FY2019 NAVAJO NATION TRIBAL TRANSPORTATION IMPROVEMENT
PROGRAM
Submitted By: Navajo Division of Transportation
August 20, 2018
N8008 ~ Round Rock, AZ N2007 ~ Navajo, AZ
N15 Fencing ~ Greasewood-Burnside, AZ N251 ~ Tselani/Cottonwood, AZ
NAVAJO DIVISION TRANSPORTATION POST OFFICE BOX 4620 TEL: 505-371-8300 WINDOW ROCK, ARIZONA 86515 FAX: 505-371-8399
Russell Begaye, President Jonathan Nez, Vice President
TABLE OF CONTENTS
Page
Executive Summary…………………………………………. 1
Completed Construction Projects FY2018………………… 2 - 3
Ongoing Construction Projects FY2018…………………… 4
Proposed Program Five Year Plan FY2019-2023…………. 5 - 29
Summary of Projects List…………………………….. 5 - 6
TIP Fiscal Summary…………………………………... 6
Project Details Listing………………………………… 7 - 29
NAVAJO DIVISION TRANSPORTATION POST OFFICE BOX 4620 TEL: 505-371-8300 WINDOW ROCK, ARIZONA 86515 FAX: 505-371-8399
Russell Begaye, President Jonathan Nez, Vice President
Tribal Transportation Improvement Program
Executive Summary The Navajo Division of Transportation (Navajo DOT), in partnership with the Bureau of Indian Affairs (BIA) Division of Transportation – Navajo Region (NRDOT), is responsible for approximately 4,900 miles of Tribal roads and 6,000 miles of BIA roads across the Navajo Nation. Approximately 14 percent of these roads are paved and the vast majority (86 percent) of these roads are unimproved dirt roads. Of the 1,500 miles of paved roads, over 50% are in poor pavement condition. Additionally, there are a total of 179 bridges maintained by the BIA NRDOT and Navajo DOT, of which 38 bridges are eligible for rehabilitation and an additional 28 bridges are eligible for replacement. The Navajo DOT and BIA NRDOT are challenged with a limited budget to maintain and improve these dirt and paved roads, and also addressed the rehabilitation and replacement of bridges.
The Navajo Nation receives approximately $54 million annually from the Federal Highway Administration (FHWA) under the Tribal Transportation Program (TTP) to plan, design, build, maintain and operate Tribal and BIA-owned roadways within the Navajo Nation in order to provide connections that improve people’s lives. Guided by the 25 Coded Federal Regulations (CFR) Part 170 Subpart D under the Tribal Transportation Program (TTP) for the Transportation Planning, Tribal Transportation Improvement Program (TTIP), Long Range Transportation Plan (LRTP) development, annual update of the Tribal Transportation Facility Inventory and Public Hearings, the Navajo DOT is charged to performed the critical functions in collaboration with the BIA NRDOT, local, state and federal agencies to develop a tribal transportation priority listing.
The FY2019 Navajo Nation Tribal Transportation Improvement Program (NNTTIP) outlines a five-year program regarding how funding is used to manage the transportation system. The funding in the TTIP is a five-year, fiscally constrained program, and it must be consistent with the goals and objectives of the Long Range Transportation Plan (LRTP), in the Navajo Nation road inventory, and adhere to all relevant provisions found in the current transportation bill, Fixing America’s Surface Transportation Act (FAST Act). Projects listed on the 5 year TTIP have funds programmed for: Preliminary studies which are cultural, environmental impact studies, rights of way, centerlines
surveys and design; Construction engineering funds are for construction administration; and Construction funds to construct the roadway improvements.
Annually, the Navajo Nation TTIP priority is updated with projects that are most critical to the communities and the Navajo Nation based on the prioritization criteria and submitted to the Resources and Development Committee (RDC) for review and approval. The RDC-approved TTIP is submitted to Federal Highway Administration (FHWA) for final approval and will be included in the national transportation improvement program by FHWA.
Page 1
NAVAJO DIVISION TRANSPORTATION POST OFFICE BOX 4620 TEL: 505-371-8300 WINDOW ROCK, ARIZONA 86515 FAX: 505-371-8399
Russell Begaye, President Jonathan Nez, Vice President
Completed Construction Projects FY2018 Construction of three (3) projects listed on the FY2018 NNTTIP were completed. These three (3) projects constructed 3.2 miles of new pavement, 1.2 miles of stabilized aggregate base course surface, one (1) six-span steel bridge, culvert and cattleguard installations, and 21.1 miles of right-of-way fencing at a total cost of $9,818,251. These projects are listed below:
1. N12(19-3) & N9(12A)(12B)2&4 – Tsaile/Wheatfields, AZ & Pueblo Pintado, NM (Chinleand Eastern Agency)The Navajo Nation, in partnership with the BIA DOT Navajo Region, reconstructed 3.2 miles ofpavement along N12 near Tsaile, AZ and N9 near Pueblo Pintado, NM. The construction workincluded milling existing asphalt, grading, processing existing asphalt and laid down of newpavement for three (3) cutout sections along N12 and seven (7) cutout sections along N9 at a costof $2,330,000. BIA DOT NR provided preliminary engineering and construction engineeringservices. The project was constructed by the BIA Force Account Section.
Page 2
2. N8008(1)1,2&3 – Round Rock, AZ (Northern Agency)The Navajo Nation, in partnership with the BIA DOT Navajo Region, constructed 1.2 miles ofgrade and drainage work, new 6-span steel girder bridge with concrete deck, placement ofstabilized aggregate base course, and miscellaneous construction work at a cost of $5,197,963.BIA DOT NR provided preliminary engineering and construction engineering services. Theproject was constructed by Weeminuche Construction Authority under a commercial constructioncontract.
3. N15 Fencing – Greasewood Springs to Burnside, AZ (Fort Defiance Agency)The Navajo Nation installed 21.1 miles of fencing, 83 cattleguard installations, 31 gateinstallations and graded turnouts along both sides of the highway from Greasewood Springs toBurnside, AZ at a cost of $2,290,288. The Navajo DOT’s consultant Dibble Engineering providedpreliminary engineering and construction engineering services. The project was constructed by theShow Low Construction.
