alternative delivery for large programs ......design-build delivery $, t, q •contract...

48
FARUK OKSUZ, P.E. ALTERNATIVE DELIVERY FOR LARGE PROGRAMS & PROJECTS September 12-15, 2016 Vice President & Infrastructure Systems Director

Upload: others

Post on 13-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

FARUK OKSUZ, P.E.

ALTERNATIVE DELIVERY FOR LARGE PROGRAMS & PROJECTS

September 12-15, 2016

Vice President & Infrastructure Systems Director

Page 2: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

Design-Build delivery is often the “norm” for global construction and tunneling industry.

• Introduction - What is “Alternative Delivery?”

• Key performance indicators and the “Delivery Spectrum”

• Drivers for large tunneling programs

• Trends and cases in the North American and Global tunneling

OUTLINE

Owners, engineers, contractors, and operators are all vested stakeholders

and beneficiaries of successful Project Delivery

Page 3: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

COMMONLY USED ALTERNATIVE DELIVERY OPTIONS • Design-Build (lowest lump sum bid) and

Progressive Design-Build

• Third Party Program Management and Construction Management (PM/CM)

• Construction Management at Risk (CMAR)

• Design-Build-Operate-Finance (DBOF)

• Design-Build-Operate/Maintain-Transfer (DBOT)

• Public Private Partnership (PPP)

• Alliance Contracting

• Others

Alternative delivery is intended to bridge gap between the Owner and Contractor during procurement.

McCook Tunnel Project above was awarded based on “best-value” selection.

Owners want flexibility - custom variations such as best value selection, are also used as alternative procurement though projects are delivered using traditional design-bid-build delivery.

Page 4: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

September 12, 2016

ACKNOWLEDGE GROUND RULES

• Safety is never compromised

• Dichotomy of quality vs. price will prevail

• Schedule certainty (speed of delivery may be accelerated)

• Inherit risks do not transfer or go away, and must be properly addressed

• Market drives the price

Basic Principles of Contracting are not

Alternatives.

Page 5: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

September 12, 2016

CONTRACTING STRATEGY MUST RESULT IN BEST DELIVERY THROUGHOUT ALL PROJECT PHASES

COMMISSIONING & OPERATION

CONSTRUCTION

PREDESIGN

PLANNING

Project Progression / Realization

Rela

tive

Impa

ct o

n Pr

ojec

t O

utco

me

& S

ucce

ss

FINAL DESIGN

Northwest Side Tunnel APWA 2006

Thornton Transitional Reservoir APWA 2016

AWARD-WINNING PROJECTS

Page 6: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

Once qualified, Bid Price should drive the selection for alternative delivery.

• Safe, constructible and operable systems

• Risks are well managed

• Meet the Owner’s primary delivery expectations: • Quality • Cost effective and within budget • On time • Regulatory compliant • Neighborhood friendly

• Cost savings through • Innovative ideas • Flexibilities in means and methods • Accelerated delivery

• Systems reliability, redundancy, guarantees

PROJECT DELIVERY MUST SATISFY INDUSTRY’S KEY PERFORMANCE INDICATORS - KPIs

Page 7: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

PROJECT DELIVERY SPECTRUM September 12, 2016

Traditional Delivery Alternative Delivery

DBB CMAR Progr. DB DB DBOF/T Alliance PM/CM

Schedule/Cost Savings

Tolerance for Risk

Owner Control

Innovation

EPCM

?

