alma field development environmental statement

Upload: casey-combs

Post on 01-Mar-2016

25 views

Category:

Documents


0 download

DESCRIPTION

Field Development Alma

TRANSCRIPT

  • EnQuest Heather LimitedAlma Field Development Environmental StatementDECC Document Ref: D/4110/2011Intertek METOC Document Ref: P1459BA_RN2525_Rev0EnQuest Heather Limited Document Ref: ENQ-KN501-HS-001-ENS-0001ISSUED: 21 JULy 2011

    WHERE ENGINEERING MEETS THE ENVIRONMENT

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    STANDARD INFORMATION SHEET Project Name Alma Field Development DECC Reference Number D/4110/2011

    Type of Project Small oil field development Undertaker Name EnQuest Heather Limited Undertaker Address 5 Floor Consort House, Stell Road, Aberdeen, AB11 5QF, United Kingdom Licencees / Owners EnQuest Heather Limited (100%)

    Short Description

    EnQuest Heather Limited wishes to redevelop the Ardmore field in the UK Central North Sea (CNS). The field, to be renamed Alma, will be developed through two drill centres tied-back via new oil production and water injection flowlines to the Uisge Gorm floating production, offloading and storage facility (FPSO). The development will consist of six production wells and two water injection wells (which will be used to drive production due to low reservoir pressures). Wells will be drilled using a combination of water and oil based muds. Cuttings and water based muds will be discharged to sea both at the seabed and from the drilling rig approximately 10m below the sea surface. Oil based mud and cuttings will not be discharged and will be skipped and shipped back to shore for disposal. Due to the relatively short expected field life of the Alma development (ten years), the Uisge Gorm FPSO will be used instead of installing a platform. Produced crude will be collect by shuttle tanker once every two weeks. The majority of the produced gas will be used for power generation, however there may be a short period early part of field life where excess gas is produced that cannot be burned, this will be flared. All produced water will be re-injected. Production flowlines will be surface laid and protected. The water injection flowline will be trenched and buried, but where trenching is not possible it will be surface laid and protected. Concrete mattresses and rock material will be used for protection. Current estimates are that based on a 10 year field life the base case recovery from the Alma field will be 20.7 million barrels (2.8 million tonnes) and a high recovery case of 32.5 million barrels (4.4 million tonnes). Peak production in the first year will be in the region of 4.5 million barrels (0.61 million tonnes) for the base case and 7.8 million barrels (1.06 million tonnes) for the high recovery case. Construction is scheduled to start in January 2012 with the drilling of the first producer wells. First oil is anticipated in August 2013.

    Anticipated Start of Works January 2012

    Previous / Other Statements Related to this Project

    N/A

    Significant Environmental Impacts Identified

    EnQuest is aiming to limit environmental effects to low impact through project design, mitigation measures and operational controls. No impacts associated with the development have been categorised as Major or Critical, meaning that the majority of the impacts were assessed as having no or minor residual impact (i.e., impacts can be managed through effective standard operating procedures). A few impacts were assessed as Moderate (i.e., the residual impact has been subject to feasible and cost effective mitigation and no further measures are practicable). During construction and production it is considered that the following activities may have an impact: on the environment; atmospheric emissions from power generation; anchoring ; discharge of chemicals and drill cuttings; positioning of structures, rock material and concrete mattressing on the seabed; and the accidental spill of hydrocarbons and/or chemicals. However in all instances the severity of the impact is limited by the nature and composition of the environment and by the fact that these activities are short-term and affect a localised area. With mitigation measures in place, the Alma field development will have a minor impact on the environment.

    Statement Prepared By Intertek METOC and EnQuest Heather Limited

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    NON-TECHNICAL SUMMARY INTRODUCTION

    EnQuest Heather Limited wishes to redevelop the Ardmore field in the UK Central North Sea

    (CNS). The field, to be renamed Alma, will be developed through two drill centres tied-back

    via new oil production and water injection flowlines to a floating production, offloading and

    storage facility (FPSO). Export will be through the use of a shuttle tanker from the FPSO.

    The proposed Alma development will be located in United Kingdom continental shelf (UKCS)

    Blocks 30/24 and 30/25, approximately 274km east of the nearest landfall on the

    Northumberland coastline and approximately 18.5km from the Norway/UK international

    boundary (median line).

    In compliance with regulatory requirements, and to responsibly manage any impacts from the

    development, EnQuest has carried out an Environmental Impact Assessment (EIA) of the

    proposed development.

    The EIA process establishes the environmental baseline in the area of the proposed

    development and identifies environmental sensitivities, particularly with relevance to the

    concerns of stakeholders and regulatory bodies. It also evaluates relevant environmental

    impacts and their significance, and finally proposes mitigation measures which the operator

    will implement to minimise these impacts.

    This document reports on the EIA process, its findings and conclusions.

    GOVERNING LEGISLATION

    Offshore oil and gas developments are governed by a collection of international, European

    Community (EU) and UK laws, policies and guidelines. These dictate the management goals

    and objectives which an environmental assessment may aim to achieve. The main UK

    regulations that apply to the project are:

    Petroleum Act 1998 Requires all offshore oil and gas development to apply for

    consent to undertake the project.

    Offshore Petroleum Production and Pipelines (Assessment of Environmental Effects)

    (Amendment) Regulations 2007 These regulations implement the EC EIA and Public

    Participation Directive, and require an ES to be submitted for offshore oil and gas

    projects and public participation in the consent process.

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    Offshore Marine Conservation (Natural Habitats, &c.) Regulations 2007 (as amended

    in 2009 and 2010) These regulations implement in the UK the EC Habitats Directive

    (92/43/EC) and the EC Birds Directive (79/409/EC) and aim to protect marine species

    and wild birds from environmentally damaging activities. It is now an offence under the

    Regulations to deliberately disturb wild animals of a European Protected Species.

    Offshore Petroleum Activities (Conservation of Habitats) Regulations 2001 (amended

    in 2007) The regulations apply the EC Habitats and EC Birds Directives in relation to

    oil and gas projects on the UKCS.

    PROJECT JUSTIFICATION

    Oil is the UKs second largest source of primary energy, supplying over 30% of the countrys

    total energy needs (OGUK 2009). In 2008, the UKCS oil production was enough to satisfy

    97% of domestic consumption, produced mainly from fields in the Central North Sea (CNS)

    basin, with some production in the NNS and Southern North Sea (SNS). In 2000, the UK

    Government identified the need to stimulate oil and gas investment and activity to ensure

    that indigenous production of oil and gas remained at significant levels into the future. The

    Promote UK campaign is designed to attract new entrants onto the UKCS, and focused on:

    Independent oil companies with the resources to drill wildcat exploration wells and

    exploit the full value chain from exploration to development; and

    Niche developers, particularly those with the skills to develop previously undeveloped

    discoveries by using technically innovative and best cost solutions (DECC 2011a).

    As a result of these initiatives, EnQuest has been active on the UKCS since 2010. It

    specialises in predominantly mature areas of the NNS and CNS, aiming to maximise the

    potential from existing fields and future developments in the UKCS. The longer term strategy

    is to become a prominent exploration and development operator.

    The Alma Field development is part of this strategy and fits many of the UK energy policy

    objectives:

    It would bring on-stream a marginal field that it is now feasible to develop with the

    prevailing oil price and the small field allowance applicable to this size of field

    It is a national resource that will help contribute towards energy security

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    Current estimates predict that P501 recovery over field life will be 20.7 million barrels of oil (2.8 million tonnes). P102 recovery is estimated to be 32.5 million barrels (4.4 million tonnes).

    PROJECT ALTERNATIVES

    EnQuest have considered a number of development options for the Alma field. Given the

    compact nature of the field and relatively short field life, the decommissioning strategy has

    played an important role in option selection. Options considered included the choice of

    surface facilities (FPSO, floating production facility (FPF), platform or subsea tie-back), the

    choice of drilling rig (semi submersible or heavy duty jack-up) and the installation philosophy

    of the flowlines (trenched and buried or surface laid and protected).

    After considerable deliberation, the FPSO, semi submersible and a combination of trenching

    and surface lay options were selected, based on combination of technical, environmental

    economic considerations. Table 3-3 details all the pros and cons of each option.

    FPSO

    A number of FPSOs are available for deployment

    Provides an integrated storage and offloading system

    Modifications required are more economic that other available options e.g. new

    platform

    FPSOs fit for expected field life

    Using an existing FPSO is cheaper than a new build

    FPSOs considered have proven track record in the UKCS

    Minimal seabed disturbance from installation

    Can be easily redeployed at end of field life

    Semi Submersible

    Less weather dependant during positioning on site

    More scope for moving rig but maintaining same anchor pattern less seabed

    disturbance. For example, moving to allow subsea infrastructure to be installed,

    moving rig if subsurface philosophy changes

    1 50% confidence level of this volume of oil being produced 2 10% confidence level of this volume of oil being produced

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    Ability to drill six wells on same anchor pattern less seabed disturbance

    Easier to run horizontal xmas trees

    Better selection options- at least two rigs are known to be available

    Current drilling team has extensive knowledge of semi submersible drilling operations

    Flowlines

    Buried

    Greater protection for flowlines no additional protection such as rock would be

    required except for mattressing and grouting at trench transition areas

    Conventional / proven solution

    Option to surface protect spans which cannot be buried due to existing subsurface

    obstructions

    Surface Laid

    Ease of installation - range of installation vessels available

    Benefit as compact field layout with possible drilling rig on site during installation

    Lower mobilisation costs for installation

    Potential of re-use / decommissioning easier

    Conventional / proven solution

    Minimal seabed disturbance

    Lower risk of subsurface obstructions because no trenching

    Additional protection such as rock material will be required for certain spans

    Technically preferred option for production flowlines due to temperature issues

    PROJECT DESCRIPTION

    SCHEDULE

    Construction is scheduled to start in January 2012 with the drilling of the first production well.

