aip for kvaerner deepwater dry tree semi approval in ...€¦ · 1.2 introduction of kvaerner...
TRANSCRIPT
AIP FOR KVAERNER DEEPWATER DRY TREE SEMI
Approval in Principle of
Kvaerner Deepwater Dry Tree
Semi RPSEA
Report No.: 15U5O2I-10, Rev. 2
Document No.: 15U5O2I-10
Date: 2014-12-30
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page ii
Table of Contents
ABBREVATIONS ........................................................................................................................... 1
CONCLUSIVE SUMMARY ................................................................................................................ 2
1 INTRODUCTION .............................................................................................................. 3
1.1 Approval in Principle Process 3
1.2 Introduction of Kvaerner Deepwater Dry Tree Semi Design Concept 6
1.3 Applicable Rules, Regulations and Standards 8
2 INTRODUCTION .............................................................................................................. 9
3 CONCLUSIONS AND WAY FORWARD ............................................................................... 11 Appendix A Drawing List Appendix B Conceptual HAZID Report Appendix C Comments and Responses
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page 1
ABBREVATIONS
AiP: Approval in Principle
API: American Petroleum Institute
DNV GL: Legacy Det Norske Veritas and legacy Germanischer Lloyds have been merged as of September
12th, 2013, DNVGL is the new brand. Legal entity remains the same. This project contact was signed in
October, 2012 between Det Norske Veritas USA (Inc.) and RPSEA.
DWDTS: Deepwater Dry Tree Semi
HAZID: Hazard Identification
HOE: Houston Offshore Engineering
KFD: Kvaerner Field Development
RPSEA: Research Partnership to Secure Energy for America
SIMOP: Simultaneous Operation of Drilling and Production
TLP: Tension Leg Platform
VIM: Vortex Induced Motion
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page 2
CONCLUSIVE SUMMARY
DNV GL has been requested by RPSEA to perform an “Approval in Principle”, AiP, for Kvaerner Deepwater
Dry Tree Semi concept design.
The AiP review has been based upon the assessment of the overall feasibility of the concept, detailed
calculations, and drawings that will be verified at the later design stages. With all identified issues being
addressed and improvements as recommended being carried out; the risks identified for the concept can be
reduced to an acceptable level that will enable the concept feasibility.
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page 3
1 INTRODUCTION
1.1 Approval in Principle Process
DNV GL has been requested by RPSEA to perform an “Approval in Principle”, AiP, of the design of Kvaerner
Deepwater Dry Tree Semi concept.
Approval in Principle (AiP) is a service offered by DNV GL to carry out an independent assessment of a
concept within an agreed requirement framework. The aim of AiP assessment is to confirm that the design is
feasible and that there are no insurmountable obstacles (“showstoppers”) that would prevent the concept
being realized.
AiP is typically carried out at an early stage of a project to confirm its feasibility towards the project team,
company management, external investors or future regulators.
It should be noted that the Approval in Principle statement does not constitute classification of the design to
DNV GL Rules for Classification. AiP will typically identify a number of areas that will need to be addressed
during detail design in order to prepare the design for final Classification Approval.
Figure below shows the methodology of the Approval in Principle process.
Figure 1-1 Approval in Principle process
1.1.1 Scope
In order to evaluate the dry tree semi concept design with respect to AiP, design documentation related to
the following disciplines has been reviewed:
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page 4
• Global performance
• Mooring
• Riser tensioning assembly (typically not class scope but included in this evaluation due to its
criticality for this concept)
• Hull structural strength
• Stability
• High level system and safety
The objective of this review is to familiarize with the design concept, identify any showstoppers or major
shortcomings with respect to compliance with the defined regulatory framework and the specified design
standards. Some limited independent calculation has been carried out as needed.
1.1.2 Initial Technology Assessment
The concept is broken down into key technology elements and these are assessed with regards to degree of
novelty. The areas identified with degree of novelty were the focus of the AiP.
1.1.3 Conceptual HAZID
In order to systematically assess the novelty of the design, maturity of technology applied and feasibility of
the concept, conceptual HAZID workshops were carried out. First an internal workshop was carried out,
which was attended by DNV GL personnel covering all disciplines. Concerns, novelty, mitigations, etc. for
each element/discipline were thoroughly discussed. A second workshop was arranged to include the lead
engineers of the designer (KFD), where the design philosophy was explained, engineering study performed
was elaborated and all concerns raised by DNV GL’s internal workshop were discussed/clarified. Finally a
workshop attended by all industry subject matter specialists was arranged. . The objectives of the
conceptual HAZID workshops are to:
Identify and describe challenges and critical elements in the design concept
Identify specific risks related to this particular project and how they are addressed in the design
Provide systematic input to the Approval in Principle (AiP) Process
The assessment is qualitative. Results of the workshop are included in Appendix B.
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page 5
Attendees of the final workshop are listed as follows:
Session Attendees Company
KFD
Concept
Jenny Lu DNV GL
Heather Davis DNV GL
Reza Mostofi DNV GL
Robert Gordon DNV GL
Lihua Wang Statoil
Oddgeir Dalane Statoil
Wei Ma Chevron
Ming-Yao Lee Chevron
Amal C. Phadke Conoco Philips
Gail Baxter Marathon Oil
Bill Head RPSEA
Aifeng Yao Shell
Sam Ryu ExxonMobil
John Murray BP
Petruska, David J BP
Ricky Thethi 2H Offshore
David Garrett Stress Engineering
Jack Zeng Kvaerner
Leiv Wanvik Kvaerner
Wan Wu Kvaerner
Knut Pedersen Kvaerner
John Koos MHD Offshore Group
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page 6
1.1.4 Review Safety Assessment and Technical Studies
The review of safety assessment and technical studies is also part of the AiP process. Any major hazards or
obstacles to the project identified through the review are to be properly addressed.
1.1.5 Assess Finalized Concept
Some comments/concerns raised in the AiP process require the designers to re-visit certain aspects of the
design and produce some additional engineering studies, evaluations, etc. Some of the comments related to
the detailed design are expected to be addressed at the later design stage.
A statement of Approval in Principle is issued once all pending comments/concerns are properly addressed
and no major show-stoppers are identified.
1.2 Introduction of Kvaerner Deepwater Dry Tree Semi Design
Concept
Table below provides main dimensions of the design. Figures below show general arrangement of this design
concept. Further details of the design basis are found in KFD’s “Dry Tree Semi Conceptual Design Report”,
Doc. No. KFD-RP-ZZZ-0001, Section 4. Lists of document that have been received and reviewed are
presented in Appendix A.
DWDTS Hull and Mooring Configuration
Hull Dimensions
Water depth (ft) 8,000
Draft (ft) 145
Main column c-c distance (ft) 236
Main column width (ft) 72
Column height (ft) 215
Pontoon height (ft) 35
Pontoon width (ft) 67
Load Balance
Topside weight (st) 34,600
Hull weight (with fluid) (st) 46,404
Riser loads (st) 17,740
Mooring loads (st) 4,137
Ballast water (st) 40,906
Total platform displacement (st) 143,787
Mooring
Number of mooring lines 16
Chain size/diameter (in) 6.0
Polyester rope size/diameter (in) 10.75
Table 1-1 Key Design Data
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page 8
1.3 Applicable Rules, Regulations and Standards
The assessment has been carried out with respect to the requested class notations as follows:
OI Column-stabilized Drilling and Production Unit, POSMOOR
The applicable rules are given in below offshore service specifications and the Design Basis established for
the project:
• DNV-OSS-101 Rules for Classification of Offshore Drilling and Support Units, October 2012 edition
• DNV-OSS-102 Rules for Classification of Floating Production, Storage and Loading Units, October
2012 edition
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page 9
2 INTRODUCTION
The AiP review has been based upon assessment of the overall feasibility of the concept, focusing on
identified critical elements for this concept. The Approval in Principal is mostly based on document review;
where some limited independent analysis had been performed, when found necessary.
