albeni falls dam downstream water temperature study · 6/24/2014  · project authority and...

22
US Army Corps of Engineers BUILDING STRONG ® Albeni Falls Dam Downstream Water Temperature Study Interim Results Amy Reese, Chief Water Management Section Seattle District June 24, 2014

Upload: others

Post on 29-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

US Army Corps of Engineers BUILDING STRONG®

Albeni Falls Dam Downstream Water Temperature Study Interim Results

Amy Reese, Chief Water Management Section

Seattle District

June 24, 2014

Page 2: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

What we hope to cover today

Albeni Falls Dam – General Operation ►Authority and Operational Requirements ►Corps plan for 2014 operations

Kalispel MOA – ►background ►water temperature modeling work ►results and next steps

Presenter
Presentation Notes
Introduce Beth Coffey, Chief of Operations; Ryne Linehan, Operating Project Manager at Albeni Falls Dam; Robyn MacKay, Planning at BPA; Bill Maslen, Fish and Wildlife at BPA; etc.
Page 3: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Project Authority and Operation Requirements

Authorized under Flood Control Act of 1950; substantially in accordance with Senate Doc No. 9

Authorized as part of a system-wide development to respond to the great flood of 1948 and meet PNW electric generation needs

Clean Water Act, Endangered Species Act, National Environmental Policy Act, Northwest Power Act

Applicable Treaties (1964 CRT) Executive Orders, Court Orders or agreements such as

the Kokanee Agreement with the state of Idaho 1957

Presenter
Presentation Notes
For example… Agreement between US and the State of Idaho in 1957 Authorized under Section 2 of PL 732 Prevents loss or damage to wildlife resources Article III: Government will operate AFD in the primary interest of power production but will avoid operations unnecessarily detrimental to kokanee
Page 4: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Page 5: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG® 2050.0

2051.0

2052.0

2053.0

2054.0

2055.0

2056.0

2057.0

2058.0

2059.0

2060.0

2061.0

2062.0

2063.0

1-Sep 30-Sep 31-Oct 30-Nov 31-Dec 31-Jan 28-Feb 31-Mar 30-Apr 31-May 30-Jun 31-Jul 31-Aug

Hop

e G

age

Elev

atio

n (ft

)

Date

Albeni Falls and Lake Pend Oreille General Operations

Max Elevation

09-10 Elevation

Min Elevation

Elevation Range = 0.50 feet above MCE. MCE reset if lake fills.

Flexible Winter Power Operations = 5 foot above MCE. .

Flood Control Target

Page 6: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Kalispel MOA

10-year agreement between BPA, Corps and Kalispel Tribe of Indians BPA conducted a 30-day review period

June 30 – August 1, 2011 and entered a record of decision July 6, 2012 Includes schedule for fish passage studies

Page 7: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Kalispel MOA

Includes the Corps and Tribe to collaborate on temperature studies ►Can releases from Albeni Falls Dam benefit

bull trout? ►Distinguishes between post-labor day

temperature operation and pre-labor day ►Post-labor day requires “SOR” and may be

implemented ►Pre-labor day has potential to be evaluated

Presenter
Presentation Notes
The study work completed each year is spelled out in the Action Plan. The Action Plan is revised each year collaboratively between the parties to the MOA and allows for flexing and refining model studies.
Page 8: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Does this mean that we will draft the lake in summer?

No. Any change of operation from our current water control plan (which is in accordance with authorized purpose, subsequent agreements and law) would undergo NEPA documentation and coordination. There are no plans to make a change from

our water control plan at this time.