Page 3
NAVAJO DIVISION TRANSPORTATION POST OFFICE BOX 4620 TEL: 505-371-8300 WINDOW ROCK, ARIZONA 86515 FAX: 505-371-8399
Russell Begaye, President Jonathan Nez, Vice President
Ongoing Construction Projects FY2018
Four (4) projects listed on the FY2018 NNTTIP are under construction and listed in the FY2019 NNTTIP. These four (4) projects will construct 15.1 miles of new pavement, 15.2 miles of treated gravel surface, and one (1) four-span bridge at a total cost of $62,640,760. These projects are listed below:
1. N251(1-1)(2-1)(3-1)1,2&3 – Tselani/Cottonwood, AZ (Chinle Agency)The Navajo Nation, in partnership with the BIA DOT Navajo Region, will construct 15.2 miles ofgrade and drainage work, placement of treated gravel surface, and miscellaneous constructionwork at a cost of $9,243,213.
2. N2007(1-1)1,2&4 – Navajo, AZ (New Lands/Fort Defiance Agency)The Navajo Nation, in partnership with the BIA DOT Navajo Region, will construct 1.1 miles ofgrade and drainage work, new four-span precast prestressed girder bridge, placement of newpavement, and miscellaneous construction at a cost of $15,464,792.
3. N27(2-2)(2-3)(4-2)/N7(2-3)(1)/N105(1)1,2&4 – Nazlini/Chinle, AZ (Chinle Agency)The Navajo Nation, in partnership with the BIA DOT Navajo Region, will construct 11.0 miles ofgrade and drainage work, placement of new pavement, and miscellaneous construction at a cost of$33,332,755.
4. N7119(1)/N481(1)2&4 – Littlewater, NM (Eastern Agency)The Navajo Nation will construct 3.0 miles of grade and drainage work, placement of newpavement, and miscellaneous construction at a cost of $4,600,000.
Page 4
UNOFFICIALSummary of Projects List Navajo Nation
UNOFFICIALProject Name Project No. Const. Yr 2019 2020 2021 2022 2023 Total
N6331(1-2)(2)/N6330(1)/N21(3A)1,2&4 Trading Post Bridge Replace N310
N6331(1-2)(2)/N6330(1)/N21(3A)1,2&4
$14,528,328 $0 $0 $0 $0 $14,528,3282018
N71(3)2&4 Birdsprings/N15 & Little Singer School Access
N71(3)2&4 $12,946,160 $0 $0 $0 $0 $12,946,1602018
N27(2-2)(2-3)(4-2)/N7(2-3)(1)/N105(1)1,2&4
N27(2-2)(2-3)(4-2)/N7(2-3)(1)/N105(1)1,2&4
$34,882,755 $0 $0 $0 $0 $34,882,7552018
N35(8)/N5045(1)1,2&4 N35(8)/N5045(1)1,2&4
$10,896,000 $0 $0 $0 $0 $10,896,0002018
Greasewood Gravel Pit $2,000,000 $0 $0 $0 $0 $2,000,0002018
N4(5)/N8031(2)(3)(4)1,2&3 Pinon to Hardrock
N4(5)/N8031(2)(3)(4)1,2&3
$22,700,000 $750,000 $0 $0 $0 $23,450,0002019
N36 N36 $842,000 $0 $0 $0 $0 $842,0002019
N5012(1)1,2&3 Sanostee Wash Bridge N204
N5012(1)1,2&3 $150,000 $3,925,000 $0 $0 $0 $4,075,0002020
Highway Safety Education Program
$76,559 $0 $0 $0 $0 $76,559
Traffic and Criminal Software (TraCs)
$693,000 $0 $0 $0 $0 $693,000
NDOT $5,200,000 $5,200,000 $5,200,000 $5,200,000 $5,200,000 $26,000,000
Airport Maintenance $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000
NNDOT Safety Projects $750,000 $750,000 $750,000 $750,000 $750,000 $3,750,000
N251(5-2)2,3 North Loop Tselani off N4
N251(5-2)2,3 $828,039 $0 $0 $0 $0 $828,0392015
N7119(1)/N481(1)2&4 Littlewater Chapter Access Road
N7119(1)/N481(1)2&4
$4,942,763 $0 $0 $0 $0 $4,942,7632018
Page 1 of 508/20/2018 8:52:57 AMUNOFFICIAL
N101(1)2&4 Ojo Amarillo School Access
N101(1)2&4 $1,795,000 $0 $0 $0 $0 $1,795,0002018
N12(19-4)1,2&4 Wheatfields Lake to Tsaile/N64 Junction
N12(19-4)1,2&4 $20,300,000 $0 $0 $0 $0 $20,300,0002018
N15(2-3)2&4 Cornfields to Burnside
N15(2-3)2&4 $16,810,000 $0 $0 $0 $0 $16,810,0002018
N7054(1)(2)2,3 Pinedale Loop Road
N7054(1)(2)2,3 $3,750,000 $0 $0 $0 $0 $3,750,0002018
N11(1a)1,2&4 N9 to Mariano Lake South End
N11(1a)1,2&4 $12,250,000 $400,000 $0 $0 $0 $12,650,0002019
N9073(1)(2)1,2&4 Blue Canyon Road w/ Bridge N606
N9073(1)(2)1,2&4
$18,426,717 $706,283 $0 $0 $0 $19,133,0002019
N5001(1)1,2&4 with N241 & N214 Bridge Replacement
N5001(1)1,2&4 $100,000 $10,300,000 $100,000 $0 $0 $10,500,0002020
N46(4)/N474(4)1,2&4 to Counselor US550
N46(4)/N474(4)1,2&4
$250,000 $15,000,000 $250,000 $0 $0 $15,500,0002020
N8084(1)1,2&3 Many Farms to N64
N8084(1)1,2&3 $50,000 $4,695,283 $7,691,717 $200,000 $0 $12,637,0002021
N13(3-3)4 Red Valley Pavement Rehabilitation
N13(3-3)4 $250,000 $50,000 $5,450,000 $500,000 $0 $6,250,0002021
N8066(3)/N8065(1)1,2&4 N41 to Kitsilli
N8066(3)/N8065(1)1,2&4
$150,000 $131,717 $17,200,000 $350,000 $0 $17,831,7172021
N71(1-1)(2-1)/N2(1)2&4 N71(1-1)(2-1)/N2(1)2&4
$0 $400,000 $100,000 $8,850,000 $250,000 $9,600,0002022
N55(1-1)2&4 N55(1-1)2&4 $0 $0 $100,000 $7,762,175 $200,000 $8,062,1752022
N36(5A-1)4 US 491 to Chaco Wash
N36(5A-1)4 $0 $0 $150,000 $4,987,825 $5,612,175 $10,750,0002023
N6486(1)1,2&3 N308 & N314 Lower Laguna Creek Bridge Replacement
N6486(1)1,2&3 $30,000 $0 $0 $0 $0 $30,0002023
N9402(1)1,2&3 Rio Puerco Bridge N656 Replacement
N9402(1)1,2&3 $10,000 $0 $0 $0 $0 $10,0002023
N203(2)1,2&3 Kinlichee Wash Bridge N629 Replacement
N203(2)1,2&3 $20,000 $0 $0 $0 $0 $20,0002023
Page 2 of 508/20/2018 8:52:57 AMUNOFFICIALPage 5
N12(13-2)1,2&4 Agency Line to Wheatfields Lake
N12(13-2)1,2&4 $950,000 $5,591,717 $10,608,283 $300,000 $0 $17,450,0002021
N609(2)2&4 Kerly Street N609(2)2&4 $0 $0 $150,000 $2,650,000 $200,000 $3,000,0002022
N15(3-1)(4-1)2&4 Cornfields-Sunrise
N15(3-1)(4-1) $0 $50,000 $50,000 $16,350,000 $4,850,000 $21,300,0002023
N6485(1)2&4 N6485(1)2&4 $0 $0 $150,000 $50,000 $4,750,000 $4,950,0002023
N6720(1)1,2&3 Bridge N309 Replacement
N6720(1)1,2&3 $5,000 $0 $0 $0 $0 $5,0002023
N108(1)1,2&4 Bridge N651 Replacement
N108(1)1,2&4 $15,000 $0 $0 $0 $0 $15,0002023
Navajo Nation Tribal Transportation Safety Plan
$145 $0 $0 $0 $0 $145
Traffic and Criminal Software (TraCs License)
$293,219 $0 $0 $0 $0 $293,219
NDOT 2% Planning Funds $1,200,000 $1,200,000 $1,200,000 $1,200,000 $1,200,000 $6,000,000
NDOT Maintenance $4,400,000 $4,400,000 $4,400,000 $4,400,000 $4,400,000 $22,000,000
Navajo Nation Gravel Pit Development
$550,000 $0 $0 $0 $0 $550,000
BIA NRDOT Maintenance $150,000 $150,000 $150,000 $150,000 $150,000 $750,000
N2007(1-1)1,2&4 N666 New Lands Rio Puerco Bridge Replacement
N2007(1-1)1,2&4 N666
$12,120,613 $0 $0 $0 $0 $12,120,6132017
N6461(1-2)/N6460(1)1,2&4 Dennehotso Loop Road
N6461(1-2)/N6460(1)1,2&4
$8,009,300 $0 $0 $0 $0 $8,009,3002018
$213,620,598 $54,000,000 $54,000,000 $54,000,000 $27,862,175 $403,482,773
