AFRICAN DEVELOPMENT FUND
MOZAMBIQUE
EMERGENCY HUMANITARIAN RELIEF ASSISTANCE RELATED TO THE 2013 FLOODS DISASTER
PROJECT APPRAISAL REPORT
MZFO/OWAS/GECL
September 2013
Table of Contents
ACRONYMS ....................................................................................................................................................... i
PROJECT SIMPLIFIED LOGICAL FRAMEWORK ................................................................................................... ii
1 BACKGROUND AND JUSTIFICATION FOR EMERGENCY ASSISTANCE ........................................................ 1
1.1 BACKGROUND – FLOODS AND THE EMERGENCY CRISIS IN MOZAMBIQUE ................ 1
1.2 JUSTIFICATION FOR EMERGENCY ASSISTANCE ........................................................... 1
2 OVERVIEW OF THE APPEAL FOR EMERGENCY ASSISTANCE ..................................................................... 2
3 THE PROPOSED EMERGENCY ASSISTANCE OPERATION .......................................................................... 3
3.1 OBJECTIVES AND DESCRIPTION OF THE EMERGENCY ASSISTANCE............................ 3
3.2 COST AND SOURCE OF FINANCE ................................................................................... 3
3.3 IMPLEMENTATION ARRANGEMENTS AND SCHEDULE .................................................. 4
3.4 PROCUREMENT AND DISBURSEMENT ARRANGEMENTS ............................................... 4
3.5 REPORTING, SUPERVISION AND AUDITING ................................................................... 5
4 CONCLUSIONS, RECOMMENDATIONS AND CONDITIONS FOR DISBURSEMENT ...................................... 5
4.1 CONCLUSIONS AND RECOMMENDATIONS ..................................................................... 5
4.2 CONDITIONS FOR DISBURSEMENT ................................................................................ 5
ANNEX I – MAP
ANNEX II –GOVERNMENT EMERGENCY DECLARATION
ANNEX III- GOVERNMENT REQUEST
i
Abbreviations and Acronyms
ADB : African Development Bank
CBO : Community Based Organization
CCGC : Disaster Management Coordination Council
CENOE : National Operational Emergency Centre
DMA : Disaster Management Authority
DNA : National Directorate of Water
GACOR : Reconstruction Coordination Office at the INGC
GDP : Gross Domestic Product
GOM : Government of Mozambique
IA : Implementing Agency
IFRC : International Federation of the Red Cross
INAM : National Institute of Meteorology
INGC : National Institute of Disaster Management
LOA : Letter of Agreement
MZFO : Mozambique Field Office
SRF : Special Relief Fund
UN : United Nations
UNOCHA : United Nations Office for the Coordination of Humanitarian Affairs
Project Simplified Logical Framework Country and Project Name: Mozambique: Proposal for a Grant of USD 1 Million for Emergency Humanitarian Relief Assistance related to the 2013 Floods
Disaster
RESULTS CHAIN PERFORMANCE INDICATORS MEANS OF
VERIFICATION
RISK/MITIGATION MEASURES
Indicator Baseline Target
IMP
AC
T The number of most
vulnerable segment of
flood displaced
population is reduced.
Percentage of vulnerable
people in Gaza Province
classified as most
vulnerable
20% 15% Progress and Final
report, Financial Audits
and Field Supervision.
OU
TC
OM
ES
Livelihoods of flood
victims improved in Gaza
province
Number of direct beneficiaries
of the grant’s assistance.
N/A 28,000 Annual household
surveys.
Risk: Deviation from the predefined criteria
for the identification of the beneficiaries.
Mitigation: Bank and other partners to
dialogue with Government on its criteria for
defining vulnerable groups.
OU
TP
UT
S
a) Temporary shelters
erected;
b) Family tents available;
c) Tarpaulins provided
d) Rescue speed boat
a) Number of shelters
b) Number of tents
c) Number of tarpaulins
d) Number of speed boat
N/A
N/A
N/A
N/A
2000
1500
10000
1
IA reports Risk: Delivery of equipment/Kit may take a
long time.
Mitigation: Expedite procurement with
requests to suppliers already underway.
KEY ACTIVITIES
Erection of temporary relocation family tents and tarpaulins;
Procurement of shelter kits;
Procurement of a rescue speed boat to access flooded areas.
Inputs:
Emergency shelter kits : USD 80,000.
Family tents : USD 590,000.
Tarpaulins : USD 150,000.
Rescue speed boat : USD 160,000.