    Construction activities will continue through to May 2013 with first oil expected in third quarter

    2013. A total of six production wells and two water injector wells will be batch drilled and are

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    expected to take approximately three months each to drill and complete. Field life is

    anticipated to be ten years.

    CONSTRUCTION

    The development will consist of:

    The drilling of six producers and two water injectors

    The Uisge Gorm FPSO

    Two 10-inch production flowlines, one 10-inch water-injection flowline, two control

    umbilicals and one power cable

    Production wells will target a total of three reservoirs within the Alma Development area:

    Devonian, Zechstein and Rotliegend. Three production wells will be drilled in five sections

    using a combination of water based mud (WBM) and oil based mud (OBM), with each

    section cement cased. The remaining three production wells and the two water injection

    wells will be drilled in four sections also using a combination of WBM and OBM, with each

    section cement cased. Cuttings and WBM will either be discharged at the seabed or to sea

    approximately 10m below sea surface from the drilling rig. All OBM and cuttings will be

    skipped and shipped to shore for disposal.

    The water injection flowline will be trenched and backfilled. In the event of any undulations in

    the trench (and subsequently the flowline) a contingency will be in place for the provision of

    approximately 5,000 tonnes of rock for deposition for protection. The rock will be deployed to

    mitigate any upheaval buckling (less of a problem with flexible flowlines) or pipeline out of

    straightness events experienced during the trenching and pipe-lay activities. This may be

    required for pipeline protection, depth of cover anomalies or dropped object protection. The

    requirement for rock deposition will be identified during post lay survey and if required the

    rock will be placed accurately utilising a dynamically positioned fall pipe rock installation

    vessel. The vessel will be equipped with a fall pipe to deploy rock accurately in the spot

    location. Where trenching is not possible the water injection flowline will be surface laid and

    protected where required with concrete mattress to eliminate any pipe-spans or seabed

    obstructions. The production flowlines will be surface laid and protected. They cannot be

    trenched as the arrival temperature of the production fluids at the FPSO would be too high.

    After tie-in, the flowlines will be hydrotested and leak tested before being dewatered and then

    commissioned. Concrete mattresses and rock material will be used for dropped object

    protection and stability. The water-injection flowlines will terminate directly in the FPSO. The

    production flowlines will terminate at a bolted straight T piece from which flexible risers will

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    take produced fluids to the FPSO. All flexible risers will be secured by either vertical piled or

    gravity base anchors and horizontal clump weight anchors.

    The Uisge Gorm FPSO will be held permanently on station without any aid from thrusters or

    other external sources by nine anchors. Modifications and upgrades will be carried out on

    the FPSO turret to accommodate the new flowline/umbilical riser systems required to receive

    and process the Alma hydrocarbons and to export injected water. The upgrades will be

    finished before the FPSO is mobilised to the field.

    Note: Image is for illustrative purposes only and does not necessarily reflect exact layout of flowlines and associated infrastructure

    PRODUCTION

    Produced crude oil and associated gas will be produced back to the FPSO and oil then

    offloaded onto shuttle tankers for export.

    First oil is currently expected in third quarter 2013. Current estimates are that based on a 10

    year field life the base case recovery from the Alma field will be 20.7 million barrels (2.8

    million tonnes) of crude oil and a high recovery case of 32.5 million barrels (4.4 million

    tonnes). Peak production in the first year will be in the region of 4.5 million barrels (0.61

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    million tonnes) for the base case and 7.8 million barrels (1.06 million tonnes) for the high

    recovery case. The reservoir pressure at Alma is such that produced water re-injection is

    required to ensure that satisfactory quantities of crude oil are produced. Sufficient quantities

    of gas are expected to be produced with the crude to be used for power generation onboard

    the FPSO.

    Produced water will be passed through a bank of hydrocyclones which will take oil in water

    (OIW) concentrations from approximately 1000mgl-1 to below 30mgl-1. It will then be routed

    through a degasser and settling vessel. The produced water then passes through the pumps

    past an overboard discharge point and into four injection pumps that push the produced

    water down the water injection flowline to be re-injected. Should any produced water be

    discharged (due to temporary failure, or routine maintenance of the produced water re-

    injection system) then OIW concentrations will be below 30mgl-1.

    Early in the field life there will be the need to flare gas. This would be due to either

    insufficient gas production to power the generators on the FPSO or because of an excess of

    gas produced, over that demanded for fuel.

    DECOMMISSIONING

    Field life is expected to be ten years. Before the end of field life, arrangements for

    decommissioning will be developed in accordance with the prevailing UK government and

    international legislation. The development plan is based on the assumption that similar

    requirements to current legislation will be applicable. These requirements have been

    considered in the design of the facilities and during project planning. The impacts of

    decommissioning activities on the environment have not been assessed under the scope of

    this document as they will be the subject of a separate EIA.

    ENVIRONMENTAL IMPACT AND MITIGATION

    Mitigation is an integral part of the Alma development. All of the potential interactions

    between project activities and environmental receptors are subject to either standard

    recognised best practice mitigation measures or to impact specific, feasible and cost

    effective mitigation. In general, the mitigation proposed will be sufficient to reduce the effects

    of activities to below levels which will cause a significant residual impact. For those where

    mitigation isnt enough, the residual impacts are detailed below with a discussion of the

    mitigation that will help to reduce the impact to the acceptable levels identified.

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    The following table summarises the findings of the detailed EIA process undertaken in

    relation to the Alma development and outlines details of the impacts that were considered to

    have a residual impact on the environment.

    Receptor & Type of Impact

    Baseline & Impact Assessment Significance of Residual Impact

    Mitigation

    Construction Seabed Conditions: Disaggregation of surface sediments Change in seabed topography

    The Alma development area comprises a

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    Receptor & Type of Impact

    Baseline & Impact Assessment Significance of Residual Impact

    Mitigation

    Physical damage to individuals or habitats and smothering (Drill cuttings)

    direct impact on the benthic community. Cuttings discharged through the water column could have an impact on the benthic community as they settle out on the seabed. Cuttings will be incorporated in the sediment through bioturbation and general sediment mobility. Significant erosion of cuttings piles starts when the seabed critical velocity reaches 0.35ms-1 (UKOOA 1999). Seabed currents (0.42ms-1) will ensure that all cuttings piles will disperse quickly, although there is the possibility that they may persist for a number of years. Experience in the CNS region indicates that cuttings piles will persist for 5-10 years.

    No mitigation envisaged

    Fish and Shellfish: Loss or disturbance of spawning and nursery grounds effecting stock viability

    Mackerel, lemon sole, sprat, haddock and whiting all spawn and/or nurse in the vicinity of the Alma development. Spawning occurs mainly between April and September, with peaks in May, June and July. Juveniles may be present in the region all year round. As the majority of the noise generated by offshore oil installations is low frequency (

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    Receptor & Type of Impact

    Baseline & Impact Assessment Significance of Residual Impact

    Mitigation

    any residual impact after mitigation. production and water injection pipelines between the FPSO and the production and water injection drill centres The drilling rig and construction vessels will be appropriately lit and sound warnings will be broadcast in poor visibility. Users of the sea will be notified of the presence and intended movements of construction vessels via the Kingfisher fortnightly bulletins, Notices to Mariners and VHF radio broadcast.

    Shipping and Navigation: Impact on vessel movement

    The nearest shipping route is within 2nm of the Alma development. Some shipping will be displaced from the immediate vicinity of the development; however there is ample sea room to do so. The 500m safety exclusion zone around the drilling rig is intended to prevent potential collisions with any vessels that may be in the area. This will be enforced by a guard vessel.

    Minor

    Archaeology: Physical damage to undiscovered archaeology

    It is unlikely that any remains of archaeological significance exist within the Alma area. However, the proposed mitigation measures would ensure damage to the site would be minimised and the nature of the discovery properly reported. It is therefore likely that any damage would be of minor significance, while the value of the discovery may be of moderate/major (positive) significance.

    Minor The British Marine Aggregate Producers Association (BMAPA) protocol for reporting finds of archaeological significance will be followed

    Production Commercial Fishing: Exclusion from fishing grounds Potential collision risk

    The project area is not considered to be a commercially important for fishing. The continued presence of development and the exclusion zones around the drill centers and the FPSO will typically preclude fishing in this area due to the small development size.

    Minor A 500m safety exclusion zone will be enforced around the FPSO. The FPSO will be appropriately lit and sound warnings will be broadcast in poor visibility. Users of the sea will be notified of the presence of the FPSO and new safety exclusion zones via the Kingfisher fortnightly bulletins, Notices to Mariners and VHF radio broadcast. All vessels will comply with international navigation regulations and codes.

    Accidental Events Water Resource: Deterioration in water quality

    Water quality is likely to deteriorate in the immediate vicinity of the spill (>10 tonnes) as hydrocarbons are dispersed through the water column. However, it will be naturally biodegraded by microbes within one to two months (NOAA 2006). The concentration and likelihood of natural biodegradation will obviously be dependent on the scale of the incident. However, generally the deterioration in water quality will be short term.

