Adopted Capital Improvement Program - Summary By Category 1
Adopted Capital Improvement Program - Summary By Funding Source 3
Adopted General Capital Improvements Funding Analysis Capital Projects Funds 4
Adopted Capital Improvement Program - By Category 8
Adopted Capital Improvement Program - By Funding Source 19
Adopted Capital Improvement Program – Index of Projects 30
Adopted Capital Improvement Program - Project Detail 34
-
i
MARION COUNTY, FLORIDA COUNTY OFFICIALS
BOARD OF COUNTY COMMISSIONERS
Kathy Bryant................................................................ Chairman - District 2
Carl Zalak III........................................................ Vice-Chairman - District 4
David Moore ........................................................ Commissioner - District 1
Stan McClain ....................................................... Commissioner - District 3
Earl Arnett ........................................................... Commissioner - District 5
ELECTED COUNTY OFFICERS
David R. Ellspermann......................................... Clerk of the Circuit Court
Villie M. Smith ................................................................Property Appraiser
Chris Blair............................................................................................Sheriff
Wesley Wilcox........................................................ Supervisor of Elections
George Albright....................................................................... Tax Collector
-
CLERK OF THE CIRCUIT COURT AND COMPTROLLER David R. Ellspermann
September 17, 2013
Marion County Board of County Commissioners 601 SE 25th Avenue Ocala, Florida 34471
Dear Commissioners,
Provided herein, is the Adopted Capital Improvement Program for fiscal years 2013/14 – 2017/18. This document serves to provide the Board of County Commissioners with an overview of funding for the Capital Improvement needs of the County over the next five fiscal years. This document does not address the County’s Transportation Improvement Program or the County’s Stormwater Implementation Program which are adopted separately. The Capital Improvement Program serves only as a capital outlay funding plan and does not represent an official appropriation of County funds. Official appropriations for capital projects are dependent upon their inclusion in the current and future annual budgets of the county as adopted through the statutorily required annual budget process.
For the five fiscal years 2013/14 – 2017/18 the Capital Improvement Program as adopted is in the total amount of $134,391,916. This total includes projects covering a broad range of purposes and funding sources. In addition to $39,419,773 appropriated for General Capital Improvement projects, the Capital Improvement Program includes total project amounts of $57,104,193 for Utilities, $20,168,711 for Solid Waste, and $17,699,239 for various Municipal Taxing / Assessment Districts and other funds within the County.
Approximately $195,453 of Local Option Sales Tax proceeds is projected to be available and not appropriated for specific capital projects. Approximately $1,285,336 is projected to be available in the Surplus Land Sales – Capital Projects Fund for capital expenditures beyond the appropriations detailed in this plan.
Marion County Clerk of the Circuit Court and Comptroller Post Office Box 1030 • Ocala Florida 34478-1030 • Telephone (352) 671-5604 • Facsimile (352) 671-5600 • www.marioncountyclerk.org
ii
http:www.marioncountyclerk.org
-
September 17, 2013 Page 2
The County's fiscal year 2013-14 budget includes $981,718 appropriated from general revenue. This appropriation includes $716,718 of re-appropriated funds that were carried forward from the previous fiscal year to the current fiscal year as well as $265,000 funded from fund balance carried forward from current and prior fiscal years. Other countywide projects in the amount of $35,820,682 for future fiscal years 2014-15 and beyond are included in the Capital Improvement Program and are currently designated as "Unfunded". The decline in taxable property values and the reduced levels of other general operating revenue have effectively eliminated the County's capacity to readily fund these projects from the general revenue stream. The projects are presented in the Capital Improvement Program for the Board's consideration and prioritization for whatever limited funds may be available in future years.
We would be pleased to answer any questions concerning the Capital Improvement Program or provide further information as needed.
Respectfully submitted,
~~ ... -~ DAVID R. ELLSPERMANN Clerk of the Circuit Court and Comptroller Marion County, Florida
iii
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Summary By Category
Fiscal Years 2014 thru 2018
Appropriated Five Year Category / Funding To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
General Capital Improvements General Fund - Operating 289,426 981,718 0 0 0 0 981,718
General Fund - Grants 0 0 0 1,000,000 1,000,000 552,000 2,552,000
General Fund - Unfunded 0 0 9,478,682 5,196,000 4,021,000 15,625,000 34,320,682
Capital Projects Fund 153,998 845,501 0 0 0 0 845,501
Local Option Sales Tax 1,055,922 616,985 0 0 0 0 616,985
Fire / Rescue - Operating 72,728 89,104 0 0 0 0 89,104
EMT - Operating 76,217 13,783 0 0 0 0 13,783
Total General Capital Improvements 1,648,291 2,547,091 9,478,682 6,196,000 5,021,000 16,177,000 39,419,773
Transportation Capital Projects Fund 107,051 0 0 0 0 0 0
Local Option Sales Tax 2,064,482 0 0 0 0 0 0
Others 0 365,000 0 0 0 0 365,000
Total Transportation 2,171,533 365,000 0 0 0 0 365,000
Parks & Recreation General Fund - Grants 200,000 1,635,850 0 0 2,613,750 0 4,249,600
Parks Fees - Operating 2,225,456 473,054 307,453 336,703 322,203 0 1,439,413
Pennies for Parks - Debt 26,018 236,907 0 0 0 0 236,907 Proceeds
Total Parks & Recreation 2,451,474 2,345,811 307,453 336,703 2,935,953 0 5,925,920
Airport Airport - Operating 97,447 187,553 58,653 288,737 346,042 0 880,985
Airport - Grants 389,786 750,214 1,114,414 2,891,103 1,506,723 0 6,262,454
Total Airport 487,233 937,767 1,173,067 3,179,840 1,852,765 0 7,143,439
1 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Summary By Category
Fiscal Years 2014 thru 2018
Appropriated Five Year Category / Funding To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
9-1-1 Emergency Communications General Fund - Operating 450,000 0 0 0 0 0 0
General Fund - Unfunded 0 0 1,500,000 0 0 0 1,500,000
Local Option Sales Tax 1,102,618 192,382 0 0 0 0 192,382
9-1-1 Management - Operating 0 0 500,000 0 0 0 500,000
Fire / Rescue - Operating 2,500,000 45,000 0 0 0 0 45,000
EMT - Operating 1,300,000 0 0 0 0 0 0
Solid Waste - Operating 0 45,000 0 0 0 0 45,000
Others 0 45,000 0 0 0 0 45,000
Total 9-1-1 Emergency 5,352,618 327,382 2,000,000 0 0 0 2,327,382Communications
Marion Oaks Recreation Marion Oaks MSTU - Operating 2,455,288 233,501 0 0 0 0 233,501
Total Marion Oaks 2,455,288 233,501 0 0 0 0 233,501Recreation
Fire / Rescue & EMS Services Fire / Rescue - Operating 800,000 1,270,890 0 0 0 0 1,270,890
EMT - Operating 244,875 53,997 0 0 0 0 53,997
Others 0 379,110 0 0 0 0 379,110
Total Fire / Rescue & EMS 1,044,875 1,703,997 0 0 0 0 1,703,997Services
Solid Waste Solid Waste - Operating 30,432,463 11,881,711 2,185,000 540,000 1,390,000 4,172,000 20,168,711
Total Solid Waste 30,432,463 11,881,711 2,185,000 540,000 1,390,000 4,172,000 20,168,711
Utilities Utilities - Operating 14,380,862 24,582,420 0 0 0 0 24,582,420
Utilities - Grants 1,514,500 43,500 0 0 0 0 43,500
Utilities - Debt Proceeds 5,997,710 300,711 0 0 0 0 300,711
Utilities - Future Capital 0 0 4,340,286 16,730,551 5,891,514 5,215,211 32,177,562
Total Utilities 21,893,072 24,926,631 4,340,286 16,730,551 5,891,514 5,215,211 57,104,193
Total - All Categories 67,936,847 45,268,891 19,484,488 26,983,094 17,091,232 25,564,211 134,391,916
2 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Summary By Funding Source
Fiscal Years 2014 thru 2018
Appropriated Five Year Funding Source To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
General Fund - Operating 739,426 981,718 0 0 0 0 981,718
General Fund - Grants 200,000 1,635,850 0 1,000,000 3,613,750 552,000 6,801,600
General Fund - Unfunded 0 0 10,978,682 5,196,000 4,021,000 15,625,000 35,820,682
Capital Projects Fund 261,049 845,501 0 0 0 0 845,501
Local Option Sales Tax 4,223,022 809,367 0 0 0 0 809,367
Transportation - Operating 0 410,000 0 0 0 0 410,000