Page 8: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

WHEN TO DECIDE BEST DELIVERY OPTION – PROJECT GATEWAYS

Stage 1 – Initiation

Engineering Deliverables

Contract Packages &

Delivery Options

Stage 2 - Feasibility

Front End Engineering

Performance Specifications

Stage 3 - Execution

Design / Design- Build

Stage 4 - Operations

Startup & Turnover

1

3

2

1 Gateway 1 – Program Management Strategy and Implementation

Stage 2 - Feasibility • Facilities Layout • Investigations • P&I D • Alternatives Definition • Alternatives Selection • FEED • Performance Specs • Cost Estimates • Schedule • Value Analysis, Constructability Review • Preliminary Engineering • Guidance Documents and SOPs for Engineering and Construction • Market Conditions •Project Sanction Prior to Execution and Delivery Decisions

Stage 1- Initiation • Program Objectives • Program Organization • Program Controls (budget, schedule, documentation, information technology, communications) • Safety • Stakeholders • Risk Management • Quality • Environmental Management • Sustainability • Regulatory •Technical Integrity Panel • Legal • Financial • Operations • Contract Packaging Strategy • Delivery Options

Stage 3 – Execution • Design • Design and Design-Build Contracts • Construction • CM and RE Roles • Contractor VE Proposals • Chartering • Award / Penalty Criteria • Performance Management

Stage 4 – Operations • Substantial Completion • Testing and Startups • Commissioning • O&M Manuals • Training • Warranty Transfers • Facilities Acceptance and Turnover • Project Records • Project Awards

Construction ►

2 Gateway 2 – Program Components, Delivery, Design Liability, Procurement and Execution Strategy, Safety, Budget, Schedule, Operations, and Quality Criteria and Performance Metrics are Established.

3 Gateway 3 – Compliant Facilities Construction Using Various Procurement Methods, Assurances to Meet Design and Operations Intent and Criteria, Implement Project Controls and Documentation

Owner Determines Gateways - Critical Project Milestone Accomplishments

Project Completion and Close Out

2016 2017

DELIVERY OPTIONS BECOMES CLEAR

September 12, 2016

Page 9: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

Alternative delivery drivers overlap with KPIs for successful execution

• Single Point Accountability

• Accelerated (speed of) Delivery

• Transfer of Risks and Fewer Change Orders

• Leveraging innovations in construction industry and flexibility in the means and methods

• Lower Price (due to shorter schedule)

• Resources (or lack thereof) including funding, project professionals, etc.

DRIVERS FOR LARGE DESIGN-BUILD PROGRAMS & PROJECTS

Water Design-Build Council Handbook waterdesignbuild.com

Page 10: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

Is there a design-build in the cards?

• Front-End (Preliminary) Engineering • Operational criteria (regulatory compliant) • Site engineering (geology, geotech, utilities,

hydraulics, etc.) • Assessment of risks • Permitting & easements • Neighborhood friendly • Scope of work (quantities)

• DB Procurement Contract • Safety, quality, cost & schedule • Minimum requirements, reviews, approvals • Bid form and payment terms (lump sum and

negotiated or unit priced items) • Legal framework • Must achieve competitive bids

DESIGN-BUILD DELIVERY

$, T, Q

Page 11: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

• Contract specifications must include owner’s typical details, state and local codes (building, fire, health department, etc.)

• References and compliance with applicable industry standards (ASTM, NASSCO, AWWA, AASHTO, DOTs, etc.)

• Completion, payment, and acceptance terms

• Warranty transfers

DB CONTRACTS MUST BE COMPLIANT WITH CODES, INDUSTRY STANDARDS AND OWNER’S SPECIFICATIONS

Page 12: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

Partnering, disputes resolution, and contract contingencies and allowances are essential for successful implementation

• Lump Sum • Safety • Project management / administration • Regulatory compliance • General mobilization and crew setup • General geologic/ground conditions

established • Length, size, type of pipeline for water

tunnels • Early design effort and reports • Typical traffic control, bypass, and

permits • Typical disposal, site cleanup, &

restoration

DESIGN-BUILD CONTRACT SETUP FOR TUNNEL CONSTRUCTION

• Negotiated (based on contract unit prices established or change orders) • Additional inspections and

investigations • Additional easements • Dealing with unknown or

concealed conditions • Utility conflicts resolution • Access and schedule restrictions

due to operations of existing systems

• Community concerns (working hours, noise, dust control, etc.)