Financial Audit : USD 10,000
Operational costs : USD 10,000
1
1 BACKGROUND AND JUSTIFICATION FOR EMERGENCY ASSISTANCE
1.1 Background – Floods and the Emergency Crisis in Mozambique
1.1.1 Mozambique is located in a region cyclically threatened by extreme natural events like
floods, droughts, tropical cyclones, earthquakes, and disease epidemics. Records on natural
disasters show that over the 52 years period of 1956-2008, the country experienced 10 droughts, 20
floods, 13 tropical cyclones, 18 epidemics and 1 earthquake. Epidemics predominate during the
rainy season (October-March) with varying impacts. Focusing only on floods, that of the year 2000
was the worst in terms of its impacts, which left 700 people dead, and 650,000 people displaced.
1.1.2 More recently in January 2013, Mozambique was again devastated by heavy rains resulting
in the main rivers bursting their banks in the southern (Limpopo, Incomati, Inhanombe and Save)
and central (Zambezi, Pungoe and Buzi) regions. Due to the destructive impact of the floods on the
communities, the Government of Mozambique (GoM) declared an institutional Orange emergency1
alert on 12 January 2013, which was upgraded to a Red emergency
2 alert on 22 January 2013.
Maputo City, Gaza, Zambezia and Inhambane Provinces were the most affected by the floods,
where 113 people were killed and over 185,000 displaced. Cumulatively, more than 240,000 people
were affected by the floods. The most affected provinces were the southern province of Gaza which
saw 172,589 people temporarily displaced.
1.1.3 This proposal for emergency assistance for the victims of the 2013 Floods is justified as it
fulfills the three criteria required to qualify for Bank Group assistance in that: (i) the emergency
situation is of a scale which is clearly beyond the capacity of the Government of Mozambique to
handle alone; (ii) the proposed activities can be carried out expeditiously and effectively within the
required time frame; and (iii) the emergency relief assistance aims at restoring a degree of normalcy
in both the social and economic life of the affected populations as quickly as possible and addresses
corrective measures for future flood related disasters. The proposal is thus in compliance with the
provisions of the Revised Policy Guidelines and Procedures for Emergency Relief Assistance, and
General Regulations of the Special Relief Fund (ADB/BD/WP/2008/211/Rev.1)
1.2 Justification for Emergency Assistance
1.2.1 From 12 January, when the Orange Alert was declared by the GoM, to 19 April 2013, when
the red alert warning were lifted, the flooding situation wrecked massive damage to the town of
Chokwe in Gaza Province, due to soil saturation and flooding, arising from the damage to the dykes
from the tropical depression Dando in 2012, which had not been fully rehabilitated. Further
northwards, in the provinces of Inhambane, Manica, Sofala, and Zambezia, continuous rains also
left an estimated 20,000 people affected, damaged infrastructure and caused loss of 110,000
hectares of cultivated agricultural land.
1.2.2 The accumulated impact of successive floods, tropical storms and cyclones has increased the
vulnerability of the affected population and exhausted their coping mechanisms. Most of the
affected people, especially in rural areas were already suffering from extreme poverty and
deprivation before the disaster. The biggest impact of the disaster has been in shelter, much of
1 The orange alert means that there is imminent occurrence of an emergency and government sectors are called upon to intervene through their focal
points that should settle and work in National Operational Emergency Centre (CENOE).
2 The red alert means total activation of the National Operational Emergency Centre (CENOE) and of the National Civil Protection Unit
(UNAPROC) to coordinate search and rescue operations for people at risk, and to ensure more coordinated and effective harmonization of the
activities of the government’s various partners in humanitarian aid.
2
which was destroyed or significantly damaged, especially for those of the poorest segment of the
population, whose homes were made of locally available or traditional materials. With the
improvement to the floods situation, the focus of response interventions are on the resettlement of
displaced people from temporary accommodation centers, which has become the Government’s
priority, in order to incentivize the population to move away from the low lying areas which are
prone to floods.
1.2.3 The immediate response of the INGC (National Institute of Disaster Management), supported
by local and international relief agencies was the provision of temporary shelters for the displaced.