The following engineering disciplines have been evaluated:
• Global performance
• Mooring
• Production riser system
• Floating stability
• Structure
• Marine systems
• Safety systems
• E&I systems
• Production systems
• Geotechnical
• Construction, Transportation and Installation
• Operation
Document review was followed up by extensive discussions and meetings to clarify the questions/concerns
raised by DNV GL. These comments are attached in Appendix C.
The system design is still very preliminary and lacks specific design details. Some important safety design
principles had been discussed but they are similar to what has been applied to existing production units.
Assuming all systems are properly designed following applicable design standards, there should not be any
unique challenge in this concept that will prevent the design from being feasible. Preliminary safety related
comments have been provided to KFD as advice based on review of the general arrangement drawings.
All comments have been discussed and clarified; some additional engineering work was performed by KFD to
address the concerns raised. All critical comments have been resolved. Some comments still remain open.
These are in the nature of documentation or further engineering, not considered as show-stoppers to the
feasibility of the concept.
All critical issues/areas of concerns are registered in the Conceptual HAZID matrix in Appendix B. Such have
been further discussed at various workshops including the final workshop, additional concerns and
comments raised by subject matter specialists were registered and followed up after the workshop.
The ‘Initial risk ranking’ was assessed by DNV GL based on the likelihood of a failure and consequence of the
failure before all the design documents were thoroughly reviewed and clarified. The ‘Final risk ranking’ was
assessed by DNV GL after thoroughly reviewing all design documents and going through
discussions/clarifications/workshops, reviewing additional engineering work that were carried out and
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page 10
therefore achieve better understanding of the design concept. The likelihood of failure has been reduced in
some cases; consequence of failure mostly remains the same unless design changes have been made or
mitigations are implemented to lower the consequences. Reference is made to the definition in the
Conceptual HAZID Matrix in Appendix B. As can been seen in the Conceptual HAZID matrix, all high risk
items have been addressed; remaining items are mostly at low risk with a few at medium risk level. Further
actions are suggested for the items identified with medium risks. Other low risk items will still need to
properly follow relevant classification rules, statutory requirements, and other international
standards/practice for design, construction, installation, and operation etc. like any other design. All critical
elements identified for this concept before the beginning of the project have been fully addressed (i.e.
Technology Qualification of the riser tensioner system, VIM, comprehensive engineering work and
documentation, e.g. airgap and structural design). Details are presented in Appendix B.
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com Page 11
3 CONCLUSIONS AND WAY FORWARD
As shown in the conceptual HAZID matrix, all critical elements of this design concept have been properly
addressed. There are no remaining issues that will prevent the concept from being feasible. Provided that all
comments/concerns raised will be addressed properly at a later design stage and the design properly follows
recognized design standards, classification rules and statutory requirements, the concept should be feasible
to be further developed into projects.
Most of the items registered in the conceptual HAZID matrix are considered as low risk assuming that proper
design will be carried out following applicable classification rules, statutory requirements and other
international standards.
A couple of items ranked as medium risk require additional attention at project phase:
− Compression in lower part of riser (potentially up to 3000’ of riser under compression during the worst
of 1000-year wave cycle, with 680 kips at the lowest riser joint). KFD provided calculation to
demonstrate there is no buckling of riser joint under such compression; such should be validated with
more advanced analysis at the later design stage. Alternatively, mitigations have been considered. As
such, the compression is not considered to impact the feasibility of the design.
KFD Mitigations:
1. Increase top tension from 1.3 to 1.5. Such can be done for storm condition only - to be included in
operational procedure. However riser strength, tensioner capacity, and payload capacity of the unit
will need to be checked.
2. Optimize of the design to reduce heave RAO.
3. Adjust with initial position of tensioner to balance down stroke and up stroke.
4. Increase capacity of tensioners to accommodate higher strokes.
− The supporting structure for the riser tensioning system - further engineering work is required to
develop the details to withstand high impact load due to bottom out/top up condition.
− SIMOP (simultaneous operation of drilling and production) should be further studied including
consideration of tensioner system installation at offshore and focus on additional risks comparing to TLPs
/ spars.
− Sensitivity to wave periods: current design is based on single seastates as defined in API 2INT-MET.
Variations of period or contour seastates should be evaluated at later design stage.
− Airgap - Negative airgap (-1' to -12') have been concluded for some part of deck bottom under 1000-
year hurricane. This is acceptable provided that wave slamming is properly accounted for in the design.
Structure and risers (anything below cellar deck) should be designed for wave impact under 1000-year
wave.
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com A-1
APPENDIX A
Drawing List
Drawing No. Rev. DNV
GL No. Title
NA 9 Preliminary VIM test program
RPS-KFD-SP-ZZZ-00002 B 8 HULL VIM MODEL TEST SPECIFICATION
RPS-KFD-RP-ZZZ-0001 A 7 DRY TREE SEMI CONCEPTUAL DESIGN REPORT
1045131-KFD-N-XG-0001 A 1 SEMI-SUBMERSIBLE EAST ELEVATION LOOKING
WEST
1045131-KFD-N-XG-0002 A 2 SEMI-SUBMERSIBLE SOUTH ELEVATION LOOKING
NORTH
1045131-KFD-N-XG-0003 A 3 SEMI-SUBMERSIBLE MAIN STRUCTURE /
SCANTLING COLUMN DECK PLANS - SHEET 1
1045131-KFD-N-XG-0004 A 4 SEMI-SUBMERSIBLE MAIN STRUCTURE /
SCANTLING NODE BOTTOM PLATE PLAN
1045131-KFD-N-XG-0005 A 5 SEMI-SUBMERSIBLE MAIN STRUCTURE /
SCANTLING RING FRAMES - COLUMNS
1045131-KFD-N-XG-0006 A 6 SEMI-SUBMERSIBLE MAIN STRUCTURE /
SCANTLING RING FRAMES - NODES & PONTOONS
Action at later Design Stage Additional Follow-up 4/10/2014 Session
Later design1 Global Performance
1.1 Rigid Body Motion
Somewhat different range of motions from traditional semi
Excessive motions and excessive riser responses
Md O M L 1. KFD performed sensitivity study of heave RAO wrt different tensioner stiffness. Heave amplitude increases by about 4.5%, min airgap increase about 7.5% in 1000-yr hurricane if the tensioner stiffness change from 15 kip/ft to 25 kips/ft (a 67% increase), which slightly increases the corresponding maximum von Mises stress on the riser.2. KFD documentated that 0 and 45are most critical ones in terms of offset, heave and heel, which are the governing parameters for the riser performance.3. The total heave damping ratio is about 2% of critical damping and Cd = 4 for vertical direction at 100-yr and 1000-yr hurricane conditions, results calibrated against model test results.
OMNI direction considered for current, wind, waves - should consider additional cases (eg. no wind case with max wave) in order to not take advantge of offset for tensioner stroke
1.2 VIM Prone to VIM Potential risers/mooring system failure due to movement outside their design limits
Md S M L Model Test conducted and witnessed by DNV. Results look good. Both with (2 different heights) and without strakes on columns are tested.
1.3 Airgap Required to meet the airgap design criteria: 5' under100 year and 0' under 1000 year
Structural failure due to wave impact loads in 1000 year condition.
