CONTRACT NO: CHO/C3/2010/DFHD/015B WORK ORDER NO: DFHD/2010/042D/003
GOLDEN JOINT PROCEDURE
GUIDELINE FOR INSTALLATION OF FINAL TIE-IN GOLDEN JOINT
PETRA RESOURCES SDN BUD (172962•D)
Doc No : PRSB-2010-0156-QA-25
Page No. : 3 of 6
Rev. 1
16-06-2011
TABLE OF CONTENTS
SECTION DESCRIPTION PAGE
1.0 PURPOSE 4
2.0 SCOPE 4
3.0 REFERENCE 4
4.0 DEFINITIONS / ABBREVIATION 4
5.0 PROCEDURE 4
5.1 PRIOR TO SHUTDOWN 4
5.2 DURING SHUTDOWN 5
6.0 RECORDS 6
7.0 APPENDICES
APPENDIX I API 570 PIPING INSPECTION CODE CLAUSE 8.2.6
APPENDIX II FIGURE 1 - PLUMBERS PLUG INSTALLATION DIAGRAM
This is controlled document No part or this document may be reproduced in any form by print, photocopy, rnicra'rn or any other means withaut written permission from PRSB guatty Management Representative