Page 3 of 508/20/2018 8:52:57 AMUNOFFICIAL
TIP Fiscal Summary Navajo Nation
UNOFFICIAL
$213,620,597.54 $54,000,000.00 $54,000,000.00 $54,000,000.00
$213,620,597.54 $54,000,000.00 $54,000,000.00 $27,862,175.00
$54,000,000.00
$54,000,000.00
$0.00 $0.00 $0.00 $0.00 $26,137,825.00
Project Totals:
Summary
$403,482,772.54
Fiscal Year Remainder:
TOTAL AVAILABLE FUNDS for each year:
$0.00$0.00$0.00$0.00$2,034,922.54
$54,000,000.00$54,000,000.00$54,000,000.00$54,000,000.00
$157,585,675.00
$54,000,000.00Estimated Annual TTP Shares
Additional funds (Tiger, Safety, Bridge, Other Grants)
Carryover Funds (from previous FY) $0.00 $0.00 $0.00 $0.00
Total of All Projects on TIP
Total Available Funds $429,620,597.54
2019 2020 2021 2022 2023
Page 4 of 508/20/2018 8:52:57 AMUNOFFICIALPage 6
TOTAL $5,200,000 $5,200,000 $5,200,000 $5,200,000 $5,200,000 $26,000,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $5,200,000 $5,200,000 $5,200,000 $5,200,000 $5,200,000 $26,000,000Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name NDOT
Route Number Project Number
Location Navajo NationType of Work Administration
CountyMilesLength 0Construction YearState
Comments Executive Department, Department of Project Management and Department of Highway Safety. IDC Rate @ 17.18% = $783,300 (Estimated Amount)
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 5 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $14,528,328 $0 $0 $0 $0 $14,528,328
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $700,000 $0 $0 $0 $0 $700,000Construction $13,828,328 $0 $0 $0 $0 $13,828,328
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N6331(1-2)(2)/N6330(1)/N21(3A)1,2&4 Trading Post Bridge Replace N310
Route Number N6331-Section 10,20&4 Project Number N6331(1-2)(2)/N6330(1)/N21(3A)1,2&4
Location Kaibeto, AZType of Work New Construction
County CoconinoMilesLength 3.5Construction Year 2018State AZ
Comments Project design, EA, FONSI and ROW acquisition are complete. Project will be advertised by August 2018. For Bridge N310, the 2016 Bridge Sufficiency Rating = 60.4 and is a Closed Bridge and Structurally Deficient. Total Construction funds committed of $13,828,328.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 6 of 508/20/2018 8:52:57 AMUNOFFICIALPage 7
TOTAL $18,426,717 $706,283 $0 $0 $0 $19,133,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $193,717 $706,283 $0 $0 $0 $900,000Construction $18,033,000 $0 $0 $0 $0 $18,033,000
Preliminary Engineering $200,000 $0 $0 $0 $0 $200,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N9073(1)(2)1,2&4 Blue Canyon Road w/ Bridge N606
Route Number N9073-Section 10-60 Project Number N9073(1)(2)1,2&4
Location Fort Defiance, AZType of Work New Construction
County ApacheMilesLength 6.5Construction Year 2019State AZ
Comments Project design is 85% complete. NDOT will complete additional archaeology work in realigned areas and update BE and EA to submit to BIA for a FONSI. NDOT will complete ROW application for BIA and submit to Navajo Nation. Total Construction funds committed is $18,033,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 7 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $12,250,000 $400,000 $0 $0 $0 $12,650,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $200,000 $400,000 $0 $0 $0 $600,000Construction $12,000,000 $0 $0 $0 $0 $12,000,000
Preliminary Engineering $50,000 $0 $0 $0 $0 $50,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N11(1a)1,2&4 N9 to Mariano Lake South End
Route Number N11-Section 80 Project Number N11(1a)1,2&4
Location Mariano Lake, NMType of Work New Construction
County McKinleyMilesLength 6.2Construction Year 2019State NM
Comments Project design is 99% complete. EA and FONSI is complete. ROW is complete for Tribal Trust Land and Indian Allotment Lands. ROW is needed for Fee Land and BLM Land. Total Construction funds committed of $12,000,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 8 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 8
TOTAL $3,750,000 $0 $0 $0 $0 $3,750,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $200,000 $0 $0 $0 $0 $200,000Construction $3,500,000 $0 $0 $0 $0 $3,500,000
Preliminary Engineering $50,000 $0 $0 $0 $0 $50,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N7054(1)(2)2,3 Pinedale Loop Road
Route Number N7054-Section 10&20 Project Number N7054(1)(2)2,3
Location Pinedale, NMType of Work New Construction
County McKinleyMilesLength 7.5Construction Year 2018State NM
Comments Project design is 90% complete for 3.5 miles on east end of loop road. EA and FONSI is complete. ROW is complete for Tribal Trust Land and 9 Indian Allotments. ROW for 2 Indian Allotments is pending Agreement between BIA and Western Refining for 6-inch oil line. ROW is needed from BLM and State Land. Total Construction funds committed of $3,500,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 9 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $16,810,000 $0 $0 $0 $0 $16,810,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $810,000 $0 $0 $0 $0 $810,000Construction $16,000,000 $0 $0 $0 $0 $16,000,000
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N15(2-3)2&4 Cornfields to Burnside
Route Number N15-Section 330-346 Project Number N15(2-3)2&4
Location Cornfields and Burnside, AZType of Work Reconstruction
County ApacheMilesLength 7.1Construction Year 2018State AZ
Comments Project design is 99% complete. NDOT will complete EA and submit to BIA for a FONSI. BIA will need to submit TCE application to Navajo Nation. Total Construction funds committed of $16,000,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 10 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 9
TOTAL $20,300,000 $0 $0 $0 $0 $20,300,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $900,000 $0 $0 $0 $0 $900,000Construction $19,400,000 $0 $0 $0 $0 $19,400,000
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N12(19-4)1,2&4 Wheatfields Lake to Tsaile/N64 Junction
Route Number N12-Section 420-471 Project Number N12(19-4)1,2&4
Location Wheatfields and Tsaile, AZType of Work Reconstruction
County ApacheMilesLength 10Construction Year 2018State AZ