Mj O H M Structure / risers (anything below cellar deck) to be designed for wave impact under 1000yr wave.
Negative airgap -1' to -12'. Wave slamming force has been considered in structural design for both Morrison members and stiffened shell plates. DNV independent analysis concluded similar results.
To avoid negative airgap, deck box needs to be increased by 10 - 15 ft. For Morrison members on deckbox such as the dropdown structure and wellbay, particle velocity of 15m/s is assumed with Cs factor to be 5.5. For stiffened shell, both local slamming and global slamming are considered. At the conceptual design stage, the slamming pressures are selected from previous similar projects. Local slamming pressure used to check plate and stiffener is 450KN/m^2 and the global slamming pressure used to check girders is 255KN/m^2. Maximum vertical extent of slamming is assumed to be 2.6m.
1.4 Sensitivity to deckloads
Flexibility on the limit of deck loads and different throughput: could be more vulnerable than a conventional semi?
Potential resizing Mn S L L KFD has done some sensitivity study on varying the topside weight from 35,000 st to 40,000 st or even 50,000 st while maintaining the same hull draft. For different deck loads, slight change of column and pontoon size provide more buoyancy. The heave natural periods of the different cases remains around 20s. Thus, the heave motion is expected to be similar.
Stability will be effected by increasing deck load therefore sizing of columns and pontoons required to change; all other conditions (eg. Integration, transportation, installation) need to be assessed. Should not impact the concept but may result in reconfiguation.
Sensitivity to riser payloads
125ksi used for inner and outer riser
can be covered in design phase
High strength steel may need to be utilized for keel joint or redesign the keel joint;
Kvaerner Dry Tree Semi Concept
Comments/NotesID Critical Issues Concerns Failure mode / Consequence
Initial risk rankingFinal risk rank-ingCons. Likeli-
hoodRisk Rank
Action at later Design Stage Additional Follow-up 4/10/2014 Session
Later design1 Global Performance
Comments/NotesID Critical Issues Concerns Failure mode / Consequence
Initial risk rankingFinal risk rank-ingCons. Likeli-
hoodRisk Rank
1.5 Sensitivity to riser tensioner stiffness
Has different number of riser cases been fully considered in design?
Excessive motions due to different riser vertical restoring
Md O M L Initial risers and all-risers cases are documented.
1.6 Validity of model tests
Model the model verification to validate scaling from model test results to design - possible truncation effects, accurate damping level etc.
Inaccurate motions and responses due to incorrect model test/analytical results
Md O M L Model correlation report included all critical elements for the comparison and indicated that the analytical results are reliable.
KFD states:The mooring and risers were truncated due to the limit of water depth in the wave basin, but they were modelled with the same stiffness as the un-truncated ones. The same with the lumped riser. The lumped riser stiffness equals to the total stiffness of three risers. As long as the mooring and riser stiffness are the same, the floater motion will be similar. These methods are commonly used in wave basin model test and accepted by the industry. The truncated model under-estimated the damping due to shorter length, which means the model test results are conservative. When we do the analytical correlation, we used un-truncated mooring and risers. And each riser is modelled individually. The damping ratio in the analytical model is smaller compared to the model test (as shown in the correlation report), which means we are even more conservative. The correlated motion results are consistent with the model test results.
In addition, based on field measurement results, it is generally believed that our analytical simulation with
1.7 3rd party independent verification /analysis
Lack of validation of the lower (fatigue) seastates since model test only validates the extreme (high) seastate
Inaccurate motions and responses due to incorrect analysis results
Md O M L Fatigue including single event (also considering keel joint) needs to be further evaluated
10yr, 100yr, 1000yr were validated by model tested. DNV GL did independent strength verification on Riser analysis (1000yr).
1.8 Accidental conditions
Higher tensioner strokes due to compartment flooding
Riser and tensioner failure
Mj S M L The tensioner stroke for 10-yr winter storm with 1-compartment damage (10-yr WS TDM) is much smaller compared to 100-yr Hurricane intact case.The resulting riser stress is much smaller compared to 100-yr Hurricane case. With the same allowable stress, the utilisation for 10-yr WS TDM is much smaller than the 100-yr Hurricane case. Therefore,10-yr WS TDM is not the governing case for riser design.
Action at later Design Stage Additional Follow-up 4/10/2014 Session
Later design1 Global Performance
Comments/NotesID Critical Issues Concerns Failure mode / Consequence
Initial risk rankingFinal risk rank-ingCons. Likeli-
hoodRisk Rank
1.9 Sensitivity to design wave periods
This concept is more sensitive to selection of design wave periods than wet tree Semis. Care should be taken on how to handle the above in design. Robustness need to be demonstrated.
Excessive motions and riser responses due to wave excitation
Md O M L Sensitivity to wave periods to be - contour line seastates
100yr and 1000yr hurricane based on single seastates as defined by API-2INT MET.
2 Mooring System
2.1 Fiber ropes and TTR
Higher loads on the riser systems due to changes in elasticity of fiber ropes due to long-term effects
Failure/overstress of riser system(s)
Mj S M L TTR is more sensitive to offset than SCR. In the design, mean offset is based on lower stiffness; Dynamic analysis is based on higher stiffness. Loop current may last a period of time, the long duration caused creeping should be considered - Proper installation by pre-stretching.
2.2 Accidental conditions
Higher riser strokes due to mooring line failure
Failure/overstress of riser system
Mj R M L 2-line damage case may be checked.
One line damaged analysed. Latest API-RP17B, recommends 2-line broken under 10yr as a robustness check for flexible pipe design.
2.3 Mooring fatigue Mooring system failure, especially top chain segment.
Failure/overstress of riser system
Mj S M L More detailed study
The mooring system fatigue analysis was carried out for all the components including the chain with a safety factor of 10. Sea state fatigue and VIM fatigue are all analysed. The results shown in the report are the combined fatigue life. The minimum fatigue life is 28 yrs.
3 Production Riser System
3.1 Riser Tensioner system
1. Higher Strokes (35'' under 100 yr and bottom out/top up under 1000 yr hurricane)
2. Tensioner get stuck
Damage to the piston, top plate of the tensioner and potential damage to deck structures.
Mj O H M More detailed design
- Tensioner bottom out/top up under 1000-year wave. Similar philosophy is used on Spar and other in-service FPU. - Bottom out supported by riser support structure, will not hit tensioner barrel. - Tensioner roller is conventional. Roller can withstand normal tear and wear under applicable design conditions. - TQ of riser tensioner completed.
Action at later Design Stage Additional Follow-up 4/10/2014 Session
Later design1 Global Performance
Comments/NotesID Critical Issues Concerns Failure mode / Consequence
Initial risk rankingFinal risk rank-ingCons. Likeli-
hoodRisk Rank
3.2 Riser Tensioner system
1. Interaction of various tensioners, are they fully independent? 2. Torsion of tensioner -any mechanism to prevent rotation?3. Eccentric loading-impact on synchronicity in case of one tensioner failure?
Damage to riser Mj S M L Proper design documentation
KFD states: Non-linearity of the tensioners is also accounted for (if there is any) in the design. However, due to using relative large volume of tensioner accumulators, there is almost no non-linearity for the proposed tensioner design. This has been verified by engineering analysis and model test verification.1. Each tensioner is fully independent from the others. A bigger wellbay spacing used in this Dry Tree Semi design will avoid interference of jumpers between adjacent risers.2. The centralizing system of the riser tensioner has been designed with the riser spool joint (tension joint) to resist any rotational motion of the riser and tensioner.3. When one cylinder was offline, a review of the upper and lower centralizer loads indicated that no significant change in loading took place, as verified during the model test. The geometry of the five cylinders around the load ring was sufficient to share the slightly eccentric loading on the riser and not to affect the tensioner performance and loading on the centralizers.