Page 9: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Project Status Review of and agreement to use CE-QUAL W2 model 4 sets of modeling completed, 5th set nearing

completion. Draft triggers identified for executing a Temperature

Management Operation: ► During prominent cold weather conditions, decrease river flows

to increase exposure time in the POR ► During hot weather conditions, increase river flows to reduce

exposure time in the POR ► When surface water temps in LPO are cooler than POR at AFD,

increase flows to introduce cooler water downstream

Presenter
Presentation Notes
Talk through “Opportunistic Event” at this point. The Triggers identified are contingent on weather conditions and surface water temperatures in LPO. Introduce the example Set: Set E Case A14
Page 10: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Set E – Historical Operations

2056

2057

2058

2059

2060

2061

2062

2063

-5

0

5

10

15

20

25

30

8/14 8/19 8/24 8/29 9/3 9/8 9/13 9/18 9/23 9/28 10/3

2013 Observed Operations

Inflow Draft Outflow Elevation

Presenter
Presentation Notes
Actual observed operations in 2013
Page 11: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

2056

2057

2058

2059

2060

2061

2062

2063

-5

0

5

10

15

20

25

30

8/14 8/19 8/24 8/29 9/3 9/8 9/13 9/18 9/23 9/28 10/3

Hope

Ele

vatio

n (ft

)

Flow

(kcf

s)

2013 September Historical Operations as Modeled

Inflow Modeled Draft Modeled Ouflow (kcfs) Modeled Elevation (ft)

Set E – Historical Operations as modeled for comparison purposes

Presenter
Presentation Notes
Status Quo modeling case – used to provide comparison/common baseline with modified operations
Page 12: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

2056

2057

2058

2059

2060

2061

2062

2063

-5

0

5

10

15

20

25

30

8/14 8/19 8/24 8/29 9/3 9/8 9/13 9/18 9/23 9/28 10/3

Scenario A - Increase Outflow to 14-15 kcfs during Warm Weather

Inflow Modeled Draft Modeled Ouflow (kcfs) Modeled Elevation (ft)

Set E – scenario A

Page 13: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Set E Results

Case A14 Modeling Results Summary. Difference in Daily Maximum Volume Weighted Temperatures

1 2 3 4 5 6 7 8 9 10 11 9/1/13 0.0 0.0 0.0 0.0 -0.1 0.0 0.1 -0.1 -0.1 0.1 0.0 9/2/13 0.0 0.0 0.0 0.0 0.0 -0.1 0.1 0.0 -0.1 0.0 0.0 9/3/13 0.0 0.0 0.0 0.0 0.0 0.1 -0.1 0.0 0.0 0.0 -0.1 9/4/13 0.0 0.0 0.0 0.0 0.0 0.0 0.1 0.0 0.0 0.0 0.0 9/5/13 0.0 0.0 0.0 0.0 0.0 -0.1 0.1 0.0 0.0 0.1 0.0 9/6/13 0.0 -0.1 -0.1 0.0 0.1 -0.1 0.1 0.1 0.0 0.0 0.0 9/7/13 -0.1 -0.1 -0.2 -0.1 0.2 0.2 0.2 0.2 0.1 0.0 0.0 9/8/13 0.1 -0.2 -0.3 -0.2 -0.1 0.1 0.4 0.4 0.2 0.0 -0.1 9/9/13 0.1 -0.1 -0.3 -0.4 -0.4 -0.2 0.2 0.4 0.7 0.4 -0.1