Airport - Operating 97,447 187,553 58,653 288,737 346,042 0 880,985
Airport - Grants 389,786 750,214 1,114,414 2,891,103 1,506,723 0 6,262,454
9-1-1 Management - Operating 0 0 500,000 0 0 0 500,000
Marion Oaks MSTU - Operating 2,455,288 233,501 0 0 0 0 233,501
Fire / Rescue - Operating 3,372,728 1,404,994 0 0 0 0 1,404,994
Fire / Rescue - Impact Fees 0 379,110 0 0 0 0 379,110
EMT - Operating 1,621,092 67,780 0 0 0 0 67,780
Parks Fees - Operating 2,225,456 473,054 307,453 336,703 322,203 0 1,439,413
Pennies for Parks - Debt Proceeds 26,018 236,907 0 0 0 0 236,907
Solid Waste - Operating 30,432,463 11,926,711 2,185,000 540,000 1,390,000 4,172,000 20,213,711
Utilities - Operating 14,380,862 24,582,420 0 0 0 0 24,582,420
Utilities - Grants 1,514,500 43,500 0 0 0 0 43,500
Utilities - Debt Proceeds 5,997,710 300,711 0 0 0 0 300,711
Utilities - Future Capital 0 0 4,340,286 16,730,551 5,891,514 5,215,211 32,177,562
Total - All Funding 67,936,847 45,268,891 19,484,488 26,983,094 17,091,232 25,564,211 134,391,916
3 (All amounts stated at 2013-14 price level)
-
MARION COUNTY BOARD OF COUNTY COMMISSIONERS REVENUE & EXPENDITURE ACTUAL & PROJECTED THROUGH SEPTEMBER 30, 2013
Prepared by: Clerk of the Circuit Court - Budget Department
SURTAX CAPITAL PROJECTS FUND (ONE CENT LOCAL OPTION SALES TAX) Revenues Actual Total
Through 2011-12
Projected 2012-13
Through 2012-13
One Cent Local Option Sales Tax Proceeds Less: (Proceeds shared with Municipalities) Net Earnings on Investments
$ 69,288,790 (1,559,735) 8,643,945 2,778
$ 69,288,790 (1,559,735) 8,646,723
Total Revenues $ 76,373,000 $ 2,778 $ 76,375,778 Expenditures
Rainbow Springs Governmental Complex Expanded Office Space - BCC Departments Ocala National Bank Building Sheriff Sub-station West State Road 200 Sheriff Jail Expansion Southeastern Livestock Pavilion Parking Belleview Public Library Judicial Center Old Jury Assembly Room Renovations Clerk Annex (Renovation of SA Building) Growth Management Center Public Defender Renovation Integrated Phone Systems Re-roof Tax/Property Appraisers' Bldg Construct District Station in Ocklawaha Kennel Wings E & F Lobby Expansion/Interior Renovations Southeastern Livestock Pavilion - Phase 2 Replace roof on SELP livestock/horse barn Dunnellon Public Library Marion County Health Unit Parking Jail Maintenance Shop Kennel Roof & Drain Replacement Forest Public Library SOE Multi-Purpose Facility Sheriff's Communication Center 800 MHz Radio System Expansion Re-roof Clerk's Office Refurbish Exterior of Clerk's Office Clerk's Chillwater System Air Conditioning System Replacements Clerk of Court - Office Remodel Library Energy Management System Transportation Projects NW 35th Street Corridor
- Buildings - Bldgs & Improv - Buildings - Buildings - Buildings - Improvements - Land, Bld & Improv - Buildings - Buildings - Buildings - Land, Bld & Improv - Buildings - Buildings - Buildings - Land & Buildings - Buildings - Buildings - Buildings - Buildings - Land & Buildings - Improvements - Buildings - Buildings - Buildings - Buildings - Buildings - Buildings - Buildings - Buildings - Buildings - Buildings - Buildings - Buildings - Improvements - Improvements
$ 268,276 871,620 139,223 287,203
29,357,731 715,580
2,727,264 19,730,971 171,965
2,746,204 3,546,797 556,432 542,178 300,445 377,565 361,875 123,023 982,649 204,549
1,724,177 138,013
1,114,457 80,993 442,991 164,825
4,045,698 1,102,618 150,000 53,663 200,000 26,045
1,618,301 398,228
-28,254
----------------740 ---------
5,367 ---
18,035 37,150 10,803
$ 268,276 899,874 139,223 287,203
29,357,731 715,580
2,727,264 19,730,971 171,965
2,746,204 3,546,797 556,432 542,178 300,445 377,565 361,875 123,023 982,649 205,289
1,724,177 138,013
1,114,457 80,993 442,991 164,825
4,045,698 1,102,618 150,000 59,030 200,000 26,045
-18,035
1,655,451 409,031
Total Expenditures Fund Balance Fiscal Year End
$ $
75,271,559 1,101,441
$ 100,349 $ 1,003,870
$ $
75,371,908 1,003,870
4
-
MARION COUNTY BOARD OF COUNTY COMMISSIONERS GENERAL CAPITAL IMPROVEMENTS FUNDING ANALYSIS
Prepared by: Clerk of the Circuit Court - Budget Department
LOCAL OPTION ONE CENT SALES TAX
Expenditure Schedule - Local Option One Cent Sales Tax Projects Fiscal Year 2013-14 2014-15 2015-16 2016-17 2017-18 Total Annual Cost - Current Price $ 809,367 $ - $ - $ - $ - $ 809,367 Annual Price Level Adj. (1)
Annual Cost - Future Price Level $
0.0%
809,367 $
3.0%
- $
3.0%
- $
3.0%
-
3.0%
$ - $ 809,367
Funding Schedule - Local Option One Cent Sales Tax Projects Fiscal Year 2013-14 2014-15 2015-16 2016-17 2017-18 Total Available Proceeds -Beginning Balance $1,003,870 $ 195,453 $ 196,403 $ 196,403 $ 196,403 $1,003,870 (Less) Annual Cost - Future Price Level (809,367) - - - - (809,367) Unexpended Funds $ 194,503 $ 195,453 $ 196,403 $ 196,403 $ 196,403 $ 194,503 Projected Interest Earnings
Available Proceeds -950 950 - - - 1,900
Ending Balance $ 195,453 $ 196,403 $ 196,403 $ 196,403 $ 196,403 $ 196,403
(1) Judgmental Cost Factor representing assumed future price level increases for the costs of land, buildings, and improvements.
5
-
MARION COUNTY BOARD OF COUNTY COMMISSIONERS REVENUE & EXPENDITURE ACTUAL & PROJECTED THROUGH SEPTEMBER 30, 2013
Prepared by: Clerk of the Circuit Court - Budget Department
CAPITAL PROJECTS FUND (SURPLUS LAND SALES)
Revenues Actual Total Through Projected Through 2011-12 2012-13 2012-13
Net Surplus Land Sales Proceeds $ 13,258,725 $ - $ 13,258,725 Rent - County Owned Property 288,972 - 288,972 Net Earnings on Investments 1,604,118 5,379 1,609,497 Net Sale of Scrap or Surplus 2,933 2,933
Total Revenues $ 15,151,815 $ 8,312 $ 15,160,127
Expenditures Purchase of Blocker Building - Land, Bldgs & Improv $ 2,000,145 $ - $ 2,000,145 Renovations Records Center / Utilities - Buildings 1,001,642 - 1,001,642 Purchase of Ocala National Bank Bld - Land, Bldgs & Improv 2,250,010 - 2,250,010 Rainbow Springs Gov Complex - Buildings 441,833 - 441,833 Veterans Services Office Relocation - Buildings & Equipment 160,814 - 160,814 Growth Management Center - Equipment & Supplies 228,372 - 228,372 Sheriff Jail Expansion - Equipment 696,545 - 696,545 Kennel Wings E & F - Buildings 235,000 - 235,000 Animal Center Lobby Expansion / Reno - Buildings 9,480 - 9,480 Expanded Office Space - BCC Depts - Equipment & Supplies 64,600 445 65,045 Judicial Center Expansion - Buildings & Equipment 3,311,698 - 3,311,698 Belleview Library - Bldg,Improv,Equip/Supplies 451,926 - 451,926 Dunnellon Library - Bldg,Improv,Equip/Supplies 459,267 - 459,267 Replace Roof on SELP barn - Buildings 19,711 - 19,711 Dunnellon Airport Fencing - Improvement 18,911 - 18,911 Sheriff's Emergency Operations Center - Equipment & Supplies 60,017 - 60,017 Sheriff's 911/Communications Center - Buildings & Equipment 397,048 - 397,048 Clerk Annex (Renovation of SA Building) - Equipment 252,881 - 252,881 Clerk's Office Remodel - Buildings & Equipment 345,691 - 345,691 Clerk's Office Chillwater - Buildings 131,052 - 131,052 Air Conditioning System Replacements - Buildings - - -Facilities - Re-roofing Projects - Buildings 31,731 - 31,731 Forest Library - Equipment 299,998 - 299,998 Facilities - Renovation of Old Jail - Buildings - 57,222 57,222 NW 35th Street Cooridor 107,051 - 107,051
Total Expenditures $ 12,975,423 $ 57,667 $ 13,033,090 Fund Balance Fiscal Year End $ 2,176,392 $ 2,127,037 $ 2,127,037
6
-
MARION COUNTY BOARD OF COUNTY COMMISSIONERS GENERAL CAPITAL IMPROVEMENTS FUNDING ANALYSIS
Prepared by: Clerk of the Circuit Court - Budget Department
CAPITAL PROJECTS FUND (SURPLUS LAND SALES)
Expenditure Schedule - Capital Projects Fund (Surplus Land Sales) Fiscal Year 2013-14 2014-15 2015-16 2016-17 2017-18 Total Annual Cost - Current Price $ 845,501 $ - $ - $ - $ - $ 845,501 Annual Price Level Adj. (1) 0.0% 3.0% 3.0% 3.0% 3.0% Annual Cost - Future Price Lev $ 845,501 $ - $ - $ - $ - $ 845,501
Funding Schedule - Capital Projects Fund (Surplus Land Sales) Fiscal Year 2013-14 2014-15 2015-16 2016-17 2017-18 Total Available Proceeds -Beginning Balance $2,127,037 $1,285,336 $1,289,136 $1,289,136 $ 1,289,136 $2,127,037 (Less) Annual Cost - Future Price Level (845,501) - - - - (845,501) Unexpended Funds $1,281,536 $1,285,336 $1,289,136 $1,289,136 $ 1,289,136 $1,281,536 Projected Interest Earnings
Available Proceeds -3,800 3,800 - - - 7,600
Ending Balance $1,285,336 $1,289,136 $1,289,136 $1,289,136 $ 1,289,136 $1,289,136
(1) Judgmental Cost Factor representing assumed future price level increases for the costs of equipment.