3.3 Riser and riser tensioner system
Exposed to direct wave loading (comp. to spar)
Riser damage or failure
Md S M L Detailed riser tensioner design
The RAM style riser tensioner head and rod are located at an elevation without any wave impact even at 1000-yr hurricane condition. The riser tensioner barrel with a wall thickness 1.5 inch is designed to withstand the expected wave slamming.Note that the riser tensioner arrangement on the DWDTS will be similar or better comparing to a TLP riser tensioner arrangement.
3.4 Riser interference Evaluate possible riser/riser interference
Failure of riser system & strakes
Mj S M L Further engineering and documentation.
No difference from other TTR design This will impact the top tension factor (1.3 assumed currently)
Action at later Design Stage Additional Follow-up 4/10/2014 Session
Later design1 Global Performance
Comments/NotesID Critical Issues Concerns Failure mode / Consequence
Initial risk rankingFinal risk rank-ingCons. Likeli-
hoodRisk Rank
3.5 Loads on riser 1. compression in riser under 1000year/top up case.
2. Accuracy of the riser evaluation that should account for the presence of columns.
Buckling of risers; potential fatigue of risers due to higher stress range
Mj O H M More advanced analysis to investigate impact of compressive loads in riser or mitigations to be implemented.
1. compression in lower part of riser (680kips max tension; potentially up to 3000' of riser under compression during part of 1000-year wave cycle)2. Without the protection frame, the loads on risers are similar to TLP risers. Offbody kinematics due to the disturbed wave should be properly captured.
KFD Mitigations:1. Increase top tension from 1.3 to 1.5. Such can be done for storm condition only - to be included in operational procedure. Howevera) check riser strengthb) check tensioner capacityc) check payload capacity of the unit - 12x250kips increase2. Re-configuration of the design to reduce heave RAO.3. Adjust with initial position of tensioner to balance down stroke and up stroke.4. Increase capacity of tensioners to accomodate higher strokes.
3.6 Damping qualification/stick-slip simulations (keel guide)
Accurate evaluation of damping and riser responses for TTR design (stick/slip effects)
Overstress of the risers/components.
Mj S M L Since the floating system displacement is significantly larger than the friction force at riser keel joint/guide, it is not expected that the friction force will have major impact on global motion and riser performance as validated during wave basin model test.
3.7 Access to tensioner system
Access for Operation, maintainance, Repair of the riser system
Higher downtime/ cost due to SIMOPS
Mn S L L KFD to review the IMR plan wrt longer strokes, production vs. drilling
According to KFD: Regular, no new features, design life is > 20yrs.
3.8 Operation How can the tools go through keel guides
Higher downtime/cost Mn S L L The riser keel guide opening will be designed with sufficient diameter to run the riser components through. No special tool is required to run through the keel guide for TTRs. If there is a need to lower some other subsea equipment in the well bay area, there are two spare slots available
4 Floating Stability
4.1 Design standards Industry standards for conventional semi used. Operational limit on heeling angle?
stability problem Mj S M L Site-specific wind loads to be calculated.
USCG requires site-specific, min 100knots for production unit. 120knots for intact stability was used in design. TTR stiffness was not taken into account for stability analysis. 50knots was used for damage stability.
4.2 Pre-service stability
For deep draft semi, stability could be more critical during quay side integration and installation than in-place condition
stability problem Md S M L More detaild analysis and verification to be performed
Study report includes transition phase, stability has sufficient margin to meet the MODU rule requirment.
5 Structure
Action at later Design Stage Additional Follow-up 4/10/2014 Session
Later design1 Global Performance
Comments/NotesID Critical Issues Concerns Failure mode / Consequence
Initial risk rankingFinal risk rank-ingCons. Likeli-
hoodRisk Rank
5.1 Hull Deeper draft - higher hydrostatic pressure
Structural failure due to overstress
Mj S M L More detailed design documentation
Preliminary scantling check indicate most structure are in compliance with DNV Offshore codes.
5.2 Riser support structures/Keel guides
High impact load due to bottom out/top up.
Overstress in riser support structure and potential damage into the deck/hull
Md O M M 3rd party review of detailed calculation and structural connection design.
Supporting structure should properly designed to withstand the impact loads.
Kvaerner states: Dynamic impact load is at maximum with bottom out condition, however, this impact is a very quick impulse load and the riser can’t be stretched during this short period. Based on our calculation, the impact load is much less than our riser tensioning load at bottom out condition. Well bay structure and keel guide frame are not overstressed under our conservatively applied riser tensioning loads. We will do the detailed connection check at later design stage.
5.3 Topside/Deck Higher tensioner loads to support than conventional semi, ref. 3.3
Structural failure due to overloading
Md O M L Proper engineering design and documentation
6 Marine systems6.1 Ballast systems Sufficient ballast
capacity for in-place as well as integration/installation phase? Redundancy?
Mj S M L Capacity, redundancy and rate of filling as required for safe operation should be documented.
Active ballast only required when changing risers or topside. For semi, insallation period can be prolonged or one may use other pumps (e.g. fire pumps) for temp. ballasting function as long as they are blind off during operation. - Ballasting pumps needs to be self-priming.
6.2 Bilge systems Sufficient bilge capacity for in-place as well as integration/installation phase? Redundancy?
Mj S M L More detailed design for bilge and drainage system should be submitted. Independent bilge system, independent drainage system etc required.
7 Safety system7.1 Hazardous areas New haz. Area due to
hydrocarbon API RP505 shall be used.
Md S M L Proper design documentation
7.2 Lifesaving appliance
Mj S M L Proper design documentation
7.3 Escape Make sure escape routes is clear or well protected from well bay and other areas affected accidental loads.
Mj S M L Proper design documentation
7.4 fire/gas Mj S M L Proper design documentation
All these are important safety issues. But they are no different from existing production units. Assuming these safety aspects are properly designed following applicable design standards, likelihood of failure is low.
Action at later Design Stage Additional Follow-up 4/10/2014 Session
Later design1 Global Performance
Comments/NotesID Critical Issues Concerns Failure mode / Consequence
Initial risk rankingFinal risk rank-ingCons. Likeli-
hoodRisk Rank
7.5 ESD Mj S M L Proper design documentation
7.6 Well bay Potentially higher explosion pressure
Mj S M L Proper design documentation
blast wall required, impact on weight and CG? Wind profile.
8 E&I8.1 Regular deign
issuesMj S M L Proper design
documentation 9 SIMOP
9.1 Production/drilling New risks due to production/drilling together, probably bigger fire pump capacity.
Md S M M Further study Larger stroke, results in potential issues (e.g. more sagging in jumpers, riser clashing) of the jumpers, needs to be accounted for in design. . Space for jumpers from risers - responsibility/interface.
Additional study in the future:1. Include consideration of installation of tensioner system offshore2. Focus on additional risk comparing to TLPs / Spars
10 Geotechnical10.1 Seabed riser c-c
spacingswelling of seabed due to soil/temp. effects from production risers
Md R L L
11 Construction, Transportation and Installation11.1 Deep Draft Availability for
quayside integration, stability during installation,
Md O M L Further documentation
Preliminary documentation provided indicates sufficient margin.
11.2 Installation procedure
Any special requirements on ballast system due to installation process? Redundancy?
Md O M L Further documentation
DWDTS ballast system is no difference to any other conventional deep draft semi, many of which are still in operation now.