Comments Project design is 99% complete. EA has been completed by NDOT and pending FONSI from BIA. BIA will need to submit TCE to Navajo Nation. Total Construction funds committed of $19,400,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 11 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $1,795,000 $0 $0 $0 $0 $1,795,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $125,000 $0 $0 $0 $0 $125,000Construction $1,670,000 $0 $0 $0 $0 $1,670,000
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N101(1)2&4 Ojo Amarillo School Access
Route Number N101-Section 10&20 Project Number N101(1)2&4
Location Ojo Amarillo, NMType of Work New Construction
County San JuanMilesLength 0.6Construction Year 2018State NM
Comments Project Design, EA and FONSI is complete. BIA has submitted ROW application to Navajo Nation. Total Construction funds committed of $1,670,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 12 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 10
TOTAL $4,942,763 $0 $0 $0 $0 $4,942,763
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $342,763 $0 $0 $0 $0 $342,763Construction $4,600,000 $0 $0 $0 $0 $4,600,000
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N7119(1)/N481(1)2&4 Littlewater Chapter Access Road
Route Number N7119-Section 10&15; Project Number N7119(1)/N481(1)2&4
Location Littlewater Chapter, NMType of Work New Construction
County McKinleyMilesLength 3Construction Year 2018State NM
Comments PS&E, EA, FONSI and ROW are completed. Construction start on August 2018. Total Construction funds committed of $4,600,000. NDOT forces will construct this project.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 13 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $828,039 $0 $0 $0 $0 $828,039
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $50,000 $0 $0 $0 $0 $50,000Construction $778,039 $0 $0 $0 $0 $778,039
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N251(5-2)2,3 North Loop Tselani off N4
Route Number N251-Section 60,65,70& Project Number N251(5-2)2,3
Location Tselani/Cottonwood, AZType of Work Reconstruction
County ApacheMilesLength 15.2Construction Year 2015State AZ
Comments Project is 60% complete and under construction. Total Construction funds committed of $8,791,770.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 14 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 11
TOTAL $250,000 $15,000,000 $250,000 $0 $0 $15,500,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $200,000 $250,000 $0 $0 $450,000Construction $0 $14,800,000 $0 $0 $0 $14,800,000
Preliminary Engineering $250,000 $0 $0 $0 $0 $250,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N46(4)/N474(4)1,2&4 to Counselor US550
Route Number N46-Section 45&50; N4 Project Number N46(4)/N474(4)1,2&4
Location Counselor, NMType of Work New Construction
County San JuanMilesLength 7.6Construction Year 2020State NM
Comments Project design is 65% complete. NDOT will complete archaeology, BE and EA and submit to BIA for a FONSI. NDOT will complete ROW application and submit to Navajo Nation, fee land, BLM and State Land. Total Construction funds committed of $14,800,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 15 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000
Maintenance $300,000 $300,000 $300,000 $300,000 $300,000 $1,500,000Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name Airport Maintenance
Route Number Project Number
Location Navajo NationType of Work Maintenance
CountyMilesLength 0Construction YearState
Comments Snow removal on runways; pavement patching; fence repair; obstruction removal; repainting navigable installments; applying pavement patching to critical sections of the runways/taxiways; repairing and restoring electrical components; repairing and restoring airfield lighting fixtures and bulbs; and airfield mowing, herbicide application, wildlife/livestock removal and foreign object debris removal. IDC Rate @ 17.18% = $43,900 (Estimate Amount)
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 16 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 12
TOTAL $50,000 $4,695,283 $7,691,717 $200,000 $0 $12,637,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $200,000 $200,000 $0 $400,000Construction $0 $4,695,283 $7,491,717 $0 $0 $12,187,000
Preliminary Engineering $50,000 $0 $0 $0 $0 $50,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N8084(1)1,2&3 Many Farms to N64
Route Number N8084-Section 10,20,30, Project Number N8084(1)1,2&3
Location Many Farms, AZType of Work New Construction
County ApacheMilesLength 3.5Construction Year 2021State AZ
Comments Project design is 99% complete. Archaeology is complete. NDOT will complete EA and submit to BIA for FONSI. NDOT will complete ROW application for BIA and submit to Navajo Nation. Total Construction funds committed of $12,187,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 17 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $693,000 $0 $0 $0 $0 $693,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $693,000 $0 $0 $0 $0 $693,000Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTPSF;PROJECT INFORMATION:
Project Name Traffic and Criminal Software (TraCs)
Route Number Project Number
Location Navajo NationType of Work Administration
CountyMilesLength 0Construction YearState
Comments Awarded TTP-Safety FY2017/2018: $693,000.00. TraCs data collection software utilized within all seven police districts on the Navajo Nation to report motor vehicle crashes. This project will reduce police reporting time and increase data accuracy.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 18 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 13
TOTAL $76,559 $0 $0 $0 $0 $76,559
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $76,559 $0 $0 $0 $0 $76,559
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTPSF;PROJECT INFORMATION:
Project Name Highway Safety Education Program
Route Number Project Number
Location Navajo NationType of Work Planning
CountyMilesLength 0Construction YearState
