alice-lhcc review january 29-30, 2001 thomas c. meyer/ep-ait1 general layout four separate vessels:...
TRANSCRIPT
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 1
General LayoutGeneral Layout
Four separate vessels:– Outer containment vessel– Inner containment vessel– Outer field cage vessel– Inner field cage vessel
Two end plates for readout
Pb Pb
E
E
CO2 Insulation GapDrift Volume
End Plate Central Electrode
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 2
Design ObjectivesDesign Objectives
Provide high stability and uniformity for:Gas gain (>104): 0.5%Drift field (400 V/cm): Er/Ez < 10-4
Temperature: T < 0.1 ºCDrift gas purity: 5 ppm O2, 10 ppm H2O
Provide high mechanical precision for:Central electrode: 250 µmReadout plane: 250 µm
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 3
Technical ProgressTechnical Progress
The FC prototype has undergone intensive testing during the past two years:– Individual components (electrical, mechanical, gas)– System behavior (FC + NA35 readout chamber,
cosmics & laser runs)
Laboratory results certify the required performance of the FC in terms of field quality.
High radiation test in CERES area:– Check stability under ‘realistic’ conditions– Exposed FC to proton and Pb beams
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 4
Test-Setup in CERES ZoneTest-Setup in CERES Zone
CERES Detector
Multiplicity Array
p, Pb beams
FC Prototype
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 5
High Intensity: Proton RunsHigh Intensity: Proton Runs Direct exposure to proton beam:
– Locally irradiated area (1-4 cm2) near central electrode:
Stable up to 100 kV
CERES p-beam: 2.5 x 105/cm2 s (3 x 105 with Pb target)ALICE: 360/cm2 s
CERES Detector
Multiplicity Array
p
FC Prototype
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 6
High Intensity: Pb-Ion RunsHigh Intensity: Pb-Ion Runs Exposure to secondaries from Pb beam:
– Global irradiation of entire cylinder
Stable to ≤ 60 kV!
CERES Pb-beam: 6000/cm2 s (secondaries)ALICE: 360 /cm2 s
CERES DetectorPb
FC Prototype
MultiplicityArray
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 7
Material Tests: HygroscopyMaterial Tests: Hygroscopy Check crucial material of field cage for hygroscopic
behavior:
– Kevlar (skins)– Carbon fiber (skins)– Glass fiber (skins)– Makrolon (rods)
Pre-condition material Choose glass fiber
instead of KevlarDrying
-250
-200
-150
-100
-50
0
50
-250
-200
-150
-100
-50
0
50
0 100 200 300 400 500
TEMPERATURE STABILIZATION : +/- 0.4 CPRECISION OF MEASUREMENT : +/- 10 μm
L/L
[µ
m/m
]
T [min]
Macrolon
Carbon Fiber
Kevlar Fiber
Glass Fiber
Wet
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 8
Material Tests: TedlarMaterial Tests: Tedlar Does Tedlar provide an efficient moisture barrier?
– Sandwich sample exposed to water-saturated air at 29 ºC on both sides:
Nomex® Honeycomb
KevlarPrepreg
Tedlar
• Maximum possible water absorption by matrix is 6% of sample weight, i.e. 13.2 g.
• After 18 days of exposure, no weight increase was observed.
• Reverse test is ongoing, i.e. the sandwich is placed in a 100% dry atmosphere.
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 9
Problems & Risks: MaterialProblems & Risks: Material
Material tests basically finished.– Kevlar fallback: glass fiber (included in
tender) Slightly cheaper More mass (<10% of total)
– Tedlar fallback: none! Aging tests planned (≥ 1 year)
– Macrolon rods replaced by ceramics? Very expensive (material and machining)
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 10
Cooling Tests: Resistor ChainCooling Tests: Resistor Chain
Four internal resistor chains supply the appropriate potentials to the strips.
Their power consumption is 60W each. This leads to temperature gradients
inside TPC of »0.1 °C.
Must cool the voltage divider!
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 11
Resistor Chain: ConceptResistor Chain: Concept
Voltage divider is placed inside rod. Liquid coolants to remove waste heat. First test with water successfully
finished, as proof of principle.
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 12
Resistor Chain: Test-SetupResistor Chain: Test-SetupThe Thermal Box
Resistor Rod
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 13
Resistor Chain: ResultsResistor Chain: Results
flow - temperature
18
18.5
19
19.5
20
20.5
21
0 100 200 300 400 500 600
flow [l/h]
inside 1 IN inside 2 inside 3 inside 4 inside 5 OUT
Achieve negligible temperature gradient inside rod:
Pt 1 Pt 2 Pt 3 Pt 4 Pt 5H2O in
H2O
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 14
Resistor Cooling: Next StepsResistor Cooling: Next Steps We have verified that water and silicon fluid FL 200/5 remove
heat equivalent to 60 W, as expected. For HV operation, only non-polar liquids can be used:
The liquid must be compatible with the rod material.