• Commissioning, Operations and Maintenance (O&M) Requirements

Page 13: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

• Set aside traditional processes

• Use a stringent prequalification process to limit proposers to 5 or less

• Provide full access to the site and data to qualified bidders

• Conduct a balanced evaluation

• Ask for reasonable submission requirements

• Develop succinct criteria specifications

• Limit early design in the RFP (or allow time and money for design)

• Conduct separate evaluation of cost and quality issues

• Use lump sum contracts, if competitive price proposal process

SUCCESSFUL PROCUREMENT TIPS FOR DESIGN-BUILD

Owners must have the opportunity to review designs and accept/reject completed work

Pain/gain provisions in the Contract help align objectives of the parties

Page 14: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

September 12, 2016

OTHER GOOD IDEAS ! • Early advertisement, contractor information meetings,

widen early competition

• Receptive to new technologies and innovations

• Good bid forms, measurement and payment terms

• Develop consistent design documents (plans, specs, geotechnical data and baseline reports, etc.)

• Owner-furnished materials, disposal sites, in-kind services

• Stiffer penalties / better incentives

• Raise the bar on quality and cost control

• Allow contractors to take “calculated” risks with incentives

• Consider Early Contractor Involvement process

• Consider Program Management/Construction Management services for large/multiple contracts

Page 15: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

RISK MANAGEMENT PROCESS

Legend:

Workshops with Risk Management Committee (RMC)

Independent Value Engineering

Independent Contractor Review at 75% Design

Start

w

OWNER/AGENCY REGULATORY COMPLIANCE / QA ASSURANCES

RISK REGISTER ESTABLISHED & CONTINOUSLY UPDATED

Finish

Risk Mngt Team Engaged

GBR Experts Engaged

W

Constructability & Bidding Review

Alternative Delivery Options – Design-Build

GBR-Bidding

W

Contractor Prequalification

GBR-Construction

Contract Documents

Disputes Resolution Board (DRB) Engaged in Inspections, Documentation, Records

CR

TM 95 - 100% DESIGN 50 % DESIGN BASIS OF DESIGN CONSTRUCTION

VE

VE

CR

W

September 12, 2016

Page 16: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

TRENDS & CASES

SUCCESSES AND OPPORTUNITIES FOR IMPROVEMENT

16

Page 17: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

OVER 65 ALTERNATIVE DELIVERY PROJECTS IN NORTH AMERICA IN THE PAST 10 YEARS

1

4

7

8

32

16

22

19

10

2

3

5

6

9

11

14 15

17 20

23

28

31

12 27

41

40 39

24

26

35

38 37 25

21

18

36

13

29 30

33 34

Detroit Water Works Park II WTP

Milwaukee, WI— Howard Avenue WTP Ozone Improvements

DBIA Award Winner

DBIA Award Winner

Longmont, CO — Nelson-Flanders WTP

Bakersfield, CA — NE Bakersfield WTP

San Bernardino Valley — Foothill Pump Station

DBIA Award Winner

Phoenix, AZ — Lake Pleasant WTP

San Bernardino Valley — Central Feeder Groundwater Banking/Conjunctive Use

Louisville, KY — Morris Forman WWTP

DBIA Award Winner

September 12, 2016

Page 18: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

JOLLYVILLE TRANSMISSION MAIN (TUNNEL)

Page 19: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

Jollyville Tunnel & Transmission Main (WTP 4) — City of Austin, Texas

Key Project Drivers: ▪ Schedule ▪ Cost Certainty ▪ Community & Environmental

CMAR Delivery Method for $ 508M Program

2 Separate Design and 7 Separate Construction Contracts (GMPs) Raw Water Intake Intake Tunnel & Pump

Station 50 MGD Water Treatment

Plant Jollyville Transmission Main

PROJECT OVERVIEW

Period of Services: 2009 - 2014 Tunnel Cost : $90M

September 12, 2016

Page 20: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

September 12, 2016

Successes (What Went Well) Single Point of Contact for City Underground Components Completed

within 1 to 3% of Original Bid Price (favorable geology)