7
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Appropriated Five Year Funding To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
General Capital Improvements Administration - Expanded Office Space Capital Projects Fund 65,045 9,955 0 0 0 0 9,955 Local Option Sales Tax 899,874 600,126 0 0 0 0 600,126
Project Total 964,919 610,081 0 0 0 0 610,081
Facilities Health - Belleview Health Department Roof/AC General Fund - Unfunded 0 0 125,000 0 0 0 125,000
Project Total 0 0 125,000 0 0 0 125,000
Facilities Health Department - Parking Local Option Sales Tax 138,013 11,987 0 0 0 0 11,987
Project Total 138,013 11,987 0 0 0 0 11,987
Facilities Health Department - Reddick Health Dept Upgrades General Fund - Operating 0 125,000 0 0 0 0 125,000
Project Total 0 125,000 0 0 0 0 125,000
Facilities Health Department - Re-roof Building General Fund - Unfunded 0 0 350,000 0 0 0 350,000
Project Total 0 0 350,000 0 0 0 350,000
Facilities Management - Cooling Tower - JC2 General Fund - Unfunded 0 0 200,000 0 0 0 200,000
Project Total 0 0 200,000 0 0 0 200,000
Facilities Management - Library Energy Management System General Fund - Operating 12,361 18,570 0 0 0 0 18,570 Local Option Sales Tax 18,035 0 0 0 0 0 0
Project Total 30,396 18,570 0 0 0 0 18,570
Facilities Management - Renovation of Old Jail General Fund - Operating 0 351,683 0 0 0 0 351,683 Capital Projects Fund 6,025 835,546 0 0 0 0 835,546 Local Option Sales Tax 0 4,872 0 0 0 0 4,872
Project Total 6,025 1,192,101 0 0 0 0 1,192,101
Facilities Management - Replace Flooring @ Sheriff's Ops & Visitation General Fund - Unfunded 0 0 75,000 0 0 0 75,000
Project Total 0 0 75,000 0 0 0 75,000
Facilities Management - Re-Roof Jail E & F Pods and Walkway General Fund - Operating 0 265,000 0 0 0 0 265,000
Project Total 0 265,000 0 0 0 0 265,000
Facilities Management - Re-Roof Old Jail General Fund - Unfunded 0 0 120,000 0 0 0 120,000
Project Total 0 0 120,000 0 0 0 120,000
(All amounts stated at 2013-14 price level) 8
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Funding
Appropriated To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Five Year Total
General Capital Improvements Facilities Management - Re-Roof original Jail facility General Fund - Unfunded 0 0 0 0 325,000 325,000 650,000
Project Total 0 0 0 0 325,000 325,000 650,000
Facilities Management - Re-roofing Projects General Fund - Operating 173,483 15,797 0 0 0 0 15,797 Capital Projects Fund 82,928 0 0 0 0 0 0
Project Total 256,411 15,797 0 0 0 0 15,797
Facilities Manangement - Duct replace/chillwater syst. Old Jail General Fund - Unfunded 0 0 350,000 0 0 0 350,000
Project Total 0 0 350,000 0 0 0 350,000
Fleet Management - New Fuel Sites General Fund - Operating 5,232 99,768 0 0 0 0 99,768 Fire / Rescue - Operating 72,728 89,104 0 0 0 0 89,104 EMT - Operating 76,217 13,783 0 0 0 0 13,783
Project Total 154,177 202,655 0 0 0 0 202,655
Library - Family Reading Garden, HQ - Ocala General Fund - Grants 0 0 0 0 0 552,000 552,000
Project Total 0 0 0 0 0 552,000 552,000
Library - Freedom General Fund - Unfunded 0 0 0 0 0 5,800,000 5,800,000
Project Total 0 0 0 0 0 5,800,000 5,800,000
Library - Marion Oaks General Fund - Unfunded 0 0 0 0 0 2,600,000 2,600,000
Project Total 0 0 0 0 0 2,600,000 2,600,000
Library - Silver Spring Shores General Fund - Unfunded 0 0 0 0 0 3,400,000 3,400,000
Project Total 0 0 0 0 0 3,400,000 3,400,000
Library - West Ocala Public Library General Fund - Unfunded 0 0 0 0 0 3,500,000 3,500,000
Project Total 0 0 0 0 0 3,500,000 3,500,000
Public Defender - Building Expansion General Fund - Unfunded 0 0 2,419,000 0 0 0 2,419,000
Project Total 0 0 2,419,000 0 0 0 2,419,000
S E Livestock Pavilion - Arena Fans General Fund - Operating 98,350 32,420 0 0 0 0 32,420
Project Total 98,350 32,420 0 0 0 0 32,420
(All amounts stated at 2013-14 price level) 9
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Funding
Appropriated To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Five Year Total
General Capital Improvements S E Livestock Pavilion - Phase 3 General Fund - Operating General Fund - Grants General Fund - Unfunded
Project Total
0 0 0 0
36,120 0 0
36,120
0 0
531,682 531,682
0 1,000,000 3,696,000 4,696,000
0 1,000,000 3,696,000 4,696,000
0 0 0 0
36,120 2,000,000 7,923,682 9,959,802
SE Livestock Pavilion - Critical Needs General Fund - Operating
Project Total 0 0
37,360 37,360
0 0
0 0
0 0
0 0
37,360 37,360
Sheriff - Pole Barn - EM Vehicle Storage General Fund - Unfunded 0
Project Total 0 0 0
120,000 120,000
0 0
0 0
0 0
120,000 120,000
Sheriff - Driving Range General Fund - Unfunded
Project Total 0 0
0 0
170,000 170,000
0 0
0 0
0 0
170,000 170,000
Sheriff - Training Facility / Indoor Shooting Range General Fund - Unfunded 0 0
Project Total 0 0 2,500,000 2,500,000
0 0
0 0
0 0
2,500,000 2,500,000
Sheriff Jail - A/C Upgrade General Fund - Unfunded
Project Total 0 0
0 0
750,000 750,000
0 0
0 0
0 0
750,000 750,000
State Attorney - 4th Floor Build-Out General Fund - Unfunded 0 0 1,518,000 0 0 0 1,518,000
Project Total 0 0 1,518,000 0 0 0 1,518,000
Supervisor of Elections - Voting Equipment General Fund - Unfunded 0
Project Total 0 0 0
0 0
1,500,000 1,500,000
0 0
0 0
1,500,000 1,500,000
Tax Collector / Property Appraiser - A/C Upgrade General Fund - Unfunded 0 0 250,000 0 0 0 250,000
Project Total 0 0 250,000 0 0 0 250,000
Total General Capital 1,648,291 2,547,091 9,478,682 6,196,000 5,021,000 16,177,000 39,419,773 Improvements
10 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Funding
Appropriated To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Five Year Total
Transportation NW 35th St Corridor Capital Projects Fund Local Option Sales Tax
Project Total
107,051 409,031 516,082
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
0 0 0
Roads N Substation Main Building Others
Project Total 0 0
365,000 365,000
0 0
0 0
0 0
0 0
365,000 365,000
Sales Tax Funded Transportation Projects Local Option Sales Tax 1,655,451 0 0 0 0 0 0
Project Total 1,655,451 0 0 0 0 0 0
Total Transportation 2,171,533 365,000 0 0 0 0 365,000
Parks & Recreation Benjamin Louis VanDuuren Park Parks Fees - Operating 75,000 0 0 0 125,000 0 125,000
Project Total 75,000 0 0 0 125,000 0 125,000
Brick City Adventure Park Parks Fees - Operating 84,450 180,550 0 0 0 0 180,550
Project Total 84,450 180,550 0 0 0 0 180,550
Coehadjoe Park Parks Fees - Operating 216,006 0 0 0 0 0 0
Project Total 216,006 0 0 0 0 0 0
Eureka Boat Ramp - West General Fund - Grants 0 125,000 0 0 0 0 125,000
Project Total 0 125,000 0 0 0 0 125,000
Gore's Landing General Fund - Grants 0 750,000 0 0 0 0 750,000
Project Total 0 750,000 0 0 0 0 750,000
Hampton Beach General Fund - Grants 0 303,250 0 0 0 0 303,250
Project Total 0 303,250 0 0 0 0 303,250
Heagy Burry Boat Ramp General Fund - Grants 0 200,000 0 0 0 0 200,000 Pennies for Parks - Debt 26,018 236,907 0 0 0 0 236,907 Proceeds
Project Total 26,018 436,907 0 0 0 0 436,907
(All amounts stated at 2013-14 price level) 11
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Appropriated Five Year Funding To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
Parks & Recreation Horseshoe Lake Park & Retreat Parks Fees - Operating 0 0 116,957 336,703 197,203 0 650,863
Project Total 0 0 116,957 336,703 197,203 0 650,863
KP Hole Parking Lot Resurface Parks Fees - Operating 190,496 192,504 190,496 0 0 0 383,000
Project Total 190,496 192,504 190,496 0 0 0 383,000
Liberty Community Park Parks Fees - Operating 250,000 0 0 0 0 0 0
Project Total 250,000 0 0 0 0 0 0
Orange Blossom Park General Fund - Grants 0 0 0 0 200,000 0 200,000
Project Total 0 0 0 0 200,000 0 200,000
Orange Lake Overlook General Fund - Grants 0 0 0 0 1,013,750 0 1,013,750
Project Total 0 0 0 0 1,013,750 0 1,013,750
Ralph Russell Park Parks Fees - Operating 0 100,000 0 0 0 0 100,000
Project Total 0 100,000 0 0 0 0 100,000
Ray Wayside Park General Fund - Grants 200,000 257,600 0 0 0 0 257,600
Project Total 200,000 257,600 0 0 0 0 257,600
Wrigley Fields-Phase Two General Fund - Grants 0 0 0 0 1,400,000 0 1,400,000 Parks Fees - Operating 1,409,504 0 0 0 0 0 0
Project Total 1,409,504 0 0 0 1,400,000 0 1,400,000
Total Parks & Recreation 2,451,474 2,345,811 307,453 336,703 2,935,953 0 5,925,920
Airport Aircraft Parking Apron Phase 1-Dunnellon Airport Airport - Operating 97,447 15,553 0 0 0 0 15,553 Airport - Grants 389,786 62,214 0 0 0 0 62,214
Project Total 487,233 77,767 0 0 0 0 77,767
12 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Funding
Appropriated To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Five Year Total
Airport Airport Master Plan Update Airport - Operating Airport - Grants
Project Total
