HOW TO REDUCE
AND CONTROL SYSTEM
DETAILED ENGINEERING COST
(When Package Units need to be Integrated)
u n ezPositive Engineering
Twitter Conference Hashtag: #EMRex
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 2/25
Presenter How to Reduce I&C En ineerin CostPresenter How to Reduce I&C En ineerin Cost
Julián Sáez
julian.saez@positiveengineering.com
. .
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 3/25
Introduction How to Reduce I&C Engineering CostIntroduction How to Reduce I&C Engineering Cost
Company presentation
os ve ng neer ng
Control & Instrumentation Solutions for Process Industry
Detailed Engineering for C&I International Projects
Inte ration of Packa e Units with the Rest of the Plant
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 4/25
Introduction How to Reduce I&C Engineering CostIntroduction How to Reduce I&C Engineering Cost
Presenter short biography
Julián Sáez (Control and Instrumentation Engineer)
BSc in Electrical Engineering
BSc in Computer Science
MSc in Electronics and Industrial Automation Engineering
,
Técnicas Reunidas (7 years), Control & Instrumentation
CPC En ineerin 9 ears Control & Instrumentation
Positive Engineering (1 year), Control & Instrumentation
Lecturer at University of Murcia (7 years), Control Systems
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 5/25
Introduction How to Reduce I&C Engineering CostIntroduction How to Reduce I&C Engineering Cost
Positive Engineering State of Business
Mid 1990s Early 2000s 2005-2010 2011-2016
DCS Programming
Loop Test
DCS HW & SW Spec
PLC
Package Unit Integration
Construction Supervision
C&I Consulting
DCS & ESD Upgrade
Simulation for OTS Commissioning Instrumentation ICSS
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 6/25
Presentation How to Reduce I&C Engineering CostPresentation How to Reduce I&C Engineering Cost
How to Reduce Instrumentation and Control System Detailed
Units need to be Integrated)
This presentation will show tips to reduce Instrumentation and Control System Detailed Engineering cost
and commissioning time in projects where several package units need to be integrated.
One of the main challenges in the development of Detailed Engineering for Instrumentations and ControlSystems is the integration of the controls of different package units.
’
sometimes overlook important details of the integration of their package units with other package units and
with the rest of the client plant. Also quite often they don’t take enough care of the client specifications.
This leads to a lot of misunderstandings and endless hours for clarifications during the detailed.
And typically not all aspects are considered during the detailed engineering phase, so they only appear
during commissioning, when the different package units and the rest of the plant need to work together.
6
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 7/25
Presentation How to Reduce I&C Engineering CostPresentation How to Reduce I&C Engineering Cost
How to Reduce
ns rumen a on an on ro ys em e a e ng neer ng os
and Commissioning Time
When Several Packa e Units need to be Inte rated
Abstract
7
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 8/25
Agenda How to Reduce I&C Engineering CostAgenda How to Reduce I&C Engineering Cost
– Typical Issues in C&I Detailed Engineering when
Package Units are Involved
– Consequences of Poor Design
– ome es rac ces or on ro ys em an eWiring Design and Commissioning
– Business Results Achieved
–
8
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 9/25
Typical Issues in C&I Detailed Engineering when Package Units InvolvedTypical Issues in C&I Detailed Engineering when Package Units Involved
Package Unit Vendor doesn’t differentiate which signals need to
e w re to an w c s gna s nee to e w re to
9
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 10/25
Typical Issues in C&I Detailed Engineering when Package Units InvolvedTypical Issues in C&I Detailed Engineering when Package Units Involved
Correct:
10
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 11/25
Typical Issues in C&I Detailed Engineering when Package Units InvolvedTypical Issues in C&I Detailed Engineering when Package Units Involved
ac age n t en or or c ent oesn t e ne mus room
is required
11
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 12/25
Typical Issues in C&I Detailed Engineering when Package Units InvolvedTypical Issues in C&I Detailed Engineering when Package Units Involved
DCS-ESD Interface: Signals hardwired between controllers
(mainly DCS-ESD) not defined
DCS ESD
It is necessary to analyze which interlocks are to be programmed in DCS and
which in ESD and where are wired to (DCS or ESD) each of the signals involved
in the interlocks
12
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 13/25
Typical Issues in C&I Detailed Engineering when Package Units InvolvedTypical Issues in C&I Detailed Engineering when Package Units Involved
DCS-ESD Interface:
Signals hardwired between controllers
DCS ESD
It is necessary to analyze which interlocks are to be programmed in DCS and
which in ESD and where are wired to (DCS or ESD) each of the signals involved
in the interlocks
13
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 14/25
Typical Issues in C&I Detailed Engineering when Package Units InvolvedTypical Issues in C&I Detailed Engineering when Package Units Involved
Hardwired signals between MCC and DCS or ESD defined too
late
P&ID 1st rev received from Vendor P&ID marked by client with MCC signals
14
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 15/25
Typical Issues in C&I Detailed Engineering when Package Units InvolvedTypical Issues in C&I Detailed Engineering when Package Units Involved
Package Unit Vendor doesn’t follow Client tagnaming criteria for
Control System Signals and wiring design (JBs, Multicables,
TBs...etc .