9/10/13 0.0 0.2 -0.3 -0.4 -0.5 -0.4 -0.2 0.1 0.4 0.7 0.6 9/11/13 0.0 0.1 -0.1 -0.4 -0.5 -0.3 -0.4 -0.3 -0.1 0.2 0.5 9/12/13 0.0 0.0 0.1 -0.2 -0.4 -0.3 -0.4 -0.3 -0.2 -0.3 -0.1 9/13/13 0.0 0.0 0.0 0.0 -0.3 -0.3 -0.4 -0.2 -0.3 -0.3 -0.3 9/14/13 0.0 0.0 0.0 0.1 0.0 -0.2 -0.3 -0.3 -0.3 -0.2 -0.3 9/15/13 0.0 0.0 0.0 0.0 0.1 -0.1 -0.2 -0.3 -0.3 -0.2 -0.3 9/16/13 0.0 0.0 0.0 0.0 0.1 0.1 0.1 0.0 -0.2 -0.2 -0.3 9/17/13 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.1 0.1 0.0 -0.2 9/18/13 0.0 0.0 0.0 0.0 0.0 -0.1 -0.1 -0.1 0.0 0.1 0.2 9/19/13 0.1 0.0 0.0 0.0 -0.1 -0.1 -0.1 -0.2 -0.1 -0.1 0.2 9/20/13 0.1 0.1 0.1 0.0 -0.1 -0.2 -0.3 -0.2 -0.1 -0.3 0.0 9/21/13 -0.1 0.4 0.2 0.0 -0.2 -0.3 -0.3 -0.3 -0.1 -0.2 0.0 9/22/13 0.0 0.2 0.5 0.1 -0.3 -0.3 -0.3 -0.4 -0.4 -0.3 -0.1 9/23/13 0.0 0.1 0.7 0.3 0.0 -0.4 -0.3 -0.4 -0.4 -0.3 -0.2 9/24/13 0.0 0.0 0.3 0.6 0.3 0.1 -0.1 -0.3 -0.4 -0.4 -0.2 9/25/13 -0.1 0.0 0.1 0.6 0.4 0.3 0.2 -0.1 -0.3 -0.3 -0.4 9/26/13 -0.1 0.2 0.1 0.3 0.5 0.5 0.3 0.0 -0.1 -0.2 -0.2 9/27/13 0.1 -0.2 0.5 0.2 0.3 0.4 0.4 0.3 0.2 0.0 -0.1 9/28/13 0.0 0.1 -0.1 0.5 0.1 0.3 0.3 0.3 0.4 0.3 0.3 9/29/13 0.0 0.0 -0.1 0.2 0.4 0.3 0.1 0.2 0.4 0.3 0.3 9/30/13 0.0 0.0 0.1 -0.2 0.3 0.7 0.4 0.3 0.1 0.3 0.4 10/1/13 0.0 0.0 0.0 0.0 -0.2 -0.2 0.2 0.5 0.4 0.3 0.1

Page 14: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Summary of Modeling Results

Set E (Operational) ►Modeling mostly completed. Partial results

under analysis. ►Flow increases during a warm weather event

in September of 2013 may have affected river temperatures.

Page 15: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Next Steps

Kalispel Tribe currently reviewing results Next phase of study will be to determine

significance of results Potential for refined model runs Explore potential post-labor day

temperature management operation Plan for fall 2014 September operation…

Page 16: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

2014 Operations

Winter lake level for support of Clark Fork Delta restoration work is 2051 ft. Target 2051 ft no later than Nov. 15th Hold lake within summer operating range

until mid-September At or above 2061 ft through the 3rd

weekend of Sept (last day of summer) Plan to be at or above elevation 2060.5 ft

at end of September

Page 17: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Summary ►Corps operates according to current water

control plan and consistent with authorities, agreements and statutes.

►No plan to change summer operation which holds lake between 2062 and 2062.5 through Labor Day

►September 2014 operation is coordinated ►Temperature studies are ongoing, and latest

results show dam releases can effect temperature.

Page 18: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Questions

Seattle District – 206.764.3750 Scott Lawrence – 206.764.6896 www.nws.usace.army.mil

►Flow updates and projections

Page 19: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Backup Slides

Page 20: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Lake Pend Oreille

AFD is ~27 miles downstream of the

lake

Dover is location of channel restriction.

Where lake elevation is measured

Page 21: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

Lake Pend Oreille – pre and post AFD

Median Elev 1930 - 1953

Median Elev 1953 - 2009

2050

2055

2060

2065

Page 22: Albeni Falls Dam Downstream Water Temperature Study · 6/24/2014  · Project Authority and Operation Requirements Authorized under Flood Control Act of 1950; substantially in accordance

BUILDING STRONG®

2035

2040

2045

2050

2055

2060

2065

0

10

20

30

40

50

60

1-Aug 1-Sep 1-Oct 1-Nov

Hop

e El

evat

ion

(ft)

Flow

(kcf

s)

Date

Albeni Falls Dam Operations Aug 1 to Nov 30, 2013

Inflow Outflow Hope Gage Upper Rule Curve Lower Rule Curve

Labor Day

Sept 25

Targeted 2060 ft 2060.5 ft on

Sept 30.

Sept 13th

Reach 0.5 feet of MCE Nov 11 - not

Nov 8th. Unit outages

/spill and TDG

management