Comments Awarded TTP-Safety FY2013 of $104,004.67 and TTP-Safety FY2014 of $102,331.25. Hired a full time safety technician and temporary employees to provide traffic safety presentations across the Navajo Nation in the areas of DUI awareness, youth alcohol campaigns, distracted driving (no texting and driving), importance of seat belt usage, teen and mature (senior citizen) driving and bike safety. Developed marketing initiatives, tools and monthly advertisements to promote traffic safety initiatives across the Navajo Nation.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 19 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $150,000 $3,925,000 $0 $0 $0 $4,075,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $225,000 $0 $0 $0 $225,000Construction $0 $3,700,000 $0 $0 $0 $3,700,000
Preliminary Engineering $150,000 $0 $0 $0 $0 $150,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N5012(1)1,2&3 Sanostee Wash Bridge N204
Route Number N5012-Section 10,20&3 Project Number N5012(1)1,2&3
Location Sanostee, NMType of Work New Construction
County San JuanMilesLength 1.2Construction Year 2020State NM
Comments Project design is 25% complete. NDOT will complete archaeology, BE, and EA and submit to BIA for a FONSI. NDOT will complete ROW application for BIA and submit to Navajo Nation. Total Construction funds committed of $3,700,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 20 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 14
TOTAL $842,000 $0 $0 $0 $0 $842,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $70,000 $0 $0 $0 $0 $70,000Construction $700,000 $0 $0 $0 $0 $700,000
Preliminary Engineering $72,000 $0 $0 $0 $0 $72,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;TTPSF;PROJECT INFORMATION:
Project Name N36
Route Number N36-Section 50&55 Project Number N36
Location San Juan Chapter, NMType of Work Reconstruction
County San JuanMilesLength 0.25Construction Year 2019State NM
Comments N36 received $72,000 in TTP Safety Funds in FY2017 which will be used for preliminary engineering services to address safety issues such as pavement reconstruction, striping and signage. Total Construction funds committed of $700,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 21 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $22,700,000 $750,000 $0 $0 $0 $23,450,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $350,000 $750,000 $0 $0 $0 $1,100,000Construction $22,300,000 $0 $0 $0 $0 $22,300,000
Preliminary Engineering $50,000 $0 $0 $0 $0 $50,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N4(5)/N8031(2)(3)(4)1,2&3 Pinon to Hardrock
Route Number N4-Section 25; N8031-S Project Number N4(5)/N8031(2)(3)(4)1,2&3
Location Pinon and Hardrock, AZType of Work New Construction
County NavajoMilesLength 15.7Construction Year 2019State AZ
Comments Project design is 99% complete. Archaeology needs to be completed on Hopi Land. NDOT will complete BE and EA and submit to BIA and Hopi NEPA Office. NDOT will complete ROW application for BIA and submit to Navajo Nation and Hopi Tribe. Total Construction funds committed of $22,300,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 22 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 15
TOTAL $2,000,000 $0 $0 $0 $0 $2,000,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $150,000 $0 $0 $0 $0 $150,000Construction $1,700,000 $0 $0 $0 $0 $1,700,000
Preliminary Engineering $150,000 $0 $0 $0 $0 $150,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name Greasewood Gravel Pit
Route Number Project Number
Location Greasewood Springs, AZType of Work New Construction
County NavajoMilesLength 0Construction Year 2018State AZ
Comments Greasewood Gravel Pit mining lease was approved by the Resources and Development Committee and has been submitted to the BIA for review and approval. Construction is pending approval of mining permit.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 23 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $10,896,000 $0 $0 $0 $0 $10,896,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $500,000 $0 $0 $0 $0 $500,000Construction $10,296,000 $0 $0 $0 $0 $10,296,000
Preliminary Engineering $100,000 $0 $0 $0 $0 $100,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N35(8)/N5045(1)1,2&4
Route Number N35-Section 20&30; N5 Project Number N35(8)/N5045(1)1,2&4
Location Sweetwater, AZType of Work New Construction
County ApacheMilesLength 6.8Construction Year 2018State AZ
Comments Project design is 85% complete. NDOT will update EA and BE and submit to BIA for a FONSI. NDOT will submit ROW application for BIA to Navajo Nation. Total Construction funds committed of $10,296,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 24 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 16
TOTAL $34,882,755 $0 $0 $0 $0 $34,882,755
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $1,550,000 $0 $0 $0 $0 $1,550,000Construction $33,332,755 $0 $0 $0 $0 $33,332,755
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N27(2-2)(2-3)(4-2)/N7(2-3)(1)/N105(1)1,2&4
Route Number N27-Section 150,160,17 Project Number N27(2-2)(2-3)(4-2)/N7(2-3)(1)/N105(1)1,2&4
Location Nazlini and Chinle, AZType of Work New Construction
County ApacheMilesLength 11Construction Year 2018State AZ
Comments Project design, EA, FONSI and ROW acquisition is complete. Construction Notice to Proceed was issue on July 9, 2018. Total Construction funds committed of $33,332,755.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 25 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $12,946,160 $0 $0 $0 $0 $12,946,160
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $600,000 $0 $0 $0 $0 $600,000Construction $12,346,160 $0 $0 $0 $0 $12,346,160
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N71(3)2&4 Birdsprings/N15 & Little Singer School Access
Route Number N71-Section 50-70 Project Number N71(3)2&4
Location Birdsprings, AZType of Work New Construction
County NavajoMilesLength 7.5Construction Year 2018State AZ
Comments Project design is 99% complete. EA has been completed by NDOT and pending FONSI at BIA. BIA will need to submit ROW application to Navajo Nation. Total Construction funds committed of $12,346,160.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 26 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 17
TOTAL $750,000 $750,000 $750,000 $750,000 $750,000 $3,750,000
Maintenance $750,000 $750,000 $750,000 $750,000 $750,000 $3,750,000Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name NNDOT Safety Projects