    Minor Accidental spills will be kept to a minimum through training, good housekeeping and through storage/handling procedures e.g., sumps, drains and bunding should catch accidental spills. Management controls will be in place to eliminate bunkering spills e.g. only bunkering during day light and in good weather. A location specific OPEP will be in place for the drilling rig and an Addendum to the North Cormorant OPEP will be applied for to cover

    Plankton: Potential toxic effect

    Marine ecology is typical for the NNS with no rare or protected benthic species identified in the baseline survey. Nine cetacean species may occur in the area, all of which are protected under the EC Habitats Directive. The region is also

    Minor

    Benthic Communities:

    Minor

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    Receptor & Type of Impact

    Baseline & Impact Assessment Significance of Residual Impact

    Mitigation

    Potential toxic effect

    important for seabirds. Biological receptors are vulnerable to the accidental release of hydrocarbons and/or chemicals. Accidental events are extremely unlikely to occur. A small spill of diesel of crude will rapidly disperse and dilute in the energetic marine environment but a large spill as a result of a loss of containment on the export tanker and FPSO has the potential to have wider reaching impacts. Modelling suggest that under typical meteorological conditions, there is the potential for a oil slick as a result of the loss of the FPSO and export tanker inventory to beach along the coastlines of the majority of countries bordering the North Sea (total probability of beaching is 1%). Numerous protected areas could potentially be impacted as shown in Figure 8-4.

    production operation. The OPEPs will detail all emergency procedures that will be in place to minimise any spill. EnQuest has access to Tier 1, 2 and 3 oil spill response capabilities through Oil Spill Response (OSR). EnQuest is a member of OSPRAG which will provide support in a well blow out event. Control measures will be in place to ensure rapid response to loss of flowline containment. These will be outlined in the Alma OPEP.

    Fish and Shellfish: Potential toxic effect

    Minor

    Seabirds: Smothering

    Moderate

    Marine Mammals and Protected Species: Smothering

    Minor

    Commercial Fishing: Damage to vessels and decrease in catch

    A major crude oil spill has the potential to cause damage to the fishing industry by long-term effects on fish stocks and damage to market confidence and could potentially exclude shipping from a number of key shipping lanes. However, the likelihood of such an event occurring is extremely rare.

    Minor

    Shipping and Navigation: Impact on vessel movement

    Minor

    Other Marine Users: Damage to vessels

    Minor

    CUMULATIVE AND INDIRECT IMPACTS

    The main concerns regarding the potential for cumulative and indirect impacts from the

    proposed development relate to impacts from activities at Alma interacting with:

    Other activities within the project

    Other oil and gas developments (past and future)

    Other marine users, such as windfarms, commercial fishing, marine aggregate

    extraction areas etc

    Climate change

    The EIA drew the following conclusions:

    The project will not have any significant cumulative or indirect effects with any other oil

    and gas developments

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    The project will not have any significant cumulative or indirect effects with any other

    seabed users

    The project will not exacerbate the changes predicted to occur as a consequence of

    climate change.

    The EIA identified the Alma development will not have any residual impacts on water depth,

    wind speed or wave conditions. Residual impacts on the environment will be short-term,

    predominantly affecting marine ecology. As climate change has the potential to affect the

    biological baseline it is possible that the project can act in combination with climate change to

    exacerbate this impact. However, the EIA concludes that, following construction, biological

    communities are anticipated to recover to pre-impact levels/structures or similar within five

    years (see Section 9.2.4.1). Given the relatively short timescale of the construction impacts,

    it is considered unlikely that any cumulative impacts from the project and climate change will

    have significant impacts on marine ecology.

    ENVIRONMENTAL MANAGEMENT SYSTEMS

    EnQuests corporate policies and environmental management system (EMS) provide a fit for

    purpose framework to implement the mitigation measures proposed in the ES.

    EnQuest is a socially responsible employer, committed to maintaining high standards in

    health, safety and environmental performance. EnQuest implements and operates an

    integrated Health, Safety and Environmental Management System (HS&EMS) and a Quality

    Management System (QMS) which has been accepted and endorsed by the Board, and

    embedded in the overall business culture. The HS&EMS is an integral part of the overall

    management system. It is laid down in policies, procedures, standards and work

    instructions. Its general purpose is to prevent EnQuests activities from putting people, the

    environment, property or the reputation of the company at risk.

    The HS&EMS is designed to match the requirements of ISO-14001:2004 and is based on the

    requirements of the Health and Safety OHSAS 18001 standard. The QMS is certified to BS

    EN ISO 9001. The purpose of the HS&EMS and QMS is to enhance health, safety,

    environmental and quality (HSEQ) performance and provide a framework for HSEQ

    management for all of the activities carried out throughout the company. The management

    systems are designed to cover HSEQ aspects which EnQuest can control and directly

    manage and those it does not control or directly manage, but can be expected to influence.

    EnQuest requires all contractors, their subcontractors and suppliers to have their own

    HS&EMS and QMS. Each contractor will be responsible for the HS&E management of their

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    scope of work and will operate according to their own HS&E Management System.

    However, contractors HS&EMS must be compatible with EnQuests HS&EMS and they are

    required to align their HS&E management with EnQuests goals and objectives. Their QMS

    must meet the applicable requirements of the BS EN ISO 9000 series of standards or an

    agreed equivalent.

    A project specific HS&E plan will be developed for the Alma development which will define

    how EnQuest will manage HS&E risks and activities. The Project HSEQ Engineer is

    responsible for maintaining and implementing the plan, and for providing HSEQ controls

    within the project to ensure that the requirements of the EnQuest HSEQ management

    systems are met.

    It is expected that the mitigation measures identified in the EIA process and reported in this

    ES will be adopted and bridged into EnQuests HSEQ Management System through the

    PLANC register.

    CONCLUSIONS

    EXISTING ENVIRONMENT

    Existing conditions at the Alma development were established through an environmental

    baseline and habitat assessment survey, which revealed that:

    The benthic habitat typically comprised of sparse sandy sediments with low benthic

    diversity. The majority of benthic taxa were polychaete worms. Stations sampled

    where historical drilling activity was prevalent were characterised by more disturbance

    and hydrocarbon contamination tolerant species and lower numbers of sensitive

    species.

    No habitats or species of conservation significance under the UKs Offshore Marine

    Conservation (Natural Habitats, &c.) (Amendment) Regulations 2010 were observed

    during seabed surveys

    The environmental baseline is similar to other regions of the CNS where oil and gas activity

    is prevalent. Meteorological conditions around the project support a dilution and dispersion

    regime which will rapidly reduce the impact significance of emissions to air, water and

    seabed (i.e. winds are sufficient to disperse atmospheric emissions, tidal currents refresh the

    water column within an estimated 1.5 hours, currents are generally sufficient to disperse drill

    cuttings or sediment piles on the seabed).

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    IMPACTS

    The potential effects of the project on the environment were identified and quantified by

    reviewing the existing baseline environmental conditions with the potential to be affected by

    the project and identifying and evaluating the effect of any activities associated with the

    project on these conditions.

    It should be noted that the majority of activities were assessed as having no or minor residual

    impact on the receiving environment, with a few identified as having a residual impact of

    moderate significance. This ES reached the following conclusions with regards to the

    projects impacts on the environment:

    Benthic Environment: The total seabed footprint of the development is 0.04km2. Due to fishing activities and previous oil and gas industry activities, the benthos in the

    project area is typical of a moderately disturbed habitat and consequently species that

    inhabit the area tend to recover quickly after disturbance. The proposed development

    is located within an area of previous drilling activity. The development area is

    sufficiently homogenous that any localised losses are unlikely to affect the integrity of

    the community as a whole. The placement of protective structures such as concrete

    mattresses will create new habitat for those species that require hard substrate for

    anchoring. This could lead to settlement of new species and the potential for a

    localised change in marine ecology. Current speeds are sufficient to erode cuttings

    piles and these are unlikely to persist for a long period of time.

    Protected Species: No protected species were identified in the marine benthic surveys. Marine mammals are likely to be the only protected species of relevance to

    the Alma development. Assuming the source to be near the seabed, for a receptor

    10m below the surface, the noise would have reduced to approximately 153 dB SEL

    vertically above the source. This is 7 dB below the lowest of the recognised

    thresholds for strong avoidance behaviour (160 dB SEL) of marine mammals. In

    conclusion, and provided mitigation measures are followed, the sound experienced will

    not exceed the injury thresholds for marine mammals. There is therefore a negligible

    risk of an offence under the Conservation (Natural Habitats &c) Regulations 1994 (as

    amended) and the Offshore Marine Conservation (Natural Habitats &c) Regulation

    2007 (as amended in 2010).

    Protected Areas: There are no protected sites within 40km of the Alma development. The nearest protected site is the Dogger Bank potential Special Area of Conservation

    (pSAC) which is approximately 78km south-east from the Alma southern drill centre.

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    Due to the distance of the protected site from the development area, it is unlikely that

    there will be any impacts during normal activities.

    Water/Sediment Quality: During normal activities, the production activities will have a negligible impact on the marine environment.

    Commercial Fishing: With consideration of other development activities in the CNS, the project will have a minor contribution to seabed smothering from cuttings piles,

    infrastructure installation and anchoring. However, this is anticipated to be limited to

    within the immediate vicinity of the wells. Safety exclusion zones are likely to have a

    moderate impact on commercial fishing in the area as this will result in vessels being

    displaced from their fishing grounds. Overall it is concluded cumulative impacts and

    the in-combination impacts with the fishing industry and other marine users are likely

    to be of negligible significance.