0 0 0
0 0 0
0 0 0
0 0 0
8,170 155,235 163,405
0 0 0
8,170 155,235 163,405
Construct Clearspan Hangar (10,000 SF) Airport - Operating 0 Airport - Grants 0
Project Total 0
0 0 0
0 0 0
0 0 0
337,872 1,351,488 1,689,360
0 0 0
337,872 1,351,488 1,689,360
Customer Service and Administration Building Airport - Operating 0 172,000 Airport - Grants 0 688,000
0 0
0 0
0 0
0 0
172,000 688,000
Project Total 0 860,000 0 0 0 0 860,000
Design and Construct Aircraft Parking Apron Phase II Airport - Operating 0 0 0 131,193 0 0 131,193 Airport - Grants 0 0 0 524,774 0 0 524,774
Project Total 0 0 0 655,967 0 0 655,967
Design and Construct Parallel Taxiway to Runway 05-23 Airport - Operating 0 0 8,500 115,744 0 0 124,244 Airport - Grants 0 0 161,500 2,199,129 0 0 2,360,629
Project Total 0 0 170,000 2,314,873 0 0 2,484,873
Relocate Existing Fuel Storage Tanks Airport - Operating 0 0 0 41,800 0 0 41,800 Airport - Grants 0 0 0 167,200 0 0 167,200
Project Total 0 0 0 209,000 0 0 209,000
Repave North-South Taxiway and Aircraft Parking Apron Airport - Operating 0 0 50,153 0 0 0 50,153 Airport - Grants 0 0 952,914 0 0 0 952,914
Project Total 0 0 1,003,067 0 0 0 1,003,067
Total Airport 487,233 937,767 1,173,067 3,179,840 1,852,765 0 7,143,439
13 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Appropriated Five Year Funding To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
9-1-1 Emergency Communications 800 MHz Radio System Expansion General Fund - Operating 450,000 0 0 0 0 0 0 Local Option Sales Tax 1,102,618 147,382 0 0 0 0 147,382 Fire / Rescue - Operating 2,500,000 0 0 0 0 0 0 EMT - Operating 1,300,000 0 0 0 0 0 0
Project Total 5,352,618 147,382 0 0 0 0 147,382
9-1-1 Regional Network 9-1-1 Management - 0 0 500,000 0 0 0 500,000 Operating
Project Total 0 0 500,000 0 0 0 500,000
Baseline Communication Tower Modifications Local Option Sales Tax 0 45,000 0 0 0 0 45,000 Fire / Rescue - Operating 0 45,000 0 0 0 0 45,000 Solid Waste - Operating 0 45,000 0 0 0 0 45,000 Others 0 45,000 0 0 0 0 45,000
Project Total 0 180,000 0
Motorola Radio Console Upgrade General Fund - Unfunded 0 0 1,500,000
Project Total 0 0 1,500,000
Total 9-1-1 Emergency 5,352,618 327,382 2,000,000 Communications
Marion Oaks Recreation Construction of Multi-Purpose Building Marion Oaks MSTU - 2,455,288 233,501 0 Operating
Project Total 2,455,288 233,501 0
Total Marion Oaks Recreation 2,455,288 233,501 0
Fire / Rescue & EMS Services East Marion / Weirsdale Fire Station Renovations Fire / Rescue - Operating 800,000 0 0 EMT - Operating 244,875 53,997 0
0
0 0
0
0
0
0
0 0
0
0 0
0
0
0
0
0 0
0
0 0
0
0
0
0
0 0
180,000
1,500,000 1,500,000
2,327,382
233,501
233,501
233,501
0 53,997
Project Total 1,044,875 53,997 0 0 0 0 53,997
14 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Funding
Appropriated To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Five Year Total
Fire / Rescue & EMS Services Weirsdale Fire Station Fire / Rescue - Operating 0 Others 0
Project Total 0
1,270,890 379,110
1,650,000
0 0 0
0 0 0
0 0 0
0 0 0
1,270,890 379,110
1,650,000
Total Fire / Rescue & EMS Services
1,044,875 1,703,997 0 0 0 0 1,703,997
Solid Waste Baseline - Regional Capacity Enhancement Solid Waste - Operating 271,013 734,525 120,000 50,000 50,000 50,000 1,004,525
Project Total 271,013 734,525 120,000 50,000 50,000 50,000 1,004,525
Baseline Landfill Solid Waste - Operating 585,679 2,609,491 1,850,000 55,000 1,170,000 2,682,000 8,366,491
Project Total 585,679 2,609,491 1,850,000 55,000 1,170,000 2,682,000 8,366,491
Baseline Landfill - Improvements I Solid Waste - Operating 1,992,382 604,903 0 125,000 0 25,000 754,903
Project Total 1,992,382 604,903 0 125,000 0 25,000 754,903
Baseline Landfill - Improvements III Solid Waste - Operating 1,364,551 907,199 65,000 160,000 30,000 0 1,162,199
Project Total 1,364,551 907,199 65,000 160,000 30,000 0 1,162,199
Davis Landfill Solid Waste - Operating 1,450,291 767,960 50,000 50,000 50,000 85,000 1,002,960
Project Total 1,450,291 767,960 50,000 50,000 50,000 85,000 1,002,960
Davis Potable Water System Solid Waste - Operating 1,271,294 1,992,804 0 0 0 0 1,992,804
Project Total 1,271,294 1,992,804 0 0 0 0 1,992,804
Hazardous Waste Collection Center Solid Waste - Operating 48,815 51,185 0 0 0 0 51,185
Project Total 48,815 51,185 0 0 0 0 51,185
Landfill Acquisition Solid Waste - Operating 20,000,000 0 0 0 0 0 0
Project Total 20,000,000 0 0 0 0 0 0
Martel Landfill Solid Waste - Operating 370,787 1,177,224 50,000 50,000 50,000 1,300,000 2,627,224
Project Total 370,787 1,177,224 50,000 50,000 50,000 1,300,000 2,627,224
(All amounts stated at 2013-14 price level) 15
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Appropriated Funding To Date FY 2014 FY 2015
Solid Waste Newton Landfill Solid Waste - Operating 3,077,651 2,795,920 50,000
Project Total 3,077,651 2,795,920 50,000
Single Stream Recycling Solid Waste - Operating 0 240,500 0
Project Total 0 240,500 0
Total Solid Waste 30,432,463 11,881,711 2,185,000
Utilities Automated Meter Reading Utilities - Operating 2,019,869 1,124,131 0 Utilities - Debt Proceeds 1,164,073 0 0 Utilities - Future Capital 0 0 710,870
Five Year FY 2016 FY 2017 FY 2018 Total
50,000 40,000 30,000 2,965,920 50,000 40,000 30,000 2,965,920
0 0 0 240,500 0 0 0 240,500
540,000 1,390,000 4,172,000 20,168,711
0 0 0 1,124,131 0 0 0 0
732,310 675,600 695,400 2,814,180 Project Total 3,183,942 1,124,131 710,870 732,310 675,600 695,400 3,938,311
Biosolids Centrifuge Structure Utilities - Debt Proceeds 156,250 0 0 0 0 0 0
Project Total 156,250 0 0 0 0 0 0
Computerized Maintenance Mgmt System Utilities - Operating 167,497 474,400 0 0 0 0 474,400
Project Total 167,497 474,400 0 0 0 0 474,400
Customer Service Building Utilities - Operating 0 2,000,000 0 0 0 0 2,000,000
Project Total 0 2,000,000 0 0 0 0 2,000,000
Lift Station and Sewer Mains Utilities - Operating 2,241,530 2,162,000 0 0 0 0 2,162,000 Utilities - Debt Proceeds 265,674 0 0 0 0 0 0 Utilities - Future Capital 0 0 848,800 1,341,111 900,800 927,200 4,017,911
Project Total 2,507,204 2,162,000 848,800 1,341,111 900,800 927,200 6,179,911
Marion Oaks/ Summerglen WWTP Utilities - Operating 44,000 0 0 0 0 0 0 Utilities - Debt Proceeds 687,750 0 0 0 0 0 0
Project Total 731,750 0 0 0 0 0 0
Master Plan Updates Utilities - Operating 54,540 45,460 0 0 0 0 45,460 Utilities - Future Capital 0 0 0 109,300 0 115,900 225,200
Project Total 54,540 45,460 0 109,300 0 115,900 270,660
(All amounts stated at 2013-14 price level) 16
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Appropriated Funding To Date FY 2014 FY 2015
Utilities Meter relocation program for Salt Springs and Lindale Utilities - Debt Proceeds 213,789 153,211 0
FY 2016
0
FY 2017
0
FY 2018
0
Five Year Total
153,211 Project Total 213,789 153,211 0 0 0 0 153,211
Oak Run Reuse to Oak Run Golf Course Utilities - Operating 300,000 0 0 0 0 0 0
Project Total 300,000 0 0 0 0 0 0
Oak Run Water Service Line Replacements Utilities - Operating 244,916 0 0 0 0 0 0 Utilities - Debt Proceeds 534,177 0 0 0 0 0 0
Project Total 779,093 0 0 0 0 0 0
Reclaimed Water Stations and Reclaim Mains Utilities - Operating 2,919,000 2,289,200 0 0 0 0 2,289,200 Utilities - Grants 1,514,500 43,500 0 0 0 0 43,500 Utilities - Future Capital 0 0 530,500 546,500 0 235,567 1,312,567
Project Total 4,433,500 2,332,700 530,500 546,500 0 235,567 3,645,267
Relocations Due to Construction Utilities - Operating 587,549 627,249 0 0 0 0 627,249 Utilities - Debt Proceeds 200,000 0 0 0 0 0 0 Utilities - Future Capital 0 0 424,400 437,200 450,400 463,600 1,775,600
Project Total 787,549 627,249 424,400 437,200 450,400 463,600 2,402,849
Salt Springs WWTF Improvements Utilities - Debt Proceeds 23,450 0 0 0 0 0 0
Project Total 23,450 0 0 0 0 0 0
SCADA Equipment and installation Utilities - Operating 843,688 1,350,000 0 0 0 0 1,350,000 Utilities - Debt Proceeds 764,376 0 0 0 0 0 0
Project Total 1,608,064 1,350,000 0 0 0 0 1,350,000
Silver Springs Regional WWTF Utilities - Debt Proceeds 29,397 0 0 0 0 0 0
Project Total 29,397 0 0 0 0 0 0
Silver Springs Shores WRF Improvements Utilities - Debt Proceeds 325,274 120,000 0 0 0 0 120,000
Project Total 325,274 120,000 0 0 0 0 120,000
Spruce Crk Preserve I&I Abatement Utilities - Operating 0 50,000 0 0 0 0 50,000
Project Total 0 50,000 0 0 0 0 50,000
17 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Category
Fiscal Years 2014 thru 2018
Category / Project / Appropriated Five Year Funding To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
Utilities SSR Building Improvements Utilities - Operating 343,113 34,478 0 0 0 0 34,478 Utilities - Debt Proceeds 272,500 27,500 0 0 0 0 27,500