15
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 16/25
Typical Issues in C&I Detailed Engineering when Package Units InvolvedTypical Issues in C&I Detailed Engineering when Package Units Involved
Controls and Interlocks oorl re resented on Packa e Unit
Vendor P&ID
Controls and Interlocks oorl defined in Packa e Unit Vendor
Control Narratives
P&ID 1st rev
received from
Vendor
16
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 17/25
Typical Issues in C&I Detailed Engineering when Package Units InvolvedTypical Issues in C&I Detailed Engineering when Package Units Involved
17
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 18/25
Typical Issues in C&I Detailed Engineering when Package Units InvolvedTypical Issues in C&I Detailed Engineering when Package Units Involved
Inte ration of Packa e Unit Vendor Controls and Interlocks with
the rest of the plant poorly defined (quite often overlooked)
Definition by client of which controllers (DCS & ESD) will receive
Package Unit Vendor hardwired signals defined too late
18
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 19/25
Consequences of Poor DesignConsequences of Poor Design
Consequences of Poor Design:Consequences of Poor Design:
Endless hours spent (email chains, telephone calls..etc)
Many revisions in (P&ID, Signal List, Logic Diagrams, Wiring
Design...etc)
Longer commissioning and start-up time
ore cu an expens ve u ure ma n enance
19
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 20/25
Some Best Practices for Control S stem and Field Wirin Desi n and CommissioninSome Best Practices for Control S stem and Field Wirin Desi n and Commissionin
Some Best PracticesSome Best Practices
For Control System and Field WiringFor Control System and Field Wiring
20
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 21/25
Some Best Practices for Control S stem and Field Wirin Desi n and CommissioninSome Best Practices for Control S stem and Field Wirin Desi n and Commissionin
Send Client C&I Desi n S ecs to Packa e Unit Vendor
Involve Client personnel in all phases of the project
Clarification meetings at Package Unit Vendor facilities
Dedicate a person to take care of the integration of Package
Unit Vendor design with rest of the plant
21
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 22/25
Some Best Practices for Control S stem and Field Wirin Desi n and CommissioninSome Best Practices for Control S stem and Field Wirin Desi n and Commissionin
Pre are Control S stem SW Functional Desi n S ecification
Request ILDs (Instrument Loop Diagrams) for all signals
Homogenize PLCs in your plant
Use AMS (or similar tool) for loop test
Re uest FAT and SAT rotocols before startin the tests
22
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 23/25
Business Results Achieved How to Reduce I&C En ineerin CostBusiness Results Achieved How to Reduce I&C En ineerin Cost
-Cost drastically reduced (many engineering hours saved)
- Commissioning and Start-up time reduced
23
8/17/2019 2016 Emerson Exchange PPT Reduce C&I Cost Rev0b JS 11Apr16
http://slidepdf.com/reader/full/2016-emerson-exchange-ppt-reduce-ci-cost-rev0b-js-11apr16 24/25
uestions and Answers How to Reduce I&C En ineerin Costuestions and Answers How to Reduce I&C En ineerin Cost
Thanks for your attentionThanks for your attention
Now: Questions and Answers