    Oil/Chemical Spill Pollution: In the unlikely event of a major oil spill, a worst case scenario loss of containment of 100,000m3 (87,000 tonnes) of crude oil from the

    export tanker has been modelled. This indicates that there is a 1% chance of

    beaching occurring on the majority of coastlines bordering the North Sea. Modelling

    also indicates that the spill could reach the UK coastline within 8 days and 10 hours

    and the Danish coastline within 5 days and 12 hours. The spill is likely to have

    completed dispersed within 417 days. Numerous protected areas along the coastlines

    of those North Sea countries that could be affected by a spill of this magnitude.

    EnQuest will have an OPEP in place.

    ENVIRONMENTAL MANAGEMENT

    The EnQuest corporate policies and environmental management system provide a fit for

    purpose framework to implement the mitigation measures proposed in this ES. The EMS

    also provides adequate control and bridging arrangements for EnQuest to ensure that the

    contractors implement these mitigation measures. During the construction and production

    operations, a set of permits and consents will be obtained from the regulatory bodies. Permit

    conditions under these will also be fed into the EMS to ensure compliance. EMS

    performance will be regularly benchmarked against recommendations from independent

    verifications, through internal and independent audits and reviews.

    With mitigation measures in place, the Alma Field development will have a minor

    impact on the environment.

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    CONTENTS 1 INTRODUCTION ............................................................................................. 1-11.1 THE DEVELOPER ............................................................................................... 1-11.2 PROJECT OVERVIEW .......................................................................................... 1-11.3 FORMAT OF THE ENVIRONMENTAL STATEMENT .................................................... 1-61.4 ES AVAILABILITY ............................................................................................... 1-7

    2 INSTITUTIONAL, POLICY AND REGULATORY FRAMEWORKS ............... 2-1

    2.1 RELEVANT POLICY GUIDELINES .......................................................................... 2-12.2 INTERNATIONAL CONVENTIONS, EC AND UK LAWS AND REGULATIONS .................. 2-12.3 SEA AND EIA GUIDELINES ................................................................................. 2-52.4 UK INSTITUTIONAL FRAMEWORK ......................................................................... 2-62.5 ENQUEST CORPORATE POLICY .......................................................................... 2-6

    3 PROJECT JUSTIFICATION AND ALTERNATIVES ...................................... 3-1

    3.1 PROJECT JUSTIFICATION .................................................................................... 3-13.2 ALTERNATIVES .................................................................................................. 3-3

    4 IMPACT ASSESSMENT METHODOLOGY ................................................... 4-1

    4.1 ENVIRONMENTAL AND HUMAN IMPACT ASSESSMENT PROCESS ............................. 4-14.2 CUMULATIVE AND INDIRECT IMPACTS ................................................................. 4-124.3 EIA STAKEHOLDER CONSULTATION .................................................................. 4-13

    5 PROJECT DESCRIPTION .............................................................................. 5-1

    5.1 SCHEDULE ........................................................................................................ 5-25.2 CONSTRUCTION ACTIVITIES ................................................................................ 5-25.3 PRODUCTION OPERATIONS ............................................................................... 5-165.4 DECOMMISSIONING .......................................................................................... 5-195.5 PROJECT ACTIVITY SUMMARY ........................................................................... 5-20

    6 PROJECT FOOTPRINT ................................................................................. 6-1

    6.1 CONSTRUCTION ................................................................................................. 6-16.2 PRODUCTION .................................................................................................. 6-11

    7 ACCIDENTAL EVENTS ................................................................................. 7-1

    7.1 TYPES OF ACCIDENTAL EVENT ............................................................................ 7-1

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    7.2 PROBABILITY OF ACCIDENTAL EVENTS OCCURRING .............................................. 7-47.3 OIL SPILL MODELLING ........................................................................................ 7-6

    8 IMPACTS ON PHYSICAL ENVIRONMENT ................................................... 8-1

    8.1 AIR ................................................................................................................... 8-18.2 CLIMATE CHANGE .............................................................................................. 8-68.3 WATER RESOURCES .......................................................................................... 8-98.4 SEABED CONDITIONS ....................................................................................... 8-16

    9 IMPACTS ON BIOLOGICAL ENVIRONMENT ............................................... 9-1

    9.1 PLANKTON ........................................................................................................ 9-19.2 BENTHIC COMMUNITIES ...................................................................................... 9-39.3 FISH AND SHELLFISH .......................................................................................... 9-69.4 SEABIRDS ....................................................................................................... 9-119.5 MARINE MAMMALS ........................................................................................... 9-179.6 PROTECTED SITES AND SPECIES ...................................................................... 9-25

    10 IMPACTS ON HUMAN ENVIRONMENT ...................................................... 10-1

    10.1 COMMERCIAL FISHERIES .................................................................................. 10-110.2 SHIPPING AND NAVIGATION .............................................................................. 10-710.3 OTHER MARINE USERS .................................................................................. 10-1110.4 ARCHAEOLOGY .............................................................................................. 10-15

    11 CUMULATIVE AND INDIRECT IMPACTS ................................................... 11-1

    11.1 OTHER OIL AND GAS DEVELOPMENTS ............................................................... 11-111.2 OTHER SEABED USERS .................................................................................... 11-511.3 CLIMATE CHANGE ............................................................................................ 11-6

    12 ENVIRONMENTAL MANAGEMENT ............................................................ 12-1

    12.1 MANAGEMENT SYSTEM .................................................................................... 12-112.2 PROJECT SPECIFIC ENVIRONMENTAL MANAGEMENT ........................................... 12-112.3 MANAGEMENT OF MITIGATION MEASURES ......................................................... 12-312.4 OIL SPILL RESPONSE ....................................................................................... 12-5

    13 CONCLUSIONS ............................................................................................ 13-1

    13.1 THE PROJECT ................................................................................................. 13-113.2 EXISTING ENVIRONMENT .................................................................................. 13-1

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    13.3 POTENTIAL IMPACTS ........................................................................................ 13-213.4 DECOMMISSIONING .......................................................................................... 13-313.5 ENVIRONMENTAL MANAGEMENT ....................................................................... 13-3

    14 REFERENCES .............................................................................................. 14-1

    APPENDIX A ENVIRONMENTAL IMPACT ASSESSMENT ................................ A-1

    A.1 INTERACTION MATRIX......................................................................................... A-2A.2 CONSTRUCTION ................................................................................................. A-3A.3 PRODUCTION .................................................................................................. A-20A.4 ACCIDENTAL EVENTS ....................................................................................... A-32

    APPENDIX B OIL SPILL MODELLING ................................................................ B-1

    B.1 INTRODUCTION .................................................................................................. B-2B.2 ALMA FIELD DEVELOPMENT ................................................................................ B-2B.3 WORST CASE OIL SPILL MODELLING ................................................................... B-3B.4 SPILL SCENARIOS AND MODELLING RESULTS ....................................................... B-4B.5 ENVIRONMENTAL IMPACT ASSESSMENT ............................................................. B-13B.6 REFERENCES .................................................................................................. B-14

    APPENDIX C SUMMARY OF CHEMICALS ......................................................... C-1

    C.1 DRILLING CHEMICALS ......................................................................................... C-2C.2 CEMENTING CHEMICALS ..................................................................................... C-6C.3 COMPLETION AND OTHER CHEMICALS ................................................................. C-6C.4 PIPELINE CHEMICALS ......................................................................................... C-8

    APPENDIX D JNCC RISK ASSESSMENT FLOW CHARTS ............................... D-1

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    TABLES TABLE 1-1: PROJECT CO-ORDINATES 1-3TABLE 1-2: STRUCTURE OF THIS ES 1-6TABLE 3-1: CUMULATIVE (BY YEAR) PRODUCTION PROFILES 3-2TABLE 3-2: PROS AND CONS OR DIFFERENT DEVELOPMENT SCENARIOS 3-6TABLE 4-1: PROJECT ACTIVITIES 4-6TABLE 4-2: EXTRACT FROM THE ALMA ISSUES SCOPING MATRIX 4-7TABLE 4-3: EXAMPLE DEVELOPMENT ACTIVITY, ASPECT AND IMPACT IDENTIFICATION 4-7TABLE 4-4: ASSESSMENT PROCESS FOR IDENTIFICATION OF POTENTIAL IMPACTS 4-8TABLE 4-5: SEVERITY DEFINITIONS 4-9TABLE 4-6: ENVIRONMENTAL AND HUMAN IMPACT SIGNIFICANCE ASSESSMENT MATRIX 4-10TABLE 5-1: PROJECT SCHEDULE 5-2TABLE 5-2: CURRENT UNMODIFIED UISGE GORM VESSEL AND PERFORMANCE DATA 5-3TABLE 5-3: SACRIFICIAL ANODE COMPOSITION 5-15TABLE 5-4: SUMMARY OF PROJECT ACTIVITIES AND ASPECTS 5-20TABLE 6-1: CONSTRUCTION EXHAUST GAS EMISSIONS 6-1TABLE 6-2: SUMMARY OF CONSTRUCTION NOISE SOURCES AND ACTIVITIES 6-2TABLE 6-3: SUMMARY OF CHEMICAL DISCHARGES (TONNES) ONE WELL 6-3TABLE 6-4: SUMMARY OF CHEMICAL DISCHARGES (TONNES) EIGHT WELLS 6-3TABLE 6-5: SUMMARY OF FLOWLINE DISCHARGES 6-4TABLE 6-6: SUMMARY OF DISCHARGES FROM WELL TIE-IN 6-4TABLE 6-7: TOTAL WASTE WATER DISCHARGE (M3) DURING CONSTRUCTION 6-5TABLE 6-8: SUMMARY OF UNDERWATER NOISE PRODUCED DURING CONSTRUCTION ACTIVITIES

