all-american canal lining project - ibwc.govhistory of the all-american canal lining project •...

23
1 All-American Canal Lining Project Presentation To: USIBWC By Todd Shields, Executive PM, AACLP December 2007

Upload: others

Post on 01-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

1

All-American Canal Lining ProjectPresentation To:

USIBWCBy

Todd Shields, Executive PM, AACLP

December 2007

Page 2: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

2

AACLP Project Location

Page 3: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

3

• Constructed in the 1930s by Reclamation• New Canal will conserve (seepage control by lining 23

miles of canal) 67,700 acre feet per year. Enough water for 500,000 people.

• Approximate lined canal construction cost is $250M.• Project being directed by the All-American Canal

Coordinating Committee (IID/San Diego County Water Authority/Reclamation)

AACLP – FACT SHEET

Page 4: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

4

History of the All-American Canal Lining Project

• Congressional authorization of the Project in 1988

• Approved Environmental Compliance in 1994• Project funding has two sources: State of

California and San Diego County Water Authority

• Construction Started June, 2006 then stopped by court ordered injunction

• Court injunction lifted in early-2007, NTP issued to both contractors by early June, 2007. Cost of Injunction: $30 million.

Page 5: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

5

AACLP Project Elements• Construct approximately 23 miles of

lined canal adjacent to existing canal• Construction started June 2007• Construction projected to be

complete by Spring 2010• Reach 2 expected to be complete by

early 2008

Page 6: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

6

All-American Canal Typical SectionProposed Lined Section

1.75H:1V side slope Reaches 1 & 2 2H:1V side slope Reach 3

Existing Unlined Section2H:1V side slope

50’

150’

130’ +/-

Spoils

24’ O&M Road

Page 7: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

7

AACLP Project OrganizationAll-American Canal Coordinating Committee (Voting Members)

• IID – Michael King • SDCWA – Kenneth Steele • Chairman – Van Tenney

IID Executive Program ManagerTodd Shields

Participants (Non-Voting)• Reclamation – John English• DWR – Chuck Keene• San Luis Rey• CVWD• PVID

IID/DWR AACLP Funding Agreement

Parsons Project ManagerUli Kappus

Environmental ActivitiesConstruction ManagementConstruction Manager –

Don Crumbley

DesignBookman-Edmonston

Project Manager – Wayne Dahl

Design CoordinationCoordinator –

Walt Long• Montgomery Watson Harza• Various Consultants- Canal Design - Dewatering- Sedimentation - Soils- Flow Measurement/Operations

- Cost Estimating- Construction Techniques

• Geotechnics, Inc.• Hale Engineering

Environmental Coordinator –

Michel Remington, IID• AFM Affiliates

Cultural Resources

• Dr. Paul KrausmanLarge Mammal Surveys

• EcoSystems RestorationAssociates

Wetlands Enhancement• RECON • Parsons

Page 8: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

8

Project Challenges

• Minimizing Project Impact due to Design, and Schedule Changes

• Environmental Constraints• Maintaining Public Access through Active

Construction Site• Security along International Border• Continuous water delivery

Page 9: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

9

Environmental Program Objectives• Compliance with Multiple

Requirements:• Air Quality• Cultural Resources• Endangered Species• Hazardous

Materials/Solid Waste• Recreation /

Transportation• Water Quality/Stormwater• Wetlands• Wildlife

Page 10: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

10

Challenge of Public Access and Recreation During Construction

• Coordinating Construction and Public Use Near Work Areas

• Interagency Coordination During Peak Use Periods

• Public Information Distribution is Essential

• Interagency Recreation and Transportation Management Plan

Page 11: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

11

Safety Program

Page 12: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

12

Current Status

• Over 12 Million CY of Earth Moved to Date

• First major concrete pour completed on August 8, 2007

• 5 miles of Production Lining of New Canal completed to date.

Page 13: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

13

Original Construction

Page 14: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

14

Completed Canal

Page 15: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

15

Construction Photos

Page 16: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

16

Construction Photos

Page 17: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

17

Construction Photos

Page 18: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

18

Page 19: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

19

Construction Photos

Page 20: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

20

Construction Photos

Page 21: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

21

Construction Photos

Page 22: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

22

Construction Photos

Page 23: All-American Canal Lining Project - ibwc.govHistory of the All-American Canal Lining Project • Congressional authorization of the Project in 1988 • Approved Environmental Compliance

23

Thank YouQuestions?