11.3 Transportation
12 Operation
Notes:
N: Not documentedY Sufficiently documented for this phase by analysis/model test or both P Partially documentedI IncidentalMn MinorMd ModerateMj MajorR RemoteS SeldomO OccasionalL Likely
Initial risk ranking: The risk ranking based on likelihood of a failure and consequence of the failure, which was assessed before reviewing design documents.
Final risk ranking: after reviewing design documents, discussion with the designer and the threat assessment, better understanding of the design concept and work performed was achieved and likelihood of failure has been reduced in some cases, consequency of failure remains the same. The final risk ranking is then evaluated.
Likely High
Occasional Medium
Seldom
Remote Low
Incidental Minor Moderate Major
Consequence of Failure
Like
lihoo
d of
Fai
lure
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-2
Ver-Com
no.: Description:
Category
*)
Status
**)
1
Please confirm that the model will be connected to a
tow carriage using a system of linear springs.
REPLY: Kvaerner confirms the use of linear springs on
the four mooring lines.
TQ C
2
Section 3.3 – Measurements calls for measurements
of mooring line tensions and drag and lift force on the
hull. Since in most of the tests, the model will be free
to move, it is not possible to directly measure the
forces acting on the hull. Rather, the forces can be
deduced by the reactions from the mooring line
tensions.
REPLY: Kvaerner is measuring the force reactions
from the model in the mooring lines.
A
3
How will the number of VIM oscillations be assured to
be sufficient to provide stable statistics of A/D? The
tow tank length is 168m. The natural sway period of
the model will be approximately 26s (Prototype sway
period is 212s. Model is Froude scaled. Time ~
sqrt(L).). Tow speeds are from 0.17 to 0.76 m/s. At
the highest tow speed (Vr=18), there will be less
than 8 resonant oscillations. With half the velocity (Vr
= 9) the number of oscillations will still only be 16. Is
this enough to get stable A/D statistics?
REPLY: Using the Froude scaled speed (VMS = VFS
/sqrt(60) scale 1:60) we will achieve model speeds
the range 0.053 – 0.307 m/s (Ur 18/ heading 45).
With a sway period of ~212sFS/27.3sMS this will
ensure about 19 cycles for Ur 18, which is sufficient
for a statistical analysis if the signal is periodically.
TQ C
DNV Project Title: DNV Project Job No:
Ultra-Deepwater Dry Tree Semi-submersible for Drilling and
Production in the Gulf of Mexico
PP055893
Document title: Prepared
by:
Date: Sign: Document. No.:
Hull VIM Model Test
Specification
RGOR 04/15/20
13
RPS-KFD-SP-ZZZ-00002
Verified by: Date: Sign: Document
rev.
VHAN 04/15/20
13
C (For
Approval)
VERIFICATION COMMENTS:
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-3
*) NC = Non-Conformance TQ=Technical Query A=Advice (need not be clarified) **) O = Open C = Closed (requires a reference) CN-(Closed with note)
DNV Project Title:
PRSEA Project 10121-4405-02
Document Title:
Hull VIM Model Test Correlation Analysis
Report
DNV Project No.:
PP055893
Document Number:
RPS-KFD-RP-ZZZ-0003, Rev A
Ver-Com
no.: Description:
Category
*)
Status
**)
1.
Effect of Strakes –Figure 3-8 shows that at a Ur of
4.5, the VIM for the small strake case is lower than
the large strake case. Please comment on this in the
report.
Kvaerner response: at Ur = 4.5, for the test case
with small strakes, VIM response is not locked-in yet,
the corresponding VIM amplitude may be lower than
that for the test case with bigger strakes, which may
be already or close to VIM lock-in. On the other
hand, we still investigate the strake effects on VIM
suppression and did not use any model test result
with strakes for our current Dry Tree Semi design.
Therefore, we suggest putting the test cases with
strakes aside at this stage.
DNV GL: Closed
TQ C
*) NC = Non-Conformance TQ=Technical Query A=Advice (need not be clarified) **) O = Open C = Closed (requires a reference) CN-(Closed with note)
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-4
DNV Project Title:
PRSEA Project 10121-4405-02
Document Title:
Dry Tree Semi Conceptual Design Report,
Deepwater Dry Tree Semi Development -
Stability Analysis Clarification
DNV Project No.:
PP055893
Document Number:
RPS-KFD-RP-ZZZ-0001 Rev. A
Ver-Com
no.: Description:
Category
*)
Status
**)
1.
The documents have been reviewed for compliance
with DNV-OS-C301 corresponding to the IMO MODU
Code Chapter 3. It is to be noted that no independent
calculations have been carried out by DNV GL in
connection with this review. It is highly recommended
that such be conducted in the later design phase.
KFD response: Noted.
TQ A
2.
It is observed that the IMO MODU CODE requirements
of Ch. 3.3.1.2, 3.4.3.2 and 3.4.4.2 related to
immersion of unprotected and weathertight openings
have not been documented. It is not clear whether
openings have been accounted for in the calculations.
KFD response: The CODE in Ch 3.3.1.2 has been
considered in the stability calculation as shown on Page
11 of Kvaerner’s “Deepwater Dry Tree Semi
Development - Stability Analysis” (dated December 19,
2013). The criterion that area ratio should be larger
than 1.3 is consistent with this code. For Code in Ch
3.4.3.3 and 3.4.4.2 regarding the watertight and
weathertight openings (such as chain lock and
ventilation pile openings), these are considered during
design and analysis of the DWDTS. In general, we
design the DWDTS stability as we designed and
delivered other Semi-submersible projects complied
with all applicable regulatory codes and requirements.
DNVGL: It is understood that the GZ curve will not be
terminated by any unprotected openings in the
relevant calculation range, and no weathertight
opening will be submerged prior to the first intercept of
the GZ curve and the wind heeling moment curve.
TQ CN
3. It is observed that a wind speed of 122 knots has been
applied for the In-place Severe Storm Condition. TQ A
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-5
Ver-Com
no.: Description:
Category
*)
Status
**)
4.
It is not clear to us why the Hull light weight and
Topside weight are different in the loading conditions
presented on page 10 of the Stability Analysis. It is
also observed that the VCG of the In-shore Tow
Condition is different in the two documents.
KFD response: In this study, we used the hull weight
during topside Integration for the In-shore Tow
stability analysis. Practically, the same weight condition
for both In-shore Tow and Wet Tow should be checked.
If we adjust the hull weight to be consistent for both
In-shore Tow and Wet Tow cases, the center of gravity
will be increased slightly. Thus, the AVCG margin and
GM values will be slightly reduced as shown in the table
below. However, since the DWDTS was designed to
float on the pontoon elevation with sufficient AVCG
margin during In-shore Tow, after adjustment of the
hull weight for In-shore Tow condition the DWDTS still
satisfies applicable requirements.
VCG (from
keel) AVCG Margin GM
(ft) (ft) (ft)
In-shore Tow 140.21 42.50 183.31
Transitioning 134.16 6.96 6.30
There is a typo for the VCG of the In-shore Tow
condition in the conceptual study report. This will be
corrected for the final version of the conceptual study
report.
DNVGL: Please update and clarify in the next revision.
TQ CN
5.
On page 11(Stability Analysis Clarification) it is
observed that the Governing Criteria for the Transition
is GM>0.164. Kindly be informed that a GM of no less
than 0.3 m/ 1 ft should be considered for any
transitory conditions.