    6-5TABLE 6-9: WEIGHT AND DISCHARGE FATE OF DRILL CUTTINGS (TONNES) 6-7TABLE 6-10: SUMMARY OF FLOWLINE INSTALLATION FOOTPRINT ON THE SEABED 6-8TABLE 6-11: SUMMARY OF SEABED FOOTPRINT - FIELD DEVELOPMENT 6-10TABLE 6-12: EMISSIONS FROM POWER GENERATION 6-11TABLE 6-13: CO2 EMISSIONS FOR THE STEAM BOILER FROM POWER GENERATION 6-12TABLE 6-14: FLARING GAS EMISSIONS DURING PRODUCTION 6-12TABLE 6-15: PRODUCTION - VESSEL EXHAUST GAS EMISSIONS 6-13TABLE 6-16: SUMMARY OF PRODUCTION NOISE SOURCES AND ACTIVITIES 6-13TABLE 6-17: TOTAL WASTE WATER DISCHARGE PER ANNUM FOR FIELD LIFE 6-14TABLE 6-18: ALMA CHEMICAL INJECTION REQUIREMENTS 6-15

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    TABLE 7-1: INDUSTRY RISER AND PIPELINES FAILURE FREQUENCIES 7-6TABLE 8-1: ANNUAL WIND PERCENTAGE FREQUENCY DISTRIBUTION AT STANDARD HEIGHT (10M)

    8-3TABLE 8-2: AIR QUALITY POTENTIAL IMPACT IDENTIFICATION 8-5TABLE 8-3: RECOMMENDED CONTINGENCY ALLOWANCES FOR NET SEA LEVEL RISE 8-7TABLE 8-4: CLIMATE CHANGE POTENTIAL IMPACT IDENTIFICATION 8-7TABLE 8-5: COMPARISON OF UK AND ALMA CO2 EMISSIONS - ANNUAL 8-9TABLE 8-6: PHYSICAL CHARACTERISTICS OF THE SEA WATER IN THE ALMA FIELD 8-10TABLE 8-7: SUMMARY OF NORTH SEA SURFACE WATERS CONTAMINANT LEVELS 8-10TABLE 8-8: SUMMARY OF TIDAL CURRENT SPEEDS AT THE ALMA FIELD 8-11TABLE 8-9: WAVE CHARACTERISTICS AT ALMA 8-13TABLE 8-10: MONTHLY WAVE HEIGHT AT ALMA 8-13TABLE 8-11: WATER RESOURCES POTENTIAL IMPACT IDENTIFICATION 8-14TABLE 8-12: WATER DEPTH 8-17TABLE 8-13: HEAVY METALS IN SEDIMENT (G.G-1) 8-23TABLE 8-14: SEABED CONDITIONS POTENTIAL IMPACT IDENTIFICATION 8-25TABLE 9-1: PLANKTON POTENTIAL IMPACT IDENTIFICATION 9-2TABLE 9-2: CONTRIBUTIONS OF THE GROSS TAXONOMIC GROUPS 9-4TABLE 9-3: SPECIES RANKING 9-4TABLE 9-4: BENTHIC COMMUNITIES POTENTIAL IMPACT IDENTIFICATION 9-2TABLE 9-5: COMMONLY CAUGHT SPECIES 9-7TABLE 9-6: KEY SENSITIVE PERIODS FOR FISH SPAWNING AND NURSERY 9-7TABLE 9-7: FISH AND SHELLFISH POTENTIAL IMPACT IDENTIFICATION 9-8TABLE 9-8: SEABIRD VULNERABILITY 9-13TABLE 9-9: SEABIRDS POTENTIAL IMPACT IDENTIFICATION 9-13TABLE 9-10: CETACEAN OBSERVATIONS IN THE AREA OF INTEREST 9-18TABLE 9-11: CETACEAN POPULATION ESTIMATES AND CONSERVATION STATUS 9-19TABLE 9-12: MARINE MAMMALS POTENTIAL IMPACT IDENTIFICATION 9-20TABLE 9-13: SOUND EXPOSURE LEVELS AT DISTANCE 9-23TABLE 9-14: PROTECTED SITES AND SPECIES POTENTIAL IMPACT IDENTIFICATION 9-27TABLE 10-1: VALUE () OF LANDING FOR THE ALMA DEVELOPMENT AREA AND SURROUNDING

    REGION (2004 2009) 10-2TABLE 10-2: COMMERCIAL FISHING POTENTIAL IMPACT IDENTIFICATION 10-5TABLE 10-3: SHIP ROUTES 10-8TABLE 10-4: SHIP/INSTALLATION COLLISION FREQUENCIES ESTIMATED FOR ALMA FPSO 10-9

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    TABLE 10-5: SHIPPING AND NAVIGATION POTENTIAL IMPACT IDENTIFICATION 10-10TABLE 10-6: WELLS WITHIN 40KM OF THE DEVELOPMENT 10-12TABLE 10-7: OTHER MARINE USERS POTENTIAL IMPACT IDENTIFICATION 10-13TABLE 10-8: ARCHAEOLOGY POTENTIAL IMPACT IDENTIFICATION 10-17TABLE 12-1: ENQUEST ENVIRONMENTAL TARGETS 12-2TABLE 12-2: SUMMARY OF MITIGATION MEASURES 12-4TABLE B-1: PROJECT CO-ORDINATES B-2TABLE B-2: SPILL SCENARIOS MODELLED B-5TABLE B-3: MODELLING RESULTS B-5

    FIGURES FIGURE 1-1: PROJECT LOCATION 1-2FIGURE 1-2: FPSO RISER HOLD-BACK TETHER EXAMPLE 1-4FIGURE 2-1: ENQUEST ENVIRONMENTAL POLICY 2-7FIGURE 3-1: CUMULATIVE (BY YEAR) PRODUCTION PROFILES 3-3FIGURE 4-1: OVERVIEW OF EIA METHODOLOGY 4-1FIGURE 4-2: ALMA DEVELOPMENT SURVEY EXTENTS 4-4FIGURE 5-1: ALMA FIELD DEVELOPMENT 5-1FIGURE 5-2: UISGE GORM FPSO 5-3FIGURE 5-3: TURRET MOORING SYSTEM 5-4FIGURE 5-4: FIELD LAYOUT SHOWING FPSO AND DRILLING RIG ANCHOR PATTERNS 5-5FIGURE 5-5: TYPICAL SEMI-SUBMERSIBLE DRILLING RIG 5-6FIGURE 5-6: TYPICAL TOP HAT RISER TETHER UTILISING PILES 5-10FIGURE 5-7: TYPICAL JET TRENCHING ROV 5-12FIGURE 5-8: OFFLOADING FROM UISGE GORM FPSO 5-16FIGURE 5-9: CUMULATIVE TOTAL CO2 (TONNES) FROM UISGE GORM FPSO (JAN-AUG 2008)

    5-17FIGURE 6-1: AREA OF SEABED COVERED BY 1 WELL CUTTINGS PILE 6-8FIGURE 7-1: STOCHASTIC MODEL RUN 100,000M3 INSTANTANEOUS SPILL OF 38 API CRUDE

    OIL (417 DAYS) 7-8FIGURE 7-2: POSSIBLE BEACHING LOCATIONS 7-8FIGURE 7-3: STOCHASTIC MODEL RUN 5,830M3 INSTANTANEOUS SPILL OF DIESEL 7-9FIGURE 7-4: SPILL TRAJECTORY UNDER 30 KNOT WIND CONDITIONS TOWARDS THE UK

    COASTLINE 7-10

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    FIGURE 7-5: SPILL TRAJECTORY UNDER 30 KNOT WIND CONDITIONS TOWARDS THE NEAREST INTERNATIONAL BOUNDARY 7-10

    FIGURE 7-6: DIESEL SPILL TRAJECTORY UNDER 30 KNOT WIND CONDITIONS TOWARDS THE UK COASTLINE 7-11

    FIGURE 7-7: DIESEL SPILL TRAJECTORY UNDER 30 KNOT WIND CONDITIONS TOWARDS THE NEAREST INTERNATIONAL BOUNDARY 7-11

    FIGURE 8-1: ANNUAL WIND ROSE FOR THE ALMA AREA 8-4FIGURE 8-2: GENERAL CURRENT CIRCULATION IN THE NORTH SEA 8-12FIGURE 8-3: BATHYMETRY AT NORTHERN DRILL CENTRE 8-18FIGURE 8-4: BATHYMETRY AT SOUTHERN DRILL CENTRE 8-19FIGURE 8-5: BATHYMETRY AT FPSO LOCATION 8-20FIGURE 8-6: EXAMPLE OF SEABED SEDIMENTS FROM SURVEY 8-21FIGURE 8-7: SAMPLING STATIONS LOCATION OVERVIEW 8-24FIGURE 9-1: SEABED PHOTOGRAPHS OF THE ALMA DEVELOPMENT AREA 9-5FIGURE 9-2: ENVIRONMENTAL OVERVIEW 9-12FIGURE 9-3: OIL SPILL BEACHING LOCATIONS IN RELATION TO PROTECTED SITES 9-29FIGURE 10-1: SEASONAL VARIATION IN FISHING ACTIVITY (2004-2009) 10-3FIGURE 10-2: AVERAGE ANNUAL CATCH AND VALUE FOR THE ALMA DEVELOPMENT AREA 10-4FIGURE 10-3: SHIPPING ROUTE POSITIONS WITHIN 10NM OF ALMA LOCATIONS 10-8FIGURE 10-4: OTHER MARINE USERS 10-14FIGURE 11-1: GALIA PRODUCTION WELL IN RELATION TO THE WIDER ALMA DEVELOPMENT 11-2FIGURE B-1- SCENARIO 1-WORST CASE CRUDE OIL SPILL OF 100,000M3 B-7FIGURE B-2-SCENARIO 2- WORSE CASE CRUDE OIL SPILL TRAJECTORY WITH 30 KNOT WIND