Opportunities for Improvement Schedule Not Being Met Contract Less than Clear on who owns the

Schedule Risk Overlapping Tasks During Construction

Jollyville Tunnel & Transmission Main (WTP 4) — City of Austin, Texas

Page 21: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

MIDDLE FORK SURGE SHAFT REHABILITATION

Page 22: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

September 12, 2016

Middle Fork Surge Shaft Rehabilitation — Placer County Water Agency, Placer County, California

Key Project Driver: ▪ Cannot dewater shaft, need to perform

repairs in the “wet”

DB Delivery Method Contractor selected on

qualifications Repair of a cracked surge shaft

lining (10 ft diameter x 600 ft deep)

Installation of an 8 ft diameter steel lining over the full depth of the shaft and grouted in place

PROJECT OVERVIEW

Period of Services: 2005 - 2007 Total Project Value: $ 35 M

Page 23: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

Middle Fork Surge Shaft Rehabilitation Placer County Water Agency

Aerial view of shaft site

Contractor developed a custom frame to hold and lower 40-ft long pipe segments

September 12, 2016

Page 24: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

September 12, 2016

Successes (What Went Well) Allowed “innovations” by the Contractor

(quick connect mechanical couplings below water)

Alignment of goals between parties Communication among key project

participants Verification test program proved certainty

of means and methods reducing risks and allowing for cost savings to be incorporated into design

Construction completed below initial target price

Middle Fork Surge Shaft Rehabilitation — Placer County Water Agency, Placer County, California

Innovation and use of mechanical pipe couplings saved valuable time for divers to install underwater

Page 25: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

TWIN FALLS HYDROPOWER PLANT ALLIANCE CONTRACT

Page 26: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

September 12, 2016

Twin Falls Hydropower Plant — WE Energies, Wisconsin

Project Drivers: Aging Infrastructure

Power generation efficiency Environmental

Alliance contract with shared risk/reward on total capital cost. B&V / CR Meyer / WE Energies

New powerhouse includes 80 foot deep rock excavation

Headwater and tailrace cofferdams

New spillway Remove existing powerhouse

PROJECT OVERVIEW

Period of Services: 2012 – 2016 Total Project Value: $70 million

Page 27: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

Twin Falls What is Working

Safety – No OSHA recordable Quality – No NCRs Partnering with Owner and

Contractor Cost is trending below budget

with contingency increasing On schedule with sense of

urgency across team

What Could be Improved Always can do better on safety Nothing identified at recent

executive review meeting

September 12, 2016

Page 28: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

LOWER BAKER HYDROELECTRIC POWERHOUSE

Page 29: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

September 12, 2016

Lower Baker Hydroelectric Unit 4 Powerhouse — Puget Sound Energy, Washington

Key Project Drivers: ▪ Schedule (Tax Credits) ▪ Cost Certainty ▪ Risks in Underground Construction

Design Build (Best Value) New Below Grade Powerhouse

30 MW Francis turbine generator

12 ft diameter, 1,000 ft long steel lined pressure tunnel

108 in. butterfly valve 60 in. Howell Bunger bypass

valve Unit and facility control systems

PROJECT OVERVIEW

Period of Services: Oct 2011 – June 2013 Total Project Value: $ 70 M

Page 30: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

September 12, 2016

Lower Baker Hydroelectric Unit 4 Powerhouse — Puget Sound Energy, Washington

Rotor Installation

Powerhouse Excavation

Tunnel Excavation

Page 31: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

Successes (What Went Well) Owner procured equipment assured PSE

got what they wanted. Project completed 3 months ahead of

schedule (tax credits received) Strong safety performance No lost time safety incidents Change orders – no surprises

Lower Baker Hydroelectric Unit 4 Powerhouse — Puget Sound Energy, Washington

Completed Unit 4 Powerhouse

September 12, 2016

Page 32: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

FIVE (5) DESIGN-BUILD CONTRACTS FOR TUNNELS

SINGAPORE PUB DEEP TUNNEL SEWERAGE SYSTEM (DTSS) PHASE 2

Page 33: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

DEEP TUNNEL SEWERAGE SYSTEM (DTSS)