KFD response: There are no specific requirements on
GM values, other than positive, on either IMO MODU
Code or DNV-OS-C301. The GM>0.164 ft criterion is
from USCG CFR46 Ch174.040: “Each unit must be
designed to have at least 50mm of positive metacentric
height in the upright equilibrium position”. We
appreciate your suggestion on the GM values.
TQ C
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-6
Ver-Com
no.: Description:
Category
*)
Status
**)
Practically, we design the DWDTS with a target of GM
> 3ft values at all conditions.
6.
It is observed that two compartments flooding has
been accounted for which is beyond the minimum IMO
MODU Code requirement.
TQ A
7.
It is observed that In-shore Tow has been checked for
70 knots wind speed and no damage stability.
KFD response: The In-shore Tow is considered as a
short period temporary condition with specific
restriction to avoid any damage of the hull
compartments. In the IMO and DNV rules, there are no
specific requirements for the damage stability on
temporary conditions. Therefore, the damage stability for In-shore Tow is not considered for this study.
DNVGL: Kindly note that we in general consider any
kind of towing as transit conditions while temporary
conditions are limited to transient conditions during
change of draught, ref. DNV-OS-C301 Ch. 1 Sec. 1
[4.2.19].red for this study. This can be further
discussed and resolved in the next phase.
TQ CN
8.
It is not clear whether your criterion “Area Ratio > 2.0”
presented on page 12 is the criteria of IMO MODU Code
3.4.3.3.
KFD response: This criterion should have been stated
as “Moment ratio > 2.0”, which is based on IMO MODU
code 3.4.3.3 “… the righting moment curve should
reach a value of at least twice the wind heeling
moment curve…” We will update it accordingly.
DNVGL: Please update in the next phase.
TQ CN
*) NC = Non-Conformance TQ=Technical Query A=Advice (need not be clarified) **) O = Open C = Closed (requires a reference) CN-(Closed with note)
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-7
DNV Project Title:
PRSEA Project 10121-4405-02
Document Title:
Dry Tree Semi Conceptual Design Report
DNV Project No.:
PP055893
Document Number:
RPS-KFD-RP-ZZZ-0001
Ver-Com
no.: Description:
Category
*)
Status
**)
1.
Section 4
To satisfy the requirements of AiP, the following
safety aspects should be addressed:
- General Layout and topside arrangement
- Hazardous Area Plan
- Area Safety Chart
- F & G Design Philosophy
- ESD Design Philosophy
- Ventilation design Philosophy
- Ventilation Ducting Design Philosophy
- Active/passive fire protection design
Philosophy
- Power management philosophy
- Lifesaving arrangement (evacuation study)
A high level Lifesaving arrangement is indicated in
Appendix A, which appears to be not in line with the
recognized standards, in case south side is impaired.
Due to simultaneous operation of drilling and production,
deck spaces appear to be limited and congested.
Therefore, the above safety philosophy document shall
be in place prior to further project development.
KFD response: With respect to the life safety
arrangement in the event that the south side is
impaired, our intention is to have alternative survival
craft located on the north end of the facility (either on
the north face of the facility or along the east or west
sides of that face). The current configuration is intended
to be in-line with items identified in the study equipment
list even though we have identified the need for
additional craft. Due to the layout requirements for
safety in the next phase of development additional
survival craft will be identified and located as required to
provide for the safety arrangement (in the north sections
of the facility).
With respect to deck congestion due to the SIMOPS
TQ O
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-8
Ver-Com
no.: Description:
Category
*)
Status
**)
functions of drilling and production - a more detailed
evaluation of SIMOPS challenges and mitigation has
been identified and is planned for the DWDTS concept.
However, in the interim we do not see the congestion
level as significantly different from that of other floating
concepts that also employ full drilling facilities. In
general we have sought to provide maximum
segregation between the processing facilities on the
north section of the platform and the drilling support
functions to the south area of the facility. While
development is still preliminary we envision fire/blast
walls segregating the manifold from the processing area
to the north and from the wellbay to the south.
The current DWDTS design is still at the concept level.
The detailed listing of safety aspects that have been
identified (lifesaving arrangement, area safety chart,
hazardous area plan, F&G design philosophy, ESD design
philosophy, active/passive fire protection design
philosophy, etc.) will all be addressed in detail in the
next phases of the concept development. We agree that
all of these design philosophies should be established
and reviewed in more detail. The project has just not yet
reached that phase of design development.
It should be noted, with respect to ventilation design
philosophy (as well as ventilation ducting design
philosophy) that a key feature of the DWDTS design is
the open wellbay area, which provides for a high level of
natural ventilation across the width of the facility.
DNVGL: Comments to be followed up in the next phase.
System design is still preliminary with limited
information. Comments are given as advice at this stage,
not considered as barriers to feasibility.
2.
Section 4.6
With higher vertical motions for a dry tree semi the
susceptibility to obtain SCR compression in the TD area
has to be controlled and checked out. What has been
done so far?
KFD response: SCR compression is not included in the
scope of work of this conceptual study, but it should be
noted that SCR were considered as a field proven
technology and are being used for field development
with a deep draft semi. Furthermore, to satisfy TTR
performance, the DWDTS heave motion has been
TQ C
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-9
Ver-Com
no.: Description:
Category
*)
Status
**)
reduced noticeably and is smaller than that of a typical
deep draft semi. Therefore, this should not be an issue.
3.
Section 5.1 Description, Page 37
It is noted that the design of the tensioner system is (or
has been) conducted by MHD Offshore Group. Design
documentation of the MHD Offshore group requires to be
reviewed.
KFD response: Due to concern of the riser tensioner IP
design, detail tensioner design information will not be
provided in the public domain, but has been provided to
DNV TQ group for technology qualification process.
DNVGL: refer to TQ report.
TQ CN
4.
Section 5.2 Tensioner Configuration, Page 38
“An additional benefit of having 6 cylinders in a tensioner
is the increase in system redundancy if a cylinder fails.
Since an instantaneous failure of one cylinder only
reduces the riser tensioning capacity by 16.6 % as
opposed to 25% in a 4-cylinder system.”
The proposed design appears to require balancing by de-
activating another tensioner in case of loss of a
tensioner. Therefore, using a 4-tensioner system does
not seem to satisfy the redundancy requirement. Hence,
a minimum of six tensioners in the system is not so
much a benefit but a necessity. Please clarify.
KFD response: If there are only 4 cylinders, when one
cylinder fails, the opposite one will also be de-activated.
Therefore, for 4-cylinder tensioner system, the capacity
will reduce by 50%. While for 6-cylinder tensioner
system, the capacity will only reduce by 16.6% when
one cylinder fails, or 25% when one cylinder fails and
the opposite cylinder is also de-activated. It is
extremely important to support a heavy riser for ultra-
deep water development.
DNV GL: Comment closed with the note that the current
6-cylinder tensioner design is the minimum requirement
for providing system redundancy in case of the loss of a
single cylinder.
TQ CN
5.
Section 5.2 Tensioner Configuration, Page 38
“The tensioner system is designed to have sufficient
capacity after one cylinder failing and allow for manually
TQ CN
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-10
Ver-Com
no.: Description:
Category
*)
Status
**)
taking one cylinder (opposite to the failed cylinder)
offline, but increasing the pressure in the remaining 4
cylinders to continuously operate at the required null
riser tension..”
Is the stated pressure increase in the remaining
tensioners carried out manually? Or does the system
dynamically adjust for the tensioner loss by tensioner
stroke? If the adjustment is performed manually as
seems to be the case, how quickly should the
adjustment take place? What happens if there is any
delay in performing pressure adjustment?