    TOWARDS THE UK B-8FIGURE B-3-SCENARIO 3- WORSE CASE CRUDE OIL SPILL TRAJECTORY WITH 30 KNOT WIND

    TOWARDS THE CLOSEST INTERNATIONAL BOUNDARY (AND DENMARK) B-9FIGURE B-4- SCENARIO 4- INSTANTANEOUS DIESEL SPILL OF 5,830M3 B-10FIGURE B-5- SCENARIO 5- WORST CASE DIESEL SPILL TRAJECTORY WITH 30 KNOT WIND

    TOWARDS THE UK B-11FIGURE B-6- SCENARIO 6- WORST CASE DIESEL SPILL TRAJECTORY WITH 30 KNOT WIND

    TOWARDS THE CLOSEST INTERNATIONAL BOUNDARY B-12FIGURE D-1: RISK ASSESSMENT FLOW CHART FOR DELIBERATE INJURY D-2FIGURE D-2: RISK ASSESSMENT FLOW CHART FOR NON-TRIVIAL DISTURBANCE D-2FIGURE D-3: M-WEIGHTING FUNCTIONS FOR LOW-, MID-, AND HIGH-FREQUENCY CETACEANS D-3

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    ACRONYMNS AND UNITS < Less than

    > More than A

    ACOPS Advisory Committee on Protection of the Sea ALSF Aggregates Levy Sustainability Fund API American Petroleum Institute

    B B.P Before Present BAT Best Available Technique bbls Barrels BGS British Geological Society BOP Blow-Out Preventer bopd Barrels of Oil Per Day BS&W Bottom Sediment and Water BSI British Standards Institute bwpd Barrels of Water Per Day

    C CBD Convention on Biological Diversity CEFAS Centre for Environment, Fisheries and Aquaculture Science CH4 Methane CMT EnQuest Crisis Management Team CNS Central North Sea CO Carbon Monoxide CO2 Carbon Dioxide CPR Continuous Plankton Recorder

    D dB Decibel DECC Department of Energy and Climate Change Defra Department for Environment, Food and Rural Affairs DMRB Design Manual for Roads and Bridges DP Dynamic Positioning DSV Diving Support Vessel DTI Department of Trade and Industry

    E EC European Commission EEMS Environmental Emissions Monitoring Scheme EIA Environmental Impact Assessment EMS Environmental Management System EPS European Protected Species ERC Emergency Response Centre ES Environmental Statement ESP Electrical Submersible Pump EU ETS European Union Emissions Trading Scheme

    F FAO Food and Agriculture Organisation FDP Field Development Plan FPSO Floating, Production, Storage and Offloading FRS Fisheries Research Service

    G GESAMP The Joint Group of Experts on the Scientific Aspects of Marine Environmental Protection GGL Gardline Geosurvey Limited GIS Geographical Information Service

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    H HQ Hazard Quotient HR Conservation (Natural Habitats &c.) Regulations 1994 (as amended) HSE Health and Safety Executive HSEQ Health, Safety, Environmental and Quality Hz Hertz

    I IBA Important Bird Areas ICES International Council for the Exploration of the Seas IMT Incident Management Team IPPC Integrated Pollution Prevention and Control Directive ISO International Organization of Standardization

    J JNCC Joint Nature Conservation Committee K KISCA Kingfisher Cables

    km Kilometre km2 Kilometres squared kPa Kilo Pascal kw Kilo Watt

    L LAQM Local Air Quality Management (LAQM) Support. Defra, UK Local Air Quality Management LAT Lowest Astronomical Tide

    M gl-1 Microgram per Litre gm-3 Microgram per Cubic Metre Pa Micro Pascal m Metre m2 Metre Squared m3 Cubic Metre MBES Multi-Beam Echo Sounder MCA Maritime and Coastguard Agency MCAA Marine and Coastal Access Act MCZ Marine Conservation Zone MEG Monoethylene Glycol mgl-1 Milligram per Litre mmbbls Million Barrels MMO Marine Mammal Observer MMO Marine Management Organisation MMscf/d Million Standard Cubic Feet per Day MODU Mobile Offshore Drilling Unit ms-1 Metres per Second MW Mega Watt MW(th) Mega Watt (Thermal) MWh Mega Watt Hour

    N N2O Nitrous Oxide nm Nautical Miles NNE North-North East NNS Northern North Sea NO2 Nitrogen Dioxide NOEC No Observed Effect Concentration NOx Nitric Oxides

    O OBM Oil Based Mud

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    OCNS Offshore Chemical Notification Scheme OCR Offshore Chemical Regulators OESEA Offshore Energy Strategic Environmental Assessment OGED Oil and Gas Exploration and Development OGUK Oil and Gas UK OIW Oil in Water OMR Offshore Marine Conservation (Natural Habitats &c) Regulations 2007 (as amended in 2010) OPEP Oil Pollution Emergency Plan OPPC Oil Pollution Prevention and Control OSPAR Convention for the Protection of the Marine Environment of the North East Atlantic (Oslo Paris Convention) OSRL Oil Spill Response Limited

    P PAH Polycyclic Aromatic Hydrocarbons PAIH Potential Annex I Habitat PEXA Practice and Exercise Areas PIG Pipeline Inspection Gauge PLANC Permits Licenses Approvals Notifications and Consents PLONOR Posing Little or No Risk PLV Pipeline Laying Vessels PM 10 Particles Measuring 10m or less PM 2.5 Particles Measuring 2.5m or less PON Petroleum Operations Notice ppb Parts per billion ppm Parts per million PSA Particle size analysis psia Pounds per Square Inch Atmospheric PW Produced Water PWA Pipelines Works Authorisation PWRI Produced Water Reinjection

    Q QMS Quality Management System R REACH Registration, Evaluation, Authorisation and restriction of Chemicals

    ROV Remotely Operated Vehicle RYA Royal Yachting Association

    S SAC Special Area of Conservation SCANS Small Cetaceans in the European Atlantic and North Sea scfd-1 Standard Cubic Foot per Day SCI Sites of Community Importance SEA Strategic Environmental Assessment SFF Scottish Fishermen's Federation SMRU Sea Mammal Research Unit SNS Southern North Sea SO2 Sulphur Dioxide SoS Secretary of State SOx Oxides of Sulphur SPA Special Protection Area SPL Sound Pressure Levels SSE Scottish and Southern Energy SSS Sidescan Sonar

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    SSW South-South West SUB Substitution

    T THC Total Hydrocarbons U UK United Kingdom

    UK BAP UK Biodiversity Action Plan UKCIP UK Climate Impact Programme UKCP United Kingdom Climate Predictions UKCS United Kingdom Continental Shelf UKMMAS UK Marine Monitoring and Assessment Strategy UKOOA United Kingdom Offshore Operators Association (now Oil and Gas UK) UNFCCC United Nations Framework Convention on Climate Change

    V VHF Very High Frequency VOC Volatile Organic Compounds

    W WBM Water Based Mud WLCDF Well Life-Cycle Decision Framework

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    GLOSSARY A Air Gun Source of seismic energy used in acquisition of marine seismic data. This gun releases highly

    compressed air into water.

    Analogue Survey e.g., bathymetry, sonar imagery and shallow profiling. Technique of representing a sensor's input as amplitude modulated electrical signal (e.g., analogue profiles are output on sweep recorders as opposed to digital).

    Anode Positive electrode.

    Appraisal Well Phase of petroleum operations that immediately follows successful exploratory drilling. Appraisal wells might be drilled to determine the size of the oil or gas field and how to develop it most efficiently.

    Aspect (environmental) Element of an organisations activities, products or services that can interact with the environment.

    B Backfill The replacement of excavated sediment into a trench. Bathymetry The measurement of the depth of the ocean floor from the water surface; the oceanic equivalent of

    topography.

    Beaufort Force Empirical measure (scale of 0 to 12) for describing wind velocity based mainly on observed sea conditions established by Admiral Francis Beaufort (1774 to 1857).

    Benthic Pertaining to the environment and conditions of organisms living at the bottom of the sea.

    Biogenic Chemicals or material produced by living organisms or biological processes.

    Blow-out Uncontrolled flow of reservoir fluids into the wellbore, and sometimes catastrophically to the surface. A blow-out may consist of salt water, oil, gas or a mixture of these.

    Blow-out Preventer (BOP)

    A large valve at the top of a well that may be closed if the drilling crew loses control of the pressure within the well.

    C Catch Per Unit Effort (CPUE)

    Measurement of the mass of fish caught for a given amount of energy and resources expended by a fishing fleet.

    Conductor Casing string that is usually put in to the wellbore at the surface to stop the sides of the well falling in.

    Cone Penetrometer Test (CPT)

    Method of providing data for use in characterising subsurface marine sediments consisting of a steel cone that is hydraulically pushed into the ground. Sensors on the tip of the cone collect data to classify sediment type by measuring cone-tip pressure and friction.

    Cuttings Small pieces of rock that break away due to the action of the bit teeth. Cuttings are screened out of the liquid mud system at the shale shakers and are monitored for composition, size, shape, colour, texture, hydrocarbon content and other properties.

    D Demersal Organisms dwelling at or near the bottom of the sea. Development The phase of petroleum operations that occurs after exploration has proven successful, and before

    full-scale production. The newly discovered oil or gas field is assessed during an appraisal phase, a plan to fully and efficiently exploit it is created, and additional wells are usually drilled.