Route Number Project Number
Location Navajo NationType of Work Maintenance
CountyMilesLength 0Construction YearState
Comments Navajo Nation wide graveling of Regional Routes and Red Dog Hauling and Placement.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 27 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $0 $0 $150,000 $2,650,000 $200,000 $3,000,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $200,000 $200,000Construction $0 $0 $0 $2,600,000 $0 $2,600,000
Preliminary Engineering $0 $0 $150,000 $50,000 $0 $200,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N609(2)2&4 Kerly Street
Route Number N609-Section 10,20,22& Project Number N609(2)2&4
Location Tuba City, AZType of Work New Construction
County CoconinoMilesLength 1.3Construction Year 2022State AZ
Comments Total Construction funds committed of $2,600,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 28 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 18
TOTAL $12,120,613 $0 $0 $0 $0 $12,120,613
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $50,000 $0 $0 $0 $0 $50,000Construction $12,070,613 $0 $0 $0 $0 $12,070,613
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N2007(1-1)1,2&4 N666 New Lands Rio Puerco Bridge Replacement
Route Number N2007-Section 40 Project Number N2007(1-1)1,2&4 N666
Location Navajo, AZType of Work New Construction
County ApacheMilesLength 1.1Construction Year 2017State AZ
Comments Total Construction funds committed of $15,464,792. Project is under construction.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 29 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $150,000 $150,000 $150,000 $150,000 $150,000 $750,000
Maintenance $150,000 $150,000 $150,000 $150,000 $150,000 $750,000Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name BIA NRDOT Maintenance
Route Number Project Number
Location Navajo NationType of Work Maintenance
CountyMilesLength 0Construction YearState
Comments TTP funds provided to BIA NRDOT for Intergovernmental Agreement with Coconino County to provide road maintenance activities on BIA roads. Activities include blading, road reconnaisance, culvert cleanouts and snow removal.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 30 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 19
TOTAL $550,000 $0 $0 $0 $0 $550,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $550,000 $0 $0 $0 $0 $550,000
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name Navajo Nation Gravel Pit Development
Route Number Project Number
Location Navajo NationType of Work Planning
CountyMilesLength 0Construction YearState
Comments Planning effort to identify and develop seven (7) gravel pits across the Navajo Nation. This planning phase will be the basis for further development of operational gravel pits.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 31 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $4,400,000 $4,400,000 $4,400,000 $4,400,000 $4,400,000 $22,000,000
Maintenance $4,400,000 $4,400,000 $4,400,000 $4,400,000 $4,400,000 $22,000,000Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name NDOT Maintenance
Route Number Project Number
Location Navajo NationType of Work Maintenance
CountyMilesLength 0Construction YearState
Comments Navajo Nation Regional Route Maintenance Plan includes blading, sand removal, road reconnaisance, snow removal, culvert clean outs, cattleguard clean outs, mowing, washout repairs, roadway debris pickup, emergency traffic control and response. IDC Rate @ 17.18% = $605,300 (Estimated Amount)
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 32 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 20
TOTAL $1,200,000 $1,200,000 $1,200,000 $1,200,000 $1,200,000 $6,000,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $1,200,000 $1,200,000 $1,200,000 $1,200,000 $1,200,000 $6,000,000
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP 2% Planning;PROJECT INFORMATION:
Project Name NDOT 2% Planning Funds
Route Number Project Number
Location Navajo NationType of Work
CountyMilesLength 0Construction YearState
Comments Activities include develop Long Range Transportation Plan updates, performing annual transportation facilities updates, Tribal Transportation Improvement Program development, conducting public hearing/outreach, and overall transportation planning. IDC Rate @ 17.18% = $216,800 (Estimated Amount)
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 33 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $293,219 $0 $0 $0 $0 $293,219
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $0 $0 $0 $0 $0 $0
Administration $293,219 $0 $0 $0 $0 $293,219Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTPSF;PROJECT INFORMATION:
Project Name Traffic and Criminal Software (TraCs License)
Route Number Project Number
LocationType of Work Administration
CountyMilesLength 0Construction YearState
Comments Awarded TTP-Safety FY2013: $294,406.50. Develop and implement a computerized crash data system in collaboration with the Navajo Nation Division of Public Safety. Due to the size of the Navajo Nation, a pilot project would utilize the funds to purchase needed equipment and data server to assist with the data.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 34 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 21
TOTAL $145 $0 $0 $0 $0 $145
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $0 $0 $0 $0 $0 $0Planning $145 $0 $0 $0 $0 $145
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTPSF;PROJECT INFORMATION:
Project Name Navajo Nation Tribal Transportation Safety Plan
Route Number Project Number
Location Navajo NationType of Work Planning
CountyMilesLength 0Construction YearState
Comments Awarded TTP-Safety FY2013: $12,500. Develop the Navajo Nation Strategic Highway Safety Plan to evaluate safety system performance, assemble advisory team, identify and analyze current processes, establish regional vision and goals for transportation safety, identify emphasis areas and strategies, develop implementation plan, develop performance measures, and establish safety improvement program processes.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 35 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $15,000 $0 $0 $0 $0 $15,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $15,000 $0 $0 $0 $0 $15,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N108(1)1,2&4 Bridge N651 Replacement