The crisis depleted the stocks of Emergency kits and Family tents, including the more than 10,000
additional units that were ferried in by the various humanitarian organizations. A process of plots
demarcation is ongoing in the floods-affected districts. In Gaza province, the Government plans to
demarcate, and allocate a total of 11,150 plots. The process has encountered severe challenges due
to a lack of basic household items necessary for the resettlement or home return materials for the
victims to rebuild their homes. The process of sheltering the displaced persons, under conditions of
safety and dignity would be facilitated through the provision of Family tents (16 m2), Tarpaulins
(4mx6m) and basic Shelter kits, which consists of simple survival tools of nails, hoe, spade, saw,
etc. Other goods to be acquired include one rescue speed boat for rescue and good distribution
operations.
2 OVERVIEW OF THE APPEAL FOR EMERGENCY ASSISTANCE
2.1.1 From the onset of the floods, the GoM took the leadership in coordinating the response, and in
mobilizing resources at its disposal as a response to the emergency in the floods devastated areas.
Nonetheless, resources available at the initial phase of the crisis were not sufficient to meet the needs
of the affected population; and on 30 January 2013 the GoM requested immediate assistance from
national and international humanitarian partners, in accordance with the National Contingency Plan
for Rain and Cyclone Season of 2012-2013.
2.1.2 Two separate appeals were launched by the Government (31 January 2013) and it’s supporting
International partners (30 April 2013). The initial Response and Recovery Proposal sought US$ 30.6
million to enable the International Community: United Nations agencies, non-governmental
organizations and the Societies of the Red Cross to support the GoM in addressing the needs of
150,000 flood-affected persons in Gaza Province for the period of six months. The proposal was based
on additional assessments done during the humanitarian phase; including information from the last
week of January 2013 and an initial early recovery strategy for assisting people recover and rebuild
their lives. As of 24 April 2013, a total of US$ 19 million was contributed by multi-lateral and
bilateral donors. However, only US$ 4.3 million was received to cover early recovery activities. The
second Early Recovery Strategy and appeal seeks US$ 11.7 million to enable the International
Community to support the GoM effort in addressing early recovery needs for 140,000 people. In this
regard, the GoM, on September 6th
, 2013, submitted to the Bank, a request for humanitarian
assistance.
3
3 THE PROPOSED EMERGENCY ASSISTANCE OPERATION
3.1 Objectives and Description of the Emergency Assistance
3.1.1 The objective of the proposed Bank Group Emergency Relief Assistance to the Government of
Mozambique is to contribute to the on-going efforts of the Government and other humanitarian
partners to mobilize resources for the interventions of the early recovery phase, whose needs have
been compiled per cluster, and an estimate of the budget per cluster. It is envisaged that heavy
rehabilitation works for community infrastructures like roads and other infrastructures will be
undertaken by the GoM technical ministries and development partners like the MDBs and other
bilateral/multilateral donors.
3.1.2 The Bank will contribute US$ 1 million in response to the appeal of the Government of
Mozambique channeled towards ameliorating the plight of the displaced persons from the low lying
floods in areas recently demarcated for vulnerable families estimated to constitute about 20% of the
affected population, and made up largely of women and child headed households, widows, the aged
and the infirms in the Chihaquelane area of Chokwe District.
3.1.3 The proposed Emergency Relief Assistance Operation will be funded from the Bank’s Special
Relief Fund (SRF). It will purchase emergency kits (family tents, tarpaulins and shelter tool kits) and a
Rescue speed boat. Included are local transportation costs, insurance, freight, and overhead customs
clearance. It will also cover the management cost of the executing agency and the financial audit of
the special account.
3.2 Cost and Source of Finance
3.2.1 The total cost of the Bank’s emergency assistance to the Government of Mozambique is
estimated at US$ 1,000,000. The funds provided by the Bank are restricted and earmarked for the
purposes of urgent humanitarian assistance to the affected populations.
Table 1
ITEM QTY. ESTIMATED COST
(US $)
1 Emergency Shelter Kits (standard IFRC
specifications)
2,000 80,000
2 Family tents (16 m2) 1,500 590,000
3 Tarpaulins (4mx6m) 10,000 150,000
4 Rescue speed boat and accessories (fibre glass, 6
metre, 55 HP engineer, and anchor)
1 160,000
5 Financial Audit 10,000
6 Operational costs (Transportation, Insurance,
Inspections, Clearance)
10,000
1,000,000
4
3.3 Implementation Arrangements and Schedule
3.3.1 According to the Bank’s Revised Policy Guidelines and Procedures for Emergency Relief
Assistance and General Regulations of the Special Relief Fund (ADB/BD/WP/2008/211/Rev.1 and
ADF/BD/WP/2008/173/Rev.1) (the “Guidelines”), implementation of emergency humanitarian
relief assistance will be entrusted to a suitable Implementing Agency to be selected from within UN
specialized agencies which are operating at field level, competent Government institutions, or
credible NGOs with a good track record of implementing emergency operations. The INGC will be
the executing agency.