    Downhole In a well bore. E Echolocation Used by animals to orientate, navigate, and find food it is the detection of the position, distance and

    size of an object by means of reflected sound.

    Echosounding The action or process of sounding or ascertaining the depth of water or of an object below a ship by measuring the time taken for a transmitted sound-signal to return as an echo.

    Effort Measure of input extended by people to catch fish (expressed in days fished). Environmental Impact

    Assessment (EIA) The critical appraisal of the likely effects of a proposed project, activity, or policy on the environment, both positive and negative.

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    Environmental Statement (ES)

    A means of submitting to the regulatory authority, statutory consultees, non-government organisations and the wider public, the findings of an EIA.

    Epifauna Organisms living on the seabed surface. Epilithic Organisms growing attached to an inorganic substratum, such as rocks, stones, etc. F Flaring The burning of unwanted gas through a pipe. Flaring is a means of disposal used when there is no

    way to transport the gas to market and the operator cannot use the gas for another purpose.

    G Geohazard Any geological or hydrological process that poses a threat to people and/or their property. Geophysical The study of the earth by quantitative physical methods, especially by seismic reflection and

    refraction, gravity, magnetic, electrical, electromagnetic, and radioactivity methods.

    Geotechnical The study of soil and rock below the ground to determine its properties. Grey Water Non-industrial wastewater generated from domestic processes such as washing dishes, laundry

    and bathing.

    H Hydrotest The process of pumping water through a pipeline at a higher pressure level than is normally used when transporting petroleum to confirm the continued safe operation of the pipeline, ensuring that it's free of any defects.

    I ICES rectangles Statistical divisions of the sea. Impact (environmental) Any change to the environment, whether adverse or beneficial, wholly or partially resulting from an

    organisation's activities, products or services.

    Infauna Organisms that live within the sediment. K Kingfisher Bulletins Fortnightly bulletin providing free safety information to all sea users. Kilometre Point (KP) A general term for the distance along a route from a fixed reference point. L Lowest Astronomical

    Tide (LAT) The lowest level that can be expected to occur under average meteorological conditions and under any combination of astronomical conditions.

    M Macrofauna Benthic animals larger than 1 mm in size and include the large polychaete worms, corals, shellfish, and starfish.

    Magnetometer An instrument for measuring the strength of a magnetic field. MARPOL Convention International Convention for the Prevention of Pollution from Ships (1973/1978). Median Line Offshore international boundary. Mobile Offshore Drilling

    Unit (MoDU) A generic term for several classes of self-contained floatable or floating drilling machines such as jack-ups, and semi-submersibles.

    Multivariate Describes a collection of procedures which involve observation and analysis of two or more statistical variables at a time.

    N North Atlantic Oscillation

    A climatic phenomenon in the North Atlantic Ocean of fluctuations in the difference of sea-level pressure between the Icelandic Low and the Azores high.

    Notices to Mariners Information issued from a number of different sources, such as the UK Hydrographic Office, Trinity House or Local Harbour Authorities and may contain a variety of information such as chart updates, changes in buoyage, prior warning of activities such as dredging, exclusion zones, etc.

    O Oil Producer A well producing oil. OSPAR Instrument guiding international cooperation on the protection of the marine environment of the

    North-East Atlantic.

    P Pelagic Relating to or occurring or living in or frequenting the open ocean. Petrogenic A contaminant produced from unburned petroleum products.

    Phytoplankton Microscopic floating plants that exist within the water column.

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    Phytoplankton Bloom

    High concentration of phytoplankton in an area, caused by increased reproduction.

    Pinger Seismic source.

    Platform An offshore structure that is permanently fixed to the seabed used to house workers and machinery needed to drill and then produce oil and natural gas in the ocean.

    Plugged and Abandoned

    To prepare a well to be closed permanently with cement plugs and salvage all recoverable equipment, usually after either logs determine there is insufficient hydrocarbon potential to complete the well, or after production operations have drained the reservoir.

    Potential Annex I Habitat (PAIH)

    Habitat (as defined in Annex I of the EC Habitats Directive) identified in offshore areas to be put forward to the government for protection as part of the Natura 2000 in UK offshore waters programme.

    Produced Water (PW) Formation water (naturally occurring layer of water in oil and gas reservoirs) and injected water that is produced along with hydrocarbons. At the surface, the water is separated from the hydrocarbons, treated to remove as much of the hydrocarbons as possible and discharged into the sea or injected back into wells.

    R Ramsar Site Wetland of international importance designated under the Ramsar Convention (1971). Receptor

    (environmental) Element of the environment that an environmental aspect can interact with or impact.

    Re-injection (produced water)

    Method of enhanced oil recovery to compensate for the natural decline of an oil field production by increasing the pressure in the reservoir. Produced water is injected to maintain reservoir pressure and hydraulically drive oil toward a producing well.

    Reservoir Subsurface body of rock having sufficient porosity and permeability to store and transmit fluids

    Rig A drilling unit that is not permanently fixed to the seabed, e.g., a drillship, a semi-submersible or a jack-up unit. Also means the derrick and its associated machinery.

    Riser The pipe which connects a rig or platform to a subsea wellhead or subsea pipeline during drilling or production operations to take mud returns to the surface; or the pipe which connects a pipeline to a platform.

    S Seismic Pertaining to waves of elastic energy, such as that transmitted by P-waves and S-waves, in the frequency range of approximately 1 to 100 Hz, used to interpret the composition, fluid content, extent and geometry of rocks in the subsurface.

    Semi-Diurnal Occurring once every 12 hours. Semi-Submersible Rig Floating vessel that can be used for drilling supported primarily on large pontoon-like structures

    submerged below the sea surface usually anchored with six to twelve anchors.

    Shellfish An aquatic animal, such as a mollusc or crustacean, which has a shell or shell-like exoskeleton. Side-Scan Sonar (SSS) Sonar device used for mapping the seabed. Spawning Reproductive activity of fish; the act of releasing eggs into the water by female fish for fertilisation by

    male fish.

    Species A group of related organisms having common characteristics and capable of interbreeding. Stochastic Model A model involving or containing a random variable or variables; involving chance or probability. Subsea Situated or occurring underwater. Subsea Control System Subsea system that provides electro/hydraulic control of subsea and downhole hydraulically

    operated valves. It also provides a data link to the platform control system conveying subsea/downhole operating parameters and performance.

    Subsea Control Umbilical

    Connects remotely positioned subsea satellite production and/or injection trees to subsea template controls or to surface controls on a platform. An umbilical can include up to eighteen separate control hoses within a casing e.g., hydraulic hoses, chemical injection hoses and electrical cables.

    Suspended (well) A well that has been capped-off temporarily.

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 21/07/2011

    T Taxa Categories in the biological classification system for all living organisms (i.e., kingdom, phylum, class, order, family, genus, species).

    Thermocline The vertical zone in the water column where temperature changes rapidly with depth.

    Tie-in An operation in pipeline construction in which two sections of line are connected; a loop tied into the main line.

    Topside The superstructure of a platform. U Umbilical A conduit through which hydraulic fluids, chemicals, power and data are supplied (see subsea

    control umbilical).

    Univariate Describes a collection of procedures which involve observation and analysis of one statistical variable.

    V Vibrocore Acquisition of seabed sediment cores using a vibrating steel tube which penetrates the seabed to a particular depth.

    W Water Injector A well in which filtered and treated seawater is injected into a lower water-bearing section of the reservoir, the primary objective typically being to maintain reservoir pressure.

    Well Head The surface termination of a wellbore that incorporates facilities for installing casing hangers during the well construction phase. The wellhead also incorporates a means of hanging the production tubing and installing the Christmas tree and surface flow-control facilities in preparation for the production phase of the well.

    Well-Test A test whereby the nature and quantity of the formation fluids in a possible oil- or gas-bearing stratum are determined by allowing them to flow to the surface through the drill string under carefully controlled conditions.

    X Xmas Tree An array of pipes and valves fitted to a production wellhead to control the flow of oil or gas and prevent a possible blow-out.

    Z Zooplankton Small aquatic animals that float or weakly swim within the water column. Generally longer than 153 m, up to about 5,000 m (5 mm).

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 1-1 21/07/2011

    1 INTRODUCTION

    EnQuest Heather Limited wishes to redevelop the Ardmore field in the UK Central North Sea (CNS). The field, to be renamed Alma, will be developed through two drill centres tied-back via new oil production and water injection flowlines to a floating production, offloading and storage facility (FPSO).

    This Environmental Statement (ES) has been prepared on behalf of EnQuest to meet the requirements of United Kingdom (UK) legislation and in support of their field development plan. It covers:

    Drilling of six production wells and two water-injection wells

    Installation of two 10-inch production flowlines, one 10-inch water-injection flowline, two control umbilicals and one power cable

    Installation of the Uisge Gorm Floating, Production, Storage and Offloading (FPSO) facility

    Export of crude oil via shuttle tanker

    Operation and production of the field for an expected 10 years

    1.1 THE DEVELOPER

    EnQuest Heather Limited is an independent oil and gas production and development company with a geographic focus on the UK continental shelf (UKCS). The Groups asset portfolio comprises primarily producing assets and development opportunities, together with exploration and appraisal opportunities, all of which are located in the UKCS. It has working interests in the Don, Thistle, Deveron, Heather, Ivy and Broom oil fields.

    EnQuest believes that the UKCS represents a significant hydrocarbon basin in a low-risk region. The UKCS continues to benefit from an extensive installed infrastructure base and skilled labour to develop, operate and manage assets. EnQuests management has considerable experience of working in the UKCS region and is familiar with the regulatory authorities and competitive landscape.

