Clinton McAdams, P.E.Daniel Rodriguez, P.E.

City of San Diego Programmatic Water Transmission Pipelines Condition Assessment

vvWhen we continue to 

Think •Plan •Act we will achieve 

Zero Injuries Today

Black &Veatch 2

Safety Moment – Cell Phones

• Try to place calls while the vehicle is stationary

• Use a hands‐free or speaker phone accessory

• Do not text and drive

• Never read or write, apply makeup, etc. while 

driving

• Be careful when pulling over to place calls —

do not stop in dangerous areas

vv

Black &Veatch 3

Learning Objectives

• Benefits of programmatic condition assessment approach.

• Present lessons learned from evaluating raw and potable water 

pipelines.

vv

Black &Veatch

Agenda

• Project Background

• Project Approach

• Assessment Methods

• Project Results

• Lessons Learned

• Q&A4

Black &Veatch

Project Background

5

vv

Black &Veatch 6

Pilot Project

• Three Transmission Pipelines Condition Assessment

• Highest‐risk pipelines inspected first

• 2 potable and 1 raw

• Established baseline for condition assessment approach

• Developed risk analysis factors and model

Black &Veatch 7

• Proactive condition assessments on 136 miles of the oldest and largest‐

diameter water transmission mains

• 3 raw and 32 potable water pipelines 

• Original install 1940s through 1960s

• 20‐inch to 54‐inch diameter

Current Project

Black &Veatch

AWWA C200 + C205/C214 AWWA C300 AWWA C303

Cylinder Bar + Cylinder Pretensioned bars + Cylinder

Predominant Pipe Types

8

vv

Black &Veatch

Project Location

9

Black &Veatch

Project Approach

10

Black &Veatch 11

• Improve system reliability and reduce future O&M and replacement costs• Determine the current condition of each pipeline based on review of existing records and field investigations

• Perform inspections as safely as possible and minimize operational impact• Identify and prioritize pipeline segments for needed maintenance, rehabilitation, repair, and follow up monitoring actions

Project Objectives

Black &Veatch 12

• Identifying and locating potential defects that present a risk of water supply service interruption

• Remaining flexible during inspection activities with regard to conditions encountered in the field and proposed changes to inspection methods

• Following the established safety protocol• Engaging the City

Project Objectives Achieved by…

Black &Veatch

Project Workflow

13

DATA COLLECTION AND RECORDS REVIEW• Asset Inventory• GIS Database

RISK AND PRIORITIZATION MODEL• Risk factors and weightings• Risk areas – focused 

inspections

RESULTS AND RECOMMENDATIONS• Condition assessment 

reports• Cost estimates

PRELIMINARY EVALUATIONS• Soil corrosivity• Geotechnical conditions• Environmental mapping

FIELD INVESTIGATIONS• Internal inspections• External inspections

ENGINEERING EVALUATIONS• Pipeline structural• Remaining service life

Black &Veatch 14

Project Collaboration

ProjectCity

General Contractor

Technology Vendors

Subconsultants

Black & Veatch

Black &Veatch

Assessment Methods

15

Black &Veatch 16

Assessment MethodsAssessment Method Raw Water 

PipelinesPotable Water 

PipelinesBackground data and records review

Geotechnical desktop study Soil corrosivity evaluation Environmental evaluation Internal inspection  Manned entry,

CCTV and leak detection CCTV and leak detectionValve assessments External inspection Extensive

(Visual, soil samples, SPR, SIR, mortar coating samples, UT)

Localized(Visual, soil samples, SIR, mortar coating samples, UT)

Structural analysis Risk analysis

Black &Veatch

Assessment Methods – Raw Water Pipelines

17

Black &Veatch

Assessment Methods – Potable Water Pipelines

18

Black &Veatch

Project Results

19

Black &Veatch

Condition Results – Correlations

20

Black &Veatch

Condition Results – Risk Analysis

21

Black &Veatch

Condition Results – Condition Curve

22

Black &Veatch

Lessons Learned

23

vv

Black &Veatch

Inspection Method Effectiveness• Results justified future work 

as well as urgent repair of observed defects –example shown

• Manned‐entry allowed temporary repair of defects during the shutdown that was already in effect

24

vv

Black &Veatch

Inspection Method Effectiveness• Leak detection useful, 

especially when televised• Poor image quality when 

televised during live‐flow conditions

• No silver bullet –excavations to investigate internal findings

25

vv

Black &Veatch

Project Approach Effectiveness

• No safety incidents occurred• Minimized operational impact 

‐ inspected many potable pipelines without taking them offline, as shown

• Minimized environmental and social impacts

26

vv

Black &Veatch

Project Approach Effectiveness• Proved value of preemptive 

pipeline assessment —example shown of high‐risk areas discovered, preventing future failures and service disruptions

• Data necessary to form condition baseline and to manage entire water transmission system

27

Black &Veatch

Next Steps

28

vv

Black &Veatch 29

Next Steps

• Final condition assessment reports for potable pipelines

• Transmission main management plan

• Repair, rehabilitation, or replacement

• Future inspection and monitoring

• Operational & maintenance activities

Black &Veatch

Questions & Answers

30