Kranji WRP & NEWater Factory

Changi WRP & NEWater Factory

DTSS Phase 2 DTSS Phase 1

Tuas WRP & NEWater Factory

DTSS Phase 1 (2000 – 2008) Cost: S$3.4 billion • 48km tunnels (3.3m to 6m ID) • 60km link sewers (0.3m to 3m ID) • 176 MGD plant at Changi • 5km outfall (3m ID)

DE

EP

TU

NN

EL

SEW

ER

AG

E S

YST

EM

Page 34: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

DTSS PHASE 2

• 50km sewer tunnels by TBM (3m to 6m ID) • 50km sewers by pipe-jacking (0.3m to 3m ID) • 176MGD plant at Tuas with 25MGD NEWater capacity

Industrial Tunnel

South Tunnel

Tunnel and Link Sewers

• Sized adequately for the future • Design for Maintenance and Resilience

DE

EP

TU

NN

EL

SEW

ER

AG

E S

YST

EM

Page 35: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

DTSS PHASE 2 – SOUTH TUNNEL

• 50km of tunneling works delivered via DB contracts • Tunnel ID ranges from 3m to 6m • Includes construction of hydraulic structures & air management

facilities

Industrial Tunnel

South Tunnel

Northwest Link Sewer Tunnel

Southern Region Link Sewer Tunnel

Pasir Panjang Link Sewer Tunnel

Holland Link Sewer Tunnel

South Spur

DE

EP

TU

NN

EL

SE

WE

RA

GE

SY

ST

EM

Tuas WRP

Conveyance System Key Features: • Corrosion Protection • Tunnel Monitoring (fiber optic) • Air Management • Tunnel Isolation GATES • Tunnel Inspections • Integrated Data Management System (IDMS)

Page 36: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

DE

EP

TU

NN

EL

SE

WE

RA

GE

SY

ST

EM

LINK SEWERS - PIPE JACKING INSTALLATIONS

• 50 km of pipe-jacking works delivered via DBB contracts • Pipe ID ranges from 0.3m to 3m

Page 37: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

HDPE Lining

Inner Secondary Lining (MIC* Resistant Concrete)

Concrete Segmental Tunnel (Primary Lining)

*MIC – Microbiological Induced Corrosion

DE

EP

TU

NN

EL

SE

WE

RA

GE

SY

ST

EM

Sewer Tunnel Cross Section - General

Proposed system is expected to withstand the corrosive sewer

environment over its design life of 100 years.

37

Ranges from ~10 to 20 ft (3 to 6m) dia.

Page 38: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

38 38

GATE PANEL ASSEMBLY

ISOMETRIC VIEW SHAFT STRUCTURE

(BASE) ISOLATION GATE SHAFT SECTION

Gate Module Rollers

Gate System

Tunnel

Link Sewer

Modular Gate System

Working Platform

Gate System (Assembled & Lowered)

DE

EP

TU

NN

EL

SE

WE

RA

GE

SY

ST

EM

Tunnel Isolation with Roller Gates

September 12, 2016

Page 39: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

39

DE

EP

TU

NN

EL

SE

WE

RA

GE

SY

ST

EM

Fiber Optic Strain Monitoring for Structural Integrity

• Longitudinal installation • Fiber optic cables cast directly into segments during fabrication

FO Cable 1 FO Cable 2

September 12, 2016

Page 40: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

DTSS PHASE 2 CONTRACTS & IMPLEMENTATION TIMELINE

Page 41: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

Link Sewers

Tunnels

Tuas WRP

IWMF

Construction Consultant Tender

Detailed Design

Construction Consultant Tender

Detailed Design

Design & Construction D&B Tender

Design & Construction Pre-Q, EPC Contractor(s) & call EPC Tender(s)

