanes in each direction

• Improve ramp capacity at the Sharon Road interchange

• Add auxiliary lanes between Glendale Milford Road and Sharon Road and between Sharon Road and IR 275

• HAM- Demo Stearns / Foster, PID 95567; Award Date – May 2014; Completion Date – Jan. 2015 • The scope is to demolish the remaining Stearns and Foster structure.

* Earliest possible Award Dates. Phases 7 and 8 do not have committed construction funding

Page 32: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

Northern Corridor Projects

• Hamilton/Butler I-75 Widening; Award Date – 2002; Completion Date – 2005

• Rehabilitation of I-75 and overpasses between I-275 and Tylersville Road.

• Addition of 1 through lane in each direction of I-75

• Butler/Warren I-75 Widening; Award Date – 2007; Completion Date – 2011

• Rehabilitation of I-75 and overpasses between Tylersville Road. and SR 122

• Addition of 1 through lane in each direction of I-75

• Reconstruction of SR 63 interchange into a SPUI

• Warren I-75 Widening; Award Date – 2009; Completion Date – 2012

• Rehabilitation of I-75 and overpasses between SR 122 and Montgomery County Line

• Addition of 1 through lane in each direction of I-75

• Reconstruction of SR 122 interchange

• Reconstruction of the SR 73 interchange

• Widening of SR 122

Page 33: I-75 Update - BCEO · I-75 Update Northern ... • Widen Mitchell Avenue to accommodate the new interchange ... IR 75 at Glendale Milford road to tie in to the new local road. •

THANK YOU