Route Number N108-Section 40 Project Number N108(1)1,2&4
Location Tohatchi, NMType of Work New Construction
County McKinleyMilesLength 0.02Construction Year 2023State NM
Comments Project design is 100% complete. EA was completed with FONSI issued. NDOT will complete ROW for BIA. PE funds will be used to complete PS&E, Environmental Clearance and ROW Clearance. The 2016 Bridge Sufficiency Rating = 16.3 and is a Fracture Critical Bridge. NDOT will apply for TTP Bridge funds for Construction. Construction cost is estimated at $2,200,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 36 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 22
TOTAL $5,000 $0 $0 $0 $0 $5,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $5,000 $0 $0 $0 $0 $5,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N6720(1)1,2&3 Bridge N309 Replacement
Route Number N6720-Section 40 Project Number N6720(1)1,2&3
Location Sand Springs, AZType of Work New Construction
County CoconinoMilesLength 0.01Construction Year 2023State AZ
Comments Project design is 99% complete. EA was completed with FONSI. NEPA documents will need to be sent to Hopi Tribe for approval. ROW is needed from the Hopi Tribe. PE funds will be used to complete PS&E, Environmental Clearance and ROW Clearance. The 2016 Bridge Sufficiency Rating = 36.9 and is Functionally Obsolete. NDOT will apply for TTP Bridge funds for Construction. Construction cost is estimated at $1,900,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 37 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $100,000 $10,300,000 $100,000 $0 $0 $10,500,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $300,000 $100,000 $0 $0 $400,000Construction $0 $10,000,000 $0 $0 $0 $10,000,000
Preliminary Engineering $100,000 $0 $0 $0 $0 $100,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N5001(1)1,2&4 with N241 & N214 Bridge Replacement
Route Number N5001-Section 10-72 Project Number N5001(1)1,2&4
Location Toadlena, NMType of Work New Construction
County San JuanMilesLength 6.1Construction Year 2020State NM
Comments Project design is 80% complete. NDOT will complete updates to BE and EA and submit to BIA for a FONSI. NDOT will complete ROW application for BIA and submit to Navajo Nation. For Bridge N241, the 2016 Bridge Sufficiency Rating = 21.5 and is Structurally Deficient. For Bridge N214, the 2016 Bridge Sufficiency Rating = 16.6 and is a Closed Bridge and Structurally Deficient. Total Construction funds committed of $10,000,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 38 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 23
TOTAL $0 $50,000 $50,000 $16,350,000 $4,850,000 $21,300,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $350,000 $850,000 $1,200,000Construction $0 $0 $0 $16,000,000 $4,000,000 $20,000,000
Preliminary Engineering $0 $50,000 $50,000 $0 $0 $100,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N15(3-1)(4-1)2&4 Cornfields-Sunrise
Route Number N15-Section 320-330 Project Number N15(3-1)(4-1)
Location Cornfields-Sunrise, AZType of Work Reconstruction
County ApacheMilesLength 7.1Construction Year 2023State AZ
Comments Project design is 95% complete. Archaeology is complete. NDOT will complete EA and submit to BIA for a FONSI. NDOT will complete TCE for BIA and submit to Navajo Nation. Total Construction funds committed of $20,000,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 39 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $8,009,300 $0 $0 $0 $0 $8,009,300
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $650,000 $0 $0 $0 $0 $650,000Construction $6,750,000 $0 $0 $0 $0 $6,750,000
Preliminary Engineering $609,300 $0 $0 $0 $0 $609,300Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N6461(1-2)/N6460(1)1,2&4 Dennehotso Loop Road
Route Number N6460-Section 20,40,50, Project Number N6461(1-2)/N6460(1)1,2&4
Location Dennehotso, AZType of Work New Construction
County ApacheMilesLength 5.7Construction Year 2018State AZ
Comments Project Design is 95% complete. Archaeology is complete and EA will be completed by NDOT. NDOT will apply for ROW. Total Construction funds committed of $6,750,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 40 of 508/20/2018 8:52:57 AMUNOFFICIAL
Page 24
TOTAL $950,000 $5,591,717 $10,608,283 $300,000 $0 $17,450,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $200,000 $300,000 $0 $500,000Construction $0 $5,591,717 $10,408,283 $0 $0 $16,000,000
Preliminary Engineering $950,000 $0 $0 $0 $0 $950,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N12(13-2)1,2&4 Agency Line to Wheatfields Lake
Route Number N12-Section 420 Project Number N12(13-2)1,2&4
Location Wheatfields, AZType of Work Reconstruction
County ApacheMilesLength 10Construction Year 2021State AZ
Comments Project design is 25% complete. NDOT will update archaeology, BE and EA. NDOT will complete TCE for BIA and submit to Navajo Nation. Total Construction funds committed of $16,000,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 41 of 508/20/2018 8:52:57 AMUNOFFICIAL
TOTAL $20,000 $0 $0 $0 $0 $20,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $20,000 $0 $0 $0 $0 $20,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N203(2)1,2&3 Kinlichee Wash Bridge N629 Replacement
Route Number N203-Section 30 Project Number N203(2)1,2&3
Location Kinlichee, AZType of Work New Construction
County ApacheMilesLength 0.2Construction Year 2023State AZ
Comments Project design is 100% complete. Archaeology is complete. BE and EA are complete but need to be updated before sending to BIA for FONSI. NDOT will complete ROW for BIA. PE funds will be used to complete PS&E, Environmental Clearance and ROW Clearance. The 2016 Bridge Sufficiency Rating = 61.0 and is Functionally Obsolete. NDOT will apply for TTP Bridge funds for Construction. Construction cost is estimated at $2,200,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 42 of 508/20/2018 8:52:58 AMUNOFFICIAL
Page 25