CoolantDensity[kg/cm3]
Viscosity[m2/s]
Heat Capacity[J/kg °C]
Flow[l/h]
H2O 998 .00114 4190 516
Silicon Fl 200/5 913 .000055 1632 1450
Shell Diala 882 .00042 1850 1320
C5F12 1630 .00046 1050 1260
C6F14 1680 .00067 1050 1220
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 15
Problems & Risks: ChargingProblems & Risks: Charging
Understand field cage charging under high radiation load:– Examine field cage in laboratory:
Bleed 300 MBe of 83Kr into field cage gas to simulate charged particle flux.
Separate tests for drift and insulation volume.
– Increase number of guard rings.– Eventually repeat beam test.
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 16
Problems & Risks: CoolingProblems & Risks: Cooling
The resistor rod is a high risk item...– Choose liquid that is safe for apparatus.
No chemical decomposition, dissolution etc.
– Run circuit below atmospheric pressure. Absolutely no leaks, cracks, capillary effects!
– Tight quality control.– If all fails, use gas as coolant:
Double walled cooling circuit; Needs additional, extensive testing.
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 17
Stability Study: Why?Stability Study: Why?
ITS Induced Forces
-500
0
500
1000
1500
2000
2500
3000
1 2 3 4 5 6 7 8 9 10 11
Load Cases for TPC
Series1
Series2
Series3
Series4
C1
C2
C3
C4
Weights [N]:120020004000
2 RailsITS + Vac. Ch.Services
C1 C2 C3 C4ITS
TPC Inner Vessels
ITS and beam pipe are supported by TPC.TPC moves (!) out for ITS interventions.
Deformations must not harm TPC and ITS.
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 18
FEA: Critical AreaFEA: Critical Area
Nomex® HoneycombKevlar®
Fiber
Tedlar®
Tedlar®
Aluminum
Aluminum
Transition from solid Al flange to laminar composite structure
Aluminum
Carbon-Fiber-Nomex-Composite
1.2 MPa
8.4 MPa4.8 MPa
10.8 MPa
Equivalent shear stress (van Mises) indicates
critical zone
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 19
FEA: ResultsFEA: Results Buckling:
– No buckling modes induced until load is increased by a factor of ~ 60.
Stresses:– The critical zone is the transition from flange to
cylinder (“ovalization” under load).– Maximum shear stress in glue joint is
≤ 3 MPa (factor of 6 from failure).– Interlaminar shear stress in composite matrix is ~ 5
kPa (6% risk of delamination)
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 20
Problems & Risks: StabilityProblems & Risks: Stability
Flexible joint for central drum?:
Removes load from critical zone Engineering design underway Lower cost than original version
ITS attached here
.
Aluminum
Bellows
Central SectionConical Section
Critical zone
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 21
Problems Related to ContractingProblems Related to Contracting Cylinders:
– Only five offers received
– Lowest offer still 3 x higher than budget
End Plates:– Lowest bid exceeds budget by factor of 5
– Splitting of production processes Separate raw material, welding and machining
– Design changes
Alternative scenarios require new tenders– Could lead to delays and increased risks
– Avoid market surveys (6 months delay)
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 22
Future ActivitiesFuture Activities R&D and prototyping continues during
construction in 2001:– Entire infrastructure of field cage
Central electrode (3 options) Strips & Rods (4 different types) Gas distribution Alignment
– Tooling and assembly techniques Prepare DELPHI support frame Test facilities (gas, survey, HV, LV, readout)
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 23
Project ScheduleProject ScheduleR & D Design & Prototyping Construction & Assembly Physics
Program Chronology of the TPC Project:
We are here!
ID Task Name1 The TPC Field Cage Project
2 R&D and Prototyping
160 TDR
161 Design
178 Issue of contract
179 Fabrication & Construction
181 Inspection & Certification
188 Assembly & Equipment of Field Cage
201 Pre-installation in Zone 2
210 Installation in Underground Area
219 TPC Ready
220
R&D and Prototyping
TDR
Design
Issue of contract
Fabrication & Construction
Inspection & Certification
Assembly & Equipment of Field Cage
Pre-installation in Zone 2
Installation in Underground Area
TPC Ready
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 41998 1999 2000 2001 2002 2003 2004 2005 2006 2007
ALICE-LHCC Review January 29-30, 2001
Thomas C. Meyer/EP-AIT 24
Field Cage: SummaryField Cage: Summary Performance
– All technical issues have been studied, certifying the viability of the chosen field cage principle.
Reliability– No serious risks have been identified, except..
charging at high particle flux (tests underway)
Schedule is very tight due to increased in-house production load.