CHANCELLOR SECONDARY CAMPUSFUTURE FACILITIES REVIEW
SITE OBSERVATONS:Student population expected to reach 2300 by 2020 (currently 1852)Future proosed facilities include:• 8-10 GLA’s (680m2)• New Resource building to make way for reinstatement of staff offices and
administration facilities• New / additional SEP to suit growing student numbers (currently 180/190
students on campus with 3 high special needs which require feeding area and dedicated DDA amenities.
• Additional amenities to suit population increase.• Future community hall for 1000 student capacity (suits Middle school func-
tions). Note 1900 student capacity would be required for entire secondary school to congregate.
• Covered outdoor learning areas to be maximised where possible.• Possible new kiss and go facility to spread traffic load across site.Other consideratons:• Future soccer futsal playing field and touch footballs to be considered to
northern site allotment.• Possible overpass connection over Sippy Down Drive (via future kiss and
go provisions) to this site.• Manual Arts building could easily be extended• Site option 4 has site levels prepared for new building.
SITE OPTION 1 SITE OPTION 3 SITE OPTION 4SITE OPTION 2NEW KISS AND GO
FUTURE PLAYING FIELDS
SITE OPTION 1• Removal of existing demountables• Site scale and presentation to adjacent commercial building will define
rear region of site.• Opporunities for future green space between O block and D block.• Remote Construction site location with easy access to rear driveways.• Opportunities for pedestrian covered links to future Kiss and go.• Easy extension and upgrade to existing amenities block to suit new popu-
lation numbers
FUTURE KISS AND GO• Minor reconfiguration of driveway access and roadway required to suit
new kiss and go access.• Covered links to adjacent buildings, and future road overpass possible
SITE OPTION 2• Possible extension to existing G block • Direct access off rear parking, to suit possible new SEP facilities within new learning building• Opportunities for direct connections to D block• Strengthens northern site allotment with future kiss and go, and covered access way connections.
SITE OPTION 3• Extension to existing L block development centre
SITE OPTION 4• New GLA / learning building (with ground level resource facilitiy)• Existing resource library to be relocated for reinstatement of offices
CHANCELLOR SECONDARY CAMPUSBUILDINGS FOR FUTURE DEMOLITION / RELOCATION
OPTION 1
OPTION 2
OPTION 4
OPTION 3
TERRACED OUTDOOR LEARNING
AREA
CHANCELLOR SECONDARY CAMPUSPROPOSED NEW LEARNING BUILDING OPTIONS
FUTURE GREEN SPACE / OUTDOOR LEARNING
OPTIO
N 1
PEDES
TRIA
N LINKS
FUTURE KISS AND GOFUTURE COVERED OVERPASS
OPTIO
N 2
OPTION
3
FUTURE OUTDOOR LEARNING
OPTIO
N 4
OPTION
4
BUS BAYADMIN
SEP
CAFEC BLOCK
B BLOCKJUNIOR SECONDARY
J BLOCK
MULTIPURPOSE
COURTS
CRICKETNETS
BEACHVOLLEYBALL
INDUSTRIAL
TECHNOLOGY
R BLOCK
E BLOCKFOOD TECH
COVEREDOUTDOOR
M BLOCK
N BLOCK
P BLOCK
MUSIC
D BLOCK
CHANCELLOR SECONDARY CAMPUS FUTURE FACILITIES REVIEW
SITE OPTION 1 • Removal of existing demountables. • Site scale and presentation to adjacent commercial building will
define rear region of site. • Opportunities for future green space between O block and D block. • Remote Construction site location with easy access to rear
driveways. • Opportunities for pedestrian covered links to future Kiss and Go. • Easy extension and upgrade to existing amenities block to suit new
population numbers. SITE OPTION 2 • Possible extension to existing G block. • Direct access off rear parking, to suit possible new SEP facilities
within new learning building. • Opportunities for direct connections to D block. • Strengthens northern site allotment with future kiss and go, and
covered access way connections. SITE OPTION 3 • Extension to existing L block development centre SITE OPTION 4 • New GLA / learning building (with ground level resource facility) • Existing resource library to be relocated for reinstatement of offices. FUTURE KISS AND GO • Minor reconfiguration of driveway access and roadway required to
suit new kiss and go access. • Covered links to adjacent buildings, and future road overpass
possible.
SITE OPTION 1 • Double storey
5 upstairs (2 dry labs) plus staffroom
SITE OPTION 2 • Double storey
4 upstairs (1 wet lab) plus staffroom
• gain 1 classroom in B Block currently used as staffroom.
SITE OPTION 3 • 2 S.E.P. SITE OPTION 4 • Resource centre
4 upstairs
+ OVAL
FEEDBACK FOR FACILITIES CONSULTATION MASTER PLAN REVIEW
Question 1.
What are the most important factors for the Facilities Working Party to consider when making recommendations about future facilities growth at Chancellor State College?
1 .....................................................................................................................................................................
2 .....................................................................................................................................................................
3 .....................................................................................................................................................................
4 .....................................................................................................................................................................
5 .....................................................................................................................................................................
6 .....................................................................................................................................................................
7 .....................................................................................................................................................................
8 .....................................................................................................................................................................
Question 2.
What is your preference with regards to additional buildings, single storey buildings or multi-storey with lifts?
1 .....................................................................................................................................................................
2 .....................................................................................................................................................................
3 .....................................................................................................................................................................
4 .....................................................................................................................................................................
Question 3.
Where would you like to see additional secondary building/s placed within the Master Plan?
1 .....................................................................................................................................................................
2 .....................................................................................................................................................................
3 .....................................................................................................................................................................
4 .....................................................................................................................................................................
5 .....................................................................................................................................................................
6 .....................................................................................................................................................................
FEEDBACK FOR FACILITIES CONSULTATION MASTER PLAN REVIEW
Question 4.
Where would you like to see additional primary building/s placed within the Master Plan?
1 .....................................................................................................................................................................
2 .....................................................................................................................................................................
3 .....................................................................................................................................................................
4 .....................................................................................................................................................................
5 .....................................................................................................................................................................
6 .....................................................................................................................................................................
Question 5.
What features will be important in the new classrooms to ensure they are 21st Century learning spaces?
1 .....................................................................................................................................................................
2 .....................................................................................................................................................................
3 .....................................................................................................................................................................
4 .....................................................................................................................................................................
5 .....................................................................................................................................................................
6 .....................................................................................................................................................................
7 .....................................................................................................................................................................
8 .....................................................................................................................................................................
Other Comments
1 .....................................................................................................................................................................
2 .....................................................................................................................................................................
3 .....................................................................................................................................................................
4 .....................................................................................................................................................................
5 .....................................................................................................................................................................
6 .....................................................................................................................................................................
7 .....................................................................................................................................................................
top related