TOTAL $10,000 $0 $0 $0 $0 $10,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $10,000 $0 $0 $0 $0 $10,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N9402(1)1,2&3 Rio Puerco Bridge N656 Replacement
Route Number N9402-Section 110 Project Number N9402(1)1,2&3
Location Lupton, AZType of Work New Construction
County ApacheMilesLength 0.1Construction Year 2023State AZ
Comments Project design, EA, FONSI and ROW is complete. The 2016 Brdige Sufficiency Rating = 46.7 and is Functionally Obsolete. NDOT will apply for TTP Bridge funds for Construction. Construction cost is estimated at $5,200,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 43 of 508/20/2018 8:52:58 AMUNOFFICIAL
TOTAL $30,000 $0 $0 $0 $0 $30,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $0 $0Construction $0 $0 $0 $0 $0 $0
Preliminary Engineering $30,000 $0 $0 $0 $0 $30,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N6486(1)1,2&3 N308 & N314 Lower Laguna Creek Bridge Replacement
Route Number N6486-Section 20&40 Project Number N6486(1)1,2&3
Location Kayenta, AZType of Work New Construction
County NavajoMilesLength 0.6Construction Year 2023State AZ
Comments Project design is 100% complete. NDOT will complete EA and ROW needs to be acquired. PE funds will be used to complete PS&E, Environmental Clearance and ROW Clearance. For Bridge N308, the 2016 Bridge Sufficiency Rating = 71.3 and is Functionally Obsolete. For Bridge N314, the 2016 Bridge Sufficiency Rating = 13.4 and is Structurally Deficient. NDOT will apply for TTP Bridge Funds for Construction. Construction cost is estimated at $6,100,000 for both bridges.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 44 of 508/20/2018 8:52:58 AMUNOFFICIAL
Page 26
TOTAL $0 $0 $150,000 $4,987,825 $5,612,175 $10,750,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $350,000 $350,000Construction $0 $0 $0 $4,737,825 $5,262,175 $10,000,000
Preliminary Engineering $0 $0 $150,000 $250,000 $0 $400,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N36(5A-1)4 US 491 to Chaco Wash
Route Number N36-Section 10&20 Project Number N36(5A-1)4
Location Shiprock, NMType of Work Reconstruction
County San JuanMilesLength 7.9Construction Year 2023State NM
Comments Total Construction funds committed of $10,000,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 45 of 508/20/2018 8:52:58 AMUNOFFICIAL
TOTAL $0 $0 $100,000 $7,762,175 $200,000 $8,062,175
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $300,000 $200,000 $500,000Construction $0 $0 $0 $7,462,175 $0 $7,462,175
Preliminary Engineering $0 $0 $100,000 $0 $0 $100,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N55(1-1)2&4
Route Number N55-Section 10 Project Number N55(1-1)2&4
Location Alamo, NMType of Work Reconstruction
County CibolaMilesLength 6.8Construction Year 2022State NM
Comments Project design is 95% complete. BIA has completed NEPA document from previous construction project. NDOT will submit for Categorical Exclusion to BIA and FHWA. No ROW is needed. Total Construction funds committed of $7,462,175.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 46 of 508/20/2018 8:52:58 AMUNOFFICIAL
Page 27
TOTAL $0 $400,000 $100,000 $8,850,000 $250,000 $9,600,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $350,000 $250,000 $600,000Construction $0 $0 $0 $8,500,000 $0 $8,500,000
Preliminary Engineering $0 $400,000 $100,000 $0 $0 $500,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N71(1-1)(2-1)/N2(1)2&4
Route Number N71-Section 10,30&50; Project Number N71(1-1)(2-1)/N2(1)2&4
Location Birdsprings, AZType of Work New Construction
County NavajoMilesLength 5.2Construction Year 2022State AZ
Comments Total Construction Funds committed of $8,500,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 47 of 508/20/2018 8:52:58 AMUNOFFICIAL
TOTAL $150,000 $131,717 $17,200,000 $350,000 $0 $17,831,717
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $200,000 $350,000 $0 $550,000Construction $0 $0 $17,000,000 $0 $0 $17,000,000
Preliminary Engineering $150,000 $131,717 $0 $0 $0 $281,717Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N8066(3)/N8065(1)1,2&4 N41 to Kitsilli
Route Number N8066-Section 55,60&7 Project Number N8066(3)/N8065(1)1,2&4
Location Black Mesa, AZType of Work New Construction
County NavajoMilesLength 7.5Construction Year 2021State AZ
Comments Project design is 60% complete. Archaeology is complete. NDOT will complete BE and EA and submit to BIA for FONSI. NDOT will complete ROW application for BIA and submit to Navajo Nation. Total Construction funds committed of $17,000,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 48 of 508/20/2018 8:52:58 AMUNOFFICIAL
Page 28
TOTAL $250,000 $50,000 $5,450,000 $500,000 $0 $6,250,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $200,000 $50,000 $0 $250,000Construction $0 $0 $5,250,000 $450,000 $0 $5,700,000
Preliminary Engineering $250,000 $50,000 $0 $0 $0 $300,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N13(3-3)4 Red Valley Pavement Rehabilitation
Route Number N13-Section 110-175 Project Number N13(3-3)4
Location Red Valley, NMType of Work Reconstruction
County San JuanMilesLength 10Construction Year 2021State NM
Comments Total Construction funds committed of $5,700,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 49 of 508/20/2018 8:52:58 AMUNOFFICIAL
TOTAL $0 $0 $150,000 $50,000 $4,750,000 $4,950,000
Maintenance $0 $0 $0 $0 $0 $0Transit $0 $0 $0 $0 $0 $0
Construction Engineering $0 $0 $0 $0 $350,000 $350,000Construction $0 $0 $0 $0 $4,400,000 $4,400,000
Preliminary Engineering $0 $0 $150,000 $50,000 $0 $200,000Planning $0 $0 $0 $0 $0 $0
Administration $0 $0 $0 $0 $0 $0Activity
Consortium:
Tribal Transportation Program Transportation Improvement ProgramProject Details Listing
DateTribe Navajo NationCurrent FY 2019
(examples: TTP, TTPBP, 2% Planning, HPPP)Funding Source TTP;PROJECT INFORMATION:
Project Name N6485(1)2&4
Route Number N6485-Section 13&16 Project Number N6485(1)2&4
Location Kayenta, AZType of Work New Construction
County NavajoMilesLength 2.2Construction Year 2023State AZ
Comments Total Construction funds committed of $4,400,000.
TOTAL
Tribe Code N00780
2019 2020 2021 2022 2023
Illustrative List
UNOFFICIAL UNOFFICIAL
Page 50 of 508/20/2018 8:52:58 AMUNOFFICIAL