Project Total 615,613 61,978 0 0 0 0 61,978
SSS WWTF Reclaimed Pump Station & Storage Utilities - Debt Proceeds 86,000 0 0 0 0 0 0
Project Total 86,000 0 0 0 0 0 0
Stonecrest WRF Effluent Improvements Utilities - Debt Proceeds 100,000 0 0 0 0 0 0
Project Total 100,000 0 0 0 0 0 0
Toilet Rebate/Minor Capital Replacements Utilities - Operating 218,436 118,564 0 0 0 0 118,564 Utilities - Future Capital 0 0 53,050 54,650 56,300 57,950 221,950
Project Total 218,436 118,564 53,050 54,650 56,300 57,950 340,514
Wastewater Treatment Plant Improvements Utilities - Operating 1,124,350 4,060,000 0 0 0 0 4,060,000 Utilities - Future Capital 0 0 755,963 10,581,606 0 0 11,337,569
Project Total 1,124,350 4,060,000 755,963 10,581,606 0 0 15,397,569
Water Mains and Fire Hydrants Utilities - Operating 2,695,000 7,891,583 0 0 0 0 7,891,583 Utilities - Debt Proceeds 1,175,000 0 0 0 0 0 0 Utilities - Future Capital 0 0 1,016,703 2,000,737 1,506,025 2,200,941 6,724,406
Project Total 3,870,000 7,891,583 1,016,703 2,000,737 1,506,025 2,200,941 14,615,989
Water Plant C Rebuild Utilities - Operating 245,229 0 0 0 0 0 0
Project Total 245,229 0 0 0 0 0 0
Water Treatment Plant Improvements Utilities - Operating 332,145 2,355,355 0 0 0 0 2,355,355 Utilities - Future Capital 0 0 0 927,137 2,302,389 518,653 3,748,179
Project Total 332,145 2,355,355 0 927,137 2,302,389 518,653 6,103,534
Total Utilities 21,893,072 24,926,631 4,340,286 16,730,551 5,891,514 5,215,211 57,104,193
Total - All Categories 67,936,847 45,268,891 19,484,488 26,983,094 17,091,232 25,564,211 134,391,916
18 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / AppropriatedOrganization / To Date FY 2014 FY 2015Project
General Fund - Operating General Fund
800 MHz Radio System Expansion 450,000 0 0
Facilities Health Department - Reddick Health Dept Upgrades 0 125,000 0
Facilities Management - Library Energy Management System 12,361 18,570 0
Facilities Management - Renovation of Old Jail 0 351,683 0
Facilities Management - Re-Roof Jail E & F Pods and Walkway 0 265,000 0
Facilities Management - Re-roofing Projects 173,483 15,797 0
Fleet Management - New Fuel Sites 5,232 99,768 0
S E Livestock Pavilion - Arena Fans 98,350 32,420 0
S E Livestock Pavilion - Phase 3 0 36,120 0
SE Livestock Pavilion - Critical Needs 0 37,360 0
Organization Total 739,426 981,718 0
Total General Fund - 739,426 981,718 0 Operating
General Fund - Grants Marion County Public Library System
Library - Family Reading Garden, HQ - Ocala 0 0 0
FY 2016
0
0
0
0
0
0
0
0
0
0 0
0
0
FY 2017
0
0
0
0
0
0
0
0
0
0 0
0
0
FY 2018
0
0
0
0
0
0
0
0
0
0 0
0
552,000
Five Year Total
0
125,000
18,570
351,683
265,000
15,797
99,768
32,420
36,120
37,360 981,718
981,718
552,000 Organization Total 0 0 0 0 0 552,000 552,000
Other Recreation Programs
Eureka Boat Ramp - West 0 125,000 0 0 0 0 125,000
Gore's Landing 0 750,000 0 0 0 0 750,000
Hampton Beach 0 303,250 0 0 0 0 303,250
Heagy Burry Boat Ramp 0 200,000 0 0 0 0 200,000
Orange Blossom Park 0 0 0 0 200,000 0 200,000
19 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / Organization /
Project Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Five Year
Total
General Fund - Grants Other Recreation Programs
Orange Lake Overlook
Ray Wayside Park
Wrigley Fields-Phase Two
Organization Total
0 0
200,000 257,600
0 0 200,000 1,635,850
0
0
0 0
0
0
0 0
1,013,750
0
1,400,000 2,613,750
0
0
0 0
1,013,750
257,600
1,400,000 4,249,600
Southeastern Livestock Pavilion
S E Livestock Pavilion - Phase 3 0 0 0 1,000,000 1,000,000 0 2,000,000
Organization Total 0 0 0 1,000,000 1,000,000 0
Total General Fund - Grants 200,000 1,635,850 0 1,000,000 3,613,750 552,000
General Fund - Unfunded General Fund
Facilities Health - Belleview Health Department Roof/AC 0 0 125,000 0 0 0
Facilities Health Department - Re-roof Building 0 0 350,000 0 0 0
Facilities Management - Cooling Tower - JC2 0 0 200,000 0 0 0
Facilities Management - Replace Flooring @ Sheriff's Ops & Visitation 0 0 75,000 0 0 0
Facilities Management - Re-Roof Old Jail 0 0 120,000 0 0 0
Facilities Management - Re-Roof original Jail facility 0 0 0 0 325,000 325,000
Facilities Manangement - Duct replace/chillwater syst. Old Jail 0 0 350,000 0 0 0
Library - Freedom 0 0 0 0 0 5,800,000
Library - Marion Oaks 0 0 0 0 0 2,600,000
Library - Silver Spring Shores 0 0 0 0 0 3,400,000
Library - West Ocala Public Library 0 0 0 0 0 3,500,000
Motorola Radio Console Upgrade 0 0 1,500,000 0 0 0
2,000,000
6,801,600
125,000
350,000
200,000
75,000
120,000
650,000
350,000
5,800,000
2,600,000
3,400,000
3,500,000
1,500,000
20 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / Organization /
Project Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Five Year
Total
General Fund - Unfunded General Fund
Public Defender - Building Expansion 0 0 2,419,000 0 0 0 2,419,000
S E Livestock Pavilion - Phase 3 0 0 531,682 3,696,000 3,696,000 0 7,923,682
Sheriff - Pole Barn - EM Vehicle Storage 0 0 120,000 0 0 0 120,000
Sheriff - Driving Range 0 0 170,000 0 0 0 170,000
Sheriff - Training Facility / Indoor Shooting Range 0 0 2,500,000 0 0 0 2,500,000
Sheriff Jail - A/C Upgrade 0 0 750,000 0 0 0 750,000
State Attorney - 4th Floor Build-Out 0 0 1,518,000 0 0 0 1,518,000
Supervisor of Elections - Voting Equipment 0 0 0 1,500,000 0 0 1,500,000
Tax Collector / Property Appraiser - A/C Upgrade 0 0 250,000 0 0 0 250,000
Organization Total 0 0 10,978,682 5,196,000 4,021,000 15,625,000 35,820,682
Total General Fund -Unfunded
0 0 10,978,682 5,196,000 4,021,000 15,625,000 35,820,682
Capital Projects Fund CIP Capital Project Fund
Administration - Expanded Office Space 65,045 9,955
Facilities Management - Renovation of Old Jail 6,025 835,546
Facilities Management - Re-roofing Projects 82,928 0
NW 35th St Corridor 107,051 0
Organization Total 261,049 845,501
0
0
0
0 0
0
0
0
0 0
0
0
0
0 0
0
0
0
0 0
9,955
835,546
0
0 845,501
Total Capital Projects Fund 261,049 845,501 0 0 0 0 845,501
Local Option Sales Tax Surtax Capital Projects
800 MHz Radio System Expansion 1,102,618 147,382 0 0 0 0 147,382
(All amounts stated at 2013-14 price level) 21
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / AppropriatedOrganization / To Date FY 2014 FY 2015Project
Local Option Sales Tax Surtax Capital Projects
Administration - Expanded Office Space 899,874 600,126 0
Baseline Communication Tower Modifications 0 45,000 0
Facilities Health Department - Parking 138,013 11,987 0
Facilities Management - Library Energy Management System 18,035 0 0
Facilities Management - Renovation of Old Jail 0 4,872 0
NW 35th St Corridor 409,031 0 0
Sales Tax Funded Transportation Projects 1,655,451 0 0
Organization Total 4,223,022 809,367 0
Total Local Option Sales Tax 4,223,022 809,367 0
Transportation - Operating County Transportation Maintenance
Baseline Communication Tower Modifications 0 45,000 0
Roads N Substation Main Building 0 365,000 0
FY 2016
0
0
0
0
0
0
0 0
0
0
0
FY 2017
0
0
0
0
0
0
0 0
0
0
0
FY 2018
0
0
0
0
0
0
0 0
0
0
0
Five Year Total
600,126
45,000
11,987
0
4,872
0
0 809,367
809,367
45,000
365,000 Organization Total 0 410,000 0 0 0 0 410,000
Total Transportation - 0 410,000 0 0 0 0 410,000 Operating
Airport - Operating Dunnellon Airport Authority Fund
Aircraft Parking Apron Phase 1-Dunnellon Airport 97,447 15,553 0 0 0 0 15,553
Airport Master Plan Update 0 0 0 0 8,170 0 8,170
Construct Clearspan Hangar (10,000 SF) 0 0 0 0 337,872 0 337,872
Customer Service and Administration Building 0 172,000 0 0 0 0 172,000
Design and Construct Aircraft Parking Apron Phase II 0 0 0 131,193 0 0 131,193
22 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / Organization /
Project Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Five Year
Total
Airport - Operating Dunnellon Airport Authority Fund
Design and Construct Parallel Taxiway to Runway 05-23 0 0
Relocate Existing Fuel Storage Tanks 0 0
Repave North-South Taxiway and Aircraft Parking Apron 0 0
Organization Total 97,447 187,553
8,500
0
50,153 58,653
115,744
41,800
0 288,737
0
0
0 346,042
0
0
0 0
124,244
41,800
50,153 880,985
Total Airport - Operating 97,447 187,553 58,653 288,737 346,042 0 880,985
Airport - Grants Dunnellon Airport
Aircraft Parking Apron Phase 1-Dunnellon Airport 389,786 62,214
Airport Master Plan Update 0 0
Construct Clearspan Hangar (10,000 SF) 0 0
Customer Service and Administration Building 0 688,000
Design and Construct Aircraft Parking Apron Phase II 0 0
Design and Construct Parallel Taxiway to Runway 05-23 0 0
Relocate Existing Fuel Storage Tanks 0 0
Repave North-South Taxiway and Aircraft Parking Apron 0 0
0
0
0
0
0
161,500
0
952,914
0
0
0
0
524,774
2,199,129
167,200
0
0
155,235
1,351,488
0
0
0
0
0
0
0
0
0
0
