advanced project management tools and techniques of project planning ms. ghazala amin slides...
TRANSCRIPT
Advanced Project Management
Tools and Techniques of Project Planning
Ms. Ghazala Amin
Slides Courtesy: Dr. A Z. Khan
Project Planning
Project Planning lays the foundation for organizing, implementing, closing as well as monitoring, evaluating and controlling a project with a view to realizing the project goal and objectives within the constraints of time, budget, given requirements and stakeholder expectations.
Project Planning
Project Planning reduces uncertainty and increases understanding of the project as well as boosting efficiency in the way it is being carried out.
Many project failures are attributed to mistakes and shortcomings which occurred in the project’s planning phase.
Project Planning: A Sentence to Remember
Project Planning
On simple projects, planning may be undertaken by a few individuals within a short period of time at little cost.
On complex projects, project planning may require weeks and months of costly work input by the project team and involved stakeholders.
Project Planning
The quality of the project plan is determined primarily by the quality of the information used, the knowledge and experience of the stakeholders who are assigned the responsibility of developing the plan and the resources and time frame made available for it.
Project Planning
Project plans are not static entities. They must be periodically updated as and when new information which warrants a modification or revision of the project scope, requirements and specifications, cost, schedule, risks, stakeholder informational needs and so forth comes to light.
Ideally, anything that may have an impact on the project should be considered in developing the project plan.
Project Planning
The Project Management Plan is the key deliverable output of the project planning phase.
The Plan will include, inter alia, specific information on the individual project activities and tasks that need to be performed, why they need to be done, when they will be done and who will do them, what resources are needed and what criteria must be met in order for the project to be considered successful.
Project Planning
Project Scope Plan
Project Communication Plan
Project Cost Plan
Project Time Plan
Project Quality Plan
Project Risk Plan
Project Human Resource Plan
Project Procurement Plan
Project Integration Plan
PMI Standard
Project Stakeholder Management
Selected Tools in Project Planning
11
Project GoalProject Goal
Work ElementWork Element Work ElementWork Element Work ElementWork Element Level 1Level 1
Work ElementWork Element Work ElementWork Element Work ElementWork Element
Work ElementWork Element
Work Packages
Level 2Level 2
Level NLevel N
The WBS divides the whole project into work elementsthat represent singular work units, assigned either to theorganization or to an out-side agency, such as, a contractor or project partner
The underlying philosophy ofthe WBS is to divide the project into assignable “work packages” for whichaccountability can be expectedProjects are planned, organizedand controlled around the lowestlevel of the WBS, i.e., the workpackages
Work Breakdown Structure Visualization
12
Work Breakdown Structure: Example 1
13
Work Breakdown Structure: Example 2
14
Work Breakdown Structure: Example 3
15
Work Breakdown Structure: Example 4
16
Work Breakdown Structure: Example 5
17
Work Breakdown Structure: Example 6
Project ManagerProject Manager
Project Team Member Deliverable 1
Project Team Member Deliverable 1
Project Team MemberDeliverable 2
Project Team MemberDeliverable 2
Project Team MemberDeliverable 3
Project Team MemberDeliverable 3
WPM 1WPM 1 WPM 2WPM 2 Project Team MemberSub deliverable 2A
Project Team MemberSub deliverable 2A
WPM 2AAWPM 2AA
WPM 2ABWPM 2AB
Project Team MemberSub deliverable 2B
Project Team MemberSub deliverable 2B
WPM 2BAWPM 2BA
WPM 2BBWPM 2BB
WPM 2BCWPM 2BC
Example of a Project Organization Chart
19
RACI ChartRACI Chart Project Team MembersProject Team Members
ActivityActivity AliyahAliyah SarfrazSarfraz QaisarQaisar FarhanFarhan AmjadAmjad
DefineDefine AA RR II II II
DesignDesign II AA RR CC CC
DevelopDevelop II AA RR CC CC
TestTest AA II II RR II
RACI (R = Responsible; A = Accountable; C = Consult; I = Inform)
Responsibility Assignment Matrix (RACI)
20
1=Actual Responsibility; 2=General Supervision; 3=Must be Consulted; 4=May be Consulted; 5=Must be Notified; 6=Approval Authority
Project Linear Responsibility Chart
Gantt Charts: Example 1
Gantt Charts: Example 2
Gantt Charts: Example 3
ACTIVITYDESCRIPTION
ACTIVITYIDENTIFIER
ACTIVITYDURATION
ES EF
LS LF
SLACK
The CRITICAL PATH of a project is the sequence of activities that determine the project completion date – any delay in an activity or activities comprising the critical path will delay the project by a corresponding amount of time
The CRITICAL PATH of a project is the sequence of activities that determine the project completion date – any delay in an activity or activities comprising the critical path will delay the project by a corresponding amount of time
EARLY START: When can the activity start at the earliest?EARLY START: When can the activity start at the earliest?