KFD response: In operating condition, it will be manually
turned off to balance the system. In Hurricane condition,
if one cylinder down, the remaining cylinders will
continue work during the storm condition, which is the
base case for tensioner design as other dry tree systems
in service. This design condition has been tested during
the model test for this project.
DNV GL: Comment closed with the note that the
required response time in manually de-activating a
cylinder (in case the opposite cylinder fails) and also
adjusting the pressure in the remaining cylinders need to
be determined and documented in next design phase.
6.
Section 5.2 Tensioner Configuration, Page 38
“The tensioner system is designed to have sufficient
capacity after one cylinder failing and allow for manually
taking one cylinder (opposite to the failed cylinder)
offline, but increasing the pressure in the remaining 4
cylinders to continuously operate at the required null
riser tension..”
Is the de-activation of the opposite cylinder (after loss of
a tensioner) an immediate requirement? What happens
to the tensioner system if there is a delay in de-
activation or while the de-activation is carried out?
KFD response: In operating condition, the opposite
cylinder will be manually de-activated. In Hurricane
condition, if one cylinder down, the remaining cylinders
will continue work. Both cases have been tested in the
model test for this project. The test results showed no
significant change of side load on the upper and lower
centralizers for both cases attributed to proper design of
the riser tensioner components and support structure.
DNV GL: Comment closed with re-emphasizing the note
to TQ #5.
TQ CN
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-11
Ver-Com
no.: Description:
Category
*)
Status
**)
Establishing immediacy (or otherwise) of manual re-
adjustment of pressure in the remaining cylinders needs
to be evaluated at next design phase. In other words,
‘fail-safe’ nature of a cylinder and the adequacy of
mitigation against such a failure will need to be
established.
7.
Section 5.3 Primary Components, Page 38
It is recommended to include a schematic of a single
tensioner in this section of the document identifying all
the components.
KFD response: Due to concern of the riser tensioner IP
design, this information will not be provided in the public
domain, but has been provided to DNV TQ group for
technology qualification process.
DNVGL: refer to TQ report.
TQ CN
8.
Section 5.3 Primary Components, Page 38
It is recommended to include a brief description of the
functionality of the identified components.
KFD response: Due to concern of the riser tensioner IP
design, this will not be provided in the public domain,
but has been provided to DNV TQ group for technology
qualification process.
DNVGL: refer to TQ report.
TQ CN
9.
Section 5.3 Primary Components, Page 38
How is the sealing between the cylinder and the rod for a
tensioner accomplished?
KFD response: Due to concern of the riser tensioner IP
design, this information will not be provided in the public
domain, but has been provided to DNV TQ group for
technology qualification process.
DNVGL: refer to TQ report.
TQ CN
10.
Section 5.4 Layout, Page 39
Do the tensioner systems (12 in figure 5.2 arrangement)
act independent of each other? What, if any, is the
impact of failure, malfunction, or tensioner loss in any
tensioner system on the overall configuration?
KFD response: Yes, each tensioner system works
independently from each other. Failure or malfunction of
TQ CN
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-12
Ver-Com
no.: Description:
Category
*)
Status
**)
one tensioner system will not affect other tensioner
systems.
DNVGL: Further documentation is expected for next
phase.
11.
Section 6.1
The report has provided only the end results without
providing any documentation of methodologies,
calculations and assumptions etc. Please provide such.
KFD response: The detailed description of the stability
analysis will be provided in a separate document.
DNVGL: closed based on further documentation
received.
TQ C
12.
Section 6.2.3.
MOORING SYSTEM PROPERTIES – “The minimum breaking
load (MBL) of mooring chain has taken into account for
annual corrosion allowance of 0.4 mm.” Assume it is
0.4mm/year. Please clarify.
KFD response: Yes, it is assumed the chain corrosion is
0.4mm/year based on API 2SK and design basis.
TQ C
13.
Section 6.2.5.
MOORING SYSTEM FATIGUE ANALYSIS – “The combined
spectrum analysis method with dual narrow-banded
correction factor has been used for the wind/wave
induced fatigue analysis.” Should cite reference for the
method used.
KFD response: This method is based on API-RP-2SK.
Citation will be added in the report: “The combined
spectrum analysis method with dual narrow-banded
correction factor has been used for the wind/wave
induced fatigue analysis. [1]”
TQ C
14.
Section 6.2.5.
MOORING SYSTEM FATIGUE ANALYSIS – “VIM fatigue analysis
is based on the correlated results of the DWDTS VIM
model test for this project.” No details given on VIM
responses or how VIM induced fatigue has been
determined. Please clarify how much of the fatigue
damage is due to VIM. Also, what basis is used for
representing the current bins?
TQ C
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-13
Ver-Com
no.: Description:
Category
*)
Status
**)
KFD response: The co-related VIM response design
curves are listed in Figure 10-5 of the report. Max
tension variation is determined by moving the vessel
transversally according to the proposed VIM design
curves.
The detailed data of VIM fatigue damage will be provided
in a separate file.
Met-ocean data for calculating VIM is not available in the
design basis for this project. The occurrence frequency
of eddy current and the corresponding amplitude are
based on a typical metocean data in the central region of
GoM as used in the DeepStar project. The total
percentage of eddy current occurrence is approximate
27% in a year. At this stage, the selected metocean
conditions of eddy current should give a reasonable
foundation for the VIM fatigue calculation. The eddy
current metocean data include 23 bins. Each bin runs
for 24 directions (15 degrees apart).
DNVGL: acceptable for concept phase.Further study
based on site specific data in the actual project phase.
15.
Section 6.3.3.
RAO CALCULATION – The calculation of the heave response
is critical to the feasibility of this concept. There is no
discussion regarding the resonant heave performance,
such should be provided. For example, how is the low
heave peak RAO of 0.8 achieved? How is the viscous
damping modeled? If the viscous damping is significant,
then the heave RAO curves are seastate dependent and
should be presented for representative seastates.
KFD response: RAO reported in the conceptual study
report is the inverse of the time domain results for 100-
yr hurricane wave case. In the time domain motion
calculation, the viscous damping has been modeled as
nonlinear hydrodynamic drag through Morison model.
The drag coefficients have been correlated with the wave
basin model test results.
TQ C
16.
Section 6.3.4.
GLOBAL MOTION – The report should include all rigid body
motion responses of the, not just heave.
KFD response: The detailed motion response results will
be provided in an attachment.
TQ CN
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-14
Ver-Com
no.: Description:
Category
*)
Status
**)
DNVGL: To be included in updated report in the next
phase.
17.
Section 6.3.4.3
Air Gap – “An asymmetric factor is used to account for
non-linearity in the incoming waves.” Please clarify what
asymmetric factor was used? What is the basis?
KFD response: The use of asymmetric factor is based on
DNV-RP-C205. With consideration of previous project
experience, the recommended value 1.2 was used.
TQ C
18.
Section 6.2.5.2 & Table 6-7
Please specify what level of OPB effects has been
included in the fatigue estimates?
KFD response: In modern mooring fairlead design, the
fairlead can be rotated freely within a design range that
is in general larger than the maximum yaw angle, thus
OPB effects are negligible.
TQ C
19.
1. Section 8.2.1
Operating condition should be checked, because
allowable stress is lower (0.6*Fy).
KFD response: The interface structure is designed to
withstand the forces during riser tensioner bottom-out
and top-up under survival conditions. In the operating
condition, there are no bottom-out and top-up. The force
will be much smaller than the survival conditions.
Therefore, operating condition is not the governing case
at all.
DNVGL: Comment is referring to str. overall, not just
interface. Comment closed based on further discussion
with designer. Better documentation expected in the
next phase.