0
0
0
62,214
155,235
1,351,488
688,000
524,774
2,360,629
167,200
952,914 Organization Total 389,786 750,214 1,114,414 2,891,103 1,506,723 0 6,262,454
Total Airport - Grants 389,786 750,214 1,114,414 2,891,103 1,506,723 0 6,262,454
9-1-1 Management - Operating 9-1-1 Emergency Telephone System
9-1-1 Regional Network
Organization Total 0 0
0 0
500,000 500,000
0 0
0 0
0 0
500,000 500,000
Total 9-1-1 Management -Operating
0 0 500,000 0 0 0 500,000
23 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / Organization /
Project Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Five Year
Total
Marion Oaks MSTU - Operating Marion Oaks MSTU
Construction of Multi-Purpose Building 2,455,288
Organization Total 2,455,288 233,501 233,501
0 0
0 0
0 0
0 0
233,501 233,501
Total Marion Oaks MSTU -Operating
2,455,288 233,501 0 0 0 0 233,501
Fire / Rescue - Operating Fire, Rescue and EMS Fund
800 MHz Radio System Expansion 2,500,000 0
Baseline Communication Tower Modifications 0 45,000
East Marion / Weirsdale Fire Station Renovations 800,000 0
Fleet Management - New Fuel Sites 72,728 89,104
Weirsdale Fire Station 0 1,270,890
Organization Total 3,372,728 1,404,994
0
0
0
0
0 0
0
0
0
0
0 0
0
0
0
0
0 0
0
0
0
0
0 0
0
45,000
0
89,104
1,270,890 1,404,994
Total Fire / Rescue - Operating
3,372,728 1,404,994 0 0 0 0 1,404,994
Fire / Rescue - Impact Fees Fire Rescue Impact Fees Fund
Weirsdale Fire Station 0 379,110 0 0 0 0 379,110
Organization Total 0 379,110 0 0 0 0 379,110
Total Fire / Rescue - Impact Fees
0 379,110 0 0 0 0 379,110
EMT - Operating MSTU for Emergency Medical Transport
800 MHz Radio System Expansion 1,300,000 0
East Marion / Weirsdale Fire Station Renovations 244,875 53,997
Fleet Management - New Fuel Sites 76,217 13,783
0
0
0
0
0
0
0
0
0
0
0
0
0
53,997
13,783
24 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / Appropriated Five Year Organization / To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 TotalProject
EMT - Operating Organization Total 1,621,092 67,780 0 0 0 0 67,780
Total EMT - Operating 1,621,092 67,780 0 0 0 0 67,780
Parks Fees - Operating Parks and Recreation Fees Fund
Benjamin Louis VanDuuren Park 75,000 0 0 0 125,000 0 125,000
Brick City Adventure Park 84,450 180,550 0 0 0 0 180,550
Coehadjoe Park 216,006 0 0 0 0 0 0
Horseshoe Lake Park & Retreat 0 0 116,957 336,703 197,203 0 650,863
KP Hole Parking Lot Resurface 190,496 192,504 190,496 0 0 0 383,000
Liberty Community Park 250,000 0 0 0 0 0 0
Ralph Russell Park 0 100,000 0 0 0 0 100,000
Wrigley Fields-Phase Two 1,409,504 0 0 0 0 0 0
Organization Total 2,225,456 473,054 307,453 336,703 322,203 0 1,439,413
Total Parks Fees - Operating 2,225,456 473,054 307,453 336,703 322,203 0 1,439,413
Pennies for Parks - Debt Proceeds Parks & Land Capital Project Fund
Heagy Burry Boat Ramp 26,018 236,907 0 0 0 0 236,907
Organization Total 26,018 236,907 0 0 0 0 236,907
Total Pennies for Parks - Debt 26,018 236,907 0 0 0 0 236,907 Proceeds
Solid Waste - Operating Solid Waste Disposal Fund
Baseline - Regional Capacity Enhancement 271,013 734,525 120,000 50,000 50,000 50,000 1,004,525
Baseline Communication Tower Modifications 0 45,000 0 0 0 0 45,000
(All amounts stated at 2013-14 price level) 25
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / AppropriatedOrganization / To Date FY 2014 FY 2015Project
Solid Waste - Operating Solid Waste Disposal Fund
Baseline Landfill 585,679 2,609,491 1,850,000
Baseline Landfill - Improvements I 1,992,382 604,903 0
Baseline Landfill - Improvements III 1,364,551 907,199 65,000
Davis Landfill 1,450,291 767,960 50,000
Davis Potable Water System 1,271,294 1,992,804 0
Hazardous Waste Collection Center 48,815 51,185 0
Landfill Acquisition 20,000,000 0 0
Martel Landfill 370,787 1,177,224 50,000
Newton Landfill 3,077,651 2,795,920 50,000
Single Stream Recycling 0 240,500 0
Organization Total 30,432,46311,926,711 2,185,000
Total Solid Waste - Operating 30,432,46311,926,711 2,185,000
Utilities - Operating Marion County Utilities Fund
Automated Meter Reading 2,019,869 1,124,131 0
Computerized Maintenance Mgmt System 167,497 474,400 0
Customer Service Building 0 2,000,000 0
Lift Station and Sewer Mains 2,241,530 2,162,000 0
Marion Oaks/ Summerglen WWTP 44,000 0 0
Master Plan Updates 54,540 45,460 0
Oak Run Reuse to Oak Run Golf Course 300,000 0 0
Oak Run Water Service Line Replacements 244,916 0 0
Five Year FY 2016 FY 2017 FY 2018 Total
55,000 1,170,000 2,682,000 8,366,491
125,000 0 25,000 754,903
160,000 30,000 0 1,162,199
50,000 50,000 85,000 1,002,960
0 0 0 1,992,804
0 0 0 51,185
0 0 0 0
50,000 50,000 1,300,000 2,627,224
50,000 40,000 30,000 2,965,920
0 0 0 240,500 540,000 1,390,000 4,172,000 20,213,711
540,000 1,390,000 4,172,000 20,213,711
0 0 0 1,124,131
0 0 0 474,400
0 0 0 2,000,000
0 0 0 2,162,000
0 0 0 0
0 0 0 45,460
0 0 0 0
0 0 0 0
26 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / Organization /
Project Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Five Year
Total
Utilities - Operating Marion County Utilities Fund
Reclaimed Water Stations and Reclaim Mains 2,919,000 2,289,200 0 0 0 0 2,289,200
Relocations Due to Construction 587,549 627,249 0 0 0 0 627,249
SCADA Equipment and installation 843,688 1,350,000 0 0 0 0 1,350,000
Spruce Crk Preserve I&I Abatement 0 50,000 0 0 0 0 50,000
SSR Building Improvements 343,113 34,478 0 0 0 0 34,478
Toilet Rebate/Minor Capital Replacements 218,436 118,564 0 0 0 0 118,564
Wastewater Treatment Plant Improvements 1,124,350 4,060,000 0 0 0 0 4,060,000
Water Mains and Fire Hydrants 2,695,000 7,891,583 0 0 0 0 7,891,583
Water Plant C Rebuild 245,229 0 0 0 0 0 0
Water Treatment Plant Improvements 332,145 2,355,355 0 0 0 0 2,355,355
Organization Total 14,380,86224,582,420 0 0 0 0 24,582,420
Total Utilities - Operating 14,380,86224,582,420 0 0 0 0 24,582,420
Utilities - Grants Utilities - Engineering and Construction
Reclaimed Water Stations and Reclaim Mains 1,514,500 43,500 0 0 0 0 43,500
Organization Total 1,514,500 43,500 0 0 0 0 43,500
Total Utilities - Grants 1,514,500 43,500 0 0 0 0 43,500
Utilities - Debt Proceeds Marion County Utilities Fund
Biosolids Centrifuge Structure 156,250 0 0 0 0 0 0
Marion Oaks/ Summerglen WWTP 687,750 0 0 0 0 0 0
Meter relocation program for Salt Springs and Lindale 213,789 153,211 0 0 0 0 153,211
27 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / Organization /
Project Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Five Year
Total
Utilities - Debt Proceeds Marion County Utilities Fund
Oak Run Water Service Line Replacements 534,177 0 0 0 0 0 0
Relocations Due to Construction 200,000 0 0 0 0 0 0
Salt Springs WWTF Improvements 23,450 0 0 0 0 0 0
SCADA Equipment and installation 764,376 0 0 0 0 0 0
Silver Springs Regional WWTF 29,397 0 0 0 0 0 0
Silver Springs Shores WRF Improvements 325,274 120,000 0 0 0 0 120,000
SSR Building Improvements 272,500 27,500 0 0 0 0 27,500
SSS WWTF Reclaimed Pump Station & Storage 86,000 0 0 0 0 0 0
Stonecrest WRF Effluent Improvements 100,000 0 0 0 0 0 0
Water Mains and Fire Hydrants 1,175,000 0 0 0 0 0 0
Organization Total 4,567,963 300,711 0 0 0 0 300,711
Utilities - Engineering and Construction
Automated Meter Reading 1,164,073 0 0 0 0 0 0
Lift Station and Sewer Mains 265,674 0 0 0 0 0 0
Organization Total 1,429,747 0 0 0 0 0 0
Total Utilities - Debt Proceeds 5,997,710 300,711 0 0 0 0 300,711
Utilities - Future Capital Marion County Utilities Fund
Automated Meter Reading 0 0 710,870 732,310 675,600 695,400 2,814,180
Lift Station and Sewer Mains 0 0 848,800 1,341,111 900,800 927,200 4,017,911
Master Plan Updates 0 0 0 109,300 0 115,900 225,200
Reclaimed Water Stations and Reclaim Mains 0 0 530,500 546,500 0 235,567 1,312,567
28 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - By Funding Source
Fiscal Years 2014 thru 2018
Funding / Appropriated Five Year Organization / To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 TotalProject
Utilities - Future Capital Marion County Utilities Fund
Relocations Due to Construction 0 0 424,400 437,200 450,400 463,600 1,775,600
Toilet Rebate/Minor Capital Replacements 0 0 53,050 54,650 56,300 57,950 221,950
Wastewater Treatment Plant Improvements 0 0 755,963 10,581,606 0 0 11,337,569
Water Mains and Fire Hydrants 0 0 1,016,703 2,000,737 1,506,025 2,200,941 6,724,406
Water Treatment Plant Improvements 0 0 0 927,137 2,302,389 518,653 3,748,179
Organization Total 0 0 4,340,286 16,730,551 5,891,514 5,215,211 32,177,562
Total Utilities - Future Capital 0 0 4,340,286 16,730,551 5,891,514 5,215,211 32,177,562
Total - All Funding 67,936,847 45,268,891 19,484,488 26,983,094 17,091,232 25,564,211 134,391,916
