Annemarieke Grinwis

Ministry Economic Affairs, Agriculture & Innovation

25 November 2010

AgendaPosition NL Energy targets & CCS

CCS What when

NER 300

Future economic opportunity

Environmental costs will grow

Climate problem

Warming of the earth

Position Dutch government on climate change

Renewables Saving

20% ->14%

20%

Subsidy Renewable Energy (SDE&SDE+)

Energy TargetsThe Netherlands: EU targets leading

CO2

2%/year -> ?

20%

intensifying national

approach

30 -> 20%

30%-20%

ETS

more nuclear

EU Targets

Means

Position NL Government and others

NL Underground storage possible while recognizing strong safety rules and local acceptance.

IEA CCS is an important part of the lowest-cost greenhouse gas mitigation portfolio. IEA analysis suggests that without CCS, overall costs to reduce emissions to 2005 levels by 2050 increase by 70%.Technology Roadmap 2010

G8 We stress the critical role of carbon Capture and Storage in tackling the global challenges of climate change and energy security. Aomori, Japan 8 June 2008

Green4sure CCS for industry is necessary.

Green NGOStichting Natuur en Milieu

CCS is a necessary step in between

WWF Netherlands CCS mandatory but as a part of total solution

What & When

Phases in Dutch CCS programme

Phase 1

till 2008

First pilots

Mining Law

Phase 2 Phase 3 Phase 4

from 2008

small scale demo

Capture catch up

Beginning 2011

Mining Law &

Transposed CCS

Directive (EU)

2015 - 2020

Large scale

demonstrations

Transposed CCS

Directive

> 2020

Commercial

deployment

Reviewed EU

CCS directive?

Process transposition CCS Directive

Transposition CCS Directive

www.overheid.nl

dossier 32343

Nov/Dec 2009 To Council of State

March 2010 Start Parliamentary discussion

Apr-Jul 2010 Written comments (P)+reaction (G)

Jul+Oct Changes

Dec 6th Parliamentary discussion

January 2011 Definite

Decrees and ministerial rule

> open………December 2010

• History/state of play• Relevant changes and explanations

EC decision NER300• Actions Dutch government• Future time line• Useful addresses

NER 300

NER 300 State of play

• 2 February 2010: Agreement in CCC draft decision NER 300• 10 February2010: Information meeting interested parties potential

CCS projects • 7 July Information meeting interested parties potential CCS and RES

projects • 3 November: EC Decision NER 300 published • 9 November: EC Call for Proposals published CCS projects & RES

projects• 19 November: web streamed stakeholders meeting by EC

Relevant changes and explanations NER 300

• Definite decision o Content: no important differences with draft decision

concerning criteria including capacity thresholds

• Call for proposals o Explanation boundaries installation CO2 from refineries

(46)o Roles of Member States trans boundary projects (73)o Date of entry into operation 2nd half 2016 or earlier if award

decision will be taken earlier than 2nd half 2012 (48 + 82)o All relevant permits in place/underway & sufficiently

advanced (50 - 56)o Binding commitment to knowledge sharing (56)

Actions Dutch government related to EC/EIB process

NER300

Communication(Draft) decision

Call for proposalsMeetings

EGLWebsite

Selectionprocess EIB/EC

Subsidy decision

Less NationalCo financing

=More chance

National process

SelectionMinisterial RuleNational criteria

ProcessPublication decision and call for proposals including templates

EC

Publication additional national criteria Ministry EL&I

National information meeting Ministry KEMA EG Liaison

Answering questions during formulating proposals

EG Liaison

Proposal submitted to Dutch Ministry EL&I, for them KEMA

KEMA

Evaluate proposals Ministry EL&I +KEMA

Draft conclusion on proposals with EC eligibility criteria and additional national criteria

Ministry EL&I + KEMA

Definite conclusion and submission proposals to EIB

Ministry EL&I

Eventually reject proposal Ministry EL&I

Time line

• Begin December: Ministerial rule additional national criteria

• December: Information meeting by the Dutch State

• 9 February 2011: Proposals to Member State

• 9 May 2011: Eligible projects with support MS to EIB

• 2nd half 2012 Award decision by EC

• 2nd half 2016 Selected project operational

Useful addresses

http://ec.europa.eu/clima/funding/ner300/index_en.htm

information from EC on NER 300 including call for proposals and templates

www.ner300.nl Information from Dutch government on NER300, including application procedure and reviewing eligibility and selection on additional criteria

egl.energie@agentschapnl.nl Questions around call for proposals and use of the templates

Thank you for your attention