Pre-Q, Owner’s Engineer (OE) & call OE Tender

DTSS PHASE 2 & IWMF OVERALL TIMELINE D

EE

P T

UN

NE

L SE

WE

RA

GE

SY

STE

M

IWMF – Integrated Waste Management Facility

Page 42: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

42 42

Batch Contract Tunnel Length (km)

Tunnel Internal Dia. (m)

Indicative Tender Calling

Completion

1 T-07 12 3.5 - 6.0 4Q 2016 4Q 2023

1 T-08 10 3.3 - 6.0 4Q 2016 3Q 2022

1 T-09 8 6.0 4Q 2016 4Q 2022

2 T-10 8 3.5 - 6.0 1Q 2017 2Q 2023

2 T-11 12 3.0 - 3.3 1Q 2017 1Q 2024

FIVE (5) TUNNEL CONTRACT PACKAGES D

EE

P T

UN

NE

L SE

WE

RA

GE

SY

STE

M

September 12, 2016

Page 43: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

DE

EP

TU

NN

EL

SE

WE

RA

GE

SY

ST

EM

LINK SEWERS CONTRACT PACKAGING

Area 5

Area 4

Area 3

Area 2

Area 1

Detailed Design Consultants from 1Q 2017

Area Length (km)

Indicative Tender Calling Construction

1 9 Feb-Aug’18 Aug’18-Aug’24

2 11 Feb-Aug’18 Aug’18-Aug’24

3 13 Feb-Aug’18 Aug’18-Jan’24

4 9 Feb-Aug’18 Aug’18-Jan’24

5 6 Feb-Aug’18 Aug’18-Jan’24

Page 44: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

CLOSING WITH PROGRESSIVE DESIGN-BUILD

Page 45: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

PROGRESSIVE DESIGN BUILD Advantages

• One contract = one point of responsibility

• Good delivery method for retrofit projects

• Promotes Collaboration with Owner

• 100% of the equipment and construction are competitively bid

• Early involvement of construction professionals, O&M, and value engineering occurs throughout the project

• Shared incentives if GMP pricing model is adopted

• Fast track schedule

• Owner has off-ramp prior to GMP Establishment

Multiple Construction and Equipment Packages

Owner

DB Contractor

Disadvantage Not applicable for

completely designed projects

September 12, 2016

Page 46: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

TRADITIONAL DESIGN-BID-BUILD

DESIGN-BUILD

PROGRESSIVE DESIGN-BUILD

PROGRESSIVE DESIGN-BUILD OFFERS SAVINGS IN TIME AND COST

Management Plan Design Define DB Scope Proposal Procurement, Construction, Startup & Commissioning, Performance Testing

GMP Established

Lump Sum Established

Cost Established

Long Lead procurement

SAVE TIME, SAVE MONEY

Design Construction

Design

Construction

Design Construction

September 12, 2016

Page 47: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

Design-Bid-Build CMAR Design-Build Progressive DB

“Collaboration”

WHO IS AT RISK? Owner Owner Alt Delivery Contractor

Alt Delivery Contractor

WHO IS RESPONSIBLE for performance? Owner Owner Alt Delivery

Contractor Alt Delivery Contractor

WHO IS RESPONSIBLE for Management of Change Orders ?

Owner Owner Alt Delivery Contractor

Alt Delivery Contractor

Competitive YES YES YES YES

Market Based YES YES YES YES

Transparent NO YES NO YES

Defendable YES YES YES YES

Collaborative YES/NO YES NO YES

PROGRESSIVE DB ALLOWS “BEST FOR PROJECT” DECISIONS WITH SAME RISK MANAGEMENT LEVEL AS DB

September 12, 2016

Page 48: ALTERNATIVE DELIVERY FOR LARGE PROGRAMS ......DESIGN-BUILD DELIVERY $, T, Q •Contract specifications must include owner’s typical details, state and local codes (building, fire,

QUESTIONS & ANSWERS THANK YOU. Faruk Oksuz, P.E. [email protected]