29 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners
Adopted Capital Improvement Program Fiscal Years 2014 thru 2018
Capital Improvement Program - Index of Projects
General Capital Improvements
Administration - Expanded Office Space BCCEXP 34
Facilities Health - Belleview Health Department Roof/AC HDBELV 35
Facilities Health Department - Parking HDLOT 36
Facilities Health Department - Reddick Health Dept Upgrades HDREDK 37
Facilities Health Department - Re-roof Building ROOFHLTH 38
Facilities Management - Cooling Tower - JC2 COOLTW 39
Facilities Management - Library Energy Management System LIBENGS 40
Facilities Management - Renovation of Old Jail OJRENO 41
Facilities Management - Replace Flooring @ Sheriff's Ops & Visitation SHOPFL 42
Facilities Management - Re-Roof Jail E & F Pods and Walkway JAILRF 43
Facilities Management - Re-Roof Old Jail OJAILRF 44
Facilities Management - Re-Roof original Jail facility JLPODS 45
Facilities Management - Re-roofing Projects REROOF 46
Facilities Manangement - Duct replace/chillwater syst. Old Jail OJCHILL 47
Fleet Management - New Fuel Sites FMSITE 48
Library - Family Reading Garden, HQ - Ocala FRGHQ 49
Library - Freedom FREELIB 50
Library - Marion Oaks OAKSLIB 51
Library - Silver Spring Shores SSSLIB 52
Library - West Ocala Public Library OCALALIB 53
Public Defender - Building Expansion PDBLDEXP 54
S E Livestock Pavilion - Arena Fans SELPFAN 55
S E Livestock Pavilion - Phase 3 SELP3PH 56
SE Livestock Pavilion - Critical Needs SELPCN 57
Sheriff - Pole Barn - EM Vehicle Storage SHPLBN 58
Sheriff - Driving Range SHDRANGE 59
Sheriff - Training Facility / Indoor Shooting Range SHTRAIN 60
Sheriff Jail - A/C Upgrade SHHVAC 61
State Attorney - 4th Floor Build-Out STABLD 62
30
-
Supervisor of Elections - Voting Equipment SOEVID 63
Tax Collector / Property Appraiser - A/C Upgrade TXHVAC 64
Transportation
NW 35th St Corridor 60800 65
Roads N Substation Main Building RDNSUB 66
Sales Tax Funded Transportation Projects TRANSP 67
Parks & Recreation
Benjamin Louis VanDuuren Park WDVANA 68
Brick City Adventure Park PKBRIA 69
Coehadjoe Park NDCOEA 70
Eureka Boat Ramp - West NDEURA 71
Gore's Landing NDGORA 72
Hampton Beach SDHAMA 73
Heagy Burry Boat Ramp NDHEAA 74
Horseshoe Lake Park & Retreat NDHORA 75
KP Hole Parking Lot Resurface WDKPLOT 76
Liberty Community Park WDLIBER 77
Orange Blossom Park SDORAA 78
Orange Lake Overlook NDOLOA 79
Ralph Russell Park PKSSSA 80
Ray Wayside Park CDRAYA 81
Wrigley Fields-Phase Two NDWRIG2 82
Airport
Aircraft Parking Apron Phase 1-Dunnellon Airport DUNPARK 83
Airport Master Plan Update DUNMPU 84
Construct Clearspan Hangar (10,000 SF) DUNHNG 85
Customer Service and Administration Building DUNTERM 86
Design and Construct Aircraft Parking Apron Phase II DUNPK2P 87
Design and Construct Parallel Taxiway to Runway 05-23 DUNTAX 88
Relocate Existing Fuel Storage Tanks DUNFUEL 89
Repave North-South Taxiway and Aircraft Parking Apron DUNPAVE 90
31
-
9-1-1 Emergency Communications
800 MHz Radio System Expansion PS800EXP 91
9-1-1 Regional Network 911REG 92
Baseline Communication Tower Modifications BLTOWR 93
Motorola Radio Console Upgrade MRADIO 94
Marion Oaks Recreation
Construction of Multi-Purpose Building MORECFA 95
Fire / Rescue & EMS Services
East Marion / Weirsdale Fire Station Renovations FSEMW 96
Weirsdale Fire Station FSWEIR 97
Solid Waste
Baseline - Regional Capacity Enhancement 4230024 98
Baseline Landfill 4230013 99
Baseline Landfill - Improvements I 4230018 100
Baseline Landfill - Improvements III 4230020 101
Davis Landfill 4230011 102
Davis Potable Water System 4230012 103
Hazardous Waste Collection Center 4230016 104
Landfill Acquisition 4230025 105
Martel Landfill 4230006 106
Newton Landfill 4230005 107
Single Stream Recycling 4230026 108
Utilities
Automated Meter Reading 7130117 109
Biosolids Centrifuge Structure 7160120 110
Computerized Maintenance Mgmt System 7160140 111
Customer Service Building 7160150 112
Lift Station and Sewer Mains 7130059 113
Marion Oaks/ Summerglen WWTP 7160088 114
Master Plan Updates 7160142 115
32
-
Meter relocation program for Salt Springs and Lindale 7160086 116
Oak Run Reuse to Oak Run Golf Course 7160093 117
Oak Run Water Service Line Replacements 7130087 118
Reclaimed Water Stations and Reclaim Mains 7160135 119
Relocations Due to Construction 7130115 120
Salt Springs WWTF Improvements 7160122 121
SCADA Equipment and installation 7160080 122
Silver Springs Regional WWTF 7160101 123
Silver Springs Shores WRF Improvements 7160095 124
Spruce Crk Preserve I&I Abatement 7160075 125
SSR Building Improvements 7160132 126
SSS WWTF Reclaimed Pump Station & Storage 7160126 127
Stonecrest WRF Effluent Improvements 7160124 128
Toilet Rebate/Minor Capital Replacements 7160144 129
Wastewater Treatment Plant Improvements 7160138 130
Water Mains and Fire Hydrants 7130116 131
Water Plant C Rebuild 7160149 132
Water Treatment Plant Improvements 7160136 133
33
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: BCCEXP Title: Administration - Expanded Office Space Division:General Capital Improvements Category: General Capital Improvements Status: Active
Project Description
Remodel and renovate office buildings on the Maricamp Office complex for growth and expansion of county departments.
Project Schedule of Activities Project Activity - Appropriated Activity Funding Souce To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Total
Buildings
Building Construction - Local Option Sales Tax
Improvements
Other Improvements - Local Option Sales Tax
Machinery and Equipment
Furniture & Equipment -Capital Projects Fund
Operating
Operating Supplies - Capital Projects Fund
872,052 600,126 0 0 0 0 1,472,178
27,822 0 0 0 0 0 27,822
17,108 9,955 0 0 0 0 27,063
47,937 0 0 0 0 0 47,937
Project Total 964,919 610,081 0 0 0 0 1,575,000
34 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: HDBELV Title: Facilities Health - Belleview Health Department Roof/AC Division:Facilities Management Category: General Capital Improvements Status: New
Project Description
The modular building being used as Belleview Health Department is past its useful life and needs to be upgraded to include at least a new roof and new a/c units.
Project Activity - Funding Souce
Project Schedule of Activities Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Activity
Total
Buildings
Building Construction -General Fund - Unfunded 0 0 125,000 0 0 0 125,000
Project Total 0 0 125,000 0 0 0 125,000
35 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: HDLOT Title: Facilities Health Department - Parking Division:General Capital Improvements Category: General Capital Improvements Status: Active
Project Description
Parking lot repavement.
Project Activity - Funding Souce
Project Schedule of Activities Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Activity
Total
Improvements
Other Improvements - Local Option Sales Tax 138,013 11,987 0 0 0 0 150,000
Project Total 138,013 11,987 0 0 0 0 150,000
36 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: HDREDK Title: Facilities Health Department - Reddick Health Dept Upgrades Division:Facilities Management Category: General Capital Improvements Status: Active
Project Description
The modular building currently being used for the Reddick Health Department is a modular building with an EPDM roof system that needs to be replaced. Facilities' staff also expects some structural damage that will need correction and in addition, all HVAC systems need to be replaced.
Project Activity - Funding Souce
Project Schedule of Activities Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Activity
Total
Buildings
Building Construction -General Fund - Operating 0 125,000 0 0 0 0 125,000
Project Total 0 125,000 0 0 0 0 125,000
37 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: ROOFHLTH Title: Facilities Health Department - Re-roof Building Division:Facilities Management Category: General Capital Improvements Status: Active
Project Description
The Health Department roof is nearing the end of its useful life and requires replacement.
Rationale
Roof is 5 years past warranty and needs to be replaced now.
Project Activity - Funding Souce
Project Schedule of Activities Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Activity
Total
Buildings
Building Construction -General Fund - Unfunded 0 0 350,000 0 0 0 350,000
Project Total 0 0 350,000 0 0 0 350,000
38 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: COOLTW Title: Facilities Management - Cooling Tower - JC2 Division:Facilities Management Category: General Capital Improvements Status: New
Project Description
New Cooling Tower needed for JC2 Chillwater HVAC system.