EARLY FINISH: When can the activity finish at the earliest?EARLY FINISH: When can the activity finish at the earliest?
LATE FINISH: When can the activity finish at the latest?LATE FINISH: When can the activity finish at the latest?
LATE START: When can the activity start at the latest?LATE START: When can the activity start at the latest?
Project Network Diagrams: The Node
Koll Business Information Center
Activity Description Preceding Activity
Activity Duration
A Approval of Application None 5
B Construction Plans A 15
C Traffic Study A 10
D Service Availability Check A 5
E Staff Report B, C 15
F Commission Approval B, C, D 10
G Wait for Construction F 170
H Occupancy E, G 35
Activity Description Preceding Activity
Activity Duration
A Approval of Application None 5
B Construction Plans A 15
C Traffic Study A 10
D Service Availability Check A 5
E Staff Report B, C 15
F Commission Approval B, C, D 10
G Wait for Construction F 170
H Occupancy E, G 35
Project Network Diagram Example(Network Components and Details)
The BasicNetworkStructure
The BasicNetworkStructure
MergeActivities
MergeActivities
BurstActivities
BurstActivities
A Approval of Application
A Approval of Application
C Traffic Study
C Traffic Study
D Service Avail-ability Check
D Service Avail-ability Check
EStaff Report
EStaff Report
F Commission
Approval
F Commission
Approval
B Construction
Plans
B Construction
Plans
HOccupancy
HOccupancy
G Wait for
Construction
G Wait for
Construction
Project Network Diagram Example(Graphical Depiction of the Network Components)
ApplicationApproval
ConstructionPlans
Traffic Study
ServiceCheck
CommissionApproval
StaffReport
Wait forConstruction
Occupancy
A
B
C
D
F
E
G
H
5
15
10
5
10
15
170
35
50
205
155
105
3020
3520
20030
235200
Forward PassES + Duration = EF
Forward PassES + Duration = EF
2020
1515
1010
2020
1515
200200
3535
55
55
55
3030
Project Network Diagram Example(Determining the Forward Pass)
ApplicationApproval
A
5
ConstructionPlans
B
15
Traffic Study
C
10
ServiceCheck
D
5
CommissionApproval
F
10
StaffReport
E
15
Wait forConstruction
G
170
Occupancy
H
35
50
205
155
105
3020
3520
20030
235200
Backward PassLS + Duration = LF
Backward PassLS + Duration = LF
50 10 20
205
2015
3020
200185
20030
235200
2020
2020
2020
200200
55
1010
1515
3030
200200185185
185185
Project Network Diagram Example(Determining the Bckward Pass)
ApplicationApproval
A
5
ConstructionPlans
B
15
Traffic Study
C
10
ServiceCheck
D
5
CommissionApproval
F
10
StaffReport
E
15
Wait forConstruction
G
170
Occupancy
H
35
50
205
155
105
3020
3520
20030
235200
50 10 20
205
2015
3020
200185
20030
235200
Slack = LS – ESSlack = LF - EF
Slack = LS – ESSlack = LF - EF
0
0
5
10
0
165
0
0
Project Network Diagram Example (Determining Slack and the Critical Path)