    EnQuest Heather Limited owns a 100% stake of the equity of the Alma Field.

    1.2 PROJECT OVERVIEW

    As a redevelopment of the Ardmore field, the Alma field will be a small oil development with a field life of ten years. The field is located in UKCS Blocks 30/24 and 30/25, 274km east of the nearest landfall on the Northumberland coastline in the CNS. It is approximately 18.5km from the Norway/UK international boundary (median line). The project location is shown in Figure 1-1 and the co-ordinates are given in Table 1-1.

  • AAA

    A

    AA

    AAAA

    AAA

    A

    AAAAAAA

    AA

    AAAAAAAAAAAAAAAAA

    A

    A

    A

    AAA

    A

    A

    A A

    A

    A

    AAA

    A

    A

    A

    A

    A

    AAA

    A

    AA

    A

    AAA

    A

    A

    A

    AA

    A

    A

    A

    A

    A

    A

    A

    AA

    A

    A

    AA

    A AA

    A

    A

    AAAAAAA

    AA

    A

    AA

    AA

    A

    A

    A

    AAA

    AAA

    A

    AAAAAAAAAAA

    AAA

    A

    A

    A

    AAA

    A

    AA

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    AA

    A

    A

    A

    AAAAAA

    A

    A

    A

    AA

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    AA

    AAAA

    AAAAA

    A

    A

    A

    AAAAA

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    AAA

    A

    AA

    AAAA

    AA A

    A

    AA

    A

    AAAAAAA

    AAA

    A

    AAAAAAA

    A

    AAAA

    A

    AAAAAAAAAAAA

    AAA

    A

    A

    AA

    AA

    A

    A A

    AA

    A

    AA

    A

    AAA

    A

    A

    A

    AAAAAAAA

    AA

    A

    A

    AAAAA

    A

    A

    A

    A

    A

    A

    A

    AAA

    A

    AA

    A

    A

    A

    A

    A

    A

    A

    A

    A

    AAA

    A

    A

    AA

    AA

    AA

    A

    AAA

    A

    AA

    AA

    A AA

    AA

    A

    AAAA

    AAAAAAAAAAAAAAAAAA

    AAA

    A

    A

    A

    AA

    A

    AA

    A

    AAA AAAAAAAAAA

    A

    AA

    AAAAA

    AAA

    AAAA

    A

    A

    A

    A

    A

    AAA

    AAAAA

    AAA

    AA

    A

    A

    A

    A

    A

    A

    A

    AA

    A

    AAAA

    AAA

    AAAAAAAAA

    AA

    A

    A

    A

    AAAAAA

    A

    A

    A

    AAA

    A

    AA

    A

    A

    A

    A

    AAA

    A

    A

    A

    AAAAAA

    AA

    AAA

    AAAAAAAAAAAA

    AAAAAAA

    A

    A

    A

    A

    A

    A

    A

    AAAAA

    AA

    AAAAAAAAA

    AA

    A

    A

    AA

    AAA

    A

    AAA

    AA

    A

    AAAAA

    A

    A

    A

    A

    AA

    A

    A

    A

    A

    A

    A

    AA

    AA

    A

    A

    A

    A

    A

    A

    A

    ")

    ")

    ")

    ")

    ")

    ")

    ")

    ")

    XW

    XW!.

    !.

    320'E

    320'E

    240'E

    240'E

    20'E

    20'E56

    40'N

    5640'N

    5615'N

    5615'N

    5550'N

    5550'N

    .

    Alma Field Development Environmental StatementFigure 1-1: Project Location

    NOTE: Not to be used for navigation

    Produced ByReviewed By

    Louise MannAnna Farley

    Wednesday, July 6, 2011 15:10:52ED 1950 UTM Zone 31N

    D European 1950EnQuest, UKDeal, KISCAJ:\P1459\Mxd\Environmental Statement\.mxdFigure 1-1 Project Location

    International 1924

    Metoc Ltd, 2011.

    DateProjection

    DatumData SourceFile Reference

    Spheroid

    Checked

    All rights reserved.0 8 16 24 32 404 km

    LegendMedian lineLandUKCS Block

    XW Uisge Gorm FPSO!. Northern Drill Centre!. Southern Drill Centre

    Production FlowlineWI Flowline

    XW FPSO") PlatformA Well

    PipelineCableHydrocarbon Field

    A

    A

    A

    AA

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    A

    AA

    A

    A

    A

    A

    A

    A

    A XW

    !.

    !.Block 30/25

    Block 30/24

    0 0.8 1.6 2.4 3.20.4Kilometers

    Southern Drill Centre

    Uisge Gorm FPSO

    Northern Drill Centre

    Janice Alpha

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 1-3 21/07/2011

    Table 1-1: Project co-ordinates Structure Easting (E) Northing (N) Latitude (N) Longitude (E) Uisge Gorm FPSO 488 250 6 227 000 56 11' 16.16" 02 48' 38.45" Northern drill centre (production wells) 485 469 6 228 541 56 12' 05.72" 02 45' 56.84" Southern drill centre (water-injection wells) 485 858 6 224 891 56 10' 07.71" 02 46' 20.12"

    Datum: WGS84

    1.2.1 Field History

    The Argyll field was discovered in 1971 and brought on stream as the UKs first oilfield by the Hamilton Brothers. The Field was decommissioned in 1992 due to the low oil price prevalent at the time. Between 1975 and 1992 Argyll produced 74.8 mmbbl (million barrels) oil. The final field rate was 5,000 bopd (barrels oil per day) with a 70% water cut.

    The Argyll Field was renamed Ardmore and redeveloped by Tuscan and Acorn, with second phase first oil in 2003. Between 2003 and 2005 Ardmore produced a further 5.2 mmbbl oil. The field was the decommissioned again in 2008 because of low profitability.

    EnQuest now plan to rename and redevelop the Ardmore field as Alma as it is now commercially viable to develop from a small marginal field due to the prevailing oil price. As the entire previous field infrastructure was removed during the Ardmore decommissioning, and as Alma is a marginal field and production will likely be short-term, EnQuest are proposing to use an FPSO rather than install a platform.

    The Field consists of three main productive intervals, namely Zechstein carbonates and evaporates, Rotliegend Aeolian sandstone and Devonian sandstone/siltstone. It is located on a large Palaeozoic, southwest to northeast trending tilted fault block on the south-western flank of the Central Graben. The Field structure measures approximately 2.5km wide and 6km long.

    1.2.2 Schedule

    Construction is scheduled to start in January 2012 with the drilling of the first production well. Construction activities will continue through to May 2013 with first oil expected in third quarter 2013. A total of six production wells and two water injector wells will be batch drilled and are expected to take approximately three months each to drill and complete. Field life is anticipated to be ten years.

    1.2.3 Construction

    The Alma field development will consist of eight wells; six oil producers and two water-injectors. The water injectors will be drilled from a southern drill centre and the production wells from a northern drill centre. All wells will be tied-back via new flexible flowlines to the Uisge Gorm FPSO.

    Flowlines will consist of one 10-inch water-injection flowline to the southern drill centre and two 10-inch production flowlines to the northern drill centre. As a general rule the water injection flowline will be trenched and backfilled where possible. In the event of any undulations in the trench (and subsequently the flowline) a contingency will be in place for the provision of approximately 5,000

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 1-4 21/07/2011

    tonnes of rock for deposition for protection. The rock will be deployed to mitigate any upheaval buckling (low risk for flexible flowlines) or pipeline out of straightness events experienced during the trenching and pipe-lay activities. This may be required for pipeline protection, depth of cover anomalies or dropped object protection. The requirement for rock deposition will be identified during post lay survey and if required the rock will be placed accurately using a dynamically positioned installation vessel. The vessel will be equipped with a fall pipe to deploy rock accurately in the spot location. Due to the infield debris (both buried and on the seabed), wellheads and the associated infrastructure in place from previous field operations, it is difficult to establish a clear route and therefore it will not always be possible to trench and backfill the flowline. Where it is not possible to trench, the line will be surface-laid and protected by concrete mattresses and grout bags. The use of trenching and backfilling will be optimised and surface laid pipe minimised. The production flowlines cannot be trenched and backfilled as this would result in high arrival temperatures of the production fluids at the FPSO. The flowlines will instead be surface laid and protected by concrete mattresses and rock material where required.

    Production wells will be fitted with electrical submersible pumps (ESPs) to assist flow rates. The wells will be drilled from a semi-submersible drilling rig. Drilling is expected to commence in January 2012, with the rig remaining on site until April 2013.

    The production flowlines will terminate in a manifold at the northern drill centre and in a bolted straight T piece to the flexible risers beneath the FPSO. This T piece will allow for future tie-ins. The risers will then connect to the FPSO in a lazy S configuration. In addition a control umbilical will be surface laid out to each drill centre and a power cable will also be laid out to the production wells. The flowline corridor will be approximately 30m wide to the southern drill centre and 50m wide to the northern drill centre. Each riser will be held in place with a vertical and horizontal hold-back tether. Each hold-back tether will consist of one upper piled or gravity riser base (vertical) and one lower clump weight holdback anchor (horizontal) (Figure 1-2).

    Figure 1-2: FPSO riser hold-back tether example

    Note: Image is for illustrative purposes only and does not necessarily reflect exact layout of flowlines and associated infrastructure.

  • ENQUEST HEATHER LIMITED ALMA FIELD DEVELOPMENT

    REPORT REF: P1459BA_RN2525_REV0 1-5 21/07/2011

    It is possible that the flowlines will require dropped object protection around the well head areas. This will take the