Rationale
The cooling towers have begun to rust due to the necessity to chemically treat. This is a normal process but need to be replaced every 15 years.
Project Activity - Funding Souce
Project Schedule of Activities Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Activity
Total
Buildings
Building Construction -General Fund - Unfunded 0 0 200,000 0 0 0 200,000
Project Total 0 0 200,000 0 0 0 200,000
39 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: LIBENGS Title: Facilities Management - Library Energy Management System Division:Facilities Management Category: General Capital Improvements Status: Active
Project Description
Replace existing EMS Systems with new State of the Art energy-saving devices.
Project Schedule of Activities Project Activity - Appropriated Funding Souce To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Buildings
Building Construction -General Fund - Operating 12,361 18,570 0 0 0 0
Building Construction - Local Option Sales Tax 18,035 0 0 0 0 0
Project Total 30,396 18,570 0 0 0 0
Activity Total
30,931
18,035
48,966
40 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: OJRENO Title: Facilities Management - Renovation of Old Jail Division:General Capital Improvements Category: General Capital Improvements Status: Active
Project Description
Renovation of the Old Jail, located at 412 NW 9th Street in Ocala, FL, into suitable space to be used by the Clerk's Office for offices and storage for offical records.
Project Schedule of Activities Project Activity - Appropriated Funding Souce To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Buildings
Building Construction -General Fund - Operating 0 351,683 0 0 0 0
Building Construction - Capital Projects Fund 6,025 835,546 0 0 0 0
Building Construction - Local Option Sales Tax 0 4,872 0 0 0 0
Project Total 6,025 1,192,101 0 0 0 0
Activity Total
351,683
841,571
4,872
1,198,126
41 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: SHOPFL Title: Facilities Management - Replace Flooring @ Sheriff's Ops & Visitation Division:Facilities Management Category: General Capital Improvements Status: Active
Project Description
Replace carpeting in offices as they can no longer be cleaned.
Rationale
Required upkeep and maintenance in long-term strategic plan for building upkeep and maintenance.
Funding Strategy and Operating Impacts
General Fund
Project Activity - Funding Souce
Project Schedule of Activities Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Activity
Total
Buildings
Building Construction -General Fund - Unfunded 0 0 75,000 0 0 0 75,000
Project Total 0 0 75,000 0 0 0 75,000
42 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: JAILRF Title: Facilities Management - Re-Roof Jail E & F Pods and Walkway Division:Facilities Management Category: General Capital Improvements Status: Active
Project Description
The existing Jail E & F Pod roofs are over 20 years old; they are beyond their warranty period and have already been repaired numerous times. In order to maintain the integrity of the overall structure, the most cost effective and efficient measure would be to replace the failing roofs. The existing walkway is in need of replacement to ensure proper safety standards.
Rationale
The project is necessary to maintain the integrity of the overall structure and to ensure proper safety standards.
Project Activity - Funding Souce
Project Schedule of Activities Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Activity
Total
Buildings
Building Construction -General Fund - Operating 0 265,000 0 0 0 0 265,000
Project Total 0 265,000 0 0 0 0 265,000
43 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: OJAILRF Title: Facilities Management - Re-Roof Old Jail Division:Facilities Management Category: General Capital Improvements Status: New
Project Description
Project is to re-roof the Old Jail building located at 412 NW 9th St. in Ocala. This is a 2-story, 22,000 square foot building.
Rationale
This building was last re-roofed in July of 1996. The roof has outlived the 15 year no dollar manufacturer's warranty and nearing the end of its useful life.
Funding Strategy and Operating Impacts
General Fund
Project Activity - Funding Souce
Project Schedule of Activities Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Activity
Total
Buildings
Building Construction -General Fund - Unfunded 0 0 120,000 0 0 0 120,000
Project Total 0 0 120,000 0 0 0 120,000
44 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: JLPODS Title: Facilities Management - Re-Roof original Jail facility Division:Facilities Management Category: General Capital Improvements Status: New
Project Description
Re-Roof original Jail facility, to include Pods A,B,C, D, and corridor
Rationale
The current roof has outlived its useful life and is beginning to leak.
Project Activity - Funding Souce
Project Schedule of Activities Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Activity
Total
Buildings
Building Construction -General Fund - Unfunded 0 0 0 0 325,000 325,000 650,000
Project Total 0 0 0 0 325,000 325,000 650,000
45 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: REROOF Title: Facilities Management - Re-roofing Projects Division:Facilities Management Category: General Capital Improvements Status: Active
Project Description
Several roofs on County-owned buildings are reaching the end of their useful lives and will need to be replaced soon.Some of these buildings are: 1. Administration 2. Lake Tropicana Fire Department 3. East Hall Museum 4. Coleman Building
Project Schedule of Activities Project Activity - Appropriated Funding Souce To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Buildings
Building Construction -General Fund - Operating 134,203 15,797 0 0 0 0
Building Construction - Capital Projects Fund 82,928 0 0 0 0 0
Operating
Repairs & Maint - General Fund - Operating 39,280 0 0 0 0 0
Project Total 256,411 15,797 0 0 0 0
Activity Total
150,000
82,928
39,280
272,208
46 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: OJCHILL Title: Facilities Manangement - Duct replace/chillwater syst. Old Jail Division:Facilities Management Category: General Capital Improvements Status: New
Project Description
The ductwork at this facility is over 30 years old, and is internally-lined ductwork, which is no longer an acceptable practice. We need to replace with externally-lined ductwork because of the dirt and bacteria that has built up inside.
Rationale
Our primary concern with this facility is indoor air quality. This replacement will allow for clean air and is part of our strategic plan for energy savings and cost-effective maintenance.
Project Activity - Funding Souce
Project Schedule of Activities Appropriated
To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018 Activity
Total
Buildings
Building Construction -General Fund - Unfunded 0 0 350,000 0 0 0 350,000
Project Total 0 0 350,000 0 0 0 350,000
47 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: FMSITE Title: Fleet Management - New Fuel Sites Division:Fleet Management Category: General Capital Improvements Status: Active
Project Description
Purchase and install six (6) 10,000 gallon fuel tanks with fuel pedestals. These sites are to include a concrete slab for each site and electric hook-up to our Fuelmaster fuel system.
Project Schedule of Activities Project Activity - Appropriated Funding Souce To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Improvements
Other Improvements - General Fund - Operating 5,232 99,768 0 0 0 0
Other Improvements - Fire / Rescue - Operating 72,728 89,104 0 0 0 0
Other Improvements - EMT -Operating 76,217 13,783 0 0 0 0
Project Total 154,177 202,655 0 0 0 0
Activity Total
105,000
161,832
90,000
356,832
48 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: FRGHQ Title: Library - Family Reading Garden, HQ - Ocala Division:Public Library System Category: General Capital Improvements Status: Active
Project Description
Since renovations were completed on the new Headquarters – Ocala Public Library there have been discussions of creating a Family Reading Garden to the south of the library between the library and what is currently the bowling alley. To that end, a local landscape architect has donated his services to create an imaginative plan designed to appeal to our youngest library users and their families. It is intended that the entire project be completed utilizing donated funds, products and in-kind services. The Friends of the Ocala Public Library have ear-marked $50,000 toward the project and are willing to be stewards of the donations, similar to their role in the original enhancements of the Headquarters- Ocala Library. Green building and maintenance principles will be incorporated into the design.
Funding Strategy and Operating Impacts
The estimated ongoing cost to maintain this garden is estimated at $22,000.
Project Schedule of Activities Project Activity - Appropriated Funding Souce To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Improvements
Other Improvements - General Fund - Grants 0 0 0 0 0 552,000
Project Total 0 0 0 0 0 552,000
Activity Total
552,000
552,000
49 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: FREELIB Title: Library - Freedom Division:Public Library System Category: General Capital Improvements Status: Active
Project Description
The Freedom Public Library opened in 2000. Almost immediately upon opening, library users began asking when the expansion would begin. Property, as well as a site plan, exist to expand the facility up to 32,000 sq. ft. Presently the library is 9,700 sq. ft., including the portico. The facility serves over 25,000 registered borrowers and houses over 54,300 volumes.
Year 1 - Complete architectural design. Seek State of Florida construction grant. Prepare site, initiate construction of a 24,000 sq. ft library addition. Year 2 - Complete construction of the addition. Purchase FF&E. Move into new space. Renovate existing space with new carpet and painting.
Funding Strategy and Operating Impacts
Expenditure estimates are based on the construction of a 24,000 sq. ft. addition. It is estimated that the architectural design will begin during FY2014-15 and construction completed the following year. Architectural design must be completed to submit a construction grant.
Additional staffing needs are estimated as: 2 – Public Services Librarian IIs 2 – Public Services Librarian IIs 8 - Public Services Assistants An additional 25% has been calculated for benefits.
“Operations” reflects cost estimates for utilities, services, and miscellaneous consumables. “Maintenance” reflects cost estimates for various cleaning services as well as grounds maintenance. “Future years” reflects current expenses as well as estimated operational costs associated with the expansion. If a State of Florida construction grant is secured, eligible reimbursement includes FF&E, architectural fees and construction.
Project Schedule of Activities Project Activity - Appropriated Funding Souce To Date FY 2014 FY 2015 FY 2016 FY 2017 FY 2018
Buildings
Building Construction -General Fund - Unfunded 0 0 0 0 0 5,000,000
Machinery and Equipment
Furniture & Equipment -General Fund - Unfunded 0 0 0 0 0 800,000
Project Total 0 0 0 0 0 5,800,000
Activity Total
5,000,000
800,000
5,800,000
50 (All amounts stated at 2013-14 price level)
-
Marion County Board of County Commissioners Adopted Capital Improvement Program - Project Detail
Fiscal Years 2014 thru 2018
Project: OAKSLIB Title: Library - Marion Oaks Division:Public Library System Category: General Capital Improvements Status: Active
Project Description
The Marion Oaks Public Library has been part of the Marion County Library System since 1996. The library is housed in an 800 sq. ft. room in the Marion Oaks Community Center. This room currently serves over 6,500 registered borrowers and houses over 20,500 volumes. The construction of a new 12,000 sq. ft. free-standing library is needed to better serve the residents in and around the Marion Oaks area. The design will be a re-use of the Forest Public Library and will be such that it can be expanded.