TQ CN
*) NC = Non-Conformance TQ=Technical Query A=Advice (need not be clarified)
**) O = Open C = Closed (requires a reference) CN-(Closed with note)
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-15
DNV Project Title: RPSEA Ultra-Deepwater Dry Tree System for Drilling and Production
in the Gulf of Mexico
Document Title:
Dry Tree Semi Conceptual Design Report by
Kvaerner Field Development Inc.
DNV Project No.:
PP055893
Document Number:
RPS-KFD-RP-ZZZ-0001
Ver-Com
no.:
Description: Category
*)
Status
**)
1. Weight of internal tubing inconsistent:
Table 3-4: 35.4 vs. Table 7-1: 33.7
Please clarify – will update.
33.7 is the old number in which the tubing is 5.5”OD and
0.65” Wall Thickness. Then we realized in the design
basis the wall thickness is 0.689”, which increases the
unit dry weight from 33.7 lb/ft to 35.4 lb/ft. So 35.4 is
the correct number. The number 33.7 in Table 7-1 should
be 35.4 and will be updated in the final version of the
study report.
DNV GL (11-14-2014): Comment closed per clarification
above. Please ensure the final version is updated
accordingly.
TQ C
2. Page 80
“Experience also indicates that riser fatigue performance
is not a concern for the proposed top tensioned risers.”
Please clarify the experience referred to herein. Is it from
the field or simply based on past design? From the
lessons learned in the field, a fatigue study along with a
thorough modal analysis of the TTRs is strongly
recommended.
Fatigue needs to be addressed at design stage, marine
growth should also be accounted for.
In a past project with top-tensioned risers, fatigue
analysis was performed on similar production riser and
the analysis results showed fatigue was not a concern.
In this dry tree semi design, tensioner only bottoms out
or tops up in 1000 hurricane survival conditions, which
TQ CN
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-16
Ver-Com
no.:
Description: Category
*)
Status
**)
happens at a very low probability. Most of the time, the
top tension varies in a small range because the long
stroke tensioner has a low stiffness. Under this condition,
the stress range in the riser will be small, which is similar
to the top-tensioned risers supported through buoyancy
cans. Therefore we state that fatigue is not a concern for
the top tensioned riser in our design.
DNV GL (11-14-2014): The explanation provided means
the stress range for ‘most of the time’ is ‘probably’ small.
Whilst the argument has its merits, it cannot be regarded
as a substitute for actual fatigue damage evaluation.
Comment will be closed upon receiving fatigue results.
This is expected to be documented at next design phase.
3. Has marine growth been considered? If not, please
explain why. Please also estimate the potential impact on
riser design.
The marine growth was not considered. First, marine
growth will affect slightly the hydrodynamic force and
increase the weight of the riser. But marine growth is
concentrated near the sea surface. The water depth in the
design is 8000 ft, which is much longer than the marine-
growth portion. A small portion of marine growth on the
riser is not expected to affect the riser global
performance significantly.
Secondly, for this ultra-deep water top-tensioned riser
with relative high riser pretension and stiffness, the effect
of marine growth on riser displacement and stress will not
be significant and could be considered at the project
detail design phase.
Third, marine growth build up can be controlled by
routine cleaning as needed, using anti-fouling materials,
etc.
So marine growth was not considered in the analysis for
this conceptual study.
DNV GL (11-14-2014): Appreciate the clarification.
However, the technical inquiry is not solely related to
weights and stresses which we agree would have limited
consequences. The issue of marine growth on material
TQ CN
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-17
Ver-Com
no.:
Description: Category
*)
Status
**)
integrity should also be addressed – whether marine
growth will impact material characteristics. Such can be
addressed at next design phase.
4. As per API RP 2RD
Several tensioner failure conditions should generally be
examined, including one where there is reduced capacity
and one where there is total collapse of the tensioning
system.
Tensioner failure analysis is recommended.
Under 1000year condition, when the tensioner tops up,
lower part of the riser is under compression – is that a
concern? DNV will discuss internally to investigate the
relevant design criteria.
Under the extreme conditions, loss of one cylinder will not
cause a problem. In case one cylinder is damaged and
has lost its capacity, its opposite cylinder will be
deactivated. The remaining cylinders will be enhanced to
meet the working requirement.
This has been proved by tensioner model test.
Loss of one cylinder in survival conditions and the total
collapse of the tensioning system are not design criteria.
DNV GL (11-14-2014): Advisory comment. Appreciate the
explanation that there is redundancy in the number of
tensioners and two opposite tensioners can be de-
activated without any loss of performance.
A
5. Independent Analysis by DNV:
(See Appendix)
Please re-check the maximum stress in the inner casing
of the production riser in 1000-year hurricane event
(7.3.3.1 Governing Heel Case)
Stress on inner casing and tubing could be under-
estimated.
(1) To obtain the shared effective tensions for three
tubes is not straightforward. One assumption is that
these three tubes have the same axial strain. By
solving the following equations, one can get effective
TQ O
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-18
Ver-Com
no.:
Description: Category
*)
Status
**)
tensions and wall tensions for three tubes.
333333
222222
111111
eooiiw
eooiiw
eooiiw
TApApT
TApApT
TApApT
+−=+−=
+−=
( ) ( ) ( ) zwww
eeee
oioi
EA
T
EA
T
EA
T
TTTT
pppp
ε===
++===
3
3
2
2
1
1
321
3221,
where
Tw1, Tw2 and Tw3: wall tension of outer casing, inner
casing and tubing respectively;
p1i, p2i and p3i: internal pressure of outer casing,
inner casing and tubing respectively;
p1o, p2o and p3o: external pressure of outer casing,
inner casing and tubing respectively;
Te1, Te2 and Te3: effective tension of outer casing,
inner casing and tubing respectively;
A1i, A2i and A3i: internal cross section area of outer
casing, inner casing and tubing respectively;
A1o, A2o and A3o: external cross section area of
outer casing, inner casing and tubing respectively.
Te : effective tension of the production riser;
(EA)1, (EA)2 and (EA)3: axial stiffness of outer
casing, inner casing and tubing respectively;
z: axial strain of the production riser.
(2) The maximum effective tension is always at the load
ring position on the riser. It depends on the tensioner
stroke which depends on the vessel motion. The
maximum curvature also depends on the vessel
motion. In addition, it depends on the environmental
conditions like current.
5. Con DNV GL (11-14-2014): Appreciate the explanation.
However, the above does not address the specific
technical inquiry. We are not in agreement with the
argument advanced towards (what might be considered)
indeterminacy of load-sharing between casing strings.
The technical inquiry relates to a load case where the
DNV GL – Report No. 15U5O2I-10, Rev. 2 – www.dnvgl.com C-19
Ver-Com
no.:
Description: Category
*)
Status
**)
outer casing stresses from KFD and DNVGL analyses are
in agreement but there is noticeable variation between
the respective results on both inner casing and the
tubing. (See table 1-3 in the appendix). This discrepancy
and its implications should be explained. This is not
considered as a barrier to feasibility but should be
properly addressed at later design stage.
*) NC = Non-Conformance TQ=Technical Query A=Advice (need not be clarified) **) O = Open C = Closed (requires a reference) CN-(Closed with note)
About DNV GL Driven by our purpose of safeguarding life, property and the environment, DNV GL enables organizations to
advance the safety and sustainability of their business. We provide classification and technical assurance
along with software and independent expert advisory services to the maritime, oil and gas, and energy
industries. We also provide certification services to customers across a wide range of industries. Operating in
more than 100 countries, our 16,000 professionals are dedicated to helping our customers make the world
safer, smarter and greener.