3.3.2 The INGC, which was established in 1999, coordinates disaster risk management activities
in Mozambique and operates under the Ministry of State Administration (MAE) with a mandate to
coordinate emergencies, promote disaster prevention through population and government
mobilization; protect human lives; ensure multi-sectoral coordination in disaster emergency;
coordinate early warning systems; carry out public awareness; and re-utilize arid and semi-arid
zones. They are responsible for coordinating disaster risk management at the national, provincial
and district levels. They have received and continue to receive technical and financial assistance
towards improving their effectiveness. The reduced number of deaths in the 2013 floods, despite the
huge volume of water displaced attests to their improved efficiencies, outlook and approach to their
mandate.
3.3.3 A letter of Agreement will be signed between the Bank, and the Government of
Mozambique (Ministry of Planning and Development ) outlining the terms and conditions for the
grant, responsibilities, and obligations of each party.
3.4 Procurement and Disbursement Arrangements
Procurement
3.4.1 The Bank’s resources will be used to procure the various goods items. The Bank, through a
provision in the Letter of Agreement, will exercise a post review of this acquisition process. The
Bank’s MZFO will monitor the process of ensuring that the goods effectively reach the warehouses
of the INGC, and are distributed to the beneficiaries in the quantity and quality required.
3.4.2 The procurement of the emergency goods will be through a single source contract with the
IFRC, in accordance with the Bank’s Rules and Procedures for the Procurement of Goods and
Works (2012), as the Emergency goods are off the shelf products (IFRC), and are standard
requisition items in times of emergencies internationally, using global reach, and branding of the
International Federation of the Red Cross. The procurement of the rescue speed boat shall be by
means of shopping.
3.4.3 Audit: Acquisition of consultancy services for the Audit will be done through Least Cost
Selection method using a National Shortlist.
Duration
3.4.4 The Guidelines and Procedures stipulate that emergency humanitarian relief assistance is
typically a short-term operation, lasting a few months. Consequently, a period of 6 months from the
date of signature of the memorandum has been proposed for this emergency relief assistance. Funds
not disbursed after this period will be cancelled.
5
Disbursement
3.4.5 The funds will be disbursed in one single tranche payment, into a dedicated account at a
bank acceptable to the AfDB, to be operated by the INGC, and whose details shall be provided to
the AfDB.
3.5 Reporting, Supervision and Auditing
3.5.1 The INGC will submit through the Ministry of State Administration a detailed Project
Completion and financial Report and a formal Audit Report within six months of full disbursement.
The financial Audit report shall be compiled by an external audit firm acceptable to the Bank. The
audit fee, not exceeding 1% of the grant amount, will be part of the grant amount.
3.5.2 The Bank’s Field Office in Mozambique will provide ongoing support and monitor the
execution of this operation and the submission of the required reports.
4 CONCLUSIONS, RECOMMENDATIONS AND CONDITIONS FOR
DISBURSEMENT
4.1 Conclusions and Recommendations
4.1.1 The Government of Mozambique is facing severe challenges to relocate the flood victims
away from the flood plains. The sheer magnitude of moving families away from places that they
have called home, and which has served as a source of livelihood to them is gargantuan. This has
prompted support to the Government by the International Cooperating Partners to provide relief to
the affected community. The Bank’s Grant of USD 1 million will address an important component
of the early recovery efforts, in this case the provision of alternative temporary shelters, to the most
vulnerable segment of the affected population in more secure resettlement area of Chihaquelane in
Chokwe District of Gaza Province, through the provision of family tents, a rescue boat, emergency
kits and tarpaulins.
4.1.2 It is recommended that the Board of Directors approves a US$ 1 million grant from the SRF
for Emergency Assistance to the Government of Mozambique to help restore the livelihoods of
vulnerable populations that were severely affected by floods in the Province of Gaza and the
District of Chokwe of Mozambique.
4.2 Conditions for Disbursement
The grant resources will be disbursed in one tranche, subject to the following conditions:
Signature of the LoA by the Bank and the Government of Mozambique (Ministry of State
Administration);
Opening of a special account in a bank acceptable to the Bank and, communication by the
Government of Mozambique to the Bank of the details of the account